CN204778237U - Can have enough to meet need construction elevator layer door connects material platform - Google Patents

Can have enough to meet need construction elevator layer door connects material platform Download PDF

Info

Publication number
CN204778237U
CN204778237U CN201520519273.7U CN201520519273U CN204778237U CN 204778237 U CN204778237 U CN 204778237U CN 201520519273 U CN201520519273 U CN 201520519273U CN 204778237 U CN204778237 U CN 204778237U
Authority
CN
China
Prior art keywords
angle steel
supporting leg
steel supporting
mounting hole
construction elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520519273.7U
Other languages
Chinese (zh)
Inventor
张涛
丁晓冬
李军
董福永
邱雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201520519273.7U priority Critical patent/CN204778237U/en
Application granted granted Critical
Publication of CN204778237U publication Critical patent/CN204778237U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model provides a can have enough to meet need construction elevator layer door connects material platform relates to the building and connects material equipment field, and its structure is provided with the angle steel landing leg of several right angle shape including connecing the flitch at the lower surface that connects the flitch, two angle steel landing legs and connecing in the outside are in the same place through bolted connection between the flitch, the angle steel bracing of fixed action has been provided with on the angle steel landing leg, still being provided with the several on every angle steel landing leg and being used for the mounting hole of fixed religion pole landing leg, also be provided with two on the flitch connecing of angle steel landing leg rear and be used for the location and connect the mounting hole of flitch position, this mounting hole sets up on same straight line, and the position of mounting hole is corresponding with two angle steel landing legs of outermost respectively. Save the scaffold and connect the material platform for construction elevator is close to the building, the expense of having practiced thrift, the safe risk that has reduced.

Description

One can have enough to meet the need construction elevator layer door splicing platform
Technical field
The utility model relates to building splicing apparatus field, and specifically one can have enough to meet the need construction elevator layer door splicing platform.
Background technology
Conventional construction elevator layer door is arranged on outside external scaffolding; When opening construction elevator layer door after the safety door opening construction elevator again, then, material enters in floor by the outer body panel between construction elevator and building; This performance to this position scaffold proposes very high requirement, and scaffold should bear the weight of multiple tracks construction elevator layer door, also will bear the weight of multilayer material receiving, often there is larger security risk.
During elevation building operation, external scaffolding adopts repeatedly builder's jack, according to traditional handicraft erection construction elevator splicing platform: the load one, increasing outrigger, strengthens the security risk of site operation; Two, time-consumingly take artificial, and be not easy to workman's construction, affect construction speed; Three, remove after equal single use, do not meet the requirement of green construction.Therefore need between building and construction elevator to adopt a kind of safer materials device of Novel connecting efficiently.
Summary of the invention
The purpose of this utility model overcomes the deficiency existed in existing operating technique, provides a kind of safety factor high, and the novel of constructability has enough to meet the need construction elevator layer door and splicing platform.
The technical solution of the utility model realizes in the following manner, and its structure will be combined into material receiving by splicing plate, angle steel supporting leg, angle steel diagonal brace, adopts expansion bolt to be fixed on building.
One can have enough to meet the need construction elevator layer door splicing platform, comprise splicing plate, described splicing plate is square, the angle steel supporting leg of several square is provided with at the lower surface of splicing plate, angle steel supporting leg arranges in a row and be arranged in parallel between angle steel supporting leg, and the arrangement position of angle steel supporting leg matches with the width of splicing plate; All angle steel supporting legs are all arranged on the front portion of splicing plate; Outermost two angle steel supporting legs are together with being bolted between splicing plate; Angle steel supporting leg is provided with the angle steel diagonal brace of fixation;
Each angle steel supporting leg is also provided with several mounting hole in order to fixing teaching pole supporting leg, the splicing plate at angle steel supporting leg rear is also provided with the mounting hole that two row are used for locating splicing Board position, this mounting hole is arranged on same straight line, and the position of mounting hole is corresponding with outmost two angle steel supporting legs respectively.
Further, angle steel supporting leg is provided with three through holes for being connected with splicing plate, in order to regulate the relative position of splicing plate and angle steel supporting leg, three through holes are all arranged on the same line.
Described mounting hole is provided with expansion bolt.
Further, the front end of splicing plate is 0-30cm to the distance of angle steel supporting leg.
Bear peak load through material receiving to calculate, in conjunction with on-the-spot actual, determine the thickness of splicing plate and size, the size of angle steel diagonal brace, elevator bridge case and distance between buildings, made with reference to the dimensioned of splicing plate, angle steel diagonal brace by workman, then construction elevator is opened to installation floor, splicing platform steel plate distance construction elevator safety door distance is kept to be 5cm, location will on building the position of expandable implant bolt hole, expandable implant bolt, stagger angle steel leg, angle steel diagonal brace and splicing plate, after debugging, after meeting on-the-spot actual use, place in operation.
The beneficial effects of the utility model:
The utility model compared with prior art, can effectively reduce site operation security risk, eliminate scaffold and material receiving, make construction elevator near building; Save expense, reduce security risk;
Be convenient to operative's construction, reach simultaneously save time, the effect of less manpower, material repeatedly can have enough to meet the need utilization, meets " material-saving " requirement in green construction, and the utility model have reasonable in design, structure simple, be easy to the features such as processing.
Accompanying drawing explanation
Fig. 1 is mounting structure schematic diagram of the present utility model;
Fig. 2 is front elevation of the present utility model;
Fig. 3 is birds-eye view of the present utility model.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in detail below.
As shown in Figure 1, one of the present utility model can have enough to meet the need construction elevator layer splicing platform, and its structure is by 3mm plate iron 1(1.40X0.5m), 5 high by 0.4, wide 0.2m of angle steel supporting leg 3(), 5 long 0.44m of angle steel diagonal brace 5(), M8 expansion bolt 2 forms; According to construction elevator bridge case size and on-the-spot reality, design size and the size of steel plate 1, angle steel supporting leg 3 and angle steel diagonal brace 5 in advance, processed by producer; Opened by elevator bridge case to installation floor, angle steel supporting leg 3 and steel plate 1 position (guaranteeing to borrow the distance 5cm of material platform and elevator bridge case) are determined in unwrapping wire location, indicate expansion bolt 2 position simultaneously; M8 expansion bolt 2 is implanted, stagger angle steel leg 3 and angle steel diagonal brace 5 at building 6 side bar place; 3mm plate iron 1 is installed as splicing plate, tightens M8 expansion bolt 2, install, after qualified on inspection, place in operation.
For adapting to different situations, three through holes 4 can be offered on angle steel supporting leg 3 top, being used for regulating the relative position of steel plate 1 and angle steel supporting leg 3.
Except the technical characteristic described in specification sheets, be the known technology of those skilled in the art.

Claims (4)

1. one kind can have enough to meet the need construction elevator layer door splicing platform, comprise splicing plate, it is characterized in that, described splicing plate is square, the angle steel supporting leg of several square is provided with at the lower surface of splicing plate, angle steel supporting leg arranges in a row and be arranged in parallel between angle steel supporting leg, and the arrangement position of angle steel supporting leg matches with the width of splicing plate; All angle steel supporting legs are all arranged on the front portion of splicing plate; Outermost two angle steel supporting legs are together with being bolted between splicing plate; Angle steel supporting leg is provided with the angle steel diagonal brace of fixation;
Each angle steel supporting leg is also provided with several mounting hole in order to fixing teaching pole supporting leg, the splicing plate at angle steel supporting leg rear is also provided with the mounting hole that two row are used for locating splicing Board position, this mounting hole is arranged on same straight line, and the position of mounting hole is corresponding with outmost two angle steel supporting legs respectively.
2. according to claim 1ly have enough to meet the need construction elevator layer door splicing platform, it is characterized in that, angle steel supporting leg is provided with three through holes for being connected with splicing plate, in order to regulate the relative position of splicing plate and angle steel supporting leg, three through holes are all arranged on the same line.
3. according to claim 1 and 2ly have enough to meet the need construction elevator layer door splicing platform, it is characterized in that, described mounting hole is provided with expansion bolt.
4. according to claim 1ly have enough to meet the need construction elevator layer door splicing platform, it is characterized in that, the front end of splicing plate is 0-30cm to the distance of angle steel supporting leg.
CN201520519273.7U 2015-07-17 2015-07-17 Can have enough to meet need construction elevator layer door connects material platform Expired - Fee Related CN204778237U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520519273.7U CN204778237U (en) 2015-07-17 2015-07-17 Can have enough to meet need construction elevator layer door connects material platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520519273.7U CN204778237U (en) 2015-07-17 2015-07-17 Can have enough to meet need construction elevator layer door connects material platform

Publications (1)

Publication Number Publication Date
CN204778237U true CN204778237U (en) 2015-11-18

Family

ID=54518329

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520519273.7U Expired - Fee Related CN204778237U (en) 2015-07-17 2015-07-17 Can have enough to meet need construction elevator layer door connects material platform

Country Status (1)

Country Link
CN (1) CN204778237U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088602A (en) * 2016-07-23 2016-11-09 尚梅 A kind of construction of super highrise building elevator material-receiving device
CN106193565A (en) * 2016-08-29 2016-12-07 中国建筑第五工程局有限公司安徽分公司 A kind of tool combination type people's goods elevator material receiving and installation method
CN108910760A (en) * 2018-08-08 2018-11-30 北京鼎翰科技有限公司 A kind of high-building construction elevator material-receiving device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106088602A (en) * 2016-07-23 2016-11-09 尚梅 A kind of construction of super highrise building elevator material-receiving device
CN106088602B (en) * 2016-07-23 2018-01-16 西安科技大学 A kind of construction of super highrise building lift material-receiving device
CN106193565A (en) * 2016-08-29 2016-12-07 中国建筑第五工程局有限公司安徽分公司 A kind of tool combination type people's goods elevator material receiving and installation method
CN108910760A (en) * 2018-08-08 2018-11-30 北京鼎翰科技有限公司 A kind of high-building construction elevator material-receiving device

Similar Documents

Publication Publication Date Title
CN103711323B (en) Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing
CN101775907A (en) Space truss structure aerial pairing integral slide installation method
CN204778237U (en) Can have enough to meet need construction elevator layer door connects material platform
CN206467994U (en) A kind of novel hanging basket support
CN102337781B (en) Tool-type combined and attached lifting scaffold
CN107060098A (en) A kind of high-altitude wire frame Steel Structure Installation method based on sliding platform
TWM457761U (en) Construction lifting platform
CN203143872U (en) Mobile platform for elevator installation construction
CN204754226U (en) Detachable construction platform of unloading
CN207526083U (en) A kind of detachable overhanging support construction
CN206569938U (en) Roofing crane rood beam underframe
CN203947758U (en) Novel hydraulic automatic climbing discharging platform
CN206750508U (en) A kind of prefabricated wall plate piling bin
CN202658867U (en) Overhanging construction platform
CN205955171U (en) Fall to ground scaffold collet device
CN207844948U (en) A kind of internally climbing tower crane jack up drilling platform
CN204754150U (en) Dish -type node formula scaffold
CN107905379A (en) Totally-enclosed layer construction method in high-rise building Core Walls Structure
CN203769341U (en) Anti-falling grating plate of steel platform
CN208870409U (en) A kind of vertical pump line room external fixer of concrete
CN208054770U (en) A kind of adjustable hoisting balance beam device of light-duty center of gravity
CN205348824U (en) Outer facade safety plain net device of prefabricated construction
CN104675093B (en) Dish-type node type scaffold
CN104947925A (en) Elevator shaft protection operation platform
CN107780644B (en) Operation platform for elevator shaft construction and use method thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151118