CN106088146A - A kind of interim ground-connecting-wall Demolition Construction method - Google Patents

A kind of interim ground-connecting-wall Demolition Construction method Download PDF

Info

Publication number
CN106088146A
CN106088146A CN201610580185.7A CN201610580185A CN106088146A CN 106088146 A CN106088146 A CN 106088146A CN 201610580185 A CN201610580185 A CN 201610580185A CN 106088146 A CN106088146 A CN 106088146A
Authority
CN
China
Prior art keywords
wall
sole plate
interim ground
construction method
soil body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610580185.7A
Other languages
Chinese (zh)
Other versions
CN106088146B (en
Inventor
于海申
裴鸿斌
亓立刚
苏亚武
刘鹏
柯子平
孙加齐
杨红岩
高辉
戚明浩
汤淼
王凯峰
肖大伟
杨晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201610580185.7A priority Critical patent/CN106088146B/en
Publication of CN106088146A publication Critical patent/CN106088146A/en
Application granted granted Critical
Publication of CN106088146B publication Critical patent/CN106088146B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention discloses a kind of interim ground-connecting-wall Demolition Construction method, including step: remove interim ground-connecting-wall in the bottom soil body below sole plate bottom cushion;Backfill described bottom soil body to sole plate bottom cushion;Fill up sole plate bottom cushion;Close sole plate.The present invention uses and will remove in the bottom soil body to sole plate bottom cushion bottom interim ground-connecting-wall, and reduce the sole plate rigidity at the polycrystalline substance connecting wall displacement provisionally by backfill soil, thus reduce the base plate drawing crack that sole plate causes because of differential settlement, while ensureing basis and job safety, ensure that the integrity of sole plate, it is therefore prevented that subsoil water seepage.

Description

A kind of interim ground-connecting-wall Demolition Construction method
Technical field
The present invention relates to a kind of building field, particularly relate to a kind of interim ground-connecting-wall Demolition Construction method.
Background technology
Coastal Soft Deep Foundation Pit has significantly " tau-effect ", and open-assembly time is the longest, and foundation ditch area is the biggest, and foundation ditch becomes Shape amount is the biggest.Therefore the methods that many employing point storehouses are implemented in construction, reduce foundation ditch area, and wherein the interim ground-connecting-wall of many employings enters Row separates.Need to remove interim ground-connecting-wall after interim ground-connecting-wall both sides agent structure goes out foundation ditch.But remove interim ground-connecting-wall Construction method needs science, rationally, on the premise of ensureing deep pit monitor, it is ensured that the integrity of sole plate.Because connecting provisionally The vertical elevation that wall is removed directly determines the water penetration on basis, integrity.If removing to sole plate bottom interim ground-connecting-wall Epithelium, then subsoil water can from the gap of interim ground-connecting-wall and both sides base plate seepage.If interim ground-connecting-wall 21 is removed to basis Base plate 22 bed course 23 times, the most again construction sole plate 22, as it is shown in figure 1, because sole plate 22 is at interim ground-connecting-wall 21 Position is different from the rigidity of other position sole plate bottom solums 24, therefore sole plate can be caused to draw because of differential settlement Split, thus cause subsoil water seepage.
Summary of the invention
The technical problem to be solved is to provide a kind of interim ground-connecting-wall Demolition Construction method, it is possible to effectively reduce Sole plate is connecting the bottom rigidity of wall displacement provisionally, thus reduces the base plate that sole plate causes because of differential settlement and draw Split.
For realizing above-mentioned technique effect, the invention discloses a kind of interim ground-connecting-wall Demolition Construction method, including step:
Remove interim ground-connecting-wall in the bottom soil body below sole plate bottom cushion;
Backfill described bottom soil body to sole plate bottom cushion;
Fill up sole plate bottom cushion;
Close sole plate.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and removes interim ground-connecting-wall at the bottom of sole plate Before in bottom soil body below portion's bed course, also include: remove the interim ground-connecting-wall of each floor the most successively, and removing The beam slab post-cast strip of the interim ground-connecting-wall rear enclosed correspondence floor of each floor.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and described interim ground-connecting-wall was removed to the end, basis 200mm~400mm below plate bottom cushion, forms the refill spaces of the corresponding degree of depth in described bottom soil body.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and also includes before backfilling described bottom soil body Step: waterproof layer is set in described refill spaces.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and described waterproof layer is completely laid on described backfill sky Between and extend to the upper surface of sole plate bottom cushion.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and uses consistent with described bottom soil body intensity The soil body backfill described refill spaces to the lower surface of sole plate bottom cushion.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and when closing sole plate, connects in closing Seam arranges waterproof construction.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and described waterproof construction includes steel plate for sealing water And/or rubber water-proof bar.
Described interim ground-connecting-wall Demolition Construction method is further improved by, and sole plate is base plate of foundation pit.
Due to the fact that and have employed above technical scheme so that it is have the advantages that by interim ground-connecting-wall is torn open Remove in the bottom soil body to sole plate bottom cushion, and reduce sole plate in interim ground-connecting-wall position by backfill soil The rigidity of the polycrystalline substance put, thus reduce the base plate drawing crack that sole plate causes because of differential settlement, ensureing basis and making While industry safety, it is ensured that the integrity of sole plate, it is therefore prevented that subsoil water seepage.
Accompanying drawing explanation
Fig. 1 is Demolition Construction figure bottom conventional interim ground-connecting-wall.
Fig. 2 is the construction process figure of the present invention interim ground-connecting-wall Demolition Construction method.
Fig. 3~6 is Demolition Construction schematic diagram bottom interim ground-connecting-wall in the present invention interim ground-connecting-wall Demolition Construction method.
Fig. 7~14 is that in the present invention interim ground-connecting-wall Demolition Construction method, interim ground-connecting-wall is removed above bottom base panel Construction schematic diagram.
Detailed description of the invention
Below in conjunction with the accompanying drawings and detailed description of the invention the present invention is further detailed explanation.
First, refering to shown in Fig. 2~6, a kind of interim ground-connecting-wall Demolition Construction method of the present invention mainly includes construction procedure:
S001: remove in the bottom soil body 14 below interim ground-connecting-wall 11 to sole plate 12 bottom cushion 13, such as Fig. 3 institute Show;
S002: backfill bottom soil body is to sole plate 12 bottom cushion 13, as shown in Figure 4;
S003: fill up sole plate 12 bottom cushion 13, as shown in Figure 5;
S004: close sole plate 12, as shown in Figure 6.
Wherein, the bottom of interim ground-connecting-wall 11 the most dismountable to about 200mm below sole plate 12 bottom cushion 13~ 400mm, preferably 300mm (through repeatedly Check computations, it is contemplated that efficiency of construction, engine request and economic benefit, show this thickness Can reach preferable construction effect), now, in the bottom soil body 14 below bed course 13, form the refill spaces of the corresponding degree of depth 141。
In step S002: before backfill bottom soil body, further comprise the steps of: the refill spaces 141 formed in bottom soil body 14 Inside arranging waterproof layer (not showing waterproof layer in figure), this waterproof layer can completely be laid on refill spaces 141 and extend to sole plate 12 The upper surface of bottom cushion 13, prevents bed course 13 seepage.
When backfilling the refill spaces 141 of bottom soil body 14, the soil body consistent with bottom soil body 14 intensity is generally used to enter Row backfill is the most pragmatic, and the backfill soil body is to the lower surface of sole plate 12 bottom cushion 13, to guarantee the sole plate after backfilling The rigidity of polycrystalline substance consistent, after preventing ground-connecting-wall from removing, sole plate causes differential settlement because bottom rigidity is different, Thus cause sole plate drawing crack, the problem of subsoil water seepage.
Closing in step S004: when closing sole plate 12, between sole plate and the former sole plate of new construction Arranging waterproof construction in seam, this waterproof construction can include steel plate for sealing water and/or rubber water-proof bar, in the present embodiment, simultaneously Have employed steel plate for sealing water 121 and rubber water-proof bar 122, be separately positioned between sole plate and the former sole plate of new construction In closure seam, to avoid subsoil water seepage at closure seam, waterproof effect is preferable.
A kind of interim ground-connecting-wall Demolition Construction method of the present invention is mainly by removing interim ground-connecting-wall at the bottom of sole plate In bottom soil body below portion's bed course, and reduce sole plate by backfill soil and connecting the polycrystalline substance of wall displacement provisionally Rigidity, thus reduce the base plate drawing crack that sole plate causes because of differential settlement, while ensureing basis and job safety, protect Demonstrate,prove the integrity of sole plate, it is therefore prevented that subsoil water seepage.
A kind of interim ground-connecting-wall Demolition Construction method of the present invention is applicable to the construction of coastal Soft Deep Foundation Pit.Now, basis Base plate is base plate of foundation pit, and the bottom of base plate of foundation pit is provided with bed course, is bottom soil body below bed course, and the bottom of interim ground-connecting-wall is deeply In bottom soil body, after interim ground-connecting-wall both sides agent structure goes out foundation ditch, need to remove interim ground-connecting-wall, repair base plate of foundation pit simultaneously With each floor beam slab.
Below in conjunction with the present invention interim ground-connecting-wall Demolition Construction method, enumerate the base of base plate of foundation pit room located underground five floor Cheat the overall pulling down arrangement and method for construction of interim ground-connecting-wall, shown in Fig. 7~14, specifically include following construction procedure:
The first step: remove the interim ground-connecting-wall 11 of basement one layer (B1), as shown in Figure 7 and Figure 8;
Second step: close basement one level beam, floor slab back casting band, remove the interim ground-connecting-wall of subcellar 11 subsequently, As shown in Figure 9 and Figure 10;
3rd step: close basement two level beam, floor slab back casting band, remove the interim ground-connecting-wall 11 of basement three layers subsequently, As is illustrated by figs. 11 and 12;
4th step: close basement tri-layer beam, floor slab back casting band, remove the interim ground-connecting-wall 11 of basement four layers subsequently, As shown in Figure 13 and Figure 14;
5th step: interim ground-connecting-wall 11 removes the sole plate 12 bed course 13 bottom 300mm to foundation ditch, backfill element soil also rams Real, then construction bottom cushion improve waterproof layer, steel plate for sealing water 121, rubber water-proof bar 122, finally close sole plate 12, Complete the dismounting of interim ground-connecting-wall, as illustrated in figures 3-6.
The present invention interim ground-connecting-wall Demolition Construction method first uses removes connecting provisionally of each floor the most successively Wall, and in the beam slab post-cast strip of the interim ground-connecting-wall rear enclosed correspondence floor removing each floor;Then, sole plate is being removed During the interim ground-connecting-wall of position, use and will remove the bottom soil body to sole plate bottom cushion bottom interim ground-connecting-wall In, and reduce the sole plate rigidity at the polycrystalline substance connecting wall displacement provisionally by backfill soil, thus reduce the end, basis The base plate drawing crack that plate causes because of differential settlement, while ensureing basis and job safety, it is ensured that sole plate complete Property, it is therefore prevented that subsoil water seepage.
Being described in detail the present invention above in association with drawings and Examples, those skilled in the art can basis The present invention is made many variations example by described above.Thus, some details in embodiment should not constitute limitation of the invention, The present invention by the scope that defines using appended claims as protection scope of the present invention.

Claims (9)

1. an interim ground-connecting-wall Demolition Construction method, it is characterised in that include step:
Remove interim ground-connecting-wall in the bottom soil body below sole plate bottom cushion;
Backfill described bottom soil body to sole plate bottom cushion;
Fill up sole plate bottom cushion;
Close sole plate.
2. interim ground-connecting-wall Demolition Construction method as claimed in claim 1, it is characterised in that remove interim ground-connecting-wall to basis Before in bottom soil body below base plate bottom cushion, also include: remove the interim ground-connecting-wall of each floor the most successively, and Beam slab post-cast strip at the interim ground-connecting-wall rear enclosed correspondence floor removing each floor.
3. interim ground-connecting-wall Demolition Construction method as claimed in claim 1, it is characterised in that: described interim ground-connecting-wall is removed extremely 200mm~400mm below sole plate bottom cushion, forms the refill spaces of the corresponding degree of depth in described bottom soil body.
4. interim ground-connecting-wall Demolition Construction method as claimed in claim 3, it is characterised in that before backfilling described bottom soil body Further comprise the steps of: and waterproof layer is set in described refill spaces.
5. interim ground-connecting-wall Demolition Construction method as claimed in claim 4, it is characterised in that: described waterproof layer is completely laid on described Refill spaces also extends to the upper surface of sole plate bottom cushion.
6. interim ground-connecting-wall Demolition Construction method as claimed in claim 3, it is characterised in that: use strong with described bottom soil body Spend the consistent soil body and backfill described refill spaces to the lower surface of sole plate bottom cushion.
7. interim ground-connecting-wall Demolition Construction method as claimed in claim 1, it is characterised in that: when closing sole plate, in Closure seam arranges waterproof construction.
8. interim ground-connecting-wall Demolition Construction method as claimed in claim 7, it is characterised in that: described waterproof construction includes sealing Steel plate and/or rubber water-proof bar.
9. interim ground-connecting-wall Demolition Construction method as claimed in claim 1, it is characterised in that: described sole plate is at the bottom of foundation ditch Plate.
CN201610580185.7A 2016-07-22 2016-07-22 A kind of interim ground-connecting-wall Demolition Construction method Active CN106088146B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610580185.7A CN106088146B (en) 2016-07-22 2016-07-22 A kind of interim ground-connecting-wall Demolition Construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610580185.7A CN106088146B (en) 2016-07-22 2016-07-22 A kind of interim ground-connecting-wall Demolition Construction method

Publications (2)

Publication Number Publication Date
CN106088146A true CN106088146A (en) 2016-11-09
CN106088146B CN106088146B (en) 2018-12-18

Family

ID=57449062

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610580185.7A Active CN106088146B (en) 2016-07-22 2016-07-22 A kind of interim ground-connecting-wall Demolition Construction method

Country Status (1)

Country Link
CN (1) CN106088146B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115404904A (en) * 2022-06-23 2022-11-29 中国建筑第八工程局有限公司 Underground diaphragm wall chamber-divided type dismantling construction method adjacent to subway foundation pit

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100032361A (en) * 2007-06-22 2010-03-25 덴끼 가가꾸 고교 가부시키가이샤 Method for grinding semiconductor wafer, and resin composition and protective sheet used for the method
JP2012211439A (en) * 2011-03-30 2012-11-01 Taisei Corp Construction method for underground structure, and pile head structure of temporary intermediate pile
CN105002913A (en) * 2015-08-06 2015-10-28 中铁隆工程集团有限公司 Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100032361A (en) * 2007-06-22 2010-03-25 덴끼 가가꾸 고교 가부시키가이샤 Method for grinding semiconductor wafer, and resin composition and protective sheet used for the method
JP2012211439A (en) * 2011-03-30 2012-11-01 Taisei Corp Construction method for underground structure, and pile head structure of temporary intermediate pile
CN105002913A (en) * 2015-08-06 2015-10-28 中铁隆工程集团有限公司 Strongly-permeable stratum deep foundation pit bottom sealing water stopping structure and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐伟等: "《建筑工程施工》", 31 August 2013 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115404904A (en) * 2022-06-23 2022-11-29 中国建筑第八工程局有限公司 Underground diaphragm wall chamber-divided type dismantling construction method adjacent to subway foundation pit

Also Published As

Publication number Publication date
CN106088146B (en) 2018-12-18

Similar Documents

Publication Publication Date Title
CN104652418B (en) Diaphragm wall underground utilities position construction method
CN103410175B (en) A kind of water seepage control construction method for karst water-rich geological underground structure waterproof construction
CN105220713B (en) The waterproof construction of outer wall of basement subsiding crack
CN107119691A (en) One kind is applied to the square deep basal pit of the high pressure-bearing of rich water sand gravel layer and its excavation method
CN104404974A (en) High-pressure-bearing water and thick sand and pebble formation deep foundation pit grouting bottom-sealing structure and construction technology thereof
CN104594297B (en) A kind of double face slab rock-fill dams and construction method thereof
CN106088146B (en) A kind of interim ground-connecting-wall Demolition Construction method
CN104314048B (en) Manufacturing and construction method of air bag type concrete engineering deformation joint water stop type cavity die
CN106088591A (en) With protruding concrete works movement joint vertical sealing swaging die
CN102787608B (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN204570652U (en) A kind of karst strata rock-steady structure
CN204298860U (en) Lid digs the inverse side wall construction joint waterproofing node that does and constructs
CN104878772A (en) Treating method for foundation slab leakage of deep foundation pit
CN105780938B (en) A kind of Super High core tube end plate vertical construction joint construction method
CN105672364A (en) Post-cast strip of basement floor
CN106522166A (en) Construction method for concrete engineering cavity mould with bulges and reinforcing fibers
CN104328802B (en) A kind of concrete works swaging die skeleton and manufacture method thereof
CN208533543U (en) Improve the structure and foundation pit SMW supporting construction of foundation pit side-wall waterproof performance
CN107419811A (en) The method and its structure of basement bottom board support pile and spilled water hole waterproofing and leakage-stopping
CN108661669B (en) It is a kind of suitable for Shallow-buried section and under wear the method for tunnel construction of shallow-buried water-rich section
CN205604304U (en) Leakage structure is prevented to basement reverse construction method shear force wall
CN207376767U (en) A kind of inlet channel structure
CN206385547U (en) A kind of prefabricated pile for pattern foundation pit supporting structure is combined barrier wall structure
CN204510231U (en) A kind of Circular Pit is inverse makes retaining wall
CN205557573U (en) Underground structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant