CN106088143A - A kind of construction method for pipe gallery drainage pipeline buttress - Google Patents

A kind of construction method for pipe gallery drainage pipeline buttress Download PDF

Info

Publication number
CN106088143A
CN106088143A CN201610664524.XA CN201610664524A CN106088143A CN 106088143 A CN106088143 A CN 106088143A CN 201610664524 A CN201610664524 A CN 201610664524A CN 106088143 A CN106088143 A CN 106088143A
Authority
CN
China
Prior art keywords
steel
buttress
chute
drainage pipeline
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610664524.XA
Other languages
Chinese (zh)
Other versions
CN106088143B (en
Inventor
李玉磊
许大鹏
高宇
陈帅华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201610664524.XA priority Critical patent/CN106088143B/en
Publication of CN106088143A publication Critical patent/CN106088143A/en
Application granted granted Critical
Publication of CN106088143B publication Critical patent/CN106088143B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/46Foundations for supply conduits or other canals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

It is an object of the present invention to provide a kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that described construction method comprises the following steps: A, making concrete buttress, reserved attachment structure on concrete buttress;B, utilize described attachment structure rational height adjusting means, and the steel structure support being used for fixing drainage pipeline is fixed on this arrangement for adjusting height;C, utilize arrangement for adjusting height that steel structure support is adjusted to the setting height(from bottom) preset, use non-shrinkage concrete to fill between steel structure support and concrete buttress closely knit.The present invention is by the setting height(from bottom) between regulation I-steel and steel construction chute, it is possible to resolve multiple buttress construction reference, construction error bring constructional difficulties, improves the safety of pipeline.

Description

A kind of construction method for pipe gallery drainage pipeline buttress
Technical field
The present invention relates to the technical field of the buttress of pipe gallery drainage pipeline, specifically one is for pipe gallery The construction method of drainage pipeline buttress.
Background technology
In the pipe gallery including drainage pipeline in, drainage pipeline is not fixed relative to position with piping lane base plate, and buttress is arranged Precision requires height, and is difficulty with the standardized construction of buttress or support.Concrete buttress construction error is relatively big, different size Steel structure support there is the problems such as built-in fitting, processing and fixed precision.Multiple buttress construction reference, construction error bring construction Difficulty, may cause pipeline discontinuity simultaneously, affect the safe operation of pipeline.
Summary of the invention
It is an object of the present invention to provide a kind of construction method for pipe gallery drainage pipeline buttress, at concrete buttress On, by arranging I-steel, steel construction chute, it is achieved standardization steel structure support scalable, thus meet pipe gallery draining Pipeline buttress requirement is set.
To achieve these goals, the technical scheme is that a kind of executing for pipe gallery drainage pipeline buttress Work method, it is characterised in that described construction method comprises the following steps:
A, making concrete buttress, reserved attachment structure on concrete buttress;
B, utilize described attachment structure rational height adjusting means, and the steel structure support being used for fixing drainage pipeline is fixed on On this arrangement for adjusting height;
C, utilize arrangement for adjusting height that steel structure support is adjusted to the setting height(from bottom) preset, steel structure support and concrete buttress Between use non-shrinkage concrete fill closely knit.
According to a preferred embodiment of the invention, in step A, on concrete buttress, reserved attachment structure is concrete buttress Upper reserved back-grouting hole.
According to a preferred embodiment of the invention, in step B, arrangement for adjusting height includes I-steel and matches with I-steel Close the steel construction chute arranged, in back-grouting hole reserved on concrete buttress, I-steel is set, and carries out concrete secondary Grouting is fixing, and steel structure support and the steel construction chute arranged that matches with I-steel weld mutually.
According to a preferred embodiment of the invention, concrete buttress has been arranged side by side two back-grouting holes, each secondary Arranging an I-steel in grout hole, steel structure support both sides are all welded with steel construction chute, and every I-steel and steel construction prop up The steel construction chute of frame side connects.
According to a preferred embodiment of the invention, described I-steel includes the edge of a wing, inner side, outer side wing edge and connects inboard wing Edge and the web of outer side wing edge, described steel construction chute includes the substrate welded with steel structure support side, and the two ends of substrate set Being equipped with chute, inside described I-steel, the chute at described steel construction chute two ends is inserted at the two ends on the edge of a wing respectively.
According to a preferred embodiment of the invention, steel construction chute is provided with bolt hole, steel construction chute and I-steel it Between be bolted.
According to a preferred embodiment of the invention, concrete buttress is connected with pipe gallery base plate by embedded bar.
The present invention is on concrete buttress, by arranging I-steel, steel construction chute, it is achieved standardization steel structure support can Regulation, thus meet pipe gallery drainage pipeline buttress requirement is set.The present invention is by regulation I-steel and steel construction chute Between setting height(from bottom), it is possible to resolve multiple buttress construction reference, construction error bring constructional difficulties, improve the safety of pipeline.
Accompanying drawing explanation
Fig. 1 is the structural representation of present example.
Fig. 2 is I-I profile in Fig. 1.
Fig. 3 is II-II profile in Fig. 1.
Detailed description of the invention
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
The present invention is a kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that described construction method Comprise the following steps: A, making concrete buttress 1, reserved attachment structure on concrete buttress 1;B, utilize described attachment structure Rational height adjusting means, and the steel structure support 5 being used for fixing drainage pipeline is fixed on this arrangement for adjusting height;C, profit With arrangement for adjusting height, steel structure support 5 is adjusted to the setting height(from bottom) preset, between steel structure support 5 and concrete buttress 1 Non-shrinkage concrete 8 is used to fill closely knit.
According to a preferred embodiment of the invention, on concrete buttress 1, reserved attachment structure is reserved on concrete buttress Back-grouting hole 2, arrangement for adjusting height includes I-steel 3 and the steel construction chute 4 arranged that matches with I-steel 3, coagulation I-steel 3 is set in back-grouting hole 2 reserved on soil buttress 1, and carries out concrete seven back-grouting and fix, steel structure support 5 And the steel construction chute 4 phase welding arranged that matches with I-steel 3.
Fig. 1, Fig. 2 and Fig. 3 show by the present invention make for pipe gallery drainage pipeline buttress.Concrete buttress 1 is connected with pipe gallery base plate 11 by embedded bar, reserved two back-grouting holes 2 on concrete buttress 1;Each secondary fills Slurry hole 2 is fixed an I-steel 3, and uses non-shrinkage concrete 7 to fill real;Steel construction chute 4 and steel knot with bolt hole Structure support 5 welds;I-steel 3 both sides flange plate is inserted in the chute at steel construction chute 4 two ends, adjusts size B with satisfied row Waterpipe designed elevation, uses fixing bolt 6 to tighten fixing between I-steel 3 and steel construction chute 4;Steel structure support 5 He Non-shrinkage concrete 8 is used to fill closely knit between concrete buttress 1;After non-shrinkage concrete Final 8 degree is formed, utilize fixing steel band 9 fix a drainpipe 10.Arranging two boss on steel structure support 5, arrange support seat between two boss, drainage pipeline 10 is put Putting in the bearing between two boss, fixing steel band 9 is wound on the outside of drainage pipeline 10, and the two ends of fixing steel band 9 are fixed On the boss of steel structure support 5.
According to a preferred embodiment of the invention, described I-shaped 3 ladle includes the edge of a wing, inner side, outer side wing edge and connects inboard wing Edge and the web of outer side wing edge, described steel construction chute 4 includes the substrate welded with steel structure support side, the two ends court of substrate Being provided with chute in outward direction, inside described I-steel, the cunning at described steel construction chute two ends is inserted at the two ends on the edge of a wing respectively Groove.
In figure, A is the height of concrete buttress 1, and B is the height bottom drainage pipeline 10 to concrete buttress 1 top, and C is To the height of pipe gallery base plate 11 bottom drainage pipeline 10.
Above content is to combine concrete preferred implementation further description made for the present invention, it is impossible to assert The present invention is embodied as being confined to these explanations above-mentioned.For general technical staff of the technical field of the invention, Without departing from the inventive concept of the premise, it is also possible to make some simple deduction or replace, all should be considered as belonging to the present invention Protection domain.

Claims (7)

1. the construction method for pipe gallery drainage pipeline buttress, it is characterised in that described construction method includes following step Rapid:
A, making concrete buttress, reserved attachment structure on concrete buttress;
B, utilize described attachment structure rational height adjusting means, and the steel structure support being used for fixing drainage pipeline is fixed on On this arrangement for adjusting height;
C, utilize arrangement for adjusting height that steel structure support is adjusted to the setting height(from bottom) preset, steel structure support and concrete buttress Between use non-shrinkage concrete fill closely knit.
A kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that: step In A, on concrete buttress, reserved attachment structure is reserved back-grouting hole on concrete buttress.
A kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that: step In B, arrangement for adjusting height includes I-steel and the steel construction chute arranged that matches with I-steel, reserved on concrete buttress Back-grouting hole in I-steel is set, and it is fixing to carry out concrete secondary grouting, steel structure support and matching with I-steel The steel construction chute arranged welds mutually.
A kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that: coagulation It is arranged side by side two back-grouting holes on soil buttress, an I-steel, steel structure support two have been set in each back-grouting hole Side is all welded with steel construction chute, and the steel construction chute of every I-steel and steel structure support side connects.
A kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that: described I-steel includes the edge of a wing and the web of outer side wing edge inside the edge of a wing, inner side, outer side wing edge and connection, described steel construction chute bag Including the substrate welded with steel structure support side, the two ends of substrate are provided with chute, and inside described I-steel, the two ends on the edge of a wing are divided Do not insert the chute at described steel construction chute two ends.
A kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that: steel is tied It is provided with bolt hole on structure chute, is bolted between steel construction chute and I-steel.
A kind of construction method for pipe gallery drainage pipeline buttress, it is characterised in that: coagulation Soil buttress is connected with pipe gallery base plate by embedded bar.
CN201610664524.XA 2016-08-15 2016-08-15 Construction method for comprehensive pipe rack drainage pipeline buttress Active CN106088143B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610664524.XA CN106088143B (en) 2016-08-15 2016-08-15 Construction method for comprehensive pipe rack drainage pipeline buttress

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610664524.XA CN106088143B (en) 2016-08-15 2016-08-15 Construction method for comprehensive pipe rack drainage pipeline buttress

Publications (2)

Publication Number Publication Date
CN106088143A true CN106088143A (en) 2016-11-09
CN106088143B CN106088143B (en) 2024-01-12

Family

ID=57456505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610664524.XA Active CN106088143B (en) 2016-08-15 2016-08-15 Construction method for comprehensive pipe rack drainage pipeline buttress

Country Status (1)

Country Link
CN (1) CN106088143B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740439A (en) * 2017-10-11 2018-02-27 江苏士林电气设备有限公司 A kind of piping lane support with regulatory function
CN114396074A (en) * 2021-12-22 2022-04-26 华北冶建工程建设有限公司 Cast-in-situ formwork for pipe gallery buttress

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100840191B1 (en) * 2007-12-24 2008-06-23 노윤근 The bridge section expansion method of construction for which steel synthetic concrete steel pipe and this were used
CN103526698A (en) * 2013-11-07 2014-01-22 天津城建大学 Cast-in-cantilever construction 0# block concrete supporting system and construction method
CN104452810A (en) * 2014-11-27 2015-03-25 中国二十冶集团有限公司 Device and method for installing pipeline supporting pier in pipe ditch
CN204626453U (en) * 2015-05-27 2015-09-09 中国五冶集团有限公司 The supporting device of pipeline in Urban Underground pipe gallery
CN204728213U (en) * 2015-05-26 2015-10-28 中铁二十二局集团第三工程有限公司 A kind of next-door neighbour and on across both wired combined type H profile steel cast-in-place box beam bracket
CN105735351A (en) * 2016-04-04 2016-07-06 深圳华瀚城市综合管廊技术研究开发有限公司 Pipe rack installation base structure, comprehensive pipe rack and installation and construction method of comprehensive pipe rack

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100840191B1 (en) * 2007-12-24 2008-06-23 노윤근 The bridge section expansion method of construction for which steel synthetic concrete steel pipe and this were used
CN103526698A (en) * 2013-11-07 2014-01-22 天津城建大学 Cast-in-cantilever construction 0# block concrete supporting system and construction method
CN104452810A (en) * 2014-11-27 2015-03-25 中国二十冶集团有限公司 Device and method for installing pipeline supporting pier in pipe ditch
CN204728213U (en) * 2015-05-26 2015-10-28 中铁二十二局集团第三工程有限公司 A kind of next-door neighbour and on across both wired combined type H profile steel cast-in-place box beam bracket
CN204626453U (en) * 2015-05-27 2015-09-09 中国五冶集团有限公司 The supporting device of pipeline in Urban Underground pipe gallery
CN105735351A (en) * 2016-04-04 2016-07-06 深圳华瀚城市综合管廊技术研究开发有限公司 Pipe rack installation base structure, comprehensive pipe rack and installation and construction method of comprehensive pipe rack

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740439A (en) * 2017-10-11 2018-02-27 江苏士林电气设备有限公司 A kind of piping lane support with regulatory function
CN114396074A (en) * 2021-12-22 2022-04-26 华北冶建工程建设有限公司 Cast-in-situ formwork for pipe gallery buttress

Also Published As

Publication number Publication date
CN106088143B (en) 2024-01-12

Similar Documents

Publication Publication Date Title
CN106168054B (en) Connecting structure and its construction method with dry shaped connecting piece precast shear wall plate
CN103370484B (en) Installation foundation
CN105484157B (en) Positioning device and construction method of capping beam of prefabricated bridge
CN107022947B (en) A kind of pre-buried fashioned iron carvel joint bolt type connection locator of the prefabricated arch rib of concrete segment and its construction method
CN106193253A (en) A kind of construction method of pipe gallery drainage pipeline
CN106906955A (en) A kind of integral prefabricated reinforcing bar web frame of shear wall and its construction method
CN107060075A (en) A kind of supporting construction connected for fabricated construction beam slab and installation method
CN105350454B (en) Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge
CN105544587B (en) The construction method of tower crane is fixed using combined type foundation for tower crane
CN106088143A (en) A kind of construction method for pipe gallery drainage pipeline buttress
CN106436972A (en) Prefabricated PCFexternal wall board with window frame and installing method thereof
CN110820952A (en) Steel structure column installation rapid positioning device and construction method
CN106245526A (en) The splicing structure of mining under railways protecting wall, straight wall and shield and construction method
CN110409670A (en) Monolith large form shear wall and construction method
CN103243649A (en) System and method for quickly installing and positioning cable saddle
CN106836829B (en) A kind of mounting structure and its installation method of ring crane corbel
CN103711199B (en) Method and structure for processing construction joints at large-section beam and column joints
CN108978870A (en) Fold-line-shaped girder steel and concrete combined structure construction method
CN107905554A (en) Fabricated shear wall superimposed sheet connecting integration support system and installation method
CN205975663U (en) A buttress adjusting device for utility tunnel drainage pipe
CN206070561U (en) A kind of buttress for pipe gallery drainage pipeline
CN106192608A (en) A kind of coke oven coke-pusher machine track foundation construction method
CN206034199U (en) Coke oven coke pusher rail foundation structure
CN206946064U (en) The installation supporting structure of optical cable in piping lane
CN206467578U (en) Bridge construction bracket bearing assembly

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant