CN106087978A - Pile for prestressed pipe - Google Patents

Pile for prestressed pipe Download PDF

Info

Publication number
CN106087978A
CN106087978A CN201610710891.9A CN201610710891A CN106087978A CN 106087978 A CN106087978 A CN 106087978A CN 201610710891 A CN201610710891 A CN 201610710891A CN 106087978 A CN106087978 A CN 106087978A
Authority
CN
China
Prior art keywords
pile
pipe
prestressed pipe
guide plate
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610710891.9A
Other languages
Chinese (zh)
Inventor
许陈菲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610710891.9A priority Critical patent/CN106087978A/en
Publication of CN106087978A publication Critical patent/CN106087978A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to the technical field of rig, disclose pile for prestressed pipe, pile for prestressed pipe includes pile body, the pipe pile joint being connected to pile body lower end and is connected to the pile tube pile top of pipe pile joint lower end, the lower end of described pipe pile joint connects multiple guide plate, and multiple described guide plates are adjacently positioned around described pile tube pile top periphery.Compared with prior art, the pile for prestressed pipe that the present invention provides is executed, the lower end of its pipe pile joint, multiple guide plate is set, the plurality of guide plate is looped around the periphery of pile tube pile top, so, during pile for prestressed pipe pile, guide plate can play preferable guide effect, avoid the occurrence of hole deviation phenomenon, and the stress born when can balance pile for prestressed pipe such as soil end, offset part kinetic energy, effectively reduce broken pile probability, increase formation of pile, the pile for prestressed pipe penetration capacity to soil layer, pile for prestressed pipe is made to be relatively easy to through Backfilled Stone Layer, it is greatly improved efficiency of construction.

Description

Pile for prestressed pipe
Technical field
The present invention relates to the technical field of rig, particularly relate to pile for prestressed pipe.
Background technology
Along with the needs of coastal cities development, large-scale marine reclamation land engineering can be carried out, large quantities of superelevation, super Deep building also can be rised sheer from level ground at reclaimation area, and in these reclaimation area territories, (diameter is at 800mm for major diameter ultra-deep pile for prestressed pipe Above, hole depth is more than 50m) use more and more extensive.Pile for prestressed pipe has that pile quality is good, bearing capacity of single pile is high, executes Work speed is fast, the duration is short, low cost and other advantages, and without mud off in pore forming process, it is to avoid produce a large amount of mud waste residue, Realize green construction.
In prior art, the construction method of pile for prestressed pipe mainly has hammering method, static pressure method etc., as shown in Fig. 1, in advance The principle schematic of stress pile tube 1 construction method.During pile for prestressed pipe 1 pile, provide external force by the mode such as hammering, static pressure F, this external force F acts on the upper end of pile for prestressed pipe 1 pile body, in the lower end of pile for prestressed pipe 1 pile body, is provided with cross Steel pile tip 11 is under the effect of external force F, and this steel pile tip 11 is gradually clamp-oned in soil layer, sequentially through miscellaneous fill layer 6, Backfilled Stone Layer 3 Eluvium 4, and eventually fall on basement rock 5, complete the effect of pile for prestressed pipe 2 pile.
In existing reclaimation area, widely distributed due to deep Backfilled Stone Layer 3, and by the unordered landfill of Backfilled Stone Layer 3 with fill out The impact of the lumpiness (lumpiness particle diameter 300mm~2000mm) not of uniform size of stone, major diameter of often constructing in reclaimation area During (φ 800mm) pile for prestressed pipe 1, it is frequently encountered pile for prestressed pipe 1 and is difficult to the difficulty through deep Backfilled Stone Layer 3, because of This, the lower end of pile for prestressed pipe 1 is difficult to reach on basement rock 5, causes pile failure, or needs to consume construction for a long time, Could realize pile, efficiency of construction is low, is significantly difficult to the delayed compaction cycle.
Summary of the invention
It is an object of the invention to provide pile for prestressed pipe, it is intended to solve, in pre-stress construction of the prior art, to exist The problem that pile for prestressed pipe is difficult to cause pile failure through Backfilled Stone Layer, efficiency of construction is low.
The present invention is achieved in that pile for prestressed pipe, pile for prestressed pipe include pile body, are connected to the pile tube of pile body lower end Joint and be connected to the pile tube pile top of pipe pile joint lower end, the lower end of described pipe pile joint connects multiple guide plate, multiple Described guide plate is adjacently positioned around described pile tube pile top periphery, and the lower end of described guide plate is tip, described pipe pile joint Sidewall is provided with two-way spilled water hole, the sidewall of described pile body is provided with two-way spilled water hole.
Further, the inclined shape in outside of described guide plate lower end, described tip is formed in lower end.
Further, the both sides of described guide plate lower end inclined shape respectively, and described tip it is crossed to form in lower end.
Further, the inner side of described guide plate is connected to the periphery of described pile tube pile top.
Compared with prior art, the pile for prestressed pipe that the present invention provides is executed, and the lower end of its pipe pile joint arranges multiple guiding Plate, the plurality of guide plate is looped around the periphery of pile tube pile top, and so, during pile for prestressed pipe pile, guide plate can rise To preferable guide effect, it is to avoid hole deviation phenomenon, and the stress born when can balance pile for prestressed pipe such as soil end occur, offsets Part kinetic energy, effectively reduces broken pile probability, increases formation of pile, the pile for prestressed pipe penetration capacity to soil layer so that prestressing force Pile tube is relatively easy to, through Backfilled Stone Layer, be greatly improved efficiency of construction.
Accompanying drawing explanation
Fig. 1 is the principle schematic of prestressing pipe pile construction process of the prior art;
Fig. 2 is that the down-hole hammer that provides of the embodiment of the present invention and full casing spud in the structural representation of main borehole;
Fig. 3 is the structural representation forming back-up sand hole in the reclaimation area that the embodiment of the present invention provides;
Fig. 4 is three secondary schematic top plan view holed with main borehole that the embodiment of the present invention provides;
Fig. 5 is pile for prestressed pipe structural representation of pile in back-up sand hole that the embodiment of the present invention provides;
Fig. 6 is the transverse cross sectional schematic diagram of the pile for prestressed pipe that the embodiment of the present invention provides;
Fig. 7 is the cut-away illustration of the pipe pile joint that the embodiment of the present invention provides;
Fig. 8 is the pile body schematic front view with pipe pile joint of embodiment of the present invention offer.
Detailed description of the invention
In order to make the purpose of the present invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, right The present invention is further elaborated.Should be appreciated that specific embodiment described herein only in order to explain the present invention, and It is not used in the restriction present invention.
Below in conjunction with specific embodiment, the realization of the present invention is described in detail.
With reference to shown in Fig. 2~8, for the preferred embodiment of present invention offer.
The present embodiment, pile for prestressed pipe 2 includes the pile body 27 of long tubular, is connected to the pipe pile joint of pile body 27 lower end 28 and be connected to the pile tube pile top 26 of pipe pile joint 28 lower end, connecting in the lower end of this pipe pile joint 28 has multiple guide plate 25, the plurality of guide plate 25 extends along the length direction of pile body 27, and in adjacently positioned around pile tube pile top 26 periphery.
In pipe pile joint 28 lower end, by arranging multiple guide plate 25, during the pile of pile for prestressed pipe 2, lead Preferable guide effect can be played, it is to avoid hole deviation phenomenon occurs to plate 25, and when can balance pile for prestressed pipe 2 such as soil end The stress born, offsets part kinetic energy, effectively reduces broken pile probability, increases formation of pile, and soil layer is worn by pile for prestressed pipe 2 Ability thoroughly.
Specifically, the inner side of guide plate 25 is connected on the periphery of pile tube pile top 26, so, strengthens its steadiness, makes Obtain its guide effect more preferable, and there is more preferably penetration capacity.
In the present embodiment, the lower end of guide plate 25 is in most advanced and sophisticated 29, and so, it guides and penetration capacity is higher.
Specifically, the inclined shape of lower end outside of guide plate 25, and above-mentioned tip 29 is formed in lower end, certainly, make For other embodiments, the both sides of guide plate 25 lower end are distinguished inclined shape, and are crossed to form above-mentioned tip 29.
In the present embodiment, the sidewall of pipe pile joint 28 is provided with two-way spilled water hole 281, so, during pile, and profit With this two-way spilled water hole 281, outside the water in pile for prestressed pipe 2 can being excreted, thus effectively eliminate the shadow of buoyancy force of underground water Ring, and the airtight air within pile for prestressed pipe 2 can be got rid of, prevent the phenomenon of booster.
It addition, also be provided with above-mentioned two-way spilled water hole 281 on the sidewall of pile body 27, it can play above-mentioned technology Effect.
Utilize above-mentioned pile for prestressed pipe 2 when reclaimation area carries out pile, the soil layer of reclaimation area, from top to bottom, respectively It is on miscellaneous fill layer 6, Backfilled Stone Layer 3, eluvium 4 and basement rock 5, uses pile for prestressed pipe 2 construction method for by prestressing force The lower end of pile tube 2 is plugged in basement rock 5, it is achieved the effect of pile.
Pile for prestressed pipe 2 construction method, its concrete operation step is as follows:
1), treat the position of pile at reclaimation area, use down-hole hammer 22 to offer main borehole at reclaimation area, and utilize full casing 21 Following down-hole hammer 22 to creep into, namely full casing 21 is also plugged in this main borehole, and along with down-hole hammer 22 the most down Mobile, this full casing 21 is constantly plugging down, until down-hole hammer 22 is through Backfilled Stone Layer 3, the most full casing 21 also passes through In Backfilled Stone Layer 3, i.e. main borehole passes through Backfilled Stone Layer 3;
2), down-hole hammer 22 is transferred to, and in full casing 21, fills sand, fill to the upper surface of reclaimation area until sand, Extract full casing 21 again, thus, main borehole forms back-up sand hole 23, and Backfilled Stone Layer 3 is passed through in this back-up sand hole 23;
3) hammering method or static pressure method etc., is utilized to apply external force in pile for prestressed pipe 2 upper end so that pile for prestressed pipe 2 is through filling out Sand hole 23, and lower end is embedded in the basement rock 5 below Backfilled Stone Layer 3, completes the operation of whole pile for prestressed pipe 2 pile.
In pile for prestressed pipe 2 construction method of above-mentioned offer, it has the advantage that
1), speed of fulfiling hole on reclaimation area, treat the position of pile soon, first with Major diameter downhole hammer 23 and coordinate full casing 21 with Pipe creeps into perforate, and main borehole passes through Backfilled Stone Layer 3;Rise before pulling out full casing 21, backfill main borehole with sand, upper by position, each hole Portion's Backfilled Stone Layer 3 soil body is replaced into sand.Subsequently, pile tube squeezed into continuously by recycling hammer stake machine etc., pile tube can be made to penetrate easily and rockfill Layer 3, efficiency of construction is substantially improved.
2), construction cost is low, the duration is short, draws hole technology owing to have employed down-hole hammer 22, and speed of application is fast, and unit is comprehensive Efficiency is high, and mechanical execution cost is relatively low.With use impact draw hole use mud off technique, decrease mud usage amount and The outer freight volume of useless slurry waste residue, reduces construction cost, improves environmental benefit.
3), place cleaning, field management simplify
It is mainly manifested in following aspect: construction does not use mud to circulate, and site operation environment is greatly improved, and does not deposits In the outward transport of useless slurry waste residue and difficult treatment, greatly reducing the daily management work such as waste mud storage, outward transport, management link obtains To simplifying greatly.
In step 3) in, back-up sand hole 23 is squeezed into pile for prestressed pipe 2, in order to ensure in the back-up sand hole 23 formed All Backfilled Stone Layers 3 are replaced by sand, in the present embodiment, in step 1) before 2, in treating that the axis of the position of pile is The heart, uses down-hole hammer 22 offering three secondary borings 24 the most respectively in reclaimation area, and utilizes full casing 21 to follow down-the-hole Hammer 22 creeps into, during namely full casing 21 is also plugged in this pair boring 24, and constantly moving down along with down-hole hammer 22, This full casing 21 is constantly plugging down, until down-hole hammer 22 is through Backfilled Stone Layer 3, the most full casing 21 also passes through and rockfilling In layer 3, Backfilled Stone Layer 3 is passed through in i.e. secondary boring 24;Down-hole hammer 22 is transferred to, and in full casing 21, fills sand, treat sand Fill to the upper surface of reclaimation area, then extract full casing 21, thus, secondary boring 24 formation back-up sand hole 23, this back-up sand hole 23 Pass through Backfilled Stone Layer 3.
Offer in above-mentioned three secondary borings 24, respectively centered by the axis treating pile position, intersect phase in product shape Hand over and arrange, namely intersect to intersect around shape and arrange, and three secondary borings 24 the most all treat that the axis of pile position is included in In, so, then can fully remove the Backfilled Stone Layer 3 treating pile position axis, namely by Backfilled Stone Layer 3 completely by sand Replace.
Certainly, as other embodiments, above-mentioned in step 1) before, the secondary boring 24 offered can also be three with On, as long as this secondary boring 24 of more than three is arranged in intersecting to intersect around shape, and the axis treating pile position is included Then may be used.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention Any amendment, equivalent and the improvement etc. made within god and principle, should be included within the scope of the present invention.

Claims (4)

1. pile for prestressed pipe, it is characterised in that pile for prestressed pipe includes pile body, the pipe pile joint being connected to pile body lower end and company Being connected on the pile tube pile top of pipe pile joint lower end, the lower end of described pipe pile joint connects multiple guide plate, multiple described guide plates Adjacently positioned around described pile tube pile top periphery, the lower end of described guide plate is tip, is provided with in the sidewall of described pipe pile joint Two-way spilled water hole, is provided with two-way spilled water hole in the sidewall of described pile body.
2. the pile for prestressed pipe as described in claim 1, it is characterised in that the inclined shape in outside of described guide plate lower end, Described tip is formed in lower end.
3. the pile for prestressed pipe as described in claim 1, it is characterised in that the both sides of described guide plate lower end are the most inclined Shape, and described tip it is crossed to form in lower end.
4. pile for prestressed pipe as claimed in claim 1, it is characterised in that the inner side of described guide plate is connected to described pipe pile The periphery of point.
CN201610710891.9A 2016-08-24 2016-08-24 Pile for prestressed pipe Pending CN106087978A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610710891.9A CN106087978A (en) 2016-08-24 2016-08-24 Pile for prestressed pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610710891.9A CN106087978A (en) 2016-08-24 2016-08-24 Pile for prestressed pipe

Publications (1)

Publication Number Publication Date
CN106087978A true CN106087978A (en) 2016-11-09

Family

ID=57225707

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610710891.9A Pending CN106087978A (en) 2016-08-24 2016-08-24 Pile for prestressed pipe

Country Status (1)

Country Link
CN (1) CN106087978A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111335312A (en) * 2020-03-06 2020-06-26 中交第三航务工程局有限公司 Rock-entering construction process for large-diameter lock catch steel pipe pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111335312A (en) * 2020-03-06 2020-06-26 中交第三航务工程局有限公司 Rock-entering construction process for large-diameter lock catch steel pipe pile

Similar Documents

Publication Publication Date Title
CN104164873B (en) Prestressed pipe pile and construction method thereof
CN203625893U (en) Rock-embedded cast-in-place pile
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN102691296A (en) Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN105714834B (en) A kind of construction technology of hardpan preexisting hole grouting behind shaft or drift lining H profile steel stake
CN102852141B (en) Rock-socketed pipe pile foundation with pile core by concrete pouring and pile side by static pressure grouting and construction method for rock-socketed pipe pile foundation
CN105544512A (en) Reinforced sack grouting stone-breaking pile with heat transferring tube buried therein and construction method
CN103603342A (en) Construction method of ultra-long bored concrete pile with large-diameter casing combination
CN105714772A (en) Re-drilling concrete wall protecting method for hole formation of rock-socketed pile in karst region
CN108797578A (en) Crushed stone grouting pile and its construction method with classification enlarged footing
CN104074183A (en) Drilling and concrete injected root composite pile implanting pile structure and construction method
CN101985836A (en) Processing method of pile-wall type deep base pit supporting structure in case of encountering large boulder stone
CN105780766A (en) Drilling backfill end bearing pile foundation and construction method thereof
CN204225100U (en) The construction equipment of concrete pile
CN106087978A (en) Pile for prestressed pipe
CN208545745U (en) Crushed stone grouting pile with classification enlarged footing
CN203939024U (en) Pile for prestressed pipe
CN204252120U (en) The construction equipment of concrete pile
CN104153355B (en) The constructing device of concrete-pile and construction method thereof
CN204326061U (en) A kind of pile tube be drawn out easily
CN205712130U (en) A kind of thick miscellaneous fill foundation pit slope protection pilework
CN205399438U (en) Karst area embedded rock pile pore -forming bores concrete dado structure again
CN205713982U (en) A kind of pile foundation construction drilling equipment being applicable to karst area
CN205532633U (en) Tunnel bottom plate reinforcerment system
CN102002943B (en) Construction method of rock-socketed secant filling pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161109