A kind of drain bar plugs mechanism Download PDF

Info

Publication number
CN106087954B
CN106087954B CN201610657080.7A CN201610657080A CN106087954B CN 106087954 B CN106087954 B CN 106087954B CN 201610657080 A CN201610657080 A CN 201610657080A CN 106087954 B CN106087954 B CN 106087954B
Authority
CN
China
Prior art keywords
drain bar
plate
pressing plate
pile pipe
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610657080.7A
Other languages
Chinese (zh)
Other versions
CN106087954A (en
Inventor
杨洪忠
张俊
沈海垭
潘树良
钱卓豪
蒋琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd
Original Assignee
ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd filed Critical ZHEJIANG QIAOXING CONSTRUCTION GROUP Co Ltd
Priority to CN201610657080.7A priority Critical patent/CN106087954B/en
Publication of CN106087954A publication Critical patent/CN106087954A/en
Application granted granted Critical
Publication of CN106087954B publication Critical patent/CN106087954B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/10Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention relates to building field, and in particular to a kind of drain bar plugs mechanism.It is used to be connected to the elastic component for making pressing plate rotate around pin joint to the pressing plate and pressing plate that are pressed on drain bar including being symmetrically hinged with two row in the internal sleeve pile pipe with guide plate chamber, the back taper pile crown positioned at sleeve pile pipe bottom, the guide plate chamber cavity wall;The back taper pile crown includes the two panels pile crown plate that locally overlapping and lower end can close or be open.The elastic component includes two connecting rods being arranged in respectively on two row pressing plates, the synchronous connecting plate being removably attachable at the top of two connecting rods.The application is simple in construction, cost is low, easy to operate, and operating efficiency is high, plugs that small steady quality, soil-entering resistance, simple in construction, security reliability and versatility are good, applied widely, and cost is low, is hardly damaged, and replacement cost is small after damage.

Description

A kind of drain bar plugs mechanism
Technical field
The present invention relates to building field, and in particular to a kind of drain bar plugs mechanism.
Background technology
During to Soft Ground, plate equipment construction operation mechanism is essential.At present, it is common various During the plate equipment construction operation mechanism construction operation of form, there is operating efficiency it is low, plug that quality is unstable, soil-entering resistance The technical problems such as greatly, complicated, security reliability and poor universality, scope of application limitation are big.And existing equipment structure is answered Miscellaneous, cost is high, and fragile, replacement cost greatly improves after damage.
The content of the invention
The purpose of the present invention is to provide a kind of drain bar simple in construction, easy to operate, that resistance is small regarding to the issue above to insert If mechanism.
The present invention above-mentioned technical purpose technical scheme is that:
A kind of drain bar plugs mechanism, including the internal sleeve pile pipe with guide plate chamber, falling positioned at sleeve pile pipe bottom Two row are symmetrically hinged with cone pile crown, the guide plate chamber cavity wall to be connected to for the pressing plate to being pressed on drain bar, with pressing plate The elastic component for making pressing plate be rotated around pin joint;The back taper pile crown includes what the local overlapping and lower end of two panels can close or be open Pile crown plate.
Preferably, the elastic component includes two connecting rods being arranged in respectively on two row pressing plates, detachably connected Synchronous connecting plate at the top of two connecting rods.
Preferably, the sleeve pile pipe tip shelf is provided with the force bearing plate above the synchronous connecting plate, the synchronization Connecting plate upper surface is posted by the force bearing plate bottom surface.
Preferably, the notch for passing the drain bar is offered at the top of the sleeve pile pipe.
Preferably, the pile crown plate includes the mother that bottom has pointed stake head and female groove is provided with above pointed stake head Plate and bottom have the daughter board for the positive stop strip being adapted to female groove.
Cause because the power pushed up upwards causes female, daughter board occlusion to separate under lower stake female groove and coordinating for positive stop strip, And pointed stake head is only positioned on motherboard and also ensure that lower stake is more laborsaving, conveniently.
Preferably, the sleeve pile pipe is rectangular tube, the motherboard, the both sides of daughter board are each provided with a mud guard, and Mud guard on the motherboard and daughter board positioned at the same side has an overlapping gear seam portion, the apical lateral of the motherboard and daughter board with The sleeve pile pipe Basolateral is hinged, the top inner side of the motherboard and daughter board and formation pair on the inside of the sleeve pile pipe bottom The confined planes of pressure.
Preferably, the female groove is the tipper towards daughter board opening.
Preferably, up-thin-low-thick square even power platform is installed with the force bearing plate, the square even power platform bottom surface side Edge exceeds or the sleeve pile pipe top end face outer of aliging.
Square even power platform ensure that sleeve pile pipe uniform force in down tube.
Preferably, limit spacing platform is provided with below each pressing plate hinge point in the guide plate chamber cavity wall, The pole limiting stand is triangle platform, is provided with the pressing plate for center axle position through the connecting rod and along its length In the word length hole in the plane perpendicular to the draining plate face, being provided with the connecting rod multigroup there are two to be located at institute respectively State the limit assembly of the spacing cylinder blend stop at the top and bottom of pressing plate.
The setting in one word length hole enables connecting rod to slide guarantee pressing plate smooth rotation in a word length hole.
Bent preferably, the drain bar bottom is provided with the reserved precompressed section of formation in the back taper pile crown, the stake Mud embedded hole is entered in position in head plate higher than the reserved precompressed section provided with several.
In summary, the invention has the advantages that:
1st, the drain bar of pre-buried length is first put into guide plate intracavitary by the application, then pressing plate is pressed in into guide plate chamber center and determined Position, it then will plug mechanism and squeeze into soil to behind precalculated position, elastic component being pulled up so that press plate rotary is no longer pressed in leads On plate chamber, then the drain bar to a certain amount of length of guide plate intracavitary feeding, then sleeve pile pipe is pulled out upwards, mothers and sons while pulling out upwards Plate is automatically separated, and drain bar is not rewinded and stayed in stake hole, and sleeve pile pipe is thoroughly extracted and cuts drain bar from pile crown bottom after stake is cheated, Drain bar plugs completion, then stake hole is backfilled.The setting for entering mud embedded hole may be such that bottom enters one when underthrust covers pile pipe A little mud amounts, are pressed in reserved precompressed section, carry out precompressed positioning to drain bar bottom, ensure that drain bar is buried and require depth, Resistance when effectively preventing from rewinding, while can also reduce lower stake, also may be such that when playing sleeve pile pipe female, daughter board self gravitation with And be smoothly detached under the pressure of the mud entered, ensure that pile crown plate is opened and realize drain bar stream in stake hole.Pressing plate is pressed in drain bar It ensure that drain bar installation position is accurate, while prevent drain bar from arbitrarily rocking displacement when plugging sleeve pile pipe or be stuck in guide plate chamber It is interior, even if entering mud, it can also ensure that the mud that sleeve pile pipe is entered is pressed on predeterminated position, fabric swatch is precisely more convenient for budget length, Material saving.
2nd, the application is simple in construction, cost is low, easy to operate, operating efficiency is high, it is small to plug steady quality, soil-entering resistance, Simple in construction, security reliability and versatility are good, applied widely, and cost is low, is hardly damaged, and replacement cost is small after damage.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention;
Fig. 2 is pile crown plate structure schematic diagram;
Fig. 3 is pressing plate and bar linkage structure schematic diagram;
Fig. 4 is sleeve pile pipe structural representation.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.
Embodiment one:
A kind of drain bar plugs mechanism, including the internal sleeve pile pipe 1 with guide plate chamber, falling positioned at sleeve pile pipe bottom Two row are symmetrically hinged with cone pile crown 2, the guide plate chamber cavity wall to be connected for the pressing plate 9 to being pressed on drain bar 10, with pressing plate For the elastic component for making pressing plate be rotated around pin joint;The back taper pile crown includes two panels, and locally overlapping and lower end can close or open The pile crown plate of mouth.
The elastic component includes two connecting rods 3 being arranged in respectively on two row pressing plates, is removably attachable to two institutes State the synchronous connecting plate 4 at the top of connecting rod.
The sleeve pile pipe tip shelf is provided with the force bearing plate 51 above the synchronous connecting plate, the synchronous connecting plate upper end Face is posted by the force bearing plate bottom surface.
The notch 11 for passing the drain bar is offered at the top of the sleeve pile pipe.
The stair-stepping slot pressing plate mounting groove that width from top to bottom reduces successively is offered in the guide plate chamber cavity wall, together Pressing plate in one row is sequentially arranged in the stage of stair-stepping slot pressing plate mounting groove, the pressing plate from top to bottom set gradually Hinged end width reduce successively.After stair-stepping slot pressing plate mounting groove is easy to the pressing plate of pressing plate, pressing plate to be worked good with connecting rod Insertion coordinates with slot pressing plate mounting groove at the top of sleeve pile pipe again, and the pressing plate of different hinged place width is stuck in different stages successively On, a row pressing plate can be simultaneously once wide also more convenient into installation, dismounting.
Along to enclose the circle edge in sleeve pile pipe outside wall surface, the circle, which along bottom is evenly equipped with several, to be risen and pulls out for the pile pulling Mating groove, the circle are 10-30cm along the distance to the sleeve pile pipe upper surface.
Rise pull out mating groove can promote sleeve pile pipe instrument coordinate it is more firm, be easy to pile pipe.Circle is easy along top is set Fractureing or turn over and stick up, circle is 10-30cm along the distance to the sleeve pile pipe upper surface, both ensure that sleeve pile pipe was hardly damaged, In turn ensure that has enough power branch stake tools when pulling out.
The pile crown plate includes the He of motherboard 21 that bottom has pointed stake first 211 and female groove is provided with above pointed stake head Bottom has the daughter board 22 for the positive stop strip 221 being adapted to female groove.
The sleeve pile pipe is rectangular tube, and the motherboard, the both sides of daughter board are each provided with a mud guard 23, and the motherboard There is overlapping gear seam portion, apical lateral and the sleeve of the motherboard and daughter board with the mud guard for being located at the same side on daughter board Pile pipe Basolateral is hinged, and the top inner side of the motherboard and daughter board on the inside of the sleeve pile pipe bottom with forming to the spacing of pressure Face 6.
The female groove is the tipper towards daughter board opening.
Be installed with up-thin-low-thick square even power platform 7 on the force bearing plate, the square even power platform bottom surface edge exceed or Align the sleeve pile pipe top end face outer.
In the guide plate chamber cavity wall limit spacing platform 8, the limit are provided with below each pressing plate hinge point Position platform is triangle platform, is provided with the pressing plate and is located normal to for central shaft through the connecting rod and along its length A word length hole 91 in the plane of the draining plate face, being provided with the connecting rod multigroup there are two to be located at the pressing plate respectively The limit assembly of the spacing cylinder blend stop 31 of top and bottom.
The setting in one word length hole enables connecting rod to slide guarantee pressing plate smooth rotation in a word length hole.
The drain bar bottom, which is provided with, to be bent in the reserved precompressed section 101 of formation in the back taper pile crown, the pile crown plate Mud embedded hole 24 is entered in position higher than the reserved precompressed section 101 provided with several.
The drain bar of pre-buried length is first put into guide plate intracavitary by the application, then pressing plate is pressed in into guide plate chamber center and determined Position, it then will plug mechanism and squeeze into soil to behind precalculated position, elastic component being pulled up so that press plate rotary is no longer pressed in leads On plate chamber, then the drain bar to a certain amount of length of guide plate intracavitary feeding, then sleeve pile pipe is pulled out upwards, mothers and sons while pulling out upwards Plate is automatically separated, and drain bar is not rewinded and stayed in stake hole, and sleeve pile pipe is thoroughly extracted and cuts drain bar from pile crown bottom after stake is cheated, Drain bar plugs completion, then stake hole is backfilled.The setting for entering mud embedded hole may be such that bottom enters one when underthrust covers pile pipe A little mud amounts, are pressed in reserved precompressed section, carry out precompressed positioning to drain bar bottom, ensure that drain bar is buried and require depth, Resistance when effectively preventing from rewinding, while can also reduce lower stake.

Claims (8)

1. a kind of drain bar plugs mechanism, it is characterised in that:Including the internal sleeve pile pipe with guide plate chamber(1), positioned at sleeve The back taper pile crown of pile pipe bottom(2), be symmetrically hinged with two row in the guide plate chamber cavity wall and be used for being pressed in drain bar(10)On Pressing plate(9)And pressing plate is connected to the elastic component for making pressing plate be rotated around pin joint;The back taper pile crown includes two panels and locally handed over The pile crown plate that folded and lower end can close or be open;The elastic component includes two connecting rods being arranged in respectively on two row pressing plates (3), the synchronous connecting plate that is removably attachable at the top of two connecting rods(4);The pile crown plate, which includes bottom, has pointed stake head (211)And the motherboard of female groove is provided with above pointed stake head(21)There is the positive stop strip being adapted to female groove with bottom(221) Daughter board(22).
2. a kind of drain bar plugs mechanism according to claim 1, it is characterised in that:The sleeve pile pipe tip shelf is provided with position Force bearing plate above the synchronous connecting plate(51), the synchronous connecting plate upper surface is posted by the force bearing plate bottom surface.
3. a kind of drain bar plugs mechanism according to claim 2, it is characterised in that:Use is offered at the top of the sleeve pile pipe In the notch for passing the drain bar(11).
4. a kind of drain bar plugs mechanism according to claim 1, it is characterised in that:The sleeve pile pipe is rectangular tube, institute State motherboard, the both sides of daughter board are each provided with a mud guard(23), and the mud guard on the motherboard and daughter board positioned at the same side has Have overlapping gear seam portion, the apical lateral of the motherboard and daughter board is hinged with the sleeve pile pipe Basolateral, the motherboard and The top inner side of daughter board is with forming the confined planes to pressure on the inside of the sleeve pile pipe bottom(6).
5. a kind of drain bar plugs mechanism according to claim 4, it is characterised in that:The female groove is towards daughter board opening Tipper.
6. a kind of drain bar plugs mechanism according to Claims 2 or 3, it is characterised in that:It is installed with the force bearing plate Thick square even power platform under carefully(7), the square even power platform bottom surface edge exceeds or alignd the sleeve pile pipe top end face outer.
7. a kind of drain bar plugs mechanism according to Claims 2 or 3, it is characterised in that:It is located in the guide plate chamber cavity wall Limit spacing platform is provided with below each pressing plate hinge point(8), the limit spacing platform is triangle platform, on the pressing plate It is provided with one be located normal to for central shaft through the connecting rod and along its length in the plane of the draining plate face Word length hole(91), multigroup there are two spacing cylinders gear at the top and bottom of the pressing plate respectively is provided with the connecting rod Bar(31)Limit assembly.
8. mechanism is plugged according to a kind of drain bar described in claim 2-5 any claims, it is characterised in that:The drain bar Bottom, which is provided with, to be bent in the reserved precompressed section of formation in the back taper pile crown(101), it is higher than the reserved precompressed on the pile crown plate Section(101)Position enter mud embedded hole provided with several(24).
CN201610657080.7A 2016-08-12 2016-08-12 A kind of drain bar plugs mechanism Active CN106087954B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610657080.7A CN106087954B (en) 2016-08-12 2016-08-12 A kind of drain bar plugs mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610657080.7A CN106087954B (en) 2016-08-12 2016-08-12 A kind of drain bar plugs mechanism

Publications (2)

Publication Number Publication Date
CN106087954A CN106087954A (en) 2016-11-09
CN106087954B true CN106087954B (en) 2018-01-05

Family

ID=57455474

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610657080.7A Active CN106087954B (en) 2016-08-12 2016-08-12 A kind of drain bar plugs mechanism

Country Status (1)

Country Link
CN (1) CN106087954B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090196691A1 (en) * 2008-02-01 2009-08-06 June Construction Co., Ltd Drain board installing device without anchor plate
CN201358455Y (en) * 2009-02-06 2009-12-09 江苏南水土建工程公司 Manual drainage plate inserting device for treating soft foundation by dredging and filling sludge
CN103410138A (en) * 2013-06-09 2013-11-27 浙江省围海建设集团宁波宏阳建设有限公司 Multifunctional automatic pile head for allowing plastic drainage plate to be inserted
CN204551427U (en) * 2015-02-26 2015-08-12 武汉二航路桥特种工程有限责任公司 A kind of novel plastic band drain construction equipment
CN105442525A (en) * 2015-12-31 2016-03-30 浙江宏力阳生态建设股份有限公司 Inserting mechanism for plastic drainage plate
CN206157711U (en) * 2016-08-12 2017-05-10 通州建总集团有限公司 Drain bar is inserted and is established mechanism

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100713652B1 (en) * 2006-09-27 2007-05-02 주식회사 준건설 Support pressing device for drain casing of a excavator

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090196691A1 (en) * 2008-02-01 2009-08-06 June Construction Co., Ltd Drain board installing device without anchor plate
CN201358455Y (en) * 2009-02-06 2009-12-09 江苏南水土建工程公司 Manual drainage plate inserting device for treating soft foundation by dredging and filling sludge
CN103410138A (en) * 2013-06-09 2013-11-27 浙江省围海建设集团宁波宏阳建设有限公司 Multifunctional automatic pile head for allowing plastic drainage plate to be inserted
CN204551427U (en) * 2015-02-26 2015-08-12 武汉二航路桥特种工程有限责任公司 A kind of novel plastic band drain construction equipment
CN105442525A (en) * 2015-12-31 2016-03-30 浙江宏力阳生态建设股份有限公司 Inserting mechanism for plastic drainage plate
CN206157711U (en) * 2016-08-12 2017-05-10 通州建总集团有限公司 Drain bar is inserted and is established mechanism

Also Published As

Publication number Publication date
CN106087954A (en) 2016-11-09

Similar Documents

Publication Publication Date Title
CN207727589U (en) Internal support of foundation pit device
CN206110131U (en) Drain bar cabling device
CN106088090B (en) A kind of drain bar installation aiding device
CN206110111U (en) Drain bar during soft soil foundation reinforcement equips insert equipment of establishing
CN106049415B (en) Drain bar in a kind of reinforced soft soil ground equipment plugs equipment
CN206157711U (en) Drain bar is inserted and is established mechanism
CN106087954B (en) A kind of drain bar plugs mechanism
CN208363805U (en) A kind of foundation pit edge protection fence
CN210315593U (en) Anchor rod for fixing side slope
CN206904521U (en) A kind of English teaching video recording equipment
CN106087955B (en) A kind of reinforced soft soil ground equipment
CN106087943B (en) A kind of foundation stabilization equipment
CN205894059U (en) Soft soil foundation reinforcement equips
CN205894055U (en) Foundation stabilization is with equipping
CN206003984U (en) A kind of portable temporary ground wire earthing pole device
CN106088091B (en) A kind of construction equipment for consolidated subsoil
CN208039262U (en) A kind of anti-drop device of shallow foundation hole support plate
CN207159993U (en) A kind of civil engineering built pile used temporarily
CN207027395U (en) A kind of high pressure plunger water pump pump head screw plug provision for disengagement
CN206516173U (en) A kind of Dynamic Display instrument
CN210220860U (en) Ruler for detecting quality of constructional engineering
CN110965566A (en) A clay agitator for cofferdam is transferred
CN206968263U (en) A kind of plug-type engraving machine dust shield
CN109866309A (en) A kind of building trade template
CN111719541B (en) Plate inserting device capable of destroying soil body structure and using method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant