CN106087776A - A kind of second pontic erection method of split type level bridges - Google Patents

A kind of second pontic erection method of split type level bridges Download PDF

Info

Publication number
CN106087776A
CN106087776A CN201610454340.0A CN201610454340A CN106087776A CN 106087776 A CN106087776 A CN 106087776A CN 201610454340 A CN201610454340 A CN 201610454340A CN 106087776 A CN106087776 A CN 106087776A
Authority
CN
China
Prior art keywords
pontic
split type
erection method
type level
level bridges
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610454340.0A
Other languages
Chinese (zh)
Other versions
CN106087776B (en
Inventor
张清林
汪立之
吴家骅
梁涛
刘志雄
洗振佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHONGSHAN HIGHWAY STEEL STRUCTURE MANUFACTURE CO Ltd
Original Assignee
ZHONGSHAN HIGHWAY STEEL STRUCTURE MANUFACTURE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHONGSHAN HIGHWAY STEEL STRUCTURE MANUFACTURE CO Ltd filed Critical ZHONGSHAN HIGHWAY STEEL STRUCTURE MANUFACTURE CO Ltd
Priority to CN201610454340.0A priority Critical patent/CN106087776B/en
Publication of CN106087776A publication Critical patent/CN106087776A/en
Application granted granted Critical
Publication of CN106087776B publication Critical patent/CN106087776B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Abstract

The invention discloses the second pontic erection method of a kind of split type level bridges, comprise the following steps: after one, having set up the first pontic, second pontic is pushed on the first pontic set up, after second pontic puts in place, one end of second pontic is connected with the first pontic, second pontic carries folding-unfolding mechanism, is driven by folding-unfolding mechanism and launches, and the other end controlling the second pontic gradually decreases down and the first pontic laminating;Two, release the connection between the first pontic and the second pontic, by the first pontic and the second pontic in side pivot joint, be then lifted out the second pontic so that the second pontic rotates relative to the first pontic, now the second pontic and the first pontic parallel arranged on same plane.In above-mentioned erection method, the second pontic erection method is the most ingenious, and the center of gravity of the second pontic remains at relatively low position during it sets up, and when it set up power consumption can be greatly reduced.

Description

A kind of second pontic erection method of split type level bridges
Technical field
The present invention relates to the second pontic erection method of a kind of split type level bridges.
Background technology
Fast construction bridge on river or gully is in emergency circumstances needed, now in order to ensure that bridge is quickly taken at some Building, general employing sets up split type level bridges and solves this problem, but the erection method of existing split type level bridges exists Some problems, such as need to be equipped with bigger counterweight, consume energy high, set up efficiency other shortcoming not enough etc., carry for this present invention The second pontic erection method for a kind of split type level bridges.
Summary of the invention
In order to solve the problems referred to above, the present invention provides the second pontic erection method of a kind of split type level bridges.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of second pontic erection method of split type level bridges, this split type level bridges include pedestal, one folding first Pontic and at least one collapsible second pontic, it is characterised in that comprise the following steps:
One, after having set up the first pontic, the second pontic is pushed on the first pontic set up, after the second pontic puts in place, by One end of two pontics is connected with the first pontic, and the second pontic carries folding-unfolding mechanism, is driven by folding-unfolding mechanism and launches, controls second The other end of pontic gradually decreases down and the first pontic laminating;
Two, release the connection between the first pontic and the second pontic, by the first pontic and the second pontic in side pivot joint, then carry Rise the second pontic so that the second pontic rotates relative to the first pontic, now the second pontic and the first pontic on same plane also Row arrangement.
Present invention additionally comprises:
Step 3, lifting the first pontic and the second pontic, so that thereunder erection support, complete to set up.
Described pedestal is provided with winding plant, is pushed on the first pontic set up by the second pontic by winding plant, The other end being controlled the second pontic by winding plant is gradually reduced.
In described step 2 after the second pontic has overturn, release the first pontic and the connection of the second pontic, by the second bridge Body translation setpoint distance.
The invention has the beneficial effects as follows: in above-mentioned erection method, the second pontic is the lowest to counterweight requirements when setting up, second Pontic erection method is the most ingenious, and the center of gravity of the second pontic remains at relatively low position during it sets up, can be big Width reduces power consumption when it sets up, and stability when promoting erection, the advantage with low-energy-consumption high-efficiency.
Accompanying drawing explanation
The present invention is further described with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the schematic diagram one of step one in the present invention;
Fig. 2 is the schematic diagram two of step one in the present invention;
Fig. 3 is the schematic diagram three of step one in the present invention;
Fig. 4 is the schematic diagram of step 2 in the present invention.
Detailed description of the invention
With reference to Fig. 1~Fig. 4, the present invention is the second pontic 4 erection method of a kind of split type level bridges, this split type steelframe Bridge includes folding first pontic 3 and at least one collapsible second pontic 4 of pedestal 1, it is characterised in that include following step Rapid:
One, after having set up the first pontic 3, the second pontic 4 is pushed on the first pontic 3 set up, after the second pontic 4 puts in place, Being connected with the first pontic 3 one end of second pontic 4, the second pontic 4 carries folding-unfolding mechanism, is driven by folding-unfolding mechanism and launches, Control the other end of the second pontic 4 to gradually decrease down and fit with the first pontic 3;
Two, the connection between the first pontic 3 and the second pontic 4 is released, by the first pontic 3 and the second pontic 4 in side pivot joint, so Rear lifting the second pontic 4 so that the second pontic 4 rotates relative to the first pontic 3, now the second pontic 4 and the first pontic 3 are in same Parallel arranged in plane;
Step 3, lifting the first pontic 3 and the second pontic 4, so that thereunder erection support, complete to set up.In step 2 After two pontics 4 have overturn, release the first pontic 3 and connection of the second pontic 4, the second pontic 4 is translated setpoint distance.Above-mentioned frame In equipment, method, the second pontic 4 is the lowest to counterweight requirements when setting up, and the second pontic 4 erection method is the most ingenious, the second pontic 4 Center of gravity remains at relatively low position during it sets up, and when it set up power consumption can be greatly reduced, and when promoting erection Stability, the advantage with low-energy-consumption high-efficiency.
As Figure 1-Figure 4, pedestal 1 is provided with winding plant 2, is pushed into by the second pontic 4 by winding plant 2 and sets up The first pontic 3 on, the other end being controlled the second pontic 4 by winding plant 2 is gradually reduced.Winding plant 2 working stability, can Carry out the control of big stroke.
Above-described embodiment is the preferred version of the present invention, and the present invention also can have other embodiments.The technology of this area Personnel also can make equivalent variations or replacement on the premise of spirit of the present invention, and modification or the replacement of these equivalents are all wrapped It is contained in the scope set by the application claim.

Claims (4)

1. a second pontic erection method of split type level bridges, this split type level bridges include pedestal, one folding One pontic and at least one collapsible second pontic, it is characterised in that comprise the following steps:
One, after having set up the first pontic, the second pontic is pushed on the first pontic set up, after the second pontic puts in place, by One end of two pontics is connected with the first pontic, and the second pontic carries folding-unfolding mechanism, is driven by folding-unfolding mechanism and launches, controls second The other end of pontic gradually decreases down and the first pontic laminating;
Two, release the connection between the first pontic and the second pontic, by the first pontic and the second pontic in side pivot joint, then carry Rise the second pontic so that the second pontic rotates relative to the first pontic, now the second pontic and the first pontic on same plane also Row arrangement.
Second pontic erection method of a kind of split type level bridges the most as claimed in claim 1, it is characterised in that it also includes:
Step 3, lifting the first pontic and the second pontic, so that thereunder erection support, complete to set up.
Second pontic erection method of a kind of split type level bridges the most as claimed in claim 1, it is characterised in that described pedestal It is provided with winding plant, by winding plant, the second pontic is pushed on the first pontic set up, by winding plant control The other end of the second pontic is gradually reduced.
Second pontic erection method of a kind of split type level bridges the most as claimed in claim 1, it is characterised in that described step In two after the second pontic has overturn, release the first pontic and the connection of the second pontic, by the second pontic translation setpoint distance.
CN201610454340.0A 2016-06-20 2016-06-20 A kind of second pontic erection method of split type level bridges Active CN106087776B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610454340.0A CN106087776B (en) 2016-06-20 2016-06-20 A kind of second pontic erection method of split type level bridges

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610454340.0A CN106087776B (en) 2016-06-20 2016-06-20 A kind of second pontic erection method of split type level bridges

Publications (2)

Publication Number Publication Date
CN106087776A true CN106087776A (en) 2016-11-09
CN106087776B CN106087776B (en) 2017-12-05

Family

ID=57238668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610454340.0A Active CN106087776B (en) 2016-06-20 2016-06-20 A kind of second pontic erection method of split type level bridges

Country Status (1)

Country Link
CN (1) CN106087776B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938518A (en) * 2017-11-21 2018-04-20 中铁四局集团钢结构建筑有限公司 One kind is first turned across busy railway freely-supported steel truss girder translates erection construction method again

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2556175A (en) * 1945-06-12 1951-06-12 Lester P Frost Bridge and mobile launching structure therefor
US3837027A (en) * 1972-03-11 1974-09-24 H Gehlen Vehicle with depositable ramp for the forming of bridges, particularly floating bridges and ferries
EP0280626A1 (en) * 1987-02-27 1988-08-31 Constructions Industrielles De La Mediterranee C.N.I.M. System for unfolding and placing a bridge from a vehicle such as a bridge-laying tank for passing an obstacle
CN101949127A (en) * 2010-09-29 2011-01-19 王贵宣 Movable type rescue auxiliary bridge vehicle
CN203514172U (en) * 2013-10-21 2014-04-02 贾针 Emergency rescue device
CN204023395U (en) * 2014-08-20 2014-12-17 青岛理工大学 A kind of rescue bridge layer
CN104499417A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Gravity self-balance type emergency rehabilitation rapid self-erection bridge
CN104495638A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Portable hydraulic auxiliary erected automobile obstacle crossing device
CN104499419A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Steel structure emergency traffic-repairing and traffic-keeping integrated bridge
CN104499418A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Folding assembly type vehicle-mounted bridge

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2556175A (en) * 1945-06-12 1951-06-12 Lester P Frost Bridge and mobile launching structure therefor
US3837027A (en) * 1972-03-11 1974-09-24 H Gehlen Vehicle with depositable ramp for the forming of bridges, particularly floating bridges and ferries
EP0280626A1 (en) * 1987-02-27 1988-08-31 Constructions Industrielles De La Mediterranee C.N.I.M. System for unfolding and placing a bridge from a vehicle such as a bridge-laying tank for passing an obstacle
CN101949127A (en) * 2010-09-29 2011-01-19 王贵宣 Movable type rescue auxiliary bridge vehicle
CN203514172U (en) * 2013-10-21 2014-04-02 贾针 Emergency rescue device
CN204023395U (en) * 2014-08-20 2014-12-17 青岛理工大学 A kind of rescue bridge layer
CN104499417A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Gravity self-balance type emergency rehabilitation rapid self-erection bridge
CN104495638A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Portable hydraulic auxiliary erected automobile obstacle crossing device
CN104499419A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Steel structure emergency traffic-repairing and traffic-keeping integrated bridge
CN104499418A (en) * 2014-12-03 2015-04-08 中山市公路钢结构制造有限公司 Folding assembly type vehicle-mounted bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938518A (en) * 2017-11-21 2018-04-20 中铁四局集团钢结构建筑有限公司 One kind is first turned across busy railway freely-supported steel truss girder translates erection construction method again

Also Published As

Publication number Publication date
CN106087776B (en) 2017-12-05

Similar Documents

Publication Publication Date Title
CN201942481U (en) Scissors type lifting platform arm support mechanism
CN103552572A (en) Mobile vehicle-ride bridge
CN207296344U (en) It is a kind of to carry the construction platform automatically moved with material delivery functions
CN106087776A (en) A kind of second pontic erection method of split type level bridges
CN202403166U (en) Folded outdoor light-emitting diode (LED) lighting device
CN205472522U (en) Electrical urgent repair frame
CN105926462B (en) A kind of erection method of split type level bridges
CN208544729U (en) A kind of adjustable continuity material lift equipment of architectural engineering
CN204993198U (en) Simple and easy solar cell panel support
CN101787795A (en) Large-size net rack suspension cable mounting platform and suspension cable construction method
CN203626267U (en) Building roof lifting device
CN207332457U (en) A kind of construction guardrail of detachable lifting
CN205836626U (en) A kind of horizontal strut being automatically adjusted cargo bed
CN105174114A (en) Lifting device used for solar panel
CN204000619U (en) A kind of Bridge Erector nose girder slope conditioning
CN205000620U (en) Expanded furnace is with overhauing platform
CN205777434U (en) A kind of hoistway operation rack device
CN205857005U (en) The convenient level bridges of a kind of erection
CN206590457U (en) A kind of stepless elevation device of drag conveyor
CN105305300A (en) Device used for replacing tubular bus support porcelain insulator
CN205811930U (en) A kind of collection apparatus of photovoltaic panel
CN204198046U (en) With the cloth roll stands of lift system
CN202688996U (en) Pile driver with hydraulic folding oil cylinder
CN204754194U (en) Perpendicular conveyer that uses in mould of bump top
CN204675697U (en) A kind of gantry crane's supporting legs

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant