CN106087761A - 一种地道桥施工缝止水体系施工方法 - Google Patents
一种地道桥施工缝止水体系施工方法 Download PDFInfo
- Publication number
- CN106087761A CN106087761A CN201610644904.7A CN201610644904A CN106087761A CN 106087761 A CN106087761 A CN 106087761A CN 201610644904 A CN201610644904 A CN 201610644904A CN 106087761 A CN106087761 A CN 106087761A
- Authority
- CN
- China
- Prior art keywords
- water
- sealing system
- construction
- face
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
Abstract
一种地道桥施工缝止水体系施工方法。其包括在框架桥的侧壁及底板前后端面上形成两条U字形凹槽;在每条U字形凹槽中分别安装一道遇水膨胀止水条;在安装好遇水膨胀止水条的侧壁及底板的前后端面上涂刷混凝土界面剂;将混凝土浇筑在引桥模板中,振捣过程中需注意对接缝处加强振捣等步骤。本发明优点:界面剂为透明液体,对工程质量及美观影响较少。界面剂较水泥基渗透防水结晶,防水效果更佳,遇水膨胀止水条在狭小空间内,遇水膨胀,能够充分防止地下水渗入混凝土内部。能够形成多重阻水系统,有效保证防水效果。能够在降低成本的同时保证工程的防水质量。
Description
技术领域
本发明属于地道桥施工技术领域,特别是涉及一种地道桥施工缝止水体系施工方法。
背景技术
随着我国铁路建设的快速发展,下穿式地道桥已逐渐取代平交式道口。下穿式地道桥主要由框架桥和前后引桥组成;目前这种下穿式地道桥常用的施工方法是:先在待设置下穿式地道桥处的铁路线路一侧挖掘一个基坑,然后在基坑内预制好框架桥,之后利用顶进法将上述框架桥顶进至铁路线路下方,然后在框架桥的前后端进行作为后浇段的引桥施工,由此将框架桥和前后引桥连成一体。目前框架桥顶进施工愈渐成熟,在框架桥顶进过程中,为了保证重心平衡及减少顶进阻力,通常将框架桥的前悬臂板制成刃角形状,将后悬臂板制成三角形状。由于上述结构的框架桥在顶进前无法设置止水带等止水材料,因此为了保证后浇段施工缝的防水质量,通常需将框架桥的侧壁及底板的前后端面进行凿毛,然后在后浇段施工前,在上述端面涂抹水泥基渗透防水结晶,用于增强混凝土间粘合力,填充混凝土间空隙,以此来增加后浇段混凝土结构与既有框架桥混凝土结构之间的连接性,但由于这样施工材料无法保证施工缝处完全紧密,因此地下水会沿空隙向上渗入,最终导致混凝土结构表面出现洇水现象。这时只能用后续注胶施工方法进行补救,因此对工程的社会效益和美观造成较大影响。
发明内容
为了解决上述问题,本发明的目的在于提供一种地道桥施工缝止水体系施工方法。
为了达到上述目的,本发明提供的地道桥施工缝止水体系施工方法包括按顺序进行的下列步骤:
1)对框架桥的侧壁及底板的前后端面由人工利用风镐进行凿毛处理,且在端面上形成两条U字形凹槽,凿除浮浆部分并露见石子;凿除后清扫碎屑,利用风泵将表面吹刷干净,将松动混凝土碎屑清理完毕后,用水冲洗干净;
2)在上述每条U字形凹槽中分别安装一道遇水膨胀止水条;
3)在上述安装好遇水膨胀止水条的侧壁及底板的前后端面上涂刷混凝土界面剂,采用满刷的形式,以保证界面剂全部覆盖住上述端面,并保证在后浇段混凝土施工前2小时内完成涂刷施工;
4)将混凝土浇筑在引道模板中,振捣过程中需注意对接缝处加强振捣,以保证混凝土中气泡完全冒出,并且应防止振捣棒触碰遇水膨胀止水条而导致其脱落,由此即可完成整个地道桥施工缝止水体系施工过程。
在步骤1)中,所述的端面凿毛深度大于1cm,凹槽深度大于0.5cm小于1cm。
在步骤2)中,所述的相邻遇水膨胀止水条之间的搭接长度不得小于5cm,7天的净膨胀率不大于最终膨胀率的60%,最终膨胀率大于220%。
本发明提供的地道桥施工缝止水体系施工方法具有如下优点:
(1)、界面剂为透明液体,对工程质量及美观影响较少。
(2)、界面剂较水泥基渗透防水结晶,防水效果更佳,遇水膨胀止水条在狭小空间内,遇水膨胀,能够充分防止地下水渗入混凝土内部。
(3)、能够形成多重阻水系统,有效保证防水效果。
(4)能够在降低成本的同时保证工程的防水质量。
附图说明
图1为采用本发明提供的地道桥施工缝止水体系施工方法时框架桥端面结构示意图。
图2为采用本发明提供的地道桥施工缝止水体系施工方法时框架桥上侧壁与引桥连接部位俯视图。
具体实施方式
下面结合附图和具体实施例对本发明提供的地道桥施工缝止水体系施工方法进行详细说明。
如图1—图2所示,本发明提供的地道桥施工缝止水体系施工方法包括按顺序进行的下列步骤:
1)对框架桥1的侧壁2及底板3的前后端面由人工利用风镐进行凿毛处理,且在端面上形成两条U字形凹槽4,凿除浮浆部分并露见石子;凿除后清扫碎屑,利用风泵将表面吹刷干净,将松动混凝土碎屑清理完毕后,用水冲洗干净;
2)在上述每条U字形凹槽4中分别安装一道遇水膨胀止水条5,应保证遇水膨胀止水条5与凹槽4的表面紧密贴实;
3)在上述安装好遇水膨胀止水条5的侧壁2及底板3的前后端面上涂刷混凝土界面剂,采用满刷的形式,以保证界面剂全部覆盖住上述端面,并保证在后浇段混凝土施工前2小时内完成涂刷施工;
4)将混凝土浇筑在引道模板中,振捣过程中需注意对接缝处加强振捣,以保证混凝土中气泡完全冒出,并且应防止振捣棒触碰遇水膨胀止水条5而导致其脱落,由此即可完成整个地道桥施工缝止水体系施工过程。
在步骤1)中,所述的端面凿毛深度大于1cm,凹槽4深度大于0.5cm小于1cm。
在步骤2)中,所述的相邻遇水膨胀止水条5之间的搭接长度不得小于5cm,7天的净膨胀率不大于最终膨胀率的60%,最终膨胀率大于220%。
Claims (3)
1.一种地道桥施工缝止水体系施工方法,其特征在于:所述的地道桥施工缝止水体系施工方法包括按顺序进行的下列步骤:
1)对框架桥(1)的侧壁(2)及底板(3)的前后端面由人工利用风镐进行凿毛处理,且在端面上形成两条U字形凹槽(4),凿除浮浆部分并露见石子;凿除后清扫碎屑,利用风泵将表面吹刷干净,将松动混凝土碎屑清理完毕后,用水冲洗干净;
2)在上述每条U字形凹槽(4)中分别安装一道遇水膨胀止水条(5);
3)在上述安装好遇水膨胀止水条(5)的侧壁(2)及底板(3)的前后端面上涂刷混凝土界面剂,采用满刷的形式,以保证界面剂全部覆盖住上述端面,并保证在后浇段混凝土施工前2小时内完成涂刷施工;
4)将混凝土浇筑在引道模板中,振捣过程中需注意对接缝处加强振捣,以保证混凝土中气泡完全冒出,并且应防止振捣棒触碰遇水膨胀止水条(5)而导致其脱落,由此即可完成整个地道桥施工缝止水体系施工过程。
2.根据权利要求1所述的地道桥施工缝止水体系施工方法,其特征在于:在步骤1)中,所述的端面凿毛浓度大于1cm,凹槽(4)深度大于0.5cm且小于1cm。
3.根据权利要求1所述的地道桥施工缝止水体系施工方法,其特征在于:在步骤2)中,所述的相邻遇水膨胀止水条(5)之间的搭接长度不得小于5cm,7天的净膨胀率不大于最终膨胀率的60%,最终膨胀率大于220%。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610644904.7A CN106087761A (zh) | 2016-08-05 | 2016-08-05 | 一种地道桥施工缝止水体系施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610644904.7A CN106087761A (zh) | 2016-08-05 | 2016-08-05 | 一种地道桥施工缝止水体系施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106087761A true CN106087761A (zh) | 2016-11-09 |
Family
ID=57455287
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610644904.7A Pending CN106087761A (zh) | 2016-08-05 | 2016-08-05 | 一种地道桥施工缝止水体系施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106087761A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638711A (zh) * | 2017-03-13 | 2017-05-10 | 刘国霞 | 隧道充压膨胀式止水带结构及施工工艺 |
CN110387887A (zh) * | 2019-06-28 | 2019-10-29 | 同济大学建筑设计研究院(集团)有限公司 | 导向隔墙及其施工方法和基坑围护结构的施工方法 |
CN110983982A (zh) * | 2019-12-19 | 2020-04-10 | 中铁六局集团天津铁路建设有限公司 | 一种框架桥与挡土墙间沉降缝防渗水体系施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003213708A (ja) * | 2001-11-13 | 2003-07-30 | Taisei Corp | 地下構造物の構築方法および高架式交通路 |
CN101144260A (zh) * | 2007-09-21 | 2008-03-19 | 北京交通大学 | 混凝土地道桥施工中的预应力应用方法 |
CN101413235A (zh) * | 2008-11-25 | 2009-04-22 | 中国第一冶金建设有限责任公司 | 地道桥下穿铁路轨道施工前对铁路进行加固的方法 |
CN102108679A (zh) * | 2011-02-21 | 2011-06-29 | 李家稳 | 一种顶进地道桥的组合式框架钢构及顶进地道桥的方法 |
CN104018436A (zh) * | 2014-05-07 | 2014-09-03 | 四川华西绿舍建材有限公司 | 预制箱涵系统及其安装方法 |
-
2016
- 2016-08-05 CN CN201610644904.7A patent/CN106087761A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003213708A (ja) * | 2001-11-13 | 2003-07-30 | Taisei Corp | 地下構造物の構築方法および高架式交通路 |
CN101144260A (zh) * | 2007-09-21 | 2008-03-19 | 北京交通大学 | 混凝土地道桥施工中的预应力应用方法 |
CN101413235A (zh) * | 2008-11-25 | 2009-04-22 | 中国第一冶金建设有限责任公司 | 地道桥下穿铁路轨道施工前对铁路进行加固的方法 |
CN102108679A (zh) * | 2011-02-21 | 2011-06-29 | 李家稳 | 一种顶进地道桥的组合式框架钢构及顶进地道桥的方法 |
CN104018436A (zh) * | 2014-05-07 | 2014-09-03 | 四川华西绿舍建材有限公司 | 预制箱涵系统及其安装方法 |
Non-Patent Citations (2)
Title |
---|
初向华: "《土木工程质量事故分析与处理》", 31 January 2015 * |
孙万臣: "合肥市方兴大道隧道防水施工技术", 《科技信息》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106638711A (zh) * | 2017-03-13 | 2017-05-10 | 刘国霞 | 隧道充压膨胀式止水带结构及施工工艺 |
CN110387887A (zh) * | 2019-06-28 | 2019-10-29 | 同济大学建筑设计研究院(集团)有限公司 | 导向隔墙及其施工方法和基坑围护结构的施工方法 |
CN110983982A (zh) * | 2019-12-19 | 2020-04-10 | 中铁六局集团天津铁路建设有限公司 | 一种框架桥与挡土墙间沉降缝防渗水体系施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104612698B (zh) | 一种浅埋暗挖隧道上台阶中隔壁施工方法 | |
CN102561402B (zh) | 盖挖逆作单建式地下人防工程顶板与墙施工缝的处理方法 | |
CN107676107A (zh) | 隧道加固裂缝处治方法 | |
CN106087761A (zh) | 一种地道桥施工缝止水体系施工方法 | |
CN106480993B (zh) | 一种构造外墙补漏补强内治理结构及施工方法 | |
AU2016228704B2 (en) | Hard road construction method for natural groundwater recharge | |
CN109371861A (zh) | 一种钢筋混凝土涵洞沉降缝渗水处治方法及修复结构 | |
CN110486053A (zh) | 一种城市轨道交通浅埋隧道结构缺陷整治施工方法 | |
CN110374138A (zh) | 车站主体与附属通道接口处的防水结构与施工方法 | |
CN110762286B (zh) | 排水管网人工顶管施工工艺 | |
CN210066782U (zh) | 一种土质边坡排水结构 | |
CN107587434A (zh) | 钢筋混凝土涵洞渗漏水预防处置方法 | |
CN104963364A (zh) | 盖挖逆作法结构板下侧墙施工缝的处理方法 | |
CN2937300Y (zh) | 一种frp乙烯基玻璃纤维增强筋笼 | |
CN206360137U (zh) | 一种构造外墙补漏补强内治理结构 | |
CN110042850A (zh) | 一种土质边坡排水结构及其施工方法 | |
CN113235646B (zh) | 综合管廊上跨地铁车站的施工方法 | |
CN210177585U (zh) | 一种基于bim的楼房雨水回收利用系统 | |
CN107476255A (zh) | 一种水利工程防水施工方法 | |
CN211498867U (zh) | 一种用于大范围地下工程开挖基坑工程的围护结构 | |
CN209244008U (zh) | 一种防渗水外墙结构 | |
CN209412844U (zh) | 一种装配式树脂混凝土排水沟 | |
CN208136919U (zh) | 一种基坑桩间编网防护结构 | |
CN105220699B (zh) | 围堰施工方法 | |
CN106544940B (zh) | 一种园路桩基式汀步结构及施工工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20161109 |
|
WD01 | Invention patent application deemed withdrawn after publication |