CN106087633B - Combine the manufacturing method of water-permeable brick - Google Patents
Combine the manufacturing method of water-permeable brick Download PDFInfo
- Publication number
- CN106087633B CN106087633B CN201610629459.7A CN201610629459A CN106087633B CN 106087633 B CN106087633 B CN 106087633B CN 201610629459 A CN201610629459 A CN 201610629459A CN 106087633 B CN106087633 B CN 106087633B
- Authority
- CN
- China
- Prior art keywords
- water
- permeable brick
- fixed lobe
- brick ontology
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C11/00—Details of pavings
- E01C11/22—Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
- E01C11/224—Surface drainage of streets
- E01C11/225—Paving specially adapted for through-the-surfacing drainage, e.g. perforated, porous; Preformed paving elements comprising, or adapted to form, passageways for carrying off drainage
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C5/00—Pavings made of prefabricated single units
- E01C5/06—Pavings made of prefabricated single units made of units with cement or like binders
Abstract
The invention belongs to urban construction fields, it include water-permeable brick ontology more particularly to water-permeable brick described in a kind of combination water-permeable brick and its manufacture and construction method, the right side of the water-permeable brick ontology and rear side are equipped with fixed lobe, on the left of the water-permeable brick ontology and the corresponding position of front side is equipped with the groove to match with fixed lobe, the water-permeable brick ontology is equipped with drainage hole up and down, water-permeable brick of the invention uses concave-convex mosaic connection, therefore road surface shape is integral, the phenomenon that being not in monolithic brick body protrusion or be recessed;In addition, due to not needing roadbed hardening, therefore save material and save working hour.
Description
Technical field
The invention belongs to urban construction fields, and in particular to a kind of manufacturing method for combining water-permeable brick.
Background technique
Currently, pavement laying road brick is common a kind of mode during urban construction, walking can be convenient, reduction is raised
Dirt facilitates appearance of the city construction.Traditional road brick is laid with Qian Xu road pavement base and is hardened, and influences rainwater infiltration, and pass through
Long-term rain impregnates, roadbed precipitates, therefore causes road brick to loosen, is uneven, especially in the case of rainy day ponding, tramples the road of loosening
Brick has muddy water spillage, influences pedestrian's trip;Additionally, due to the needs in construction sponge city, also it is badly in need of changing traditional paving brick
Into the water-permeable brick for that can seep water rapidly.
Summary of the invention
To solve the above-mentioned problems, while in response to the construction in sponge city it needs, city Route for pedestrians is laid with water-permeable brick
It is inevitable trend, the purpose of the present invention is to provide a kind of manufacturing methods for combining water-permeable brick, to solve above-mentioned background technique
The problem of middle proposition.
Technical solution provided by the invention is as follows: a kind of combination water-permeable brick, including water-permeable brick ontology, it is characterised in that: institute
The right side for the water-permeable brick ontology stated and rear side are equipped with fixed lobe, and the corresponding position in the water-permeable brick ontology left side and front side is equipped with
The groove to match with fixed lobe, the water-permeable brick ontology are equipped with drainage hole up and down.
Further preferred embodiment, the drainage hole are set on the fixed lobe and are evenly distributed.
Further preferred embodiment, the fixed lobe section are in isosceles triangle, and the groove section is the same as described solid
Fixed protrusion matching.
Further preferred embodiment, the front of the water-permeable brick ontology is equipped with non-slip groove laterally and/or longitudinally, described
The reverse side of water brick ontology is equipped with rhone laterally and/or longitudinally.
Further preferred embodiment, muti-piece water-permeable brick ontology with fixed lobe be embedded in adjacent one piece of groove it is combined and spliced at
Road surface, the drainage hole are hidden in adjacent groove.
The invention also discloses a kind of manufacturing methods for combining water-permeable brick, include the following steps:
1) firstly, production has the swaging die of water-permeable brick body shape: the swaging die includes the right side of water-permeable brick ontology
Side and rear side are equipped with the fixed lobe of triangle, and be evenly distributed semicircle drainage hole on the fixed lobe of the triangle, institute
It states on the left of water-permeable brick ontology and the corresponding position of front side is equipped with the groove of the triangle to match with fixed lobe, the water-permeable brick
The front of ontology is equipped with non-slip groove laterally and/or longitudinally, and the reverse side of the water-permeable brick ontology is equipped with row laterally and/or longitudinally
Sink;
2) concrete mortar is injected in swaging die, stands 3-12 hours after vibration;
3) it demoulds, conserves, storage obtains the water-permeable brick with concaveconvex structure.
The invention also discloses a kind of construction methods for combining water-permeable brick, include the following steps:
1) it arranges roadbed: the ground for needing to be laid with water-permeable brick being laid with tiny stone and/or sand 10-20cm, is arranged flat
It is whole;
2) be laid with water-permeable brick: be laid with since the one end or side on road surface, will with protrusion side be placed on front and
The right side is located at rear side and left side with reeded side, then will be before the protrusion insertion of the front side and right side of another piece of water-permeable brick
The corresponding groove in face and the right side so continues and is laid with until completing entire road surface;
3) per the gap for having one fixed width between adjacent water-permeable brick, connected by concaveconvex structure integral, drainage hole is hidden
In a groove, rainwater flows to ground along gap and drainage hole when raining for hiding, then permeates the ground.
Technical effect and advantage of the invention: the municipal administration water-permeable brick of paving the way utilizes male and fomale(M&F) when carrying out road pavement
Inlay fastening, be allowed to form an entirety, be not in loosen and the case where single water-permeable brick tilts, and without under hardening
The roadbed in face, facilitates rainwater infiltration;Especially there is discharge outlet up and down on side, accelerate rainwater infiltration, reduces road surface
Ponding;The positive laterally and/or longitudinally non-slip groove of brick body can increase friction, improve safety;The transverse direction of brick body reverse side and/
Or longitudinal drainage slot can increase the contact area of brick body and sub-surface, reinforce and stablize.In Severe rainstorm, water-permeable brick
The drainage hole of body upper surface can carry out assisted drainage, and the blocking of prevention gap accelerates the speed of entire road surface drainage, as early as possible
Restore the unimpeded of road surface, pedestrian is normally passed through.
Detailed description of the invention
Fig. 1 is schematic view of the front view of the invention;
Fig. 2 is the right side structural representation in the present invention;
Fig. 3 is schematic perspective view of the invention.
In figure: 1- fixed lobe, 2- non-slip groove, 3- drainage hole, 4- groove, 5- rhone.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Embodiment: attached drawing 1-3, a kind of combination water-permeable brick, including water-permeable brick ontology, the right side of the water-permeable brick ontology are referred to
Side and rear side are equipped with fixed lobe 1, and on the left of the water-permeable brick ontology and the corresponding position of front side with fixed lobe equipped with matching
Groove 4, the water-permeable brick ontology is equipped with drainage hole 3 up and down.
Further preferred embodiment, the drainage hole 3 are set to the fixation convex 1 above and are evenly distributed.
Further preferred embodiment, 1 section of fixed lobe are in isosceles triangle, and 4 section of groove is the same as described
Fixed lobe 1 matches.
Further preferred embodiment, the front of the water-permeable brick ontology is equipped with non-slip groove 2 laterally and/or longitudinally, described
The reverse side of water-permeable brick ontology is equipped with rhone 5 laterally and/or longitudinally.
Further preferred embodiment, it is combined and spliced that muti-piece water-permeable brick ontology with fixed lobe 1 is embedded in adjacent one piece of groove 4
At road surface, the drainage hole 3 is hidden in adjacent groove 4.
The present embodiment also discloses a kind of manufacturing method for combining water-permeable brick, includes the following steps:
(1) firstly, production has the swaging die of water-permeable brick body shape: the swaging die includes the right side of water-permeable brick ontology
Side and rear side are equipped with the fixed lobe 1 of triangle, and be evenly distributed semicircle drainage hole 3 on the fixed lobe 1 of the triangle,
On the left of the water-permeable brick ontology and the corresponding position of front side is equipped with the groove 4 of the triangle to match with fixed lobe 1, described
The front of water brick ontology is equipped with non-slip groove 2 laterally and/or longitudinally, and the reverse side of the water-permeable brick ontology is equipped with lateral and/or vertical
To rhone 5.
(2) concrete mortar is injected in swaging die, stands 3-12 hours after vibration.
(3) it is demoulded after brick body initial set hardening, water seasoning, storage obtains the water-permeable brick with concaveconvex structure.
The present embodiment also discloses a kind of construction method for combining water-permeable brick, includes the following steps:
1) it arranges roadbed: the ground for needing to be laid with water-permeable brick being laid with tiny stone and/or sand 10-20cm, is arranged flat
It is whole;
2) it is laid with water-permeable brick: being laid with since the one end or side on road surface, before the side with fixed lobe 1 is placed on
Face and the right side, the side with fluted 4 is located at rear side and left side, then that the fixation of the front side and right side of another piece of water-permeable brick is convex
1 insertion front groove 4 corresponding with the right side is played, so continues and is laid with until completing entire road surface;
3) per the gap for having one fixed width between adjacent water-permeable brick, connected by concaveconvex structure integral, drainage hole 3 is hidden
It ensconces in groove 4, rainwater flows to ground along gap and drainage hole 3 when raining, and then permeates the ground.
Water-permeable brick of the invention uses concave-convex mosaic connection, therefore road surface shape is integral, is not in monolithic brick body protrusion
Or the phenomenon that recess;In addition, due to not needing roadbed hardening, therefore save material and save working hour.
Claims (1)
1. a kind of manufacturing method for combining water-permeable brick, including water-permeable brick ontology, the right side of the water-permeable brick ontology and rear side are set
There is a fixed lobe, on the left of the water-permeable brick ontology and the corresponding position of front side is equipped with the groove to match with fixed lobe, described
Water-permeable brick ontology is equipped with drainage hole up and down, and the drainage hole is set on the fixed lobe and is evenly distributed, institute
Fixed lobe section is stated in isosceles triangle, the groove section is matched with the fixed lobe, the water-permeable brick ontology
Front is equipped with non-slip groove laterally and/or longitudinally, and the reverse side of the water-permeable brick ontology is equipped with rhone laterally and/or longitudinally,
Muti-piece water-permeable brick ontology is embedded in that adjacent one piece of groove is combined and spliced at road surface, and the drainage hole is hidden in phase with fixed lobe
In adjacent groove;
It is characterized in that, the manufacturing method of the combination water-permeable brick includes the following steps:
1) firstly, production have water-permeable brick body shape swaging die: the swaging die include water-permeable brick ontology right side and
Rear side is equipped with the fixed lobe of triangle, and be evenly distributed semicircle drainage hole on the fixed lobe of the triangle, described
On the left of water brick ontology and the corresponding position of front side is equipped with the groove of the triangle to match with fixed lobe, the water-permeable brick ontology
Front be equipped with non-slip groove laterally and/or longitudinally, the reverse side of the water-permeable brick ontology is equipped with draining laterally and/or longitudinally
Slot;
2) concrete mortar is injected in swaging die, stands 3-12 hours after vibration;
3) it demoulds, conserves, storage obtains the water-permeable brick with concaveconvex structure.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610629459.7A CN106087633B (en) | 2016-08-04 | 2016-08-04 | Combine the manufacturing method of water-permeable brick |
CN201811338304.3A CN109457565B (en) | 2016-08-04 | 2016-08-04 | Construction method of combined water permeable brick |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610629459.7A CN106087633B (en) | 2016-08-04 | 2016-08-04 | Combine the manufacturing method of water-permeable brick |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811338304.3A Division CN109457565B (en) | 2016-08-04 | 2016-08-04 | Construction method of combined water permeable brick |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106087633A CN106087633A (en) | 2016-11-09 |
CN106087633B true CN106087633B (en) | 2018-12-28 |
Family
ID=57453748
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811338304.3A Active CN109457565B (en) | 2016-08-04 | 2016-08-04 | Construction method of combined water permeable brick |
CN201610629459.7A Active CN106087633B (en) | 2016-08-04 | 2016-08-04 | Combine the manufacturing method of water-permeable brick |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811338304.3A Active CN109457565B (en) | 2016-08-04 | 2016-08-04 | Construction method of combined water permeable brick |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN109457565B (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106758678A (en) * | 2016-12-30 | 2017-05-31 | 苏州市清泽环境技术有限公司 | Multifunctional permeable water storage brick |
CN106882937A (en) * | 2017-03-01 | 2017-06-23 | 河海大学 | A kind of fiber and steel bar reinforced self-cleaning water permeable building block and preparation method thereof |
CN108221536A (en) * | 2018-01-12 | 2018-06-29 | 上海江叶园林景观工程有限公司 | A kind of regeneration floor and its application |
CN109024149A (en) * | 2018-09-20 | 2018-12-18 | 连云港东浦建筑工业化发展有限公司 | It is a kind of from saturating brick |
CN110904771B (en) * | 2019-12-16 | 2022-01-07 | 贵州瑞泰实业有限公司 | Water seepage brick capable of preventing rainwater from splashing |
CN111809473A (en) * | 2020-07-10 | 2020-10-23 | 晟远工程设计集团有限公司 | Road layered structure |
CN112627426B (en) * | 2020-12-05 | 2022-05-17 | 惠州市亚巴郎新型建材有限公司 | Environment-friendly aerated brick and preparation method thereof |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5797698A (en) * | 1996-04-10 | 1998-08-25 | F. Von Langsdorff Licensing Ltd. | Paving elements for the water-permeable reinforcement of surfaces |
CN2429551Y (en) * | 2000-06-02 | 2001-05-09 | 樊震波 | Environment protecting quick penetratable pavement |
CN1544378A (en) * | 2003-11-28 | 2004-11-10 | 北京科技大学 | Preparation and using method of steel slag colorful pavement brick with water penetrating function |
CN2673925Y (en) * | 2004-01-12 | 2005-01-26 | 谷曰能 | Environmental protection and water permeable brick for outdoor use |
US8827590B2 (en) * | 2007-01-19 | 2014-09-09 | Brock Usa | Structural underlayment support system and panel for use with paving and flooring elements |
CN205188746U (en) * | 2015-12-05 | 2016-04-27 | 海口保税区柏基彩砖有限公司 | Road protects anti -skidding brick of lock |
CN205347914U (en) * | 2015-12-11 | 2016-06-29 | 盐城市荣立新型建材有限公司 | Interlocking formula ecology concrete road surface brick that permeates water with water conservancy diversion hole |
CN205975249U (en) * | 2016-08-04 | 2017-02-22 | 苏州筑园景观规划设计股份有限公司 | Make up brick that permeates water |
Family Cites Families (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2551599C3 (en) * | 1975-11-18 | 1978-10-19 | Hoetzel-Beton Gmbh Betonsteinwerke, 7501 Eggenstein | Concrete mold plate for a floor covering for the storage of waste materials |
JPH0419048Y2 (en) * | 1988-05-16 | 1992-04-28 | ||
KR200301571Y1 (en) * | 2002-10-17 | 2003-01-24 | 김영훈 | paving brick with angled projections and slots on the tapered side wall |
CN100417767C (en) * | 2004-01-12 | 2008-09-10 | 谷曰能 | Permeable environmental protection ground tile used for outdoor service |
KR100718206B1 (en) * | 2004-09-24 | 2007-05-17 | 이인숙 | Permeable sidewalk block with non-slip protrusion |
KR100618168B1 (en) * | 2005-03-07 | 2006-09-06 | 정하영 | Permeable walking block |
CN201031335Y (en) * | 2006-09-13 | 2008-03-05 | 吴胜华 | Floor tile with tenon edge |
JP5835788B2 (en) * | 2010-10-06 | 2015-12-24 | 太平洋プレコン工業株式会社 | Drainage floor board and its laying body |
KR101316104B1 (en) * | 2011-10-07 | 2013-10-11 | 권대용 | Precast concrete panel |
CN202380373U (en) * | 2011-12-16 | 2012-08-15 | 宇杰集团股份有限公司 | Splash-proof floor tile |
CN202482730U (en) * | 2012-02-16 | 2012-10-10 | 云南省建筑科学研究院 | Permeable brick |
CN102995853A (en) * | 2012-10-28 | 2013-03-27 | 赵延波 | Drainage brick structure |
CN104032649A (en) * | 2014-05-23 | 2014-09-10 | 无锡市崇安区科技创业服务中心 | Greening brick |
CN204825542U (en) * | 2015-07-14 | 2015-12-02 | 杭州金得利装饰材料有限公司 | Multifunctional road square brick |
CN205152749U (en) * | 2015-11-06 | 2016-04-13 | 耿帅 | Composite construction drainage brick |
CN205313934U (en) * | 2015-12-15 | 2016-06-15 | 浙江凯胜园林市政建设有限公司 | Novel greening brick |
-
2016
- 2016-08-04 CN CN201811338304.3A patent/CN109457565B/en active Active
- 2016-08-04 CN CN201610629459.7A patent/CN106087633B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5797698A (en) * | 1996-04-10 | 1998-08-25 | F. Von Langsdorff Licensing Ltd. | Paving elements for the water-permeable reinforcement of surfaces |
CN2429551Y (en) * | 2000-06-02 | 2001-05-09 | 樊震波 | Environment protecting quick penetratable pavement |
CN1544378A (en) * | 2003-11-28 | 2004-11-10 | 北京科技大学 | Preparation and using method of steel slag colorful pavement brick with water penetrating function |
CN2673925Y (en) * | 2004-01-12 | 2005-01-26 | 谷曰能 | Environmental protection and water permeable brick for outdoor use |
US8827590B2 (en) * | 2007-01-19 | 2014-09-09 | Brock Usa | Structural underlayment support system and panel for use with paving and flooring elements |
CN205188746U (en) * | 2015-12-05 | 2016-04-27 | 海口保税区柏基彩砖有限公司 | Road protects anti -skidding brick of lock |
CN205347914U (en) * | 2015-12-11 | 2016-06-29 | 盐城市荣立新型建材有限公司 | Interlocking formula ecology concrete road surface brick that permeates water with water conservancy diversion hole |
CN205975249U (en) * | 2016-08-04 | 2017-02-22 | 苏州筑园景观规划设计股份有限公司 | Make up brick that permeates water |
Also Published As
Publication number | Publication date |
---|---|
CN109457565A (en) | 2019-03-12 |
CN109457565B (en) | 2020-09-04 |
CN106087633A (en) | 2016-11-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106087633B (en) | Combine the manufacturing method of water-permeable brick | |
CN205276099U (en) | Drainage formula brick that permeates water | |
CN205975249U (en) | Make up brick that permeates water | |
CN206034221U (en) | Cross combination lawn brick | |
CN207259895U (en) | A kind of municipal administration gardens greening brick | |
CN206352236U (en) | A kind of just dismounting type draining gardens floor tile | |
CN210194387U (en) | Make things convenient for ecological pavement of dismouting wooden way brick | |
CN212357853U (en) | Urban road assembled permeable pavement structure | |
KR100646814B1 (en) | Paving block | |
CN209099097U (en) | A kind of novel water permeable floor tile | |
CN209128845U (en) | A kind of anti-skidding garden path structure | |
CN205134135U (en) | Take curb of railing | |
CN206570637U (en) | A kind of curb with osculum | |
CN201183957Y (en) | Highway side slope retaining wall | |
CN207512544U (en) | A kind of road kerbstone | |
CN106065554A (en) | A kind of greening of parking yard brick and manufacture thereof and construction method | |
CN206428544U (en) | A kind of New-type paving tile | |
KR200361674Y1 (en) | EcoLogical Type Road curbstone | |
CN201981463U (en) | Drainage flat stone for road paving | |
CN210621369U (en) | Multifunctional special-shaped floor tile | |
CN211420750U (en) | Gardens road surface antiskid brick | |
CN207891681U (en) | L-type curb stone-arch culvert | |
KR200172434Y1 (en) | Assembling footpath block | |
CN218466578U (en) | Drainage guide device for beautifying drain hole of retaining wall | |
CN106284014A (en) | Cross combines lawn brick and manufacture thereof and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |