CN106050303A - Underground roadway plugging method and device - Google Patents

Underground roadway plugging method and device Download PDF

Info

Publication number
CN106050303A
CN106050303A CN201610619209.5A CN201610619209A CN106050303A CN 106050303 A CN106050303 A CN 106050303A CN 201610619209 A CN201610619209 A CN 201610619209A CN 106050303 A CN106050303 A CN 106050303A
Authority
CN
China
Prior art keywords
filling
framework
pipeline
filler
bag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610619209.5A
Other languages
Chinese (zh)
Inventor
史文豹
常聚才
马海峰
李传明
丁长栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui University of Science and Technology
Original Assignee
Anhui University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui University of Science and Technology filed Critical Anhui University of Science and Technology
Priority to CN201610619209.5A priority Critical patent/CN106050303A/en
Publication of CN106050303A publication Critical patent/CN106050303A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention relates to an underground roadway plugging method and device. According to the underground roadway plugging method and device, the structure is simple, operation is convenient and safe, the workload of workers can be reduced, and the efficiency of workers can be improved. The underground roadway plugging method and device are characterized in that a frame of a plugging wall is built with steel rods, wood plates and a steel bar net, then filling bags are arranged in the frame, a pump station is arranged within a certain distance of the frame and used for stirring high-water-content materials, the filling bags are filled with filling materials through a pipeline after being well supported, and roadway plugging can be carried out after the filling materials are solidified. The method and the device are simple, effective and beneficial to efficient production of a mine.

Description

A kind of underworkings method for blocking and device
Technical field:
The method that the present invention relates to the closure of a kind of underworkings, uses a kind of simple mechanism water blockoff, prevents fires, hinders gas.
Background technology:
At present, coal mine roadway, during driving uses, needs because producing, and some tunnel needs discarded, for avoiding tunnel The secondary harm brought, such as retention of excessive fluid, Gas Outburst or even spontaneous combustion of coal seam ignition etc., it is necessary to process tunnel.? Straightforward procedure is by laneway plugging, intercepts one section and utilizes material tunneling boring to block, and isolation tunnel contacts with mine production system. At present, the closure of underworkings is mainly cement injection closure, and closure framework mainly has two kinds, and one is in laneway plugging position The upper wall of each block front and back, then closes space cement injection to this, and another kind is to replace building a wall with plank, sets up mould with plank Son, constitutes and closes space then slip casting.Cement injection closure can block tunnel, but construction technology is complicated, and operability difficulty Greatly, especially it may happen that plugging during slip casting, cost and the amount of labour are increased.
Summary of the invention:
In order to overcome the deficiency that existing technique can not facilitate workman to construct well and cost is bigger, the present invention provides one Planting new method, this method can not only make the technique in closure tunnel simply, more can reduce mine production costs.
The technical solution adopted in the present invention is: installing pumping plant away from the tunnel rational position that need to block, facilitate haul and Equipment is put, and at filling pumping plant stirring high-water material, (height of a kind of rapid condensation coagulates water material, ratio of mud 2:1, and comprcssive strength reaches 9MPa), utilize anchor pole, plank, filling bag to put up filling mould at block-up position simultaneously, pass through after casting resin stirring fully Pipeline injects filling mould, and block wall is the formation of.
The present invention has the advantage that with good effect: equipment is simple, and labor strength is low, safe, economical, effectively.
Accompanying drawing illustrates:
Fig. 1 is the laneway plugging location drawing.
Fig. 2 is closure framework sectional drawing.
Fig. 3 is filling pumping plant figure.
Fig. 4 is filling pumping plant I-1 profile
Fig. 5 is filling bag accompanying drawing.
Wherein: 1-tunnel, 2-steel rod, 3-plank, 4-bar-mat reinforcement, 5-filling bag, 6-filling pipeline, 7-midge pipeline, 8- Filling pump, 9-hydraulic fluid tank, 10-first material agitator, 11-second material agitator, 12-stirring pool, 13-blowoff basin, 14-link, 15-note Slurry mouth.
Detailed description of the invention:
The present invention is further described with embodiment below in conjunction with the accompanying drawings.
In Fig. 1, Fig. 2, building closure framework in laneway plugging position, substitute enclosing wall, the outside composition of closure framework is filled Fill out barricade before and after bag, be made up of steel rod (2), plank (3), bar-mat reinforcement (4), then filling bag (5) is hung over closing space, fills Top and the surrounding of filling out bag (5) have the part that can be used for fixing.Closure framework build process is: utilize air drill or other instruments Play 1-2m deep drilling at closure front-and-back stop wall displacement every 1m, then firm rod (2) is inserted in boring, because of drift section diverse location Height different, press desired height connection steel rod (2) at diverse location, after connecting, plank (3) tied up at the steel rod (2) put up On, tie up lastblock every 800mm the most successively, depending on length is because of span length, then bar-mat reinforcement (4) is suspended on plank (3). Wherein plank (3) uses veneer, width about 25mm, moderate length, conveniently binds;Bar-mat reinforcement (4) is by fine steel rib Constituting, be commonly called as " reinforcing bar embankment ", use reinforcing rod to connect reinforcing rod by 10 × 20 eyelet weldings, " reinforcing bar embankment " length and width are regarding tunnel needs Fixed, it is therefore an objective to the space of plank (4) and steel rod (2) to be blocked, in order to filling bag not external drum, prevent obturator in stowing operation from inhaling Thermal expansion, causes the support of filling bag big, and generation is split up.After barricade is constructed, filling bag is sent into, each angle of filling bag is tied up Surely arrive predetermined position, with good conditionsi hang up properly filling bag after and air blast inflation in filling bag so that filling bag is heaved to needs Each corner of filling, improves the utilizing status of filling bag.Closure framying completes, followed by slip casting in filling bag.
In figure 3, during closure framework installs, Fig. 4 filling pumping plant starts spice, and first, second material is respectively with mining Railway carriage feed, railway carriage stops in orbit, and in figure, filling pump (8) is placed on centre, first, second material be individually placed to first material agitator (10), Second material agitator (11) stirs, and this equipment is positioned in stirring pool (12), and first, second material is watered the most by a certain percentage, stirs 3-5 Minute, work surface filling bag Zhi Haohou opens pressure-oil tank (9), and due to pressure effect, first, second serosity is respectively by pulp-absorbing pipe (7) Sucking, the most filled pipeline (6) is transported to work surface, connects one between filling bag pipeline and first, second filling pipeline Individual blender, makes two kinds of serosity reinject filling bag after being sufficiently mixed.After filling operation completes, with clean water pump and pipeline, Making full use of the serosity in pipeline, prevent serosity plugging, cleaned water from injecting work surface, remaining water passes through rhone (13) Being discharged in water channel, mixed serosity solidified about half an hour, within one day, i.e. can reach certain comprcssive strength, within seven days, reached maximum Comprcssive strength.

Claims (3)

1. underworkings method for blocking and a device, when plugged and abandoned tunnel, utilizes a kind of filler, from adapting to pipeline The angle of transport features proposes a kind of new method, it is characterised in that: utilize steel rod, plank, bar-mat reinforcement to construct the framework of block wall, Then being arranged in framework by filling bag, arranging pumping plant stirring high-water material in framework certain distance, bag to be filled props up Injecting in filling bag by pipeline by filler afterwards, filler solidification can be by laneway plugging.
Underworkings method for blocking the most according to claim 1 and device, it is characterised in that: Gao Shuicai selected by filler Material, it is simple to transport, filling pumping plant is placed on the correct position in tunnel.
Underworkings method for blocking the most according to claim 1 and device, it is characterised in that: the closure framework of filling bag by The compositions such as easy steel rod, plank, bar-mat reinforcement, simple and convenient, stable firm.
CN201610619209.5A 2016-07-29 2016-07-29 Underground roadway plugging method and device Pending CN106050303A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610619209.5A CN106050303A (en) 2016-07-29 2016-07-29 Underground roadway plugging method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610619209.5A CN106050303A (en) 2016-07-29 2016-07-29 Underground roadway plugging method and device

Publications (1)

Publication Number Publication Date
CN106050303A true CN106050303A (en) 2016-10-26

Family

ID=57196099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610619209.5A Pending CN106050303A (en) 2016-07-29 2016-07-29 Underground roadway plugging method and device

Country Status (1)

Country Link
CN (1) CN106050303A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107387162A (en) * 2017-06-29 2017-11-24 山东科技大学 A kind of tunnel hermatic door, tunnel brattice and preparation method thereof
CN112065503A (en) * 2020-08-31 2020-12-11 西山煤电(集团)有限责任公司 Mine roadway rapid sealing method
CN112196610A (en) * 2020-09-23 2021-01-08 贵州大学 Water drilling mining structure for eliminating gas outburst of inclined coal seam and mining method thereof
CN112627892A (en) * 2020-12-21 2021-04-09 中国矿业大学 Closed wall construction method based on reinforcing mesh and high-water-content material

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4001629A (en) * 1974-08-26 1977-01-04 Panel Technology, Inc. Segmented gas discharge display panel
CN102777208A (en) * 2012-08-02 2012-11-14 兖州煤业股份有限公司 Method for constructing mining impact-resisting sealed wall
CN103397906A (en) * 2013-08-05 2013-11-20 北京科技大学 Grouting type filling retaining wall, construction method of grouting type filling retaining wall and goaf filling system and method
CN103711518A (en) * 2014-01-03 2014-04-09 山东汇发矿业科技有限公司 Portable mine filling retaining wall
CN105736046A (en) * 2016-02-25 2016-07-06 北京瑞诺安科新能源技术有限公司 Coal mine underground sealed wall body and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4001629A (en) * 1974-08-26 1977-01-04 Panel Technology, Inc. Segmented gas discharge display panel
CN102777208A (en) * 2012-08-02 2012-11-14 兖州煤业股份有限公司 Method for constructing mining impact-resisting sealed wall
CN103397906A (en) * 2013-08-05 2013-11-20 北京科技大学 Grouting type filling retaining wall, construction method of grouting type filling retaining wall and goaf filling system and method
CN103711518A (en) * 2014-01-03 2014-04-09 山东汇发矿业科技有限公司 Portable mine filling retaining wall
CN105736046A (en) * 2016-02-25 2016-07-06 北京瑞诺安科新能源技术有限公司 Coal mine underground sealed wall body and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107387162A (en) * 2017-06-29 2017-11-24 山东科技大学 A kind of tunnel hermatic door, tunnel brattice and preparation method thereof
CN107387162B (en) * 2017-06-29 2020-02-18 山东科技大学 Roadway sealing door, roadway air wall and manufacturing method thereof
CN112065503A (en) * 2020-08-31 2020-12-11 西山煤电(集团)有限责任公司 Mine roadway rapid sealing method
CN112196610A (en) * 2020-09-23 2021-01-08 贵州大学 Water drilling mining structure for eliminating gas outburst of inclined coal seam and mining method thereof
CN112627892A (en) * 2020-12-21 2021-04-09 中国矿业大学 Closed wall construction method based on reinforcing mesh and high-water-content material

Similar Documents

Publication Publication Date Title
CN101967992B (en) Different-strength bearing roadside filler for pillar-free mining of thin coal bed
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN106050303A (en) Underground roadway plugging method and device
CN106837418B (en) Mining explosion-proof trapezoidal sealing wall and construction method thereof
CN101858215B (en) Road retained method for extrusion molding of waste rock
CN108999188A (en) Crushing device, restructuring bankrupt and the application of cast-in-situ bored pile pile crown
CN206495682U (en) A kind of stand quickly handled for Tunnel Landslide
CN101949301A (en) Different-strength bearing roadway-beside filling body of gob-side entry under coal mine
CN104653198B (en) Method for filling and constructing foam concrete in coal mine soft rock largely-deformed roadway supporter
CN110761797B (en) Construction method for shield air-pushing through mine tunnel
CN106089252B (en) Grouting reinforcement method for inhomogeneous loose bodies
CN102852551A (en) Gob-side entry retaining method using high-water material filling columns
CN203756230U (en) Mold bag type sealed retaining wall capable of being quickly formed
CN107448234A (en) A kind of colliery pours closed wall construction method
CN207620844U (en) A kind of mine high-water material filling unit
CN101439950A (en) Flexible coal powder foam concrete and preparation thereof
CN110578532A (en) Gob-side entry retaining arrangement method
CN207620842U (en) A kind of mine high-water material filling bag fixed frame
CN113756868A (en) Geotechnical engineering underground side wall construction method
CN105937400B (en) It is a kind of once to tunnel Liu Sheshuan lanes digging operation production line
CN112196617A (en) Simple combined filling retaining wall construction method
CN110863856A (en) Road-entering type cemented filling plugging wall and construction method thereof
CN104594369B (en) Karst region high-pressure group hole replacement grouting method and structure thereof
CN113803092B (en) Supporting device and method for broken soft rock roadway based on steel pipe concrete support
CN110056372A (en) Concrete pouring method in lining construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161026

WD01 Invention patent application deemed withdrawn after publication