CN106049539A - Building project construction method - Google Patents

Building project construction method Download PDF

Info

Publication number
CN106049539A
CN106049539A CN201610404378.7A CN201610404378A CN106049539A CN 106049539 A CN106049539 A CN 106049539A CN 201610404378 A CN201610404378 A CN 201610404378A CN 106049539 A CN106049539 A CN 106049539A
Authority
CN
China
Prior art keywords
construction
layer
mortar
line
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610404378.7A
Other languages
Chinese (zh)
Inventor
谢雷
史竹明
李文张
张俊
史竹远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yi An Construction Co Ltd
Original Assignee
Jiangsu Yi An Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yi An Construction Co Ltd filed Critical Jiangsu Yi An Construction Co Ltd
Priority to CN201610404378.7A priority Critical patent/CN106049539A/en
Publication of CN106049539A publication Critical patent/CN106049539A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D11/00Roof covering, as far as not restricted to features covered by only one of groups E04D1/00 - E04D9/00; Roof covering in ways not provided for by groups E04D1/00 - E04D9/00, e.g. built-up roofs, elevated load-supporting roof coverings
    • E04D11/02Build-up roofs, i.e. consisting of two or more layers bonded together in situ, at least one of the layers being of watertight composition
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/04Flooring or floor layers composed of a number of similar elements only of wood or with a top layer of wood, e.g. with wooden or metal connecting members

Abstract

The invention relates to a building project construction method. The building project construction method comprises the steps of measuring, paying off, construction of a pile foundation, construction of a foundation pit support, earthwork excavation, construction of a foundation under layer, bottom plate water prevention construction, construction of a basement formwork, binding of basement reinforced bars, basement concrete construction, basement external wall water prevention, segmental inspection and acceptance of subgrade and the foundation, earthwork backfilling, construction of a body structure, wall body laying, segmental inspection and acceptance of a main body, wall body plastering, external wall heat insulation, dry hanging of stones, constructions of wall face bricks, construction of building floor tiles, construction of laying of hardwood floors of a building floor, construction of building floor carpets, wall face emulsion paint coating, mounting of doors and windows, segmental inspection and acceptance of finishing and decorating, roof leveling blanket construction, roof slope construction, roof heat insulation layer construction, roof waterproof layer construction, construction of a polyvinyl chloride plastic thin film insulation layer, roof rigid layer construction, roof segmental inspection and acceptance, project pre-inspection and acceptance and project final inspection and acceptance. The construction steps are precise, the automation degree is high, and the construction efficiency is high.

Description

A kind of building engineering construction method
Technical field
The invention belongs to building field, be specifically related to a kind of construction techniques.
Background technology
Building engineering construction is labour-intensive operation, needs a large amount of general work and extraordinary operator construct simultaneously or intersect Operation, automatization level is the highest and human cost is high.And, often due to stop wait without operation side, cause construction Inefficient.Additionally, building engineering construction belongs to high-risk operation, need to consume a large amount of human and material resources, financial resources go ensure safety Construction.
Summary of the invention
Goal of the invention: the invention aims to overcome deficiency of the prior art, it is provided that a kind of construction procedure is rigorous, Automatization level is high, the building engineering construction method that efficiency of construction is high.
Technical scheme: in order to solve above-mentioned technical problem, a kind of building engineering construction method of the present invention, it includes Following steps,
(1) surveying setting-out: with 1 axle on architectural drawing as X-axis, with the A axle on drawing as Y-axis, with the intersection point of 1 axle with A axle be Initial point sets up rectangular coordinate system, sets up engineering plane tracking and command network with this;
(2) pile foundation construction;
(3) foundation pit support construction;
(4) earth excavation;
(5) blinding layer construction: according to drawing absolute altitude, formwork, pour concrete;
(6) Slab Waterproof Construction: water-repellent paint stirs, was finished in 30 minutes;
(7) basement template construction: according to drawing, uses safe software for calculation to carry out docking pitch of bolts and calculates, it is ensured that template The safety supported and firmness;
(8) basement reinforcing bar binding;
(9) basement concrete construction;
(10) outer wall of basement is waterproof: coil waterproof layer should be from the most upwards paving of negative and positive angular position, the first of negative and positive angular position Block coiled material, plane and facade respectively paste half range, then eject datum line on the overlap edge spreading coiled material, by line paving coiled material;
(11) ground is checked and accepted with basis branch;
(12) backfilling of earthwork;
(13) main structure construction;
(14) building wall: structurally bullet good+1000mm grade level line, and door opening, the control line of windowsill height, door on bullet The hole position line, the stile line of the good masonry of bullet on structure wall column, according to the door-window opening position line that bullet is good, determine row's stock mould number;
(15) main body branch checks and accepts;
(16) wall plastering: mortar, dust in being stitched by Door and window frame are cleaned out, by concrete component surface mortar, dust, dirt Clean with water clean, with 10% Caustic soda water, the greasy dirt in plate face is brushed off, alkali liquor is washed down with water purification, dries immediately, then use special interface Agent air pressure pump is sprayed onto on metope, and its specking is wanted uniformly, and burr length is not more than 8mm, water seasoning after final set, until cement bonded sand Slurry burr hands break motionless till, the complete suitable watering of base treatment, according to drawing mortar strength require plaster;
(17) exterior-wall heat insulation;
(18) dry-hang stone;
(19) walltile construction;
(20) flooring floor tile construction: according to sheet material size dimension, textured pattern, permission gap, bullet on clean screed-coat Control line, is carried out to both sides by center, room, finds rule and flashing, is cleaned up by the floor tile matched, puts in clear water After soaking 2-3h, taking-up is dried standby, during tile work, should smear pad cement mortar, first spread positioning belt in length and breadth by line, and positioning belt is respectively separated by 15- 20 bricks, the most from inside outwards move back the floor tile spreading in positioning belt, and it is smooth closely knit that floor tile presses control line paving, has often spread one Paragraph, slightly sprinkles water with watering can moistening, crosses about 15min, carries out dialling seam straightening by layup sequence transverse joint with wooden mallet and hardwood plate, makes Mortar on the interior remaining slurry of seam or brick face is wiped, and flattens group seam from laying mortar, should work continuously, must complete by 5-6h under room temperature, After having spread floor tile 2d, being cleaned out by sealing, swabbing moistens, and uses 1:1 pointing with cement mortar, and jointing should closely knit, smooth, light Sliding, then with napkin, floor cleaning is clean, maintenance must not be less than 4d;
(21) flooring real paving hardwood flooring construction: start with wall side, tightly spreads nail by the bar shaped wood plank heart upwards block-by-block row, seam Gap should be on rough ground less than the interface of 10mm plate;
(22) flooring carpet construction: first at basic unit's upper berth establishing set rubber cushion, nail on seta bar in top fixed point or edge, connect , according to the concrete size in room, cut out carpet, to good position, then napped to four limits by middle part, support with blanket, by carpet Pushing away whole unfolding of washing, surface tension is uniform, finally clings fixing with seta bar;
(23) metope emulsion paint: remove substrate surface dust and other bur, coating stir after from top to bottom, from left The right side carries out roller coat;
(24) erection of doors and windows: according to carrying out setting-out work shown in drawing, frame is directly fixed on the wall base body of hole, installs by label Bar, treats that erection of doors and windows is complete, and every width door and window peripheral carries out waterproof sealing process, fluid sealant and glass and sash, fan The adhesion width of section bar is not less than 5mm;
(25) fit up and decorate branch's examination;
(26) roofing screed-coat: according to optimizing figure, places rustless steel venthole, and carries out by cement mortar solid at crisscross place Fixed, look for slope to paste ash cake according to slope requirement bracing wire, press 1.5m spacing floating screed along drainage direction, with plain-water slurry pulp sweeping together, paving If cement mortar, strike off by floating screed with 2.0m long aluminium alloy floating rule, levelling after rub with the hands flat with wooden float, plasterer's trowel press polish, treat mortar Starting to condense, people has stepped on footprint when not sinking, with second time press polish of plasterer's trowel;
(27) roof slope making layer: put slope according to roofing and require to eject watershed line, look for the slope of 2% to drain gully, laying the previous day should be by Basic unit is the most moistening, lay Shi Shouchu basic unit do not feel dry, during laying, should void paving to the 130% of design height, after use plank Make real to design requirement;
(28) roofing heat-insulating layer: remove the rubbish such as the dust of substrate surface, oil thing, make surface keep cleaning, eject exhaust duct The position line, warming plate completely spreads 5 thick special adhesive mortars are flat to be bonded on roofing mortar levelling layer, places and buries underground in length and breadth at expansion joint Φ 50PVC exhaustor, exhaustor is completely beaten the aperture of quincuncial arrangement, and uses Dense mesh screen to wrap up, and rock wool is used on exhaustor top Cover;
(29) roof waterproof layer: base cleaning is clean, painting priming, 8-12h after brushing, when feel is not glued, each layer time Painting THICKNESS CONTROL is at about 0.5mm, and brushing direction is vertical with ground floor;The second layer touch dry after brushing third layer, brushing direction with Ground floor is identical, by that analogy, until design thickness;
(30) polyvinyl chloride plastic film sealing coat: should extend from side to opposite side, the landing edge of adjacent two width should be Article one, on horizontal line, should mutually stagger more than 1m, and film is typically no less than 10cm with the lap width of the seam of film;
(31) roofing rigid layer: according to optimizing figure, eject the parting seam position line, fixes 20 thick 400 grams of extrusion moldings by 1:2 cement mortar Plate, smears on sealing coat by concrete paving, and then strikes off along mark muscle with the long darby of 2m, then comes and goes with cylinder, roll in length and breadth Pressure, then strike off with the long darby of 2m, twice press polish;
(32) roofing branch checks and accepts;
(33) engineering is checked and accepted in advance;
(34) completion of works is checked and accepted.
Beneficial effect: compared with prior art, its remarkable advantage is the present invention: the present invention is executed by surveying setting-out, pile foundation The construction of work, foundation pit support construction, earth excavation, blinding layer, Slab Waterproof Construction, basement template construction, basement reinforcing bar Colligation, the construction of basement concrete, outer wall of basement is waterproof, ground and basis branch examination, backfilling of earthwork, body structure construction, body of wall Build by laying bricks or stones, the examination of main body branch, wall plastering, exterior-wall heat insulation, dry-hang stone, walltile construction, flooring floor tile construction, flooring Real paving hardwood flooring construction, the construction of flooring carpet, metope emulsion paint, erection of doors and windows, fit up with decorate branch's examination, roofing is looked for Flat bed, roof slope making layer, roofing heat-insulating layer, roof waterproof layer, polyvinyl chloride plastic film sealing coat, roofing rigid layer, roofing Branch checks and accepts, engineering is checked and accepted in advance, completion of works is checked and accepted, and above-mentioned construction procedure is rigorous, and automatization level is high, and efficiency of construction is high, builds Build engineering construction equipment and construction method has only to technical staff and manages equipment operation, material preparation and field management, can save The manual construction operation in most workers job site, thus save Construction Cost, meanwhile, engineering construction information can be improved Change, automatization and visualized construction technology level.
Detailed description of the invention
Below in conjunction with embodiment, the present invention is further illustrated.
A kind of building engineering construction method of the present invention, it comprises the following steps,
(1) surveying setting-out: with 1 axle on architectural drawing as X-axis, with the A axle on drawing as Y-axis, with the intersection point of 1 axle with A axle be Initial point sets up rectangular coordinate system, sets up engineering plane tracking and command network with this;
(2) pile foundation construction;
(3) foundation pit support construction;
(4) earth excavation;
(5) blinding layer construction: according to drawing absolute altitude, formwork, pour concrete;
(6) Slab Waterproof Construction: water-repellent paint stirs, was finished in 30 minutes;
(7) basement template construction: according to drawing, uses safe software for calculation to carry out docking pitch of bolts and calculates, it is ensured that template The safety supported and firmness;
(8) basement reinforcing bar binding;
(9) basement concrete construction;
(10) outer wall of basement is waterproof: coil waterproof layer should be from the most upwards paving of negative and positive angular position, the first of negative and positive angular position Block coiled material, plane and facade respectively paste half range, then eject datum line on the overlap edge spreading coiled material, by line paving coiled material;
(11) ground is checked and accepted with basis branch;
(12) backfilling of earthwork;
(13) main structure construction;
(14) building wall: structurally bullet good+1000mm grade level line, and door opening, the control line of windowsill height, door on bullet The hole position line, the stile line of the good masonry of bullet on structure wall column, according to the door-window opening position line that bullet is good, determine row's stock mould number;
(15) main body branch checks and accepts;
(16) wall plastering: mortar, dust in being stitched by Door and window frame are cleaned out, by concrete component surface mortar, dust, dirt Clean with water clean, with 10% Caustic soda water, the greasy dirt in plate face is brushed off, alkali liquor is washed down with water purification, dries immediately, then use special interface Agent air pressure pump is sprayed onto on metope, and its specking is wanted uniformly, and burr length is not more than 8mm, water seasoning after final set, until cement bonded sand Slurry burr hands break motionless till, the complete suitable watering of base treatment, according to drawing mortar strength require plaster;
(17) exterior-wall heat insulation;
(18) dry-hang stone;
(19) walltile construction;
(20) flooring floor tile construction: according to sheet material size dimension, textured pattern, permission gap, bullet on clean screed-coat Control line, is carried out to both sides by center, room, finds rule and flashing, is cleaned up by the floor tile matched, puts in clear water After soaking 2-3h, taking-up is dried standby, during tile work, should smear pad cement mortar, first spread positioning belt in length and breadth by line, and positioning belt is respectively separated by 15- 20 bricks, the most from inside outwards move back the floor tile spreading in positioning belt, and it is smooth closely knit that floor tile presses control line paving, has often spread one Paragraph, slightly sprinkles water with watering can moistening, crosses about 15min, carries out dialling seam straightening by layup sequence transverse joint with wooden mallet and hardwood plate, makes Mortar on the interior remaining slurry of seam or brick face is wiped, and flattens group seam from laying mortar, should work continuously, must complete by 5-6h under room temperature, After having spread floor tile 2d, being cleaned out by sealing, swabbing moistens, and uses 1:1 pointing with cement mortar, and jointing should closely knit, smooth, light Sliding, then with napkin, floor cleaning is clean, maintenance must not be less than 4d;
(21) flooring real paving hardwood flooring construction: start with wall side, tightly spreads nail by the bar shaped wood plank heart upwards block-by-block row, seam Gap should be on rough ground less than the interface of 10mm plate;
(22) flooring carpet construction: first at basic unit's upper berth establishing set rubber cushion, nail on seta bar in top fixed point or edge, connect , according to the concrete size in room, cut out carpet, to good position, then napped to four limits by middle part, support with blanket, by carpet Pushing away whole unfolding of washing, surface tension is uniform, finally clings fixing with seta bar;
(23) metope emulsion paint: remove substrate surface dust and other bur, coating stir after from top to bottom, from left The right side carries out roller coat;
(24) erection of doors and windows: according to carrying out setting-out work shown in drawing, frame is directly fixed on the wall base body of hole, installs by label Bar, treats that erection of doors and windows is complete, and every width door and window peripheral carries out waterproof sealing process, fluid sealant and glass and sash, fan The adhesion width of section bar is not less than 5mm;
(25) fit up and decorate branch's examination;
(26) roofing screed-coat: according to optimizing figure, places rustless steel venthole, and carries out by cement mortar solid at crisscross place Fixed, look for slope to paste ash cake according to slope requirement bracing wire, press 1.5m spacing floating screed along drainage direction, with plain-water slurry pulp sweeping together, paving If cement mortar, strike off by floating screed with 2.0m long aluminium alloy floating rule, levelling after rub with the hands flat with wooden float, plasterer's trowel press polish, treat mortar Starting to condense, people has stepped on footprint when not sinking, with second time press polish of plasterer's trowel;
(27) roof slope making layer: put slope according to roofing and require to eject watershed line, look for the slope of 2% to drain gully, laying the previous day should be by Basic unit is the most moistening, lay Shi Shouchu basic unit do not feel dry, during laying, should void paving to the 130% of design height, after use plank Make real to design requirement;
(28) roofing heat-insulating layer: remove the rubbish such as the dust of substrate surface, oil thing, make surface keep cleaning, eject exhaust duct The position line, warming plate completely spreads 5 thick special adhesive mortars are flat to be bonded on roofing mortar levelling layer, places and buries underground in length and breadth at expansion joint Φ 50PVC exhaustor, exhaustor is completely beaten the aperture of quincuncial arrangement, and uses Dense mesh screen to wrap up, and rock wool is used on exhaustor top Cover;
(29) roof waterproof layer: base cleaning is clean, painting priming, 8-12h after brushing, when feel is not glued, each layer time Painting THICKNESS CONTROL is at about 0.5mm, and brushing direction is vertical with ground floor;The second layer touch dry after brushing third layer, brushing direction with Ground floor is identical, by that analogy, until design thickness;
(30) polyvinyl chloride plastic film sealing coat: should extend from side to opposite side, the landing edge of adjacent two width should be Article one, on horizontal line, should mutually stagger more than 1m, and film is typically no less than 10cm with the lap width of the seam of film;
(31) roofing rigid layer: according to optimizing figure, eject the parting seam position line, fixes 20 thick 400 grams of extrusion moldings by 1:2 cement mortar Plate, smears on sealing coat by concrete paving, and then strikes off along mark muscle with the long darby of 2m, then comes and goes with cylinder, roll in length and breadth Pressure, then strike off with the long darby of 2m, twice press polish;
(32) roofing branch checks and accepts;
(33) engineering is checked and accepted in advance;
(34) completion of works is checked and accepted.
The present invention is prevented by surveying setting-out, pile foundation construction, foundation pit support construction, earth excavation, blinding layer construction, base plate Water construction, basement template construction, basement reinforcing bar binding, basement concrete are constructed, outer wall of basement is waterproof, ground divides with basis Portion's examination, backfilling of earthwork, body structure construction, building wall, the examination of main body branch, wall plastering, exterior-wall heat insulation, dry-hang stone, Walltile construction, the construction of flooring floor tile, flooring real paving hardwood flooring construction, the construction of flooring carpet, metope emulsion paint, door Window is installed, is fitted up and decorate branch's examination, roofing screed-coat, roof slope making layer, roofing heat-insulating layer, roof waterproof layer, polychlorostyrene second Alkene plastics thin film sealing coat, roofing rigid layer, roofing branch check and accept, engineering check and accept in advance, completion of works check and accept, above-mentioned construction procedure Rigorous, automatization level is high, and efficiency of construction is high, and building engineering construction equipment and construction method have only to technical staff and manage equipment Operation, material prepare and field management, can save the manual construction operation in most workers job site, thus save engineering construction Cost, meanwhile, can improve engineering construction informationization, automatization and visualized construction technology level.
The invention provides a kind of thinking and method, the method and the approach that implement this technical scheme are a lot, above institute State is only the preferred embodiment of the present invention, it is noted that for those skilled in the art, without departing from On the premise of the principle of the invention, it is also possible to make some improvements and modifications, these improvements and modifications also should be regarded as the guarantor of the present invention Protecting scope, each ingredient the clearest and the most definite in the present embodiment all can use prior art to be realized.

Claims (1)

1. a building engineering construction method, it is characterised in that: it comprises the following steps,
(1) surveying setting-out: with 1 axle on architectural drawing as X-axis, with the A axle on drawing as Y-axis, with the intersection point of 1 axle with A axle be Initial point sets up rectangular coordinate system, sets up engineering plane tracking and command network with this;
(2) pile foundation construction;
(3) foundation pit support construction;
(4) earth excavation;
(5) blinding layer construction: according to drawing absolute altitude, formwork, pour concrete;
(6) Slab Waterproof Construction: water-repellent paint stirs, was finished in 30 minutes;
(7) basement template construction: according to drawing, uses safe software for calculation to carry out docking pitch of bolts and calculates, it is ensured that template The safety supported and firmness;
(8) basement reinforcing bar binding;
(9) basement concrete construction;
(10) outer wall of basement is waterproof: coil waterproof layer should be from the most upwards paving of negative and positive angular position, the first of negative and positive angular position Block coiled material, plane and facade respectively paste half range, then eject datum line on the overlap edge spreading coiled material, by line paving coiled material;
(11) ground is checked and accepted with basis branch;
(12) backfilling of earthwork;
(13) main structure construction;
(14) building wall: structurally bullet good+1000mm grade level line, and door opening, the control line of windowsill height, door on bullet The hole position line, the stile line of the good masonry of bullet on structure wall column, according to the door-window opening position line that bullet is good, determine row's stock mould number;
(15) main body branch checks and accepts;
(16) wall plastering: mortar, dust in being stitched by Door and window frame are cleaned out, by concrete component surface mortar, dust, dirt Clean with water clean, with 10% Caustic soda water, the greasy dirt in plate face is brushed off, alkali liquor is washed down with water purification, dries immediately, then use special interface Agent air pressure pump is sprayed onto on metope, and its specking is wanted uniformly, and burr length is not more than 8mm, water seasoning after final set, until cement bonded sand Slurry burr hands break motionless till, the complete suitable watering of base treatment, according to drawing mortar strength require plaster;
(17) exterior-wall heat insulation;
(18) dry-hang stone;
(19) walltile construction;
(20) flooring floor tile construction: according to sheet material size dimension, textured pattern, permission gap, bullet on clean screed-coat Control line, is carried out to both sides by center, room, finds rule and flashing, is cleaned up by the floor tile matched, puts in clear water After soaking 2-3h, taking-up is dried standby, during tile work, should smear pad cement mortar, first spread positioning belt in length and breadth by line, and positioning belt is respectively separated by 15- 20 bricks, the most from inside outwards move back the floor tile spreading in positioning belt, and it is smooth closely knit that floor tile presses control line paving, has often spread one Paragraph, slightly sprinkles water with watering can moistening, crosses about 15min, carries out dialling seam straightening by layup sequence transverse joint with wooden mallet and hardwood plate, makes Mortar on the interior remaining slurry of seam or brick face is wiped, and flattens group seam from laying mortar, should work continuously, must complete by 5-6h under room temperature, After having spread floor tile 2d, being cleaned out by sealing, swabbing moistens, and uses 1:1 pointing with cement mortar, and jointing should closely knit, smooth, light Sliding, then with napkin, floor cleaning is clean, maintenance must not be less than 4d;
(21) flooring real paving hardwood flooring construction: start with wall side, tightly spreads nail by the bar shaped wood plank heart upwards block-by-block row, seam Gap should be on rough ground less than the interface of 10mm plate;
(22) flooring carpet construction: first at basic unit's upper berth establishing set rubber cushion, nail on seta bar in top fixed point or edge, connect , according to the concrete size in room, cut out carpet, to good position, then napped to four limits by middle part, support with blanket, by carpet Pushing away whole unfolding of washing, surface tension is uniform, finally clings fixing with seta bar;
(23) metope emulsion paint: remove substrate surface dust and other bur, coating stir after from top to bottom, from left The right side carries out roller coat;
(24) erection of doors and windows: according to carrying out setting-out work shown in drawing, frame is directly fixed on the wall base body of hole, installs by label Bar, treats that erection of doors and windows is complete, and every width door and window peripheral carries out waterproof sealing process, fluid sealant and glass and sash, fan The adhesion width of section bar is not less than 5mm;
(25) fit up and decorate branch's examination;
(26) roofing screed-coat: according to optimizing figure, places rustless steel venthole, and carries out by cement mortar solid at crisscross place Fixed, look for slope to paste ash cake according to slope requirement bracing wire, press 1.5m spacing floating screed along drainage direction, with plain-water slurry pulp sweeping together, paving If cement mortar, strike off by floating screed with 2.0m long aluminium alloy floating rule, levelling after rub with the hands flat with wooden float, plasterer's trowel press polish, treat mortar Starting to condense, people has stepped on footprint when not sinking, with second time press polish of plasterer's trowel;
(27) roof slope making layer: put slope according to roofing and require to eject watershed line, look for the slope of 2% to drain gully, laying the previous day should be by Basic unit is the most moistening, lay Shi Shouchu basic unit do not feel dry, during laying, should void paving to the 130% of design height, after use plank Make real to design requirement;
(28) roofing heat-insulating layer: remove the rubbish such as the dust of substrate surface, oil thing, make surface keep cleaning, eject exhaust duct The position line, warming plate completely spreads 5 thick special adhesive mortars are flat to be bonded on roofing mortar levelling layer, places and buries underground in length and breadth at expansion joint Φ 50PVC exhaustor, exhaustor is completely beaten the aperture of quincuncial arrangement, and uses Dense mesh screen to wrap up, and rock wool is used on exhaustor top Cover;
(29) roof waterproof layer: base cleaning is clean, painting priming, 8-12h after brushing, when feel is not glued, each layer time Painting THICKNESS CONTROL is at about 0.5mm, and brushing direction is vertical with ground floor;The second layer touch dry after brushing third layer, brushing direction with Ground floor is identical, by that analogy, until design thickness;
(30) polyvinyl chloride plastic film sealing coat: should extend from side to opposite side, the landing edge of adjacent two width should be Article one, on horizontal line, should mutually stagger more than 1m, and film is typically no less than 10cm with the lap width of the seam of film;
(31) roofing rigid layer: according to optimizing figure, eject the parting seam position line, fixes 20 thick 400 grams of extrusion moldings by 1:2 cement mortar Plate, smears on sealing coat by concrete paving, and then strikes off along mark muscle with the long darby of 2m, then comes and goes with cylinder, roll in length and breadth Pressure, then strike off with the long darby of 2m, twice press polish;
(32) roofing branch checks and accepts;
(33) engineering is checked and accepted in advance;
(34) completion of works is checked and accepted.
CN201610404378.7A 2016-06-12 2016-06-12 Building project construction method Pending CN106049539A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610404378.7A CN106049539A (en) 2016-06-12 2016-06-12 Building project construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610404378.7A CN106049539A (en) 2016-06-12 2016-06-12 Building project construction method

Publications (1)

Publication Number Publication Date
CN106049539A true CN106049539A (en) 2016-10-26

Family

ID=57170833

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610404378.7A Pending CN106049539A (en) 2016-06-12 2016-06-12 Building project construction method

Country Status (1)

Country Link
CN (1) CN106049539A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577724A (en) * 2018-12-07 2019-04-05 徐州华阳饲料有限公司 Discharge chamber and method of construction with dust reduction capability
CN109811969A (en) * 2019-01-31 2019-05-28 青岛一建集团有限公司 A kind of building body top of the slope structurally waterproof heat insulation house surface surface layer anti-crack construction technique
CN109914420A (en) * 2019-03-29 2019-06-21 广西鑫豪建筑工程有限公司 A kind of deep basal pit waterproof construction method
CN110409769A (en) * 2019-08-13 2019-11-05 南通装配式建筑与智能结构研究院 A kind of fast gravity die high intensity heavy Machine-blasting mortar construction of long-distance sand transport
CN110485592A (en) * 2019-08-20 2019-11-22 广州市卓爵建筑工程有限公司 Moisture-proof wall construction method
CN112127752A (en) * 2020-09-07 2020-12-25 青岛中筑置业有限公司 Construction process for installing and preventing leakage of outer flush type outer window
CN112726729A (en) * 2020-11-30 2021-04-30 浙江互创建筑工程有限公司 Efficient energy-saving green construction engineering construction method
CN112942832A (en) * 2021-02-03 2021-06-11 湖南宝家云建筑工程管理有限公司 Building main body structure building method
CN113090826A (en) * 2021-03-24 2021-07-09 鹏图建设有限公司 Node and process for sewage treatment plant construction
CN113152796A (en) * 2021-04-28 2021-07-23 中建一局华江建设有限公司 Ultralow-energy-consumption heat-insulation roof structure suitable for low temperature and construction method
CN113175071A (en) * 2021-04-06 2021-07-27 湖北省工业建筑集团有限公司 Green and environment-friendly building construction method
CN114562079A (en) * 2022-03-04 2022-05-31 山西翔丰建设有限公司 Construction method of roof flashing protective layer made of granite
CN114991481A (en) * 2022-07-11 2022-09-02 浙江五方建设有限公司 House building construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3728835A (en) * 1970-11-05 1973-04-24 I Mcmanus Composite concrete slab and steel joist construction
CN101148910A (en) * 2006-09-22 2008-03-26 蔡清宗 Reinforced composite dismounting-free die building construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3728835A (en) * 1970-11-05 1973-04-24 I Mcmanus Composite concrete slab and steel joist construction
CN101148910A (en) * 2006-09-22 2008-03-26 蔡清宗 Reinforced composite dismounting-free die building construction method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
冯宪伟: "《做最好的装饰装修工程施工员》", 31 December 2014, 中国建材工业出版社 *
邻水县中信建筑工程有限公司: "《北川县林业局5个林业企业管护站;安昌林业综合管理业务用房;安昌、擂鼓、禹里苗圃基地;小寨子沟自然保护区大火地、蔡家坪保护站及片口自然保护区竹林沟保护站工程项目-标段施工招标投标文件》", 19 December 2012 *
郝峻弘等: "《房屋建筑学(第2版)》", 31 October 2015, 清华大学出版社 *
陈鹏志等: "《建筑施工手册》", 31 July 2000, 吉林科学技术出版社 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577724A (en) * 2018-12-07 2019-04-05 徐州华阳饲料有限公司 Discharge chamber and method of construction with dust reduction capability
CN109811969A (en) * 2019-01-31 2019-05-28 青岛一建集团有限公司 A kind of building body top of the slope structurally waterproof heat insulation house surface surface layer anti-crack construction technique
CN109914420A (en) * 2019-03-29 2019-06-21 广西鑫豪建筑工程有限公司 A kind of deep basal pit waterproof construction method
CN110409769A (en) * 2019-08-13 2019-11-05 南通装配式建筑与智能结构研究院 A kind of fast gravity die high intensity heavy Machine-blasting mortar construction of long-distance sand transport
CN110485592A (en) * 2019-08-20 2019-11-22 广州市卓爵建筑工程有限公司 Moisture-proof wall construction method
CN112127752A (en) * 2020-09-07 2020-12-25 青岛中筑置业有限公司 Construction process for installing and preventing leakage of outer flush type outer window
CN112726729A (en) * 2020-11-30 2021-04-30 浙江互创建筑工程有限公司 Efficient energy-saving green construction engineering construction method
CN112942832A (en) * 2021-02-03 2021-06-11 湖南宝家云建筑工程管理有限公司 Building main body structure building method
CN112942832B (en) * 2021-02-03 2022-07-29 湖南宝家云建筑工程管理有限公司 Building main body structure building method
CN113090826A (en) * 2021-03-24 2021-07-09 鹏图建设有限公司 Node and process for sewage treatment plant construction
CN113175071A (en) * 2021-04-06 2021-07-27 湖北省工业建筑集团有限公司 Green and environment-friendly building construction method
CN113152796A (en) * 2021-04-28 2021-07-23 中建一局华江建设有限公司 Ultralow-energy-consumption heat-insulation roof structure suitable for low temperature and construction method
CN114562079A (en) * 2022-03-04 2022-05-31 山西翔丰建设有限公司 Construction method of roof flashing protective layer made of granite
CN114991481A (en) * 2022-07-11 2022-09-02 浙江五方建设有限公司 House building construction method

Similar Documents

Publication Publication Date Title
CN106049539A (en) Building project construction method
CN205077752U (en) Roofing flashing waterproofing membrane of department brick wall protection architecture
CN106284706A (en) The construction method of external wall outer insulation rock cotton board
CN104179263A (en) Building exterior wall external thermal insulation system waterproof and drainage construction method
CN103046709A (en) Building construction method of inner wall surface
CN106121231A (en) A kind of skyscraper interts cross construction method
CN105649285A (en) Construction method for heat insulation layer combined type exhaust hole of accessible roof
CN104120845A (en) Construction method for outer wall inorganic thermal mortar coating decorative finishing
CN102061749A (en) External wall heat insulation system with fireproofing function and manufacturing method thereof
CN112267628A (en) Construction method of plastering-free system for interior wall decoration of constructional engineering
CN113006397A (en) Construction method for square leveling of kitchen and bathroom space
CN106284998A (en) Plastering on inner walls completely spreads fiberglass gridding cloth construction method
CN110273490A (en) A kind of embedded lightweight wall plate steel building construction and construction method
CN103195218B (en) Wall ceramic sand mortar external plastering construction method
CN101105070A (en) Polyphenyl board exterior wall outer thermal insulation construction method
CN108130992A (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method
CN106368338A (en) Construction method of external thermal insulation system of foam cement thermal insulation board outer wall
CN209958651U (en) Ceramic tile outer wall waterproof construction
CN110735493B (en) Anti-leakage composite waterproof method for flat roof
CN207553357U (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative exterior wall
CN111255191A (en) Semi-pre-pasted ceramic tile and paving method thereof
CN102182323A (en) Process for dry laying of autoclaved aerated concrete blocks in low-latitude plateaus
CN211949245U (en) Roof stone flashing structure
CN103711208A (en) Heat reflection heat-insulation energy-saving system for outer wall and manufacturing method thereof
CN112127752A (en) Construction process for installing and preventing leakage of outer flush type outer window

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161026