CN109577724A - Discharge chamber and method of construction with dust reduction capability - Google Patents

Discharge chamber and method of construction with dust reduction capability Download PDF

Info

Publication number
CN109577724A
CN109577724A CN201811494221.3A CN201811494221A CN109577724A CN 109577724 A CN109577724 A CN 109577724A CN 201811494221 A CN201811494221 A CN 201811494221A CN 109577724 A CN109577724 A CN 109577724A
Authority
CN
China
Prior art keywords
discharge chamber
dust
entrance
floor
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811494221.3A
Other languages
Chinese (zh)
Inventor
曹峰
蒋志忠
魏强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Huayang Feedstuff Co Ltd
Original Assignee
Xuzhou Huayang Feedstuff Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Huayang Feedstuff Co Ltd filed Critical Xuzhou Huayang Feedstuff Co Ltd
Priority to CN201811494221.3A priority Critical patent/CN109577724A/en
Publication of CN109577724A publication Critical patent/CN109577724A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/22Containers for fluent solids, e.g. silos, bunkers; Supports therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H7/00Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
    • E04H7/22Containers for fluent solids, e.g. silos, bunkers; Supports therefor
    • E04H7/24Constructions, with or without perforated walls, depending on the use of specified materials
    • E04H7/26Constructions, with or without perforated walls, depending on the use of specified materials mainly of concrete, e.g. reinforced concrete or other stone-like materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a kind of discharge chamber and method of construction with dust reduction capability are to belong to environmental protection facility field for feed factory raw material pollutes environment into factory's discharging dust protection and designs;Discharge chamber with dust reduction capability is made of discharge chamber ceiling, discharge chamber wall, grid floor, dust-extraction unit, the dust-proof flexible wall of entrance, entrance soft threshold, ground, discharging slide carriage, telescopic joint, underground room floor;The edge of discharge chamber ceiling and discharge chamber wall vertical seal consolidate;The sealing of three face of discharge chamber wall, on one side there are entrance, entrance installs the dust-proof flexible wall of entrance, and grid floor is horizontally arranged among the ground of basement roof, and dust-extraction unit is mounted on the center of top of discharge chamber ceiling;The entrance surrounding of discharge chamber there is any discrepancy the dust-proof flexible wall of mouth and entrance soft threshold;The top of discharging slide carriage and the top plate of basement are hinged, and the one side of lower part and one end of telescopic joint are hinged;Discharging spreads dust and causes environmental pollution when making feed factory raw material into factory.

Description

Discharge chamber and method of construction with dust reduction capability
Technical field
The present invention is the method for construction with the discharge chamber of dust reduction capability, is for feed factory raw material into factory's discharging anti-gray dustiness It contaminates environment and designs, belong to environmental protection facility field.
Background technique
Feed factory mostly uses greatly corn, soya bean etc. to make primary raw material, and raw material mostly uses greatly Automobile Transportation, after marching into the arena, self-unloading Raw material is poured over ground by automobile, manually send raw material shovel to the hopper in underground, raw material is sent to processing by hopper and is set After being processed into feed, packing is sent to stockyard, transports and sells outside factory;Raw material unload and two processes of artificial feeding feed hopper all A large amount of dust can be raised, the bad environments around operation field are made;Operation in this environment, body will for a long time by operating personnel It is serious to suffer from silicosis by serious injury.
Summary of the invention
Discharge chamber and method of construction provided by the invention with dust reduction capability can solve these problems.
The technical solution adopted by the present invention is that: with dust reduction capability discharge chamber, by discharge chamber ceiling, discharge chamber wall, What the dust-proof flexible wall of grid floor, dust-extraction unit, entrance, entrance soft threshold, floor plate and underground room floor formed;Discharge chamber The edge of ceiling and discharge chamber wall vertical seal consolidate, and dust-extraction unit is installed at top center position;Discharge chamber wall three Face sealing, on one side there are entrance, there are a side lower parts of entrance and floor plate sealing to consolidate for discharge chamber wall, excess-three face It seals and consolidates with underground room floor;Grid floor is horizontally arranged among the floor plate of basement roof, and surrounding and floor plate are solid Knot, separates discharge chamber and basement together with floor plate;Dust-extraction unit is mounted on the center of top of discharge chamber ceiling, pedestal It is consolidated with discharge chamber ceiling;Entrance of discharge chamber or so and it is provided with the dust-proof flexible wall of entrance, the dust-proof flexible wall of entrance above It is consolidated with discharge chamber wall intersection and the sealing of discharge chamber wall;The lower part of the entrance of discharge chamber is provided with entrance soft door Sill, entrance soft threshold and floor plate intersection and floor plate sealing consolidate.
Discharge chamber with dust reduction capability further includes discharging slide carriage, and the discharging slide carriage is set to the lower section of grid floor, Side is hinged with floor plate, and the other side is active side, and the telescopic joint by being installed on discharge chamber wall side supports, with telescopic joint Elongate or shorten the angle of adjusting and floor plate.
The stretchy rod that the telescopic joint is made of more piece tubular part, the outer diameter of the lesser rod piece of diameter are equal to straight The internal diameter of the biggish rod piece of diameter, in the pipe for the rod piece that the lesser rod piece of diameter is deeply relatively large in diameter when shortening, when elongation, from diameter It is extracted out in biggish rod piece;The maximum tube body of its diameter and discharge chamber wall are hinged, and the smallest tube body of diameter and discharging slide carriage are cut with scissors It connects;The telescopic joint is at least arranged one.
The discharge chamber ceiling includes shock insulation waterproof layer, structure sheaf, dust exhaust apparatus and antistatic backing from top to bottom.
The dust exhaust apparatus is the square tube being fixed under structure sheaf, and the top of square tube is connect with dust-extraction unit.
The dust-extraction unit includes dust hood, centrifugal blower and sweep-up pipe, and the pedestal of centrifugal blower is mounted on discharging ceiling On the shakeproof layer of canopy, consolidated with structure sheaf;Sweep-up pipe one end and dust hood sealing consolidate, across the shock insulation waterproof of discharge chamber ceiling Layer, structure sheaf and dust exhaust apparatus sealing consolidate.
Build have dust reduction capability discharge chamber method, first line setting, carry out basement excavation, construction ground panel, Room floor under construction discharge chamber ceiling, construction ground, then dust-extraction unit and discharging slide carriage, telescopic joint are installed, grid floor is installed, entirely It is delivered for use after portion's engineering construction by checking and accepting;Specific construction process are as follows:
1) line setting is the process launched anchor point in the place of design code to ground, is put further according to anchor point Line, determines the position and excavation of foundation pit sideline of basement, then carries out basement excavation;Basement controls cutting depth when excavating, Excavation organizes check of foundation subsoil, making bed course afterwards in place;
2) basement wall carries out after cushion construction, first puts the basement wall position line on bed course, makes basement wall position It is consistent with discharge chamber wall locations line to set line, carries out basement wall body construction;
3) after the completion of basement wall body construction, beam slab branch of all round victory scaffold as floor plate is installed in the interior of basement Support controls the reserving hole of grid floor and the position of built-in fitting in the beam slab for installing floor plate, installation floor plate reinforcing bar and Pipe laying embedded part, qualified after-pouring concrete of inspecting for acceptance;After the concrete of floor plate reaches the condition for continuing up construction, construction Discharge chamber wall reaches the lower part of the beam slab of discharge chamber ceiling;
4) mounting hole that the grid floor reserved on floor plate has been closed before the construction of discharge chamber ceiling, sets up full hall on floor plate Support of the scaffold as discharge chamber ceiling beam-slab template afterwards is laid with the template and dust-extraction unit base mold of discharge chamber ceiling beam slab Plate, installation passes perpendicularly through the casing of the sweep-up pipe of the dust-extraction unit of template in template, installs the reinforcing bar of discharge chamber ceiling beam slab With the built-in fitting of plate lower part installation dust exhaust apparatus, the embedded part of the installation dust hood on plate top, qualified after-pouring coagulation of inspecting for acceptance Soil;Underground room floor carries out after the beam slab bed die demoulding of discharge chamber ceiling;Base, bed course are first handled well, in construction surface layer;
5) installation dust-extraction unit carries out after civil construction general-control reception is qualified, the top of discharge chamber ceiling installation dust hood, Centrifugal blower, sweep-up pipe, the upper end of sweep-up pipe and dust hood and centrifugal blower are tightly connected, and enter discharge chamber across service sleeve Below ceiling, lower end and dust exhaust apparatus connection;Dust exhaust apparatus is horizontally arranged on the beam slab below discharge chamber ceiling, is installed After finishing acceptance(check), antistatic backing is installed below dust exhaust apparatus;
6) discharging slide carriage installation before, first determine position, after floor plate bottom installation connection discharging slide carriage hinge and material unloading chute The hinge that plate is connect with telescopic joint, and the pedestal of telescopic joint is installed on basement metope, then discharging slide carriage and telescopic joint are installed, then In the power device of basement installation telescopic joint, debugging is completed;
7) grid floor made is mounted at the hole to be provided of floor plate, keeps floor plate smooth, horizontal, it is firm to connect.
It spreads dust the beneficial effects of the invention are as follows discharging when making feed factory raw material into factory and causes environmental pollution.
Detailed description of the invention
Fig. 1 is the discharge chamber schematic diagram with dust reduction capability.
Fig. 2 is the structural schematic diagram of dust-extraction unit.
Fig. 3 is the structural schematic diagram of discharge chamber ceiling.
In figure: 1- discharge chamber ceiling;1-1- shock insulation waterproof layer;1-2- structure sheaf;1-3- dust exhaust apparatus;1-4- antistatic Layer;2- discharge chamber wall;3- grid floor;4- dust-extraction unit;4-1- dust hood;4-2- centrifugal blower;4-3 sweep-up pipe;5- goes out The dust-proof flexible wall of entrance;6- entrance soft threshold;The ground 7-;8- discharging slide carriage;9- telescopic joint;The underground 10- room floor;11- hopper.
Specific embodiment
Embodiment
Certain feed factory uses the discharge chamber as shown in Figure 1 and Figure 2 with dust reduction capability provided by the invention, by discharge chamber The dust-proof flexible wall 5 of ceiling 1, discharge chamber wall 2, grid floor 3, dust-extraction unit 4, entrance, entrance soft threshold 6, floor plate 7, Discharging slide carriage 8, telescopic joint 9, underground room floor 10 form;The edge of discharge chamber ceiling 1 is vertical with discharge chamber wall 2 close Sealing knot, top center position are installed with dust-extraction unit 4;The sealing of 2 three face of discharge chamber wall, there are entrance, entrances on one side The dust-proof flexible wall 5 of entrance is installed, there are the lower parts of the side of entrance and the sealing of floor plate 7 to consolidate, remaining 3 face is with basement The sealing of face 10 consolidation;Grid floor 3 is horizontally arranged among the floor plate 7 of basement roof, and surrounding and floor plate 7 consolidate, with One of floor plate 7 discharge chamber and basement are separated;Dust-extraction unit 4 be mounted on discharge chamber ceiling 1 center of top year pedestal with Discharge chamber ceiling 1 consolidates;The entrance of discharge chamber is arranged in the side of discharge chamber wall 2, entrance of discharge chamber or so and upper Face is provided with the dust-proof dust-proof flexible wall 5 of 5 entrance of flexible wall of entrance, the dust-proof flexible wall 5 of entrance and 2 intersection of discharge chamber wall with unload Expect the sealing consolidation of room wall 2;The lower part of the entrance of discharge chamber is provided with entrance soft threshold 6, entrance soft threshold 6 and ground 7 intersection of plate and the sealing of floor plate 7 consolidate;The top of discharging slide carriage 8 and the top plate of basement are hinged, the one side of lower part with it is flexible One end of section 9 is hinged.
The discharge chamber is that the raw material of sealing is unloaded place, and 7 meters of free height, the standard width of a room in an old-style house and depth are 10 meters, when discharging The dust of generation will not pollute ambient enviroment in the discharge chamber of sealing, these dust are through being mounted on removing on discharge chamber ceiling 1 The effect of dirt device 4, dust are sucked into dust-extraction unit 4, ensure that the dust for generation of unloading does not pollute the environment in this way; Basement is separated discharge chamber and basement by grid floor 3 and floor plate 7 in the lower part of discharge chamber, the connection of three sidewalls;Ground Lower room is the storage of hopper and draws row ground, and by hopper as the lower section of grid floor 3 when unloading, raw material passes through grid from discharge chamber Floor 3 enters the hopper 11 on the room floor of underground, and the dust at this moment generated also take away by the negative pressure caused by dust-extraction unit 4.
The construction of the discharge chamber ceiling 1 is, from top to bottom including shock insulation waterproof layer 1-1, structure sheaf 1-2, dust suction dress Set 1-3 and antistatic backing 1-4;The shock insulation waterproof layer 1-4 is substantially exactly to set up defences on the structure sheaf upper berth of discharge chamber ceiling 1 Water coiled material, the sealing of these waterproof rolls is covered on the top of discharge chamber ceiling 1, around plant bottom case and top, sweep-up pipe Around;Centrifugal blower 4-2 has vibration, plays cushioning effect by the way that spring is arranged between blower bottom plate and pedestal;
The structure sheaf preferential recommendation is made of cast-in-place reinforced concrete girder slab;Dust exhaust apparatus 1-3 is arranged in structure What the square tube under layer was fabricated to, dust exhaust apparatus 1-3 passes through sweep-up pipe 4-3 sealing connection centrifugal blower 4-2 and dust hood 4-1;
The dust-extraction unit 4 includes dust hood 4-1, centrifugal blower 4-2, sweep-up pipe 4-3;Centrifugal blower 4-2 is mounted on pedestal On, pedestal is fixedly arranged on the structure sheaf of discharge chamber ceiling 1;Centrifugal blower 4-2 is for manufacturing negative pressure, centrifugation to discharge chamber Blower is extracted out the air of discharge chamber by sweep-up pipe 4-3, and discharge chamber is made to form negative pressure, and dust when unloading passes through antistatic Layer 1-4 enters dust exhaust apparatus 1-3, enters dust hood 4-1 by sweep-up pipe 4-3;Dust hood 4-1 is made by cloth bag, is to use It is consolidated to collect the one end sweep-up pipe 4-3 and dust hood 4-1 sealing, across shock insulation waterproof layer 1-1, the structure sheaf of discharge chamber ceiling 1 1-2 and dust exhaust apparatus 1-3 sealing consolidates.
The discharge chamber wall 2 is perpendicular to the structure sheaf on ground, using the armored concrete system with a thickness of 200 millimeters To make, three faces of discharge chamber wall 2 are located at around discharge chamber and basement, are connected to up and down, it is located at the top of floor plate 7 on one side, There are inlet and outlet on the discharge chamber wall 2 on the top of floor plate 7, the height and width of inlet and outlet are 5 meters, discharge chamber wall The dust-proof flexible wall 5 of entrance is fixed on the wall at 2 four sides, dust-proof flexible wall 5 makes of felt, the top and two for seal automobile Entrance soft threshold 6 is arranged in side, the lower part of entrance, and entrance soft threshold 6 makes of the felt with spring, and automobile, which drives into, to be outputed When, entrance soft threshold 6 lies down the space for erecting seal automobile bottom Yu floor plate 7 after ground automobile comes to a complete stop automatically.
The grid floor 3 is transparent floor plate, using No. 10 I-steel be fabricated to hole less than 100 × 100 millimeters of grid floor, grid floor 3 are located between discharge chamber and basement, and surrounding is mounted in floor plate 7, it is noted that The connection of grid floor 3 and grid floor 3 and floor plate 7 must be able to bear the load of the raw material delivered on automobile and automobile Effect;Raw material is after discharge chamber is unloaded, by the penetrating gap of grid floor 3, into basement;Floor plate 7 and grid Floor 3 is that the floor plate of discharge chamber is also the top plate of basement;The room bottom located underground of underground room floor 10, hopper 11 is in underground It stops or tows on room floor 10, the top surrounding of underground room floor 10 and the root of basement wall consolidate.
The discharging slide carriage 8 is angularly disposed under floor plate 7, recommends using long 7 meters wide 5 meters of the steel plate system of 16 millimeters thicks Make, the top of discharging slide carriage 8 is hinged with the bottom surface of floor plate 7, at lower part 1/3 away from 500 millimeters of two-end-point and telescopic joint 9 one End is hinged, with the angle for elongating or shortening adjusting Yu floor plate 7 of telescopic joint 9;When unloading, hopper is first moved on into grid floor 3 Lower section, adjust the angle of discharging slide carriage 8, make to fall in can entering hopper 11 originally and being advisable for discharging slide carriage 8, then start to unload Vehicle.
The stretchy rod that the telescopic joint 9 is made of more piece tubular part, using 40-100 millimeters of diameter, wall thickness The steel pipe of 10 millimeters of different-diameter makes, and elongating or shortening for steel pipe provides power using pneumatic device, pneumatic device and opens Pass is respectively positioned on the corner that discharge chamber facilitates operation;The outer diameter of the lesser rod piece of diameter is equal to the internal diameter for the rod piece being relatively large in diameter, contracting In the pipe for the rod piece that the lesser rod piece of diameter is deeply relatively large in diameter in short-term, when elongation, extracted out from the rod piece being relatively large in diameter.
The method of construction of the discharge chamber with dust reduction capability is that first line setting carries out basement excavation, construction Room floor 10 under floor plate 7, construction discharge chamber ceiling 1, construction ground, then dust-extraction unit 4 and discharging slide carriage 8, telescopic joint 9 are installed, Grid floor 3 is installed, all-work is delivered for use after constructing by checking and accepting.
The line setting is in the place of design code using relative position method, referring to the original building of feed factory Object measures the distance of design requirement, and deviation is not more than 5 millimeters, and anchor point is launched the position to ground, determines base with small timber This position, then in the accurate described point in the top of timber, by small iron nail nail on the point at the top of small timber;It is put further according to anchor point Line determines that the position and excavation of foundation pit sideline of basement perform label in anchor point pilot measurement to neighbouring building;Again into Row basement excavates;If geology is bad when basement excavates, supporting measure is also taken, not will cause landslide if excavated, Then controlling cutting depth not backbreak, and cutting depth excavates 100 millimeters still further below with the foundation ground absolute altitude of design requirement as control Absolute altitude processed;Excavation organizes check of foundation subsoil afterwards in place, and check of foundation subsoil is qualified, after the representatives from various walks of life's signature for participating in check of foundation subsoil, making concrete cushion.
The basement wall carries out after cushion construction, when blinding concrete poured 12 it is small when after, on bed course By anchor point by the point that is labeled on nearby buildings, in pilot measurement to bed course, the basement wall position line is put after confirmation, Keep the basement wall position line consistent with 2 position line of discharge chamber wall, carry out basement wall body construction, basement wall uses The armored concrete of 200 millimeters thicks makes, and first carries out foundation construction, then carry out wall construction, and basis and wall are all in accordance with installation Reinforcing bar, supporting module, the sequence of casting concrete carry out, and must be provided with post-cast strip in construction joint position, to prevent basement leakage.
After the basement wall demoulding, beam of all round victory scaffold as floor plate 7 is installed in the interior of basement Plate support, Man Tanghou scaffold are set up using the steel pipe scaffold of 48 millimeters of diameter, 3.5 millimeters of wall thickness, and 900 millimeters of upright bar spacing, One 1.6 meters of step frame height;The beam slab for installing floor plate 7 again controls the absolute altitude and relative dimensions of beam slab, also to control installation The position of the built-in fitting of the reserving hole and installation grid floor 3 of grid floor 3 is needed when the span of beam or plate is greater than 4 meters Arch camber is wanted, spring quantum is one thousandth to 3/1000ths;After the template acceptance(check) of the beam slab of floor plate 7,7 steel of floor plate is installed Muscle and pipe laying embedded part, reinforcing bar, embedded part are inspected for acceptance qualified after-pouring concrete;The intensity of the concrete of floor plate 7 reaches Construction construction discharge chamber wall 2, the construction of construction discharge chamber wall 2 and basement wall wall construction method phase are continued up after 1.2MPa Together, until reaching the lower part of the beam slab of discharge chamber ceiling 1.
Before the discharge chamber ceiling 1 is constructed, the mounting hole for the grid floor 3 reserved on floor plate 7 has first been closed, to prevent Falling accident occurs;Man Tanghou, support of the scaffold as 1 beam-slab template of discharge chamber ceiling are set up on floor plate 7, laying is unloaded 4 base template of template and dust-extraction unit for expecting 1 beam slab of ceiling canopy, installation passes perpendicularly through the dust-extraction unit 4 of template in template The casing of sweep-up pipe 4-3, the casing of sweep-up pipe 4-3 are just pressed the casing of production or procurement criteria using cast iron pipe, wanted according to design Specification, model production or the buying asked;After template acceptance(check), reinforcing bar and the installation of plate lower part of 1 beam slab of discharge chamber ceiling are installed The built-in fitting of dust exhaust apparatus 1-3, the embedded part of the installation dust hood 4-1 on plate top, qualified after-pouring concrete of inspecting for acceptance.
The underground room floor 10 carries out after the beam slab bed die demoulding of discharge chamber ceiling 1;First locate according to design requirement Li Hao base, bed course, in construction surface layer.
The dust-extraction unit 4 be mounted on civil construction general-control reception it is qualified after carry out, as shown in Fig. 2, in discharge chamber Dust hood 4-1, centrifugal blower 4-2, sweep-up pipe 4-3 are installed at the top of ceiling 1;Centrifugation wind first on discharge chamber ceiling 1 The center line and absolute altitude of centrifugal blower 4-2 are set on machine 4-2 pedestal, and dust hood 4-1, centrifugal blower 4-2, sweep-up pipe are installed respectively The upper end of 4-3, sweep-up pipe 4-3 and dust hood 4-1 and centrifugal blower 4-2 are tightly connected, and enter discharging ceiling across service sleeve Below canopy 1, lower end and dust exhaust apparatus 1-3 connection;Dust exhaust apparatus 1-3 is horizontally arranged under discharge chamber ceiling 1 with pipe-hanging hook On the beam slab in face, after installing acceptance(check), antistatic backing 1-4 is installed below dust exhaust apparatus;Antistatic backing 1-4 is used The bakelite plate made is erected on the keel of antistatic backing by the mode of furred ceiling.
Before the discharging slide carriage 8 is installed, first determine position, after in the bottom of floor plate 7 installation connection discharging slide carriage 8 Hinge and the hinge that is connect with telescopic joint 9 of discharging slide carriage 8, and on basement metope installation telescopic joint 9 pedestal, then material unloading chute is installed Plate 8 and telescopic joint 9, then in the power device of basement installation telescopic joint 9, debugging is completed.
The grid floor 3 is installed, and is that the grid floor 3 that will be made is mounted at the hole to be provided of floor plate 7, and with The built-in fitting on hole side is welded and fixed, and mounting and adjusting keeps floor plate 7 smooth, horizontal, and it is firm to connect.
The installation of the entrance dust-proof flexible wall 5, entrance soft threshold 6 is that unloading for the entrance of discharge chamber is being arranged Expect that the hole edge of room wall 2 is fixed by the dust-proof flexible wall 5 of entrance, opens wide the dust-proof flexible wall 5 of entrance under external force promotion, remove Automatic covering keeps off entrance after external force out;Fixed entrance soft threshold 6, makes entrance soft threshold 6 exist at the entrance of floor plate 7 It lodges under external force, withdraws from after external force perpendicular to floor plate 7, use entrance and be in completely enclosed state, do not make discharge chamber Dust overflows discharge chamber.

Claims (7)

1. the discharge chamber with dust reduction capability, characterized in that filled by discharge chamber ceiling, discharge chamber wall, grid floor, dedusting It sets, the dust-proof flexible wall of entrance, entrance soft threshold, floor plate and underground room floor form;The edge of discharge chamber ceiling It is consolidated with discharge chamber wall vertical seal, dust-extraction unit is installed at top center position;Three face of discharge chamber wall sealing, on one side there are Entrance, there are a side lower parts of entrance and floor plate sealing to consolidate for discharge chamber wall, and excess-three face and underground room floor are close Sealing knot;Grid floor is horizontally arranged among the floor plate of basement roof, and surrounding and floor plate consolidate, together with floor plate Discharge chamber and basement are separated;Dust-extraction unit is mounted on the center of top of discharge chamber ceiling, and pedestal and discharge chamber ceiling are solid Knot;Entrance of discharge chamber or so and it is provided with the dust-proof flexible wall of entrance, the dust-proof flexible wall of entrance and discharge chamber wall phase above It is consolidated at friendship with the sealing of discharge chamber wall;The lower part of the entrance of discharge chamber is provided with entrance soft threshold, entrance soft threshold It is consolidated with floor plate intersection and floor plate sealing.
2. the discharge chamber according to claim 1 with dust reduction capability, characterized in that it further include discharging slide carriage, it is described to unload Expect that slide carriage is set to the lower section of grid floor, one side is hinged with floor plate, and the other side is active side, by being installed on discharge chamber wall The telescopic joint of side supports, with the angle for elongating or shortening adjusting and floor plate of telescopic joint.
3. 1 discharge chamber with dust reduction capability according to claim, characterized in that the telescopic joint is by more piece tubulose The stretchy rod of component composition, the outer diameter of the lesser rod piece of diameter are equal to the internal diameter for the rod piece being relatively large in diameter, diameter when shortening In the pipe for the rod piece that lesser rod piece is deeply relatively large in diameter, when elongation, extracted out from the rod piece being relatively large in diameter;Its diameter is maximum Tube body and discharge chamber wall are hinged, and the smallest tube body of diameter and discharging slide carriage are hinged;The telescopic joint is at least arranged one.
4. the discharge chamber according to claim 1 with dust reduction capability, characterized in that discharge chamber ceiling includes from top to bottom Shock insulation waterproof layer, structure sheaf, dust exhaust apparatus and antistatic backing.
5. the discharge chamber according to claim 4 with dust reduction capability, characterized in that the dust exhaust apparatus is to be fixed on knot The top of square tube under structure layer, square tube is connect with dust-extraction unit.
6. the discharge chamber according to claim 4 with dust reduction capability, characterized in that dust-extraction unit include dust hood, from Heart blower and sweep-up pipe, the pedestal of centrifugal blower are mounted on the shakeproof layer of discharge chamber ceiling, are consolidated with structure sheaf;Sweep-up pipe one End is consolidated with dust hood sealing, and the shock insulation waterproof layer, structure sheaf and dust exhaust apparatus across discharge chamber ceiling seal consolidation.
7. the method for building discharge chamber described in claim 1 ~ 6 any one claim, characterized in that first line setting, Room floor under basement excavation, construction ground panel, construction discharge chamber ceiling, construction ground is carried out, then dust-extraction unit and discharging are installed Slide carriage, telescopic joint, install grid floor, and all-work is delivered for use after constructing by checking and accepting;Specific construction process are as follows:
1) line setting is the process launched anchor point in the place of design code to ground, is put further according to anchor point Line, determines the position and excavation of foundation pit sideline of basement, then carries out basement excavation;Basement controls cutting depth when excavating, Excavation organizes check of foundation subsoil, making bed course afterwards in place;
2) basement wall carries out after cushion construction, first puts the basement wall position line on bed course, makes basement wall position It is consistent with discharge chamber wall locations line to set line, carries out basement wall body construction;
3) after the completion of basement wall body construction, beam slab branch of all round victory scaffold as floor plate is installed in the interior of basement Support controls the reserving hole of grid floor and the position of built-in fitting in the beam slab for installing floor plate, installation floor plate reinforcing bar and Pipe laying embedded part, qualified after-pouring concrete of inspecting for acceptance;After the concrete of floor plate reaches the condition for continuing up construction, construction Discharge chamber wall reaches the lower part of the beam slab of discharge chamber ceiling;
4) mounting hole that the grid floor reserved on floor plate has been closed before the construction of discharge chamber ceiling, sets up full hall on floor plate Support of the scaffold as discharge chamber ceiling beam-slab template afterwards is laid with the template and dust-extraction unit base mold of discharge chamber ceiling beam slab Plate, installation passes perpendicularly through the casing of the sweep-up pipe of the dust-extraction unit of template in template, installs the reinforcing bar of discharge chamber ceiling beam slab With the built-in fitting of plate lower part installation dust exhaust apparatus, the embedded part of the installation dust hood on plate top, qualified after-pouring coagulation of inspecting for acceptance Soil;Underground room floor carries out after the beam slab bed die demoulding of discharge chamber ceiling;Base, bed course are first handled well, in construction surface layer;
5) installation dust-extraction unit carries out after civil construction general-control reception is qualified, the top of discharge chamber ceiling installation dust hood, Centrifugal blower, sweep-up pipe, the upper end of sweep-up pipe and dust hood and centrifugal blower are tightly connected, and enter discharge chamber across service sleeve Below ceiling, lower end and dust exhaust apparatus connection;Dust exhaust apparatus is horizontally arranged on the beam slab below discharge chamber ceiling, is installed After finishing acceptance(check), antistatic backing is installed below dust exhaust apparatus;
6) discharging slide carriage installation before, first determine position, after floor plate bottom installation connection discharging slide carriage hinge and material unloading chute The hinge that plate is connect with telescopic joint, and the pedestal of telescopic joint is installed on basement metope, then discharging slide carriage and telescopic joint are installed, then In the power device of basement installation telescopic joint, debugging is completed;
7) grid floor made is mounted at the hole to be provided of floor plate, keeps floor plate smooth, horizontal, it is firm to connect.
CN201811494221.3A 2018-12-07 2018-12-07 Discharge chamber and method of construction with dust reduction capability Pending CN109577724A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811494221.3A CN109577724A (en) 2018-12-07 2018-12-07 Discharge chamber and method of construction with dust reduction capability

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811494221.3A CN109577724A (en) 2018-12-07 2018-12-07 Discharge chamber and method of construction with dust reduction capability

Publications (1)

Publication Number Publication Date
CN109577724A true CN109577724A (en) 2019-04-05

Family

ID=65929111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811494221.3A Pending CN109577724A (en) 2018-12-07 2018-12-07 Discharge chamber and method of construction with dust reduction capability

Country Status (1)

Country Link
CN (1) CN109577724A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629894A (en) * 2018-12-13 2019-04-16 徐州华阳饲料有限公司 A kind of method of construction of discharging dust guard

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2639264Y (en) * 2003-09-01 2004-09-08 龙岩卫东环保科技有限公司 Electric dust remover for discharging mouth of bought clinker
CN1730367A (en) * 2005-08-10 2006-02-08 钱尧翎 Environment-friendly equipment for loading bulk material on board at dock
CN2823509Y (en) * 2004-11-17 2006-10-04 雷文产品有限公司 Sealer
CN203211963U (en) * 2013-03-26 2013-09-25 山东凝易固砂浆科技有限公司 Turning unloader
CN203862071U (en) * 2014-04-29 2014-10-08 山东鑫泽装饰工程有限公司 Dust removal system of wooden-door polishing workshop
CN204817346U (en) * 2015-07-07 2015-12-02 江西抚州国泰特种化工有限责任公司 Dust removal discharge apparatus
CN205257541U (en) * 2015-12-30 2016-05-25 上海化学工业区升达废料处理有限公司 System of unloading of coke
CN106049539A (en) * 2016-06-12 2016-10-26 江苏宜安建设有限公司 Building project construction method
CN106516812A (en) * 2016-11-08 2017-03-22 中冶东方工程技术有限公司 Automobile unloaded system and method
CN206485954U (en) * 2017-01-21 2017-09-12 天津市武清区建筑工程总公司 A kind of sandstone conveying device
CN206827683U (en) * 2017-05-04 2018-01-02 内蒙古嘉易物流供应链管理有限公司 A kind of unloading coal system
CN107618899A (en) * 2017-08-21 2018-01-23 无锡市曜通环保机械有限公司 A kind of dry powder device for discharging with sack cleaner
CN207192135U (en) * 2017-08-30 2018-04-06 湖北雄韬电源科技有限公司 A kind of lithium battery production transmitting device
CN209874612U (en) * 2018-12-07 2019-12-31 徐州华阳饲料有限公司 Unloading room with dustproof function

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2639264Y (en) * 2003-09-01 2004-09-08 龙岩卫东环保科技有限公司 Electric dust remover for discharging mouth of bought clinker
CN2823509Y (en) * 2004-11-17 2006-10-04 雷文产品有限公司 Sealer
CN1730367A (en) * 2005-08-10 2006-02-08 钱尧翎 Environment-friendly equipment for loading bulk material on board at dock
CN203211963U (en) * 2013-03-26 2013-09-25 山东凝易固砂浆科技有限公司 Turning unloader
CN203862071U (en) * 2014-04-29 2014-10-08 山东鑫泽装饰工程有限公司 Dust removal system of wooden-door polishing workshop
CN204817346U (en) * 2015-07-07 2015-12-02 江西抚州国泰特种化工有限责任公司 Dust removal discharge apparatus
CN205257541U (en) * 2015-12-30 2016-05-25 上海化学工业区升达废料处理有限公司 System of unloading of coke
CN106049539A (en) * 2016-06-12 2016-10-26 江苏宜安建设有限公司 Building project construction method
CN106516812A (en) * 2016-11-08 2017-03-22 中冶东方工程技术有限公司 Automobile unloaded system and method
CN206485954U (en) * 2017-01-21 2017-09-12 天津市武清区建筑工程总公司 A kind of sandstone conveying device
CN206827683U (en) * 2017-05-04 2018-01-02 内蒙古嘉易物流供应链管理有限公司 A kind of unloading coal system
CN107618899A (en) * 2017-08-21 2018-01-23 无锡市曜通环保机械有限公司 A kind of dry powder device for discharging with sack cleaner
CN207192135U (en) * 2017-08-30 2018-04-06 湖北雄韬电源科技有限公司 A kind of lithium battery production transmitting device
CN209874612U (en) * 2018-12-07 2019-12-31 徐州华阳饲料有限公司 Unloading room with dustproof function

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629894A (en) * 2018-12-13 2019-04-16 徐州华阳饲料有限公司 A kind of method of construction of discharging dust guard

Similar Documents

Publication Publication Date Title
CN109026065B (en) Tunnel secondary lining zero-defect construction method
CN104074199B (en) Underwater bearing platform construction method
CN104594387A (en) Improved post-pouring strip advanced water-stopping construction method
CN104234012B (en) A kind of concrete loose rock dam ultra-long concrete sliding formwork body and construction method thereof
CN108915696B (en) Construction organization method for complete mechanical equipment of tunnel
KR101401995B1 (en) The railway construction method using the precast slab track
CN109611102B (en) Construction method for cold excavation underpass overpass
CN110905523A (en) Subway vertical shaft construction method
CN108798059A (en) A kind of old masonry seismic reinforcing structure and construction method
CN114164764B (en) Construction method of high-filling bridge bearing platform structure
CN104452591A (en) Cast-in-place box beam construction technology applied to bridge constructions
US4096675A (en) Split-slab house construction
CN106436730B (en) A kind of masonry house concrete filled steel tube pillar support shock insulating foundation structure and construction method
CN109577724A (en) Discharge chamber and method of construction with dust reduction capability
CN209874612U (en) Unloading room with dustproof function
CN106337520A (en) The construction technology of large-cell point glass curtain wall
CN113700018A (en) Open caisson construction method for large-volume pump station
CN111576878A (en) Construction process for quick-release system of aluminum alloy template
CN209293068U (en) A kind of open trench tunnel falsework system
CN109629894A (en) A kind of method of construction of discharging dust guard
CN116446915A (en) Shallow tunnel portal supporting structure and construction method
CN113338993B (en) Connecting channel reinforcing ring beam structure and construction method thereof
CN216515083U (en) High bridge cushion cap structure of filling
CN113338340A (en) Reverse construction method for vertical shaft ensuring normal use of existing pipeline
CN110258890B (en) Construction method of concrete structure with connected broken line type outer wall and roof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination