CN106027178B - A kind of electric power scheduling automatization system telemeter time test method based on step response - Google Patents

A kind of electric power scheduling automatization system telemeter time test method based on step response Download PDF

Info

Publication number
CN106027178B
CN106027178B CN201610419700.3A CN201610419700A CN106027178B CN 106027178 B CN106027178 B CN 106027178B CN 201610419700 A CN201610419700 A CN 201610419700A CN 106027178 B CN106027178 B CN 106027178B
Authority
CN
China
Prior art keywords
voltage
time
test equipment
state
test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610419700.3A
Other languages
Chinese (zh)
Other versions
CN106027178A (en
Inventor
王云茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Fujian Electric Power Co Ltd
State Grid Fujian Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Fujian Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Fujian Electric Power Co Ltd
State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Fujian Electric Power Co Ltd, State Grid Fujian Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610419700.3A priority Critical patent/CN106027178B/en
Publication of CN106027178A publication Critical patent/CN106027178A/en
Application granted granted Critical
Publication of CN106027178B publication Critical patent/CN106027178B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04BTRANSMISSION
    • H04B17/00Monitoring; Testing
    • H04B17/30Monitoring; Testing of propagation channels
    • H04B17/309Measuring or estimating channel quality parameters
    • H04B17/364Delay profiles

Landscapes

  • Engineering & Computer Science (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The present invention relates to a kind of electric power scheduling automatization system telemeter time test method based on step response.Test equipment of this method when plant stand end testing ground is using with GPS pairs,Selection voltage is remote measurement amount,Instrument the first state output voltage is set as normal voltage value,Setting test equipment the second state output voltage is slightly above the alarming value of the scheduling station system voltage,Setting test equipment from the first state step to the second state at the time of,Then startup test equipment test function,At this moment,Test equipment first exports the first state voltage,Wait T1 at the time of step occurs,During to the moment,Test equipment output voltage steps to the second state,It is out-of-limit that electrical equipment voltage telemeering occurs for simulation plant-station scene,When scheduling station system receives the voltage telemeering amount,Meeting target voltage out-of-limit alarm signal when pop-up carries on interface,The markers is T2 at the time of scheduling station system receives the remote measurement amount,When due to scheduling station system and plant stand TT&C system being also by GPS pairs,Then telemeter time=T2 T1.

Description

A kind of electric power scheduling automatization system telemeter time test based on step response Method
Technical field
The present invention relates to a kind of electric power scheduling automatization system telemeter time test method based on step response.
Background technology
Electric power scheduling automatization system is based on computer, communication, control technology, is given birth to online for power dispatching stations at different levels Produce the data handling system that operations staff provides Operation of Electric Systems information, analysis decision instrument and control means.Scheduling is automatic Change system is by power plant, substation(Hereinafter referred to as plant stand)TT&C system, and the main station system of scheduling institution, and passing through The automated system that communication media or data transmission network are formed.It can realize that each plant stand in a distant place is electric by dispatch automated system The electric parameter Long Distant Transmits such as the active power of element, reactive power, voltage and current are to control centre, the person's of being scheduled for monitoring With.When the active power, reactive power, voltage and current of plant stand electrical equipment change when electric parameter, need in time by The electric parameter changed is transmitted to scheduling station, allows dispatcher to grasp in time, to carry out power scheduling work.In order to weigh electricity Gas parameter is transmitted to the speed of scheduling station from plant stand, and code is provided with " telemeter time " index, it is to embody scheduling certainly The index of dynamicization system real time, the regulatory requirements index are not more than 4 seconds.The telemeter time can be obtained by field measurement. During experiment, scheduling station end testing crew is contacted by phone with plant stand end testing crew, by scheduling station end(Or plant stand end) Testing crew is measured using stopwatch, and the measure and control device of test equipment to plant stand TT&C system exports certain electrical quantity(Such as voltage)Open Begun meter when, scheduling station end testing crew stopwatch when scheduling station system observes this electrical quantity, so as to obtain remote measurement Delivery time.It will be apparent that it is this by phone contact, the time quantum of second level is measured using stopwatch, error is larger.
The content of the invention
To solve above-mentioned drawback, the present invention uses the electric power scheduling automatization system telemeter time based on step response Test method measures the telemeter time, can improve the accuracy of measurement, reduces measurement error.
The present invention is realized using following technical scheme:A kind of electric power scheduling automatization system remote measurement based on step response passes Time test method is sent, it comprises the following steps:Test equipment when plant stand end testing ground is using with GPS pairs, selects electricity Pressure amount is remote measurement amount, sets instrument the first state output voltage as normal voltage value, and setting the second state of test equipment output voltage omits Higher than the alarming value of the scheduling station system voltage, setting test equipment from the first state step to the second state at the time of;Start The test function of the test equipment, at this time test equipment first export the first state voltage, wait T1 at the time of step occurs;During to T1 During quarter, test equipment output voltage steps to the second state, and generation electrical equipment voltage telemeering in simulation plant-station scene is out-of-limit, scheduling master When the system of station receives the voltage telemeering amount, target voltage out-of-limit alarm signal, the markers can be when pop-up carries on interface T2 at the time of scheduling station system receives the remote measurement amount, since scheduling station system and plant stand TT&C system are also by GPS couples When, then telemeter time=T2-T1.
Compared to the prior art, the invention has the advantages that:The present invention improves remote measurement to short form test workload Delivery time measurement accuracy, the real-time that guarantee dispatch automated system is run play the role of vital.
Brief description of the drawings
Fig. 1 is electric power scheduling automatization system telemeter time test method signal of the present invention based on step response Figure.
Fig. 2 is the plant stand end test connection schematic diagram of one embodiment of the invention.
Fig. 3 is that the test equipment test parameters of one embodiment of the invention sets schematic diagram.
Embodiment
Below in conjunction with the accompanying drawings, technical scheme is specifically described.
The present invention provides a kind of electric power scheduling automatization system telemeter time test method based on step response, its Comprise the following steps:Test equipment when plant stand end testing ground is using with GPS pairs, selection voltage is remote measurement amount, setting The first state of instrument output voltage is normal voltage value, and setting test equipment the second state output voltage is slightly above scheduling station system should The alarming value of voltage, setting test equipment from the first state step to the second state at the time of;Start the experiment work(of the test equipment Can, test equipment first exports the first state voltage at this time, waits T1 at the time of step occurs;During to the T1 moment, test equipment output Voltage step is to the second state, and generation electrical equipment voltage telemeering in simulation plant-station scene is out-of-limit, and scheduling station system receives the voltage During remote measurement amount, meeting target voltage out-of-limit alarm signal when pop-up carries on interface, which is that scheduling station system receives T2 at the time of the remote measurement amount, due to when scheduling station system and plant stand TT&C system are also by GPS couples, then during telemeter Between=T2-T1.Specific test schematic diagram is referring to Fig. 1.
In certain 500kV substation in one embodiment of the invention(The hereinafter referred to as substation)It is distant to carry out debugging automated system Delivery time test is surveyed, used test equipment is comprehensive automation system of transformer substation tester, when which has GPS pairs Function, can set binary states voltage output.
Utilize the 500kV line segregations of substation's interruption maintenance(The hereinafter referred to as interval)Tested, connect test The gps antenna of instrument, and guarantee to receive 4 and above satellite, the A phase voltages output of test equipment is linked into the interval surveys The A phase voltage terminal blocks of device are controlled, see Fig. 2.
Scheduling station end testing crew sets the more upper limit alarm value of circuit A phase voltages in dispatching automation main station system For 308kV(Corresponding secondary voltage is 61.7V).Plant stand end testing crew sets UA the first state voltages on test equipment interface (U1), the second state voltage (U2) and occur step at the time of, settings U1 is normal voltage value 57.7V, setting U2 magnitudes of voltage be 62.5V(More than it upper limit alarm value is got in scheduling station system), it is assumed that it is 28 minutes 10 May 23 day 11 point in 2016 now Second, then initial time can be set(At the time of generation step)For 11 when 28 divide 40 seconds, see Fig. 3.
" starting to test " button of test equipment is clicked on, starts to test, test equipment correctly after output, first exports first State voltage UA(57.7V), until experiment moment T1(28 divide 40 seconds when 11), test equipment the second state voltage of output(62.5V).Survey After the measure and control device collection that the voltage of test instrument output passes through substation's plant stand TT&C system, surveyed by the plant stand at the station Scheduling station is sent in the telecontrol communication machine of control system, since the second state voltage of test equipment output is more than the scheduling station system electricity The more upper limit alarm value of pressure amount, then after scheduling station system receives the U2 magnitudes of voltage after step, target voltage is got over when can eject band Alarm signal is limited, for example, " 2016-05-23 11:28:43 certain substation 500kV circuit A phase voltages get over the upper limit 312.7kV ", at this time, " terminating experiment " button that can press test equipment stop experiment, it can be seen that, scheduling station system receives 28 divide 43 seconds when T2 is 11 at the time of step voltage value, then telemeter time T2-T1 is 3 seconds.And then can be according to related code Judge whether the telemeter time index of the dispatch automated system meets the requirements.
Above-mentioned magnitude of voltage, more upper limit alarm value are only the test data of one embodiment of the invention, not exclusive limit value. Specific magnitude of voltage can be adjusted further as the case may be in other different grades of substations.
Above is presently preferred embodiments of the present invention, all changes made according to technical solution of the present invention, caused function are made During with scope without departing from technical solution of the present invention, protection scope of the present invention is belonged to.

Claims (3)

  1. A kind of 1. electric power scheduling automatization system telemeter time test method based on step response, it is characterised in that:Bag Include following steps:Test equipment when plant stand end testing ground is using with GPS pairs, selection voltage is remote measurement amount, sets instrument The first state of device output voltage is normal voltage value, and setting test equipment the second state output voltage is slightly above scheduling station system voltage More the corresponding secondary voltage value of upper limit alarm value, set test equipment from the first state step to the second state at the time of;Starting should The test function of test equipment, at this time test equipment first export the first state voltage, wait T1 at the time of step occurs;To the T1 moment When, test equipment output voltage steps to the second state, and generation electrical equipment voltage telemeering in simulation plant-station scene is out-of-limit, scheduling station Target voltage out-of-limit alarm signal, the markers can be to adjust when pop-up carries on interface when system receives the voltage telemeering amount Degree main station system T2 at the time of receive the remote measurement amount, due to when scheduling station system and plant stand TT&C system are also by GPS couples , then telemeter time=T2-T1.
  2. 2. the electric power scheduling automatization system telemeter time test side according to claim 1 based on step response Method, it is characterised in that:The test equipment is comprehensive automation system of transformer substation tester.
  3. 3. the electric power scheduling automatization system telemeter time test side according to claim 2 based on step response Method, it is characterised in that:The substation is 500kV substations, and the more upper limit alarm value of the voltage is 308kV, and correspondence is secondary Voltage is 61.7V.
CN201610419700.3A 2016-06-15 2016-06-15 A kind of electric power scheduling automatization system telemeter time test method based on step response Active CN106027178B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610419700.3A CN106027178B (en) 2016-06-15 2016-06-15 A kind of electric power scheduling automatization system telemeter time test method based on step response

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610419700.3A CN106027178B (en) 2016-06-15 2016-06-15 A kind of electric power scheduling automatization system telemeter time test method based on step response

Publications (2)

Publication Number Publication Date
CN106027178A CN106027178A (en) 2016-10-12
CN106027178B true CN106027178B (en) 2018-05-04

Family

ID=57087614

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610419700.3A Active CN106027178B (en) 2016-06-15 2016-06-15 A kind of electric power scheduling automatization system telemeter time test method based on step response

Country Status (1)

Country Link
CN (1) CN106027178B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111523079A (en) * 2020-04-29 2020-08-11 广西电网有限责任公司河池宜州供电局 Method for improving and self-checking load report of dispatching automation system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11220481A (en) * 1998-02-04 1999-08-10 Meidensha Corp Sampling synchronizing system, sampling data synchronizing system and abnormality reporting system for pcm relay
CN102361356A (en) * 2011-10-28 2012-02-22 安徽省电力公司芜湖供电公司 System and method for testing remote communication volume of transformer substation testing-controlling device
CN102721882A (en) * 2012-06-18 2012-10-10 辽宁省电力有限公司营口供电公司 Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method
CN203350349U (en) * 2013-05-20 2013-12-18 国家电网公司 Transformer substation bus phase voltage off-limit alarm system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11220481A (en) * 1998-02-04 1999-08-10 Meidensha Corp Sampling synchronizing system, sampling data synchronizing system and abnormality reporting system for pcm relay
CN102361356A (en) * 2011-10-28 2012-02-22 安徽省电力公司芜湖供电公司 System and method for testing remote communication volume of transformer substation testing-controlling device
CN102721882A (en) * 2012-06-18 2012-10-10 辽宁省电力有限公司营口供电公司 Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method
CN203350349U (en) * 2013-05-20 2013-12-18 国家电网公司 Transformer substation bus phase voltage off-limit alarm system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
后石电厂全停配套电压稳定控制系统及其调试;王云茂;《福建电力与电工》;20060330;第26卷(第01期);第7-9页 *

Also Published As

Publication number Publication date
CN106027178A (en) 2016-10-12

Similar Documents

Publication Publication Date Title
CN102788921B (en) Detection method of function and performance of power distribution automation terminal device
CN101900777B (en) Monitoring method and device of power system
CN202886463U (en) Intelligent electric energy meter with functions of electric leakage remote monitoring and protection
CN102879661B (en) A kind of distribution automation terminal detection method and system
CN202720296U (en) Platform for detecting function and performance of power distribution automatic terminal apparatus
CN110337626A (en) System and method for detecting the injection of the wrong data in substation
CN103885438B (en) The Auto-Test System of a kind of transformer station measuring and controlling equipment and method
WO2014154164A1 (en) Method and system for detecting and locating single-phase ground fault on low current grounded power-distribution network
CN103368257A (en) Method for testing remote communication storm by utilizing power substation measuring and control device remote communication traffic testing system
CN202159106U (en) Intelligent tester with intelligent power grid self-healing control technology
CN103604992B (en) The method and system of nuclear phase on-load school protection that Substation secondary circuit is wireless
CN107741549A (en) The intelligent substation synchronism tester synchronously occurred based on analog quantity and digital quantity
CN109217472B (en) Automatic closed-loop joint debugging method for monitoring information checking
CN104375038A (en) Extensible closed-loop synchronous power distribution automation terminal detection platform and method
CN108512730B (en) Intelligent substation telecontrol system equipment testing method, device and system
CN110942400B (en) Automatic point-to-point method and device for intelligent substation monitoring system
CN109636663B (en) Method and device for identifying household transformer relationship of back-to-back distribution transformer
CN104076805A (en) Test system for automatic control equipment of power distribution network
Knezev et al. Automated circuit breaker monitoring
CN106027178B (en) A kind of electric power scheduling automatization system telemeter time test method based on step response
CN111030301B (en) Method for checking correlation of scheduling automation information points
CN102200559B (en) Regional remote spare power source automatic transfer test method and related equipment
CN110224882A (en) A kind of energy-accumulating power station remote control time delay measuring method and device
CN110297162A (en) A kind of communication power grid detection system
CN209311566U (en) Signal validation apparatus

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 350003 No. 54 road 54 Fuzhou, Fujian

Co-patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd.

Co-patentee after: STATE GRID FUJIAN ELECTRIC POWER Research Institute

Address before: 350003 No. 54 road 54 Fuzhou, Fujian

Co-patentee before: State Grid Corporation of China

Patentee before: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd.

Co-patentee before: STATE GRID FUJIAN ELECTRIC POWER Research Institute

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20181108

Address after: 350003 No. 54 road 54 Fuzhou, Fujian

Co-patentee after: STATE GRID CORPORATION OF CHINA

Patentee after: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd.

Co-patentee after: STATE GRID FUJIAN ELECTRIC POWER Research Institute

Co-patentee after: STATE GRID FUJIAN ECONOMIC Research Institute

Address before: 350003 No. 54 road 54 Fuzhou, Fujian

Co-patentee before: STATE GRID CORPORATION OF CHINA

Patentee before: STATE GRID FUJIAN ELECTRIC POWER Co.,Ltd.

Co-patentee before: STATE GRID FUJIAN ELECTRIC POWER Research Institute

TR01 Transfer of patent right