CN102721882A - Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method - Google Patents

Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method Download PDF

Info

Publication number
CN102721882A
CN102721882A CN201210200326XA CN201210200326A CN102721882A CN 102721882 A CN102721882 A CN 102721882A CN 201210200326X A CN201210200326X A CN 201210200326XA CN 201210200326 A CN201210200326 A CN 201210200326A CN 102721882 A CN102721882 A CN 102721882A
Authority
CN
China
Prior art keywords
protection
tester
test
intelligent
transformer substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210200326XA
Other languages
Chinese (zh)
Inventor
张旗
李兆琪
赵辉
姜洪伟
曲绍生
万军
李洪东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YINGKOU POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd
State Grid Corp of China SGCC
Original Assignee
YINGKOU POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YINGKOU POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd filed Critical YINGKOU POWER SUPPLY COMPANY LIAONING ELECTRIC POWER Co Ltd
Priority to CN201210200326XA priority Critical patent/CN102721882A/en
Publication of CN102721882A publication Critical patent/CN102721882A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

The invention discloses an intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method which is characterized in that the intelligent transformer substation adopts a light inter-range instrumentation group (IRIG)-B code synchronous time tick mode, and the conventional transformer substation adopts a global positioning system (GPS) time tick mode, so that a plurality of points can be subjected to synchronous acquisition and trigger test; during test, relay protection testers on two sides are respectively connected to a GPS clock and an IRIG-B code clock; and time information comprising date, hour, minute, second and the like is sent at the frequency of one time per second. The intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method has the advantages that the intelligent transformer substation adopts the light IRIG-B code synchronous time tick mode, and the conventional transformer substation adopts the GPS time tick mode, so that protection synchronous sampling and synchronous sampling of the testers on two sides are completed by using the two clocks, and a plurality of points can be subjected to synchronous acquisition and trigger test; therefore, the test on dual-end optical fiber current longitudinal difference protection is realized; and the test method is simple, and the data is accurate.

Description

A kind of intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method
Technical field
The present invention relates to reaying protection test method and technology field, particularly a kind of intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method.
Background technology
Mostly the 220kV circuit main protection that moves in the electrical network at present is the fibre-optic current longitudinal difference protection; Be to utilize optical-fibre channel with the waveform of this side electric current or represent the signal of current amplitude, phase place to be sent to offside; Every side protection is carried out in real time synchronously relatively the amplitude and the phase place of both sides electric current, and distinguishing according to result relatively is in the district or external area error.Vertical UNICOM road united test is the key that guarantees longitudinal difference protection action logic correctness.
Along with the construction of intelligent grid, intelligent transformer station increasing employing electronic type optical current mutual inductor, digitizing, networking technology are adopted in the transmission of protection sampled data; And conventional substation adopts traditional electromagnetic transformer, and the protection sampled data is transmitted as analog quantity.When carrying out intelligent transformer station and conventional substation passage united test, adopt traditional test method, data often can not be caused the result incorrect by intelligent substation protection identification.
Summary of the invention
The objective of the invention is to utilize novel intelligent transformer station testing apparatus, introduce GPS and IRIG-B sign indicating number to the time function, improve the problem that the traditional experiment method exists, the spy provides a kind of intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method.
The invention provides a kind of intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method; It is characterized in that: described intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method; Be according to intelligent transforming plant protecting adopt light IRIG-B sign indicating number synchronously to the time mode; Conventional substation adopt GPS to the time mode, utilize above-mentioned two kinds of clocks to accomplish and trigger the synchronized sampling of both sides tester with the protection synchronized sampling, accomplish the multiple spot synchronous acquisition, trigger test;
During test; The both sides relay-protection tester inserts gps clock, IRIG-B sign indicating number clock respectively; With the frequency of per second 1 time send comprise day, the time, branch, second etc. temporal information; Being positioned at both-end is the protection tester at route protection two ends, in upper computer software " dress attitude sequential test module ", be provided with when identical, branch, second fault triggering constantly; After the protection tester reads temporal information, give upper computer software with information uploading, software compares triggered time of setting and the current time that reads according to the user, when fiducial value is identical, and trigger action; Assurance both-end digital protecting tester is exported the fault sampled value simultaneously and is given tested protective device; Realize test to both-end fibre-optic current longitudinal difference protection; Promptly verify the action definite value and the action logic of protective device, also verified the correctness of the optical fiber link of two ends protections;
According to the technical requirement of our on-the-spot test mode,, customize a kind of PWF-2F light digital protecting tester that has increased the rich electric company in Beijing production of IRIG-B sign indicating number clock and test through screening.
PWF-2F light digital protecting tester; Can simulate combiner is MU; According to IEC61850-9-1 or IEC61850-9-2 or IEC60044-7/8 is FT3, and the hardwood form transmits sampled value, also can the analog current mutual inductor, the weak signal analog quantity output after the voltage transformer (VT) conversion; Through receiving, send GOOSE message or reception, the hard contact information of output switching value, intelligent electronic devices such as intelligent substation digital relay protection, ammeter are carried out closed loop test;
Tester also is sent to equipment under test with voltage, the magnitude of current according to the IEC61850 protocol packing in real time; And the actuating signal of measurand imports contact through the switching value of tester or the GOOSE message transmissions arrives tester; Tester is realized the closed loop test of digital protection, instrument and meter according to the amplitude and the phase place of certain test method real time altering output quantity.
For example: Nan Ruiji protects PCS-931, and the optical fiber phase-splitting is differential:
The pretest inspection channel status: no error code, error code, channel delay confirm that less than 16ms passage is normal, do not send out channel alarm information.
Offside is sent out and is allowed the condition of signal to have:
1, protection of this side and difference element start;
2, this side is jumped the position and is not had stream;
3, weak feedback logic;
Pilot project:
1, this side switch closes the position, and the offside switch is closing the position, and the both sides relay-protection tester inserts gps clock, IRIG-B sign indicating number clock respectively; Add fault current; When fault current during greater than the differential protection definite value, the tripping operation of this side protection step switch, the tripping operation of offside protection step switch.
2, the weak feedback of simulation function: the both sides relay-protection tester inserts gps clock, IRIG-B sign indicating number clock respectively, and the offside switch is closing the position, and the main protection pressing plate drops into; Add normal this phase voltage 34V, less than 65%Un but greater than TV broken string alarm voltage 33V, device nothing " TV broken string " signal; This side switch is closing the position; Intend various faults at this side form, when fault current during greater than the differential protection definite value, equal would trip is protected in both sides.
3, the far away jumping tested, and makes this side switch close the position, and when this side " was far jumped and received this side control=0 ", offside made protective device have tripping far away to go into, this side protection transfer trip.When this side " was far jumped and received this side control=1 ", when offside made protective device have tripping far away to go into, this side protective device started, the transfer trip of this side defencive function.
Advantage of the present invention:
Intellectuality of the present invention and conventional substation optical-fiber longitudinal difference protection passage united test method, intelligent transforming plant protecting adopt light IRIG-B sign indicating number synchronously to the time mode, conventional substation adopt GPS to the time mode; Utilize above-mentioned two kinds of clocks to accomplish and the synchronized sampling of protecting synchronized sampling and triggering both sides tester; Accomplish the multiple spot synchronous acquisition, trigger test, assurance both-end digital protecting tester is exported the fault sampled value simultaneously and is given tested protective device, realizes the test to both-end fibre-optic current longitudinal difference protection; The action definite value and the action logic of protective device have promptly been verified; Also verified the correctness of the optical fiber link of two ends protections, test method is easy, and data are accurate.
Description of drawings
Below in conjunction with accompanying drawing and embodiment the present invention is done further detailed explanation:
Fig. 1 is intelligent and conventional substation optical-fiber longitudinal difference protection passage united test method synoptic diagram.
Embodiment
Embodiment 1
Present embodiment provides a kind of intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method; It is characterized in that: described intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method; Be according to intelligent transforming plant protecting adopt light IRIG-B sign indicating number synchronously to the time mode; Conventional substation adopt GPS to the time mode, utilize above-mentioned two kinds of clocks to accomplish and trigger the synchronized sampling of both sides tester with the protection synchronized sampling, accomplish the multiple spot synchronous acquisition, trigger test;
During test; The both sides relay-protection tester inserts gps clock, IRIG-B sign indicating number clock respectively; With the frequency of per second 1 time send comprise day, the time, branch, second etc. temporal information; Being positioned at both-end is the protection tester at route protection two ends, in upper computer software " dress attitude sequential test module ", be provided with when identical, branch, second fault triggering constantly; After the protection tester reads temporal information, give upper computer software with information uploading, software compares triggered time of setting and the current time that reads according to the user, when fiducial value is identical, and trigger action; Assurance both-end digital protecting tester is exported the fault sampled value simultaneously and is given tested protective device; Realize test to both-end fibre-optic current longitudinal difference protection; Promptly verify the action definite value and the action logic of protective device, also verified the correctness of the optical fiber link of two ends protections;
According to the technical requirement of our on-the-spot test mode,, customize a kind of PWF-2F light digital protecting tester that has increased the rich electric company in Beijing production of IRIG-B sign indicating number clock and test through screening.
PWF-2F light digital protecting tester; Can simulate combiner is MU; According to IEC61850-9-1 or IEC61850-9-2 or IEC60044-7/8 is FT3, and the hardwood form transmits sampled value, also can the analog current mutual inductor, the weak signal analog quantity output after the voltage transformer (VT) conversion; Through receiving, send GOOSE message or reception, the hard contact information of output switching value, intelligent electronic devices such as intelligent substation digital relay protection, ammeter are carried out closed loop test;
Tester also is sent to equipment under test with voltage, the magnitude of current according to the IEC61850 protocol packing in real time; And the actuating signal of measurand imports contact through the switching value of tester or the GOOSE message transmissions arrives tester; Tester is realized the closed loop test of digital protection, instrument and meter according to the amplitude and the phase place of certain test method real time altering output quantity.
For example: Nan Ruiji protects PCS-931, and the optical fiber phase-splitting is differential:
The pretest inspection channel status: no error code, error code, channel delay confirm that less than 16ms passage is normal, do not send out channel alarm information.
Offside is sent out and is allowed the condition of signal to have:
1, protection of this side and difference element start;
2, this side is jumped the position and is not had stream;
3, weak feedback logic;
Pilot project:
1, this side switch closes the position, and the offside switch is closing the position, and the both sides relay-protection tester inserts gps clock, IRIG-B sign indicating number clock respectively; Add fault current; When fault current during greater than the differential protection definite value, the tripping operation of this side protection step switch, the tripping operation of offside protection step switch.
2, the weak feedback of simulation function: the both sides relay-protection tester inserts gps clock, IRIG-B sign indicating number clock respectively, and the offside switch is closing the position, and the main protection pressing plate drops into; Add normal this phase voltage 34V, less than 65%Un but greater than TV broken string alarm voltage 33V, device nothing " TV broken string " signal; This side switch is closing the position; Intend various faults at this side form, when fault current during greater than the differential protection definite value, equal would trip is protected in both sides.
3, the far away jumping tested, and makes this side switch close the position, and when this side " was far jumped and received this side control=0 ", offside made protective device have tripping far away to go into, this side protection transfer trip.When this side " was far jumped and received this side control=1 ", when offside made protective device have tripping far away to go into, this side protective device started, the transfer trip of this side defencive function.

Claims (1)

1. intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method; It is characterized in that: described intellectuality and conventional substation optical-fiber longitudinal difference protection passage united test method; Be according to intelligent transforming plant protecting adopt light IRIG-B sign indicating number synchronously to the time mode; Conventional substation adopt GPS to the time mode, utilize above-mentioned two kinds of clocks to accomplish and trigger the synchronized sampling of both sides tester with the protection synchronized sampling, accomplish the multiple spot synchronous acquisition, trigger test;
During test; The both sides relay-protection tester inserts gps clock, IRIG-B sign indicating number clock respectively; With the frequency of per second 1 time send comprise day, the time, branch, second etc. temporal information; Being positioned at both-end is the protection tester at route protection two ends, in upper computer software " dress attitude sequential test module ", be provided with when identical, branch, second fault triggering constantly; After the protection tester reads temporal information, give upper computer software with information uploading, software compares triggered time of setting and the current time that reads according to the user, when fiducial value is identical, and trigger action; Assurance both-end digital protecting tester is exported the fault sampled value simultaneously and is given tested protective device; Realize test to both-end fibre-optic current longitudinal difference protection; Promptly verify the action definite value and the action logic of protective device, also verified the correctness of the optical fiber link of two ends protections;
PWF-2F light digital protecting tester; Can simulate combiner is MU; According to IEC61850-9-1 or IEC61850-9-2 or IEC60044-7/8 is FT3, and the hardwood form transmits sampled value, also can the analog current mutual inductor, the weak signal analog quantity output after the voltage transformer (VT) conversion; Through receiving, send GOOSE message or reception, the hard contact information of output switching value, intelligent electronic devices such as intelligent substation digital relay protection, ammeter are carried out closed loop test;
Tester also is sent to equipment under test with voltage, the magnitude of current according to the IEC61850 protocol packing in real time; And the actuating signal of measurand imports contact through the switching value of tester or the GOOSE message transmissions arrives tester; Tester is realized the closed loop test of digital protection, instrument and meter according to the amplitude and the phase place of certain test method real time altering output quantity.
CN201210200326XA 2012-06-18 2012-06-18 Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method Pending CN102721882A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210200326XA CN102721882A (en) 2012-06-18 2012-06-18 Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210200326XA CN102721882A (en) 2012-06-18 2012-06-18 Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method

Publications (1)

Publication Number Publication Date
CN102721882A true CN102721882A (en) 2012-10-10

Family

ID=46947699

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210200326XA Pending CN102721882A (en) 2012-06-18 2012-06-18 Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method

Country Status (1)

Country Link
CN (1) CN102721882A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103123482A (en) * 2012-12-12 2013-05-29 国网智能电网研究院 Valve monitoring device applicable to high-capacity multi-media card (MMC) flexible direct-current transmission converter
CN103245855A (en) * 2013-04-23 2013-08-14 国家电网公司 Digital simulation based method and system for testing relay protection function of intelligent substation
CN103293414A (en) * 2013-05-21 2013-09-11 国家电网公司 Intelligent substation protection device synchronization performance test system and method based on GPS (globe positioning system) accurate time synchronization technology
CN104467956A (en) * 2014-12-26 2015-03-25 国家电网公司 Fiber protecting channel testing system
CN104897981A (en) * 2015-03-23 2015-09-09 国网辽宁省电力有限公司锦州供电公司 Longitudinal differential protection synchronization remote test method
CN105629127A (en) * 2015-12-23 2016-06-01 南京国电南自电网自动化有限公司 EHV line protection method with integration with traveling wave ranging function
CN106027178A (en) * 2016-06-15 2016-10-12 国网福建省电力有限公司 Method for testing telemetry transmission time of electric power dispatching automation system based on step response
CN107064689A (en) * 2017-05-02 2017-08-18 许继电气股份有限公司 A kind of analogy method and system of transformer TA broken strings
CN107505563A (en) * 2017-09-14 2017-12-22 青海送变电工程公司 A kind of test method of optical difference protection joint debugging
CN107782989A (en) * 2016-08-26 2018-03-09 上海宝冶集团有限公司 The quick joint debugging method of testing of end optical difference protection passage of circuit three
CN109444531A (en) * 2018-12-21 2019-03-08 国家电网有限公司 Relay protection sample examination system and its sample examination method based on synchronous clock synchronization
CN109709477A (en) * 2018-12-12 2019-05-03 许继集团有限公司 The test macro of protective relaying device under a kind of mixed connection mode
CN112444696A (en) * 2020-11-11 2021-03-05 河南送变电建设有限公司 Unilateral-control intelligent substation optical difference protection testing device and testing method
CN113391098A (en) * 2021-06-15 2021-09-14 贵州电网有限责任公司 Optical difference protection coaxial cable channel control device and control method thereof
RU2761112C1 (en) * 2018-02-11 2021-12-06 Нр Электрик Ко., Лтд Method for detecting phase breakage of the starting/backup transformer using an optical current transformer

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101871976A (en) * 2009-04-24 2010-10-27 郑州威科姆科技股份有限公司 Power clock detecting device
CN202230321U (en) * 2011-07-12 2012-05-23 贵州电力试验研究院 Timing and time keeping accuracy test system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101871976A (en) * 2009-04-24 2010-10-27 郑州威科姆科技股份有限公司 Power clock detecting device
CN202230321U (en) * 2011-07-12 2012-05-23 贵州电力试验研究院 Timing and time keeping accuracy test system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张旗等: "智能变电站与常规变电站的通道联调试验", 《东北电力技术》 *
王洪帅等: "智能变电站非对称式光纤差动保护同步性测试方法", 《电力系统自动化》 *

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103123482B (en) * 2012-12-12 2016-05-25 国网智能电网研究院 Be applicable to the valve monitoring equipment of large capacity MMC flexible DC power transmission transverter
CN103123482A (en) * 2012-12-12 2013-05-29 国网智能电网研究院 Valve monitoring device applicable to high-capacity multi-media card (MMC) flexible direct-current transmission converter
CN103245855A (en) * 2013-04-23 2013-08-14 国家电网公司 Digital simulation based method and system for testing relay protection function of intelligent substation
CN103245855B (en) * 2013-04-23 2014-07-30 国家电网公司 Digital simulation based method and system for testing relay protection function of intelligent substation
CN103293414A (en) * 2013-05-21 2013-09-11 国家电网公司 Intelligent substation protection device synchronization performance test system and method based on GPS (globe positioning system) accurate time synchronization technology
CN104467956A (en) * 2014-12-26 2015-03-25 国家电网公司 Fiber protecting channel testing system
CN104897981A (en) * 2015-03-23 2015-09-09 国网辽宁省电力有限公司锦州供电公司 Longitudinal differential protection synchronization remote test method
CN105629127A (en) * 2015-12-23 2016-06-01 南京国电南自电网自动化有限公司 EHV line protection method with integration with traveling wave ranging function
CN106027178B (en) * 2016-06-15 2018-05-04 国网福建省电力有限公司 A kind of electric power scheduling automatization system telemeter time test method based on step response
CN106027178A (en) * 2016-06-15 2016-10-12 国网福建省电力有限公司 Method for testing telemetry transmission time of electric power dispatching automation system based on step response
CN107782989B (en) * 2016-08-26 2020-03-06 上海宝冶集团有限公司 Rapid joint debugging test method for three-terminal optical difference protection channel of line
CN107782989A (en) * 2016-08-26 2018-03-09 上海宝冶集团有限公司 The quick joint debugging method of testing of end optical difference protection passage of circuit three
CN107064689B (en) * 2017-05-02 2019-10-22 许继电气股份有限公司 A kind of analogy method and system of transformer TA broken string
CN107064689A (en) * 2017-05-02 2017-08-18 许继电气股份有限公司 A kind of analogy method and system of transformer TA broken strings
CN107505563A (en) * 2017-09-14 2017-12-22 青海送变电工程公司 A kind of test method of optical difference protection joint debugging
CN107505563B (en) * 2017-09-14 2020-01-07 青海送变电工程公司 Testing method for optical difference protection joint debugging
RU2761112C1 (en) * 2018-02-11 2021-12-06 Нр Электрик Ко., Лтд Method for detecting phase breakage of the starting/backup transformer using an optical current transformer
CN109709477A (en) * 2018-12-12 2019-05-03 许继集团有限公司 The test macro of protective relaying device under a kind of mixed connection mode
CN109444531A (en) * 2018-12-21 2019-03-08 国家电网有限公司 Relay protection sample examination system and its sample examination method based on synchronous clock synchronization
CN112444696A (en) * 2020-11-11 2021-03-05 河南送变电建设有限公司 Unilateral-control intelligent substation optical difference protection testing device and testing method
CN113391098A (en) * 2021-06-15 2021-09-14 贵州电网有限责任公司 Optical difference protection coaxial cable channel control device and control method thereof

Similar Documents

Publication Publication Date Title
CN102721882A (en) Intelligent and conventional transformer substation optical fiber longitudinal difference protection channel joint debugging test method
CN102510131B (en) Method and device for testing overall performance of intelligent transformer substation
CN102590619B (en) Method for detecting time synchronization capacity of real-time measurement equipment based on timing variable
CN102306953B (en) Test method for secondary injection of power distribution automatization system
CN104360298B (en) Performance test system and method for merging unit tester
CN103293414A (en) Intelligent substation protection device synchronization performance test system and method based on GPS (globe positioning system) accurate time synchronization technology
CN103792508A (en) Error test system and method for digitized metering device
CN109900994A (en) Intelligent substation secondary circuit comprehensive performance testing system and working method
CN107741549A (en) The intelligent substation synchronism tester synchronously occurred based on analog quantity and digital quantity
CN108089081A (en) Multi-compartment emulation test system based on digital transformer substation field application
CN202384838U (en) Secondary system real-time simulation testing platform for total station of intelligent transformer substation
Jing et al. A novel whole-view test approach for onsite commissioning in smart substation
CN107092198A (en) A kind of HVDC transmission system failure analysis methods and system
Schaub et al. Test and evaluation of Non Conventional Instrument Transformers and sampled value process bus on Powerlink's transmission network
CN110703029B (en) Fault detection system and method for primary and secondary systems of intelligent substation
CN104897981A (en) Longitudinal differential protection synchronization remote test method
CN102200559B (en) Regional remote spare power source automatic transfer test method and related equipment
CN202196132U (en) Dynamic simulation test system of power grid region stable control system
CN104734338A (en) Clock monitoring method, device and system of transformer substations
CN109581098A (en) The intelligent O&M test method of site protective device
CN104300673B (en) Detect the method and system of intelligent terminal GOOSE resolution ratio
Anombem et al. Performance testing and assessment of merging units using IEC61850
Kezunovic et al. New concept and solution for monitoring and control system for the 21 st century substation
CN102508052A (en) Test method for field band channel operation of automatic bus transfer system of area network
CN106451323B (en) It is a kind of solve intelligent substation difference combining unit between latency issue on-site calibrating method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20121106

C10 Entry into substantive examination
C41 Transfer of patent application or patent right or utility model
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20121106

Address after: Zhanqian District 115000 in Liaoning province Yingkou city Bohai street, No. 40 East

Applicant after: Yingkou Power Supply Company, Liaoning Electric Power Co., Ltd.

Applicant after: State Grid Corporation of China

Address before: Zhanqian District 115000 in Liaoning province Yingkou city Bohai street, No. 40 East

Applicant before: Yingkou Power Supply Company, Liaoning Electric Power Co., Ltd.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121010