CN106014409A - 适于平地型尾矿库尾矿干式回采的新方法 - Google Patents
适于平地型尾矿库尾矿干式回采的新方法 Download PDFInfo
- Publication number
- CN106014409A CN106014409A CN201610307674.5A CN201610307674A CN106014409A CN 106014409 A CN106014409 A CN 106014409A CN 201610307674 A CN201610307674 A CN 201610307674A CN 106014409 A CN106014409 A CN 106014409A
- Authority
- CN
- China
- Prior art keywords
- tailings
- road
- back production
- type
- granular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000011084 recovery Methods 0.000 title abstract 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 11
- 239000004575 stone Substances 0.000 claims abstract description 9
- 238000010276 construction Methods 0.000 claims abstract description 6
- 238000004519 manufacturing process Methods 0.000 claims description 49
- 238000009412 basement excavation Methods 0.000 claims description 19
- 238000005520 cutting process Methods 0.000 claims description 8
- 238000005065 mining Methods 0.000 claims description 8
- 238000009825 accumulation Methods 0.000 claims description 5
- 238000011835 investigation Methods 0.000 claims description 5
- 238000000605 extraction Methods 0.000 claims description 4
- 239000011435 rock Substances 0.000 claims description 4
- 239000000203 mixture Substances 0.000 claims description 3
- 230000000694 effects Effects 0.000 claims description 2
- 238000012946 outsourcing Methods 0.000 claims description 2
- 239000002245 particle Substances 0.000 claims description 2
- 239000002699 waste material Substances 0.000 claims description 2
- 229910052705 radium Inorganic materials 0.000 abstract 1
- HCWPIIXVSYCSAN-UHFFFAOYSA-N radium atom Chemical compound [Ra] HCWPIIXVSYCSAN-UHFFFAOYSA-N 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 5
- 230000032258 transport Effects 0.000 description 5
- 239000010410 layer Substances 0.000 description 4
- 238000007596 consolidation process Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 229910052500 inorganic mineral Inorganic materials 0.000 description 2
- 239000011707 mineral Substances 0.000 description 2
- 239000004576 sand Substances 0.000 description 2
- 239000002356 single layer Substances 0.000 description 2
- 241000196324 Embryophyta Species 0.000 description 1
- 241000521257 Hydrops Species 0.000 description 1
- 206010030113 Oedema Diseases 0.000 description 1
- 240000007594 Oryza sativa Species 0.000 description 1
- 235000007164 Oryza sativa Nutrition 0.000 description 1
- 239000003245 coal Substances 0.000 description 1
- 238000000151 deposition Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 235000009566 rice Nutrition 0.000 description 1
- 238000012216 screening Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C11/00—Details of pavings
- E01C11/22—Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
- E01C11/224—Surface drainage of streets
- E01C11/227—Gutters; Channels ; Roof drainage discharge ducts set in sidewalks
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C9/00—Special pavings; Pavings for special parts of roads or airfields
- E01C9/08—Temporary pavings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Remote Sensing (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610307674.5A CN106014409B (zh) | 2016-05-10 | 2016-05-10 | 适于平地型尾矿库尾矿干式回采的新方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610307674.5A CN106014409B (zh) | 2016-05-10 | 2016-05-10 | 适于平地型尾矿库尾矿干式回采的新方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106014409A true CN106014409A (zh) | 2016-10-12 |
CN106014409B CN106014409B (zh) | 2018-04-10 |
Family
ID=57100358
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610307674.5A Active CN106014409B (zh) | 2016-05-10 | 2016-05-10 | 适于平地型尾矿库尾矿干式回采的新方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106014409B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110905511A (zh) * | 2019-11-22 | 2020-03-24 | 西北矿冶研究院 | 一种山谷型尾矿库基于地下水排水的尾矿干式回采方法 |
CN113863931A (zh) * | 2021-11-04 | 2021-12-31 | 中冶沈勘秦皇岛工程设计研究总院有限公司 | 一种库尾细粒淤泥区尾矿回采方法 |
CN114263460A (zh) * | 2021-12-06 | 2022-04-01 | 山东金岭矿业股份有限公司 | 一种傍山型尾矿库回采方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08158305A (ja) * | 1994-12-08 | 1996-06-18 | Ohbayashi Corp | 工事用仮設道路 |
CN202140087U (zh) * | 2011-04-22 | 2012-02-08 | 长春金世纪矿业技术开发有限公司 | 一种整体式尾矿深层回采平台 |
CN102562065A (zh) * | 2012-01-12 | 2012-07-11 | 北京科技大学 | 一种分段空场嗣后充填采矿方法 |
CN103603666A (zh) * | 2013-11-11 | 2014-02-26 | 铜陵有色设计研究院 | 一种尾矿库采砂方法 |
CN103967495A (zh) * | 2014-04-16 | 2014-08-06 | 中钢集团马鞍山矿山研究院有限公司 | 一种尾矿坝坝坡尾矿回采技术 |
CN103967496A (zh) * | 2014-04-16 | 2014-08-06 | 中钢集团马鞍山矿山研究院有限公司 | 一种适于对山谷型尾矿堆积坝坝坡尾矿进行回采的新方法 |
-
2016
- 2016-05-10 CN CN201610307674.5A patent/CN106014409B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08158305A (ja) * | 1994-12-08 | 1996-06-18 | Ohbayashi Corp | 工事用仮設道路 |
CN202140087U (zh) * | 2011-04-22 | 2012-02-08 | 长春金世纪矿业技术开发有限公司 | 一种整体式尾矿深层回采平台 |
CN102562065A (zh) * | 2012-01-12 | 2012-07-11 | 北京科技大学 | 一种分段空场嗣后充填采矿方法 |
CN103603666A (zh) * | 2013-11-11 | 2014-02-26 | 铜陵有色设计研究院 | 一种尾矿库采砂方法 |
CN103967495A (zh) * | 2014-04-16 | 2014-08-06 | 中钢集团马鞍山矿山研究院有限公司 | 一种尾矿坝坝坡尾矿回采技术 |
CN103967496A (zh) * | 2014-04-16 | 2014-08-06 | 中钢集团马鞍山矿山研究院有限公司 | 一种适于对山谷型尾矿堆积坝坝坡尾矿进行回采的新方法 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110905511A (zh) * | 2019-11-22 | 2020-03-24 | 西北矿冶研究院 | 一种山谷型尾矿库基于地下水排水的尾矿干式回采方法 |
CN110905511B (zh) * | 2019-11-22 | 2021-04-20 | 西北矿冶研究院 | 一种山谷型尾矿库基于地下水排水的尾矿干式回采方法 |
CN113863931A (zh) * | 2021-11-04 | 2021-12-31 | 中冶沈勘秦皇岛工程设计研究总院有限公司 | 一种库尾细粒淤泥区尾矿回采方法 |
CN114263460A (zh) * | 2021-12-06 | 2022-04-01 | 山东金岭矿业股份有限公司 | 一种傍山型尾矿库回采方法 |
CN114263460B (zh) * | 2021-12-06 | 2023-11-17 | 山东金岭矿业股份有限公司 | 一种傍山型尾矿库回采方法 |
Also Published As
Publication number | Publication date |
---|---|
CN106014409B (zh) | 2018-04-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102535474A (zh) | 一种深基坑挖土的施工方法 | |
CN108457277A (zh) | 一种大范围深厚淤泥开挖施工方法 | |
CN106014409A (zh) | 适于平地型尾矿库尾矿干式回采的新方法 | |
Sobko et al. | SUBSTANTIATING RATIONAL SCHEDULE TO LOAD TRUCKS USING DRAGLINES WHILE MINING A PIT OF MOTRONIVSKYI MPP. | |
CN114293990A (zh) | 一种露天坑的填充方法 | |
CN112112657B (zh) | 一种煤矿斜井井筒掘砌新工法 | |
CN105952449B (zh) | 一种尾矿库尾矿干式回采的新方法 | |
CN111852554B (zh) | 大涌水量凹陷露天矿小块段全段深一次爆破快速掘沟方法 | |
CN110905511B (zh) | 一种山谷型尾矿库基于地下水排水的尾矿干式回采方法 | |
CN111852555B (zh) | 大涌水量凹陷露天矿一次爆破分层铲装的掘沟方法 | |
CN107859040A (zh) | 一种基坑大面积松软土层的开挖方法 | |
CN1814918A (zh) | 一种土方施工方法 | |
RU2469191C1 (ru) | Способ открытой разработки обводненных месторождений полезных ископаемых | |
RU2661950C1 (ru) | Способ переукладки гидроотвала | |
CN114263460B (zh) | 一种傍山型尾矿库回采方法 | |
CN110374609A (zh) | 一种超浅覆土盾构湖底筑岛掘进方法 | |
RU2199011C1 (ru) | Способ разработки хвостохранилища | |
CN112459552B (zh) | 一种大型砂石骨料加工系统生产废渣防护结构及施工方法 | |
Černoch et al. | Preparations for remediation of a former surface mine–a technical reclamation area | |
CN214091219U (zh) | 一种大型砂石骨料加工系统生产废渣安全防护结构 | |
RU2723839C1 (ru) | Способ дражной разработки техногенных запасов | |
CN111022062B (zh) | 一种斜坡道黏土层段施工方法 | |
Lane et al. | Tuttle Creek Dam of rolled shale and dredged sand | |
LYTVYNCHUK et al. | EQUIPMENT COMPLEXES AND TECHNOLOGICAL SCHEMES FOR EXCAVATING FLUVIOGLACIAL DEPOSITS IN QUARRIES | |
CN116517546A (zh) | 一种尾矿库尾砂混合回采工艺方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666 Co-patentee after: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd. Patentee after: MAANSHAN Mine Research Institute Co.,Ltd. Address before: 243000 Xitang Road, Ma'anshan Economic Development Zone, Anhui, No. 666 Co-patentee before: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd. Patentee before: SINOSTEEL MAANSHAN INSTITUTE OF MINING RESEARCH Co.,Ltd. |