Technical field
Present invention is mainly used for the construction of building engineering field overpass.
Background technology
The patent of invention that I has applied for: prefabricated assembled overpass bridge plate and the equipment of installation thereof, application number:
2016102925379
, need the special equipment that a kind of bridge plate transports, to coordinate the gantry crane of above-mentioned patent to work.
Summary of the invention
The present invention is exactly this transport special equipment, it mainly by two railcars of front and back (
1
), multiple fixed pulley (
2
), traction apparatus (
3
), steel wire rope (
4
), track (
6
), Ka Liang (
7
), bolt (
8
) composition;Railcar (
1
) by walking beam (
9
), steel wheel (
10
), girder (
11
), multistage jack (
12
), draw ring (
13
) composition, walking beam (
9
) be provided with steel wheel (
10
), girder (
11
) two ends respectively with two, left and right walking beam (
9
) side fix, girder (
11
Be provided with in) multistage jack (
12
), multistage jack (
12
) can by bridge plate (
14
) jacking and decline, girder (
11
) be fixedly arranged at the front end with draw ring (
13
);Ka Liang (
7
) there is an internal thread hole, bolt (
8
) can be screwed into Ka Liang (
7
) internal thread hole in, multiple fixed pulleys (
2
) it being arranged on each position of bridge floor on demand, its rotating shaft is fixed with bridge floor, steel wire rope (
4
) through each fixed pulley (
2
), one end and front railcar (
1
) draw ring (
13
) connect, the other end be wound on traction apparatus (
3
) driving wheel on, by driving wheel haulage cable (
4
) mobile, track (
6
) fix with bridge floor;Main operational principle and the construction method of the present invention be: first lay on the bridge floor constructed a plurality of track (
6
), track space be exactly railcar (
1
) steel wheel (
10
) span, install simultaneously fixed pulley (
2
), traction apparatus (
3
) and steel wire rope (
4
), will front and back two railcars (
1
) steel wheel (
10
) be placed in track (
6
On), then with the two of construction site cranes (
5
) by two bridge plates (
14
Before and after) two lift two railcars of front and back (
1
) girder (
11
On), Jiang Kaliang (
7
) be placed on two bridge plates (
14
On), by two, left and right bolt (
8
) be screwed into Ka Liang (
7
) internal thread hole in, by two bridge plates (
14
) upper end clamp temporarily, start traction apparatus (
3
), steel wire rope (
4
) the front railcar of drive (
1
) move right, when bridge plate (
14
) front end movement to horizontal plane and slope intersection time, need to start before and after's railcar (
1
) multistage jack (
12
), make two bridge plates (
14
) can pass through, when two bridge plates (
14
) have been enter into abutment (
16
), will enter gantry crane (
21
) time, the front railcar of decline (
1
) multistage jack (
12
), railcar after rising (
1
) multistage jack (
12
), make two bridge plates (
14
) be substantially at level, be further continued for drawing steel wire rope (
4
), make two bridge plates (
14
) front end enter gantry crane (
21
) in, with gantry crane (
21
) suspender by two bridge plates (
14
) front end sling, rear railcar (
1
) deactivate, by gantry crane (
21
) and rear railcar (
1
) continue by two bridge plates (
14
) it is transported to installation position.
Accompanying drawing explanation
Description of reference numerals:
1-
Railcar,
2-
Fixed pulley,
3-
Traction apparatus,
4-
Steel wire rope,
5-
Crane,
6-
Track,
7-
Ka Liang,
8-
Bolt,
9-
Walking beam,
10-
Steel wheel,
11-
Girder,
12-
Multistage jack,
13-
Draw ring,
14-
Bridge plate
,15-
Approach ramp
,16-
Abutment
,17-
Mounted bridge plate,
18-
Bridge pier,
19-
Bridge plate top plane in place has been installed,
20-
Top of bridge pier plane,
21-
Gantry crane.
Figure
1
It it is the initial period transport elevational schematic view of the present invention.
Figure
2
It is that normal phase of the present invention transports elevational schematic view.
Figure
3
Be two railcars of the present invention (
1
) the transport bridge plate that cooperates (
14
) floor map.
Figure
4
Be railcar of the present invention (
1
) and Ka Liang (
7
) clamp bridge plate (
14
) elevational schematic view.
Figure
5
Be railcar of the present invention (
1
) plane graph.
Figure
6
Be railcar of the present invention (
1
) side elevational view.
Figure
7
Be bridge plate of the present invention (
14
) leading portion be admitted to the elevational schematic view of gantry crane.
Figure
8
Be track of the present invention (
6
) site plan.
Detailed description of the invention
Summary of the invention has been described in detail the detailed description of the invention of the present invention, is not repeated herein, and need to be described as follows: one
.
See figure
1
, typically approach ramp (
15
) left side arrange bridge plate (
14
) prefabricated place
,
Prefabricated place be provided with two cranes (
5
)
,
By two cranes (
5
) prefabricated place infantile tic ship defeated bridge plate (
14
);When bridge plate (
14
) front end movement to horizontal plane and slope intersection time, need to rise front railcar (
1
) multistage jack (
12
), make two bridge plates (
14
) front end on rise, pass through at slope;Equally when two bridge plates (
14
) have been enter into abutment (
16
), will enter gantry crane (
21
) time, the front railcar of decline (
1
) multistage jack (
12
), railcar after rising (
1
) multistage jack (
12
), make two bridge plates (
14
) be substantially at level, so can enter smoothly gantry crane (
21
In).Two
.
See figure
4
, railcar (
1
) should design as far as possible lower, railcar (
1
) be designed to the highest, gantry crane (
21
) increase the most therewith, unnecessary waste can be caused;Design Ka Liang (
7
) purpose be to ensure that two bridge plates (
14
) steady during rising and declining, it is unlikely to topple.Three
.
See figure
4
, figure
5
, figure
6
, figure
7
, figure
8
, the present invention by two bridge plates (
14
) transport together, be to cooperate with gantry crane (
21
) work, track (
6
) spacing need corresponding Aided design, same railcar (
1
) also need corresponding Aided design.Four
.
See figure
7
, gantry crane (
21
) it is the gantry crane in the patent of invention " prefabricated assembled overpass bridge plate and the equipment of installation thereof " applied in person.Five
.
Summary of the invention be only described in detail two bridge plates (
14
) movement method at slope, on the most mounted bridge plate face, movement situation is the most simply too much, because the most mounted bridge plate face is substantially at level, movement work is the most permissible by normal method.