CN201459590U - Wide-span rapid-assembling type pedestrian bridge - Google Patents

Wide-span rapid-assembling type pedestrian bridge Download PDF

Info

Publication number
CN201459590U
CN201459590U CN2009201085181U CN200920108518U CN201459590U CN 201459590 U CN201459590 U CN 201459590U CN 2009201085181 U CN2009201085181 U CN 2009201085181U CN 200920108518 U CN200920108518 U CN 200920108518U CN 201459590 U CN201459590 U CN 201459590U
Authority
CN
China
Prior art keywords
pontic
bridge
truss
package
large span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009201085181U
Other languages
Chinese (zh)
Inventor
尹华钢
姜初伟
贺虎成
郭金锁
卢葭
刘丹
白晓燕
张慧宁
王贵滨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Engineering Design and Research Institute of General Armament Department
Original Assignee
Engineering Design and Research Institute of General Armament Department
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Engineering Design and Research Institute of General Armament Department filed Critical Engineering Design and Research Institute of General Armament Department
Priority to CN2009201085181U priority Critical patent/CN201459590U/en
Application granted granted Critical
Publication of CN201459590U publication Critical patent/CN201459590U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The utility model relates to a wide-span rapid-assembling type pedestrian bridge, which comprises a bridge body (2), a barrier (3) and pulleys. The bridge body (2) consists of a plurality of bridge body sub sections, the barrier (3) consists of a plurality of barrier sub sections which are respectively fixed on the bridge body sub sections, the pulleys are arranged on the lower portion of the bridge body (2), two ends of each bridge body sub section are provided with a flange portion, and each two adjacent bridge body sub sections are mutually connected through the flange portions. The bridge body and the barrier of the pedestrian bridge are made into standard sub sections, which brings convenience for storing and conveying, the pedestrian bridge can be fast assembled and erected manually in a short time. In addition, the wide-span rapid-assembling type pedestrian bridge can assist people to fast step over hinders such as a deep trench and the like in conditions without being limited by large-sized mechanical equipment or space, and then can be disassembled rapidly without obstructing following actions.

Description

Large span ready-package pedestrian overcrossing
Technical field
The utility model relates to a kind of movable portable bridge, particularly a kind of bailey bridge that is made of segregative standard sections.
Background technology
Do not having under the serious limited condition in heavy mechanical equipment and space, when people or thing need stride across the one section space that can't cross over only according to manpower self, need build an interim bridge and realize.Particularly, on the ditch of width, require in 1 minute, to set up and can hold the bridge that 2~4 people pass through, and dismounting bridge at short notice, withdraw the scene greater than 10m, for such large span quick fixation structure, the domestic product that does not also have moulding.
CN2752315Y discloses a kind of fast-assembling bridge that ditch is striden in irrigation and water conservancy that relates to, comprise the L-shaped basic prefabricated section of a pair of section, pair of side plates and some bridge deck, two groups of basis prefabricated section positioned opposite, two ends at basic prefabricated section are respectively equipped with clip slot, the two ends of every side plate are arranged in the relative clip slot, on the L shaped leave from office terrace of basic prefabricated section bridge deck are set.This fast-assembling bridge is applicable to the means of transportation of the middle-size and small-size ditch in field that farmland water conservancy works are built, and is used for carrying various large-scale harvestings and field Transport Machinery.
Summary of the invention
The purpose of this utility model provides a kind of large span ready-package pedestrian overcrossing that is made of standard sections member, in limited space, utilize minimum man power and material finishing setting up of a simple and easy pedestrian overcrossing, thereby help people to cross over clearance space safely and fast to reach other shore with the fastest speed.
For realizing the purpose of this utility model, a kind of large span ready-package pedestrian overcrossing is provided, comprise pontic, connect to form by a plurality of pontic segmentations; Railing is arranged on the side of pontic, is made up of a plurality of railing segmentations.
In addition, also comprise pulley, it is arranged on the bottom of pontic.Pulley comprises front wheel and the rear wheel that is positioned at the pontic two ends, establish middle pulley between front wheel and the rear wheel, distance between front wheel and the middle pulley is greater than the width for the treatment of the leaping over obstacles ditch, and the distance between middle pulley and the rear wheel is greater than the distance between front wheel and the middle pulley.
Wherein, each pontic segmentation has last truss and following truss, and the two ends of last truss and following truss have flange portion, interconnect by flange portion between the adjacent pontic segmentation.Diagonal control arm interconnection by alternately tilting between last truss and the following truss.
Particularly, intubate is established in the pontic side, and the railing segmentation has cross bar and the montant that is positioned at the cross bar two ends and fixedlys connected with it, by the side that in the intubate railing segmentation is fixed on pontic is inserted in the lower end of montant.The lower end of intubate is baffled.
Advantage applies of the present utility model is in the following areas:
1, the utility model line ready-package pedestrian overcrossing is a trussed construction, to alleviate the deadweight of overline bridge as much as possible.
2, the segmentation form that the pontic and the railing body of pedestrian overcrossing are made standard, structure is light and handy, convenient disassembly, and be convenient to storage and carrying, particularly, between the pontic segmentation fast connecting joint is set, make it can finish the assembling of overline bridge integral body at short notice, can be in a short period of time by manually assembling, build overline bridge fast, can under the condition that does not have heavy mechanical equipment or limited space, help people to realize crossing over fast obstacles such as zanjon, can withdraw overline bridge rapidly again then, not hinder follow-up action; In addition, establish in overline bridge pontic both sides can Fast Installation the railing body with the personnel's that guarantee to walk on it safety.
3, the utility model is divided into pulley at the overline bridge pontic, can finish setting up of ready-package pedestrian overcrossing fast by promoting overline bridge toward the opposite bank at limes marginis.
4, in the selection of pulley position, should guarantee to be provided with pulley in forward position of overline bridge second half section and middle part, thereby promote to overcome in the erection process power of toppling that preceding half section overline bridge deadweight causes at overline bridge, finish overline bridge smoothly and set up, realize the purpose of crossing over, passing through.
Description of drawings
Fig. 1 is the user mode schematic diagram of the utility model large span ready-package pedestrian overcrossing;
Fig. 1 a is the sectional view along A-A line among Fig. 1; (this view please be provided)
Fig. 2 is the pontic partial top view of the utility model large span ready-package pedestrian overcrossing;
Fig. 3 is the sectional view along B-B line among Fig. 2;
Fig. 4 is the partial view that railing is connected with overline bridge;
Fig. 5 is the sectional view along C-C line among Fig. 4.
Description of reference numerals: 1a, front wheel, 1b, middle pulley; 1c, rear wheel; 2, pontic; 3, railing body, 3a, cross bar; 3b, montant; 4, zanjon; 4a, opposite bank; 4b, obstacle limit; 5, following truss; 6, go up truss; 6a, right section go up truss; 6b, left side section go up truss; 61, truss pipe portion; 61a, right truss pipe portion; 61b, left truss pipe portion; 62, truss flange portion; 62a, right truss flange portion; 62b, left truss flange portion; 7, oblique connecting rod; 8, intubate; 9, shrouding.
The specific embodiment
As shown in Figure 1, large span ready-package pedestrian overcrossing of the present utility model comprises pontic 2 and is fixed on railing body 3 on the pontic, pulley 1a, 1b and 1c are installed in pontic 2 bottoms, and the effect of pulley is by finishing setting up of pedestrian overcrossing at obstacle limit 4b fast toward the opposite bank 4a promotion overline bridge of zanjon 4.
Pontic 2 is made of a plurality of pontic segmentations, pontic segmentation of expression between two dotted lines among Fig. 1, each pontic segmentation has two couple who longitudinally extends in parallel and goes up truss 5 and following truss 6 (a pair of truss 5 and the following truss 6 gone up of pontic one side has been shown among Fig. 1), every pair of a plurality of oblique connecting rod 7 that incline direction replaces variation that passes through of going up truss 5 and following truss 6 links to each other, and pulley 1a, 1b and 1c are placed in down truss 6 bottoms.
Fig. 2 shows between the two adjacent pontic segmentations and realizes the structure partial vertical view of connection fast by flange, as shown in the figure, the promptly right section of the pontic segmentation on the right goes up the flange portion that truss 6a has the 61a of pipe portion and is positioned at two ends, the pipe portion 61a left and right sides, only shows flange portion 62a of its left end among the figure; The flange portion that truss 6b also has the 61b of pipe portion and is positioned at two ends, the pipe portion 61b left and right sides is gone up in the pontic segmentation on the same left side i.e. left side section, only shows a flange portion 62b of its right-hand member among the figure.As shown in Figure 3, the right flange portion 62b of last truss 6b and the left flange portion 62a of last truss 6a interconnect by connecting bolt 63, similarly, the adjacent of the adjacent pontic segmentation in the left and right sides interconnects by same flange connection between the truss 5 down, thus two adjacent pontic segmentations is fixed together.
As shown in Figure 4, intubate 8 is established in the side of last truss 5, is appreciated that intubate 8 also can be arranged on down the side of truss 6, as shown in Figure 5, and intubate 8 bottoms baffled 9.Railing body 3 comprises the segmentation of more piece railing body, the segmentation of every joint railing body comprises two cross bars and the montant that is positioned at the cross bar two ends and links to each other with cross bar that can be used as hand rail, lower end by montant is inserted in the intubate 8 segmentation of more piece railing body is separately fixed at the side of the more piece pontic segmentation that is linked to be pontic, so that guarantee the personnel's that walk safety on pontic.
The utility model large span ready-package pedestrian overcrossing is a trussed construction, before setting up, at first the flange portion with the truss up and down 5,6 of adjacent pontic segmentation interfixes, form whole pontic, the montant lower end of each railing body segmentation is being inserted in the intubate 8 of pontic both sides, thereby establish the safety of railing in the pontic both sides with the personnel that guarantee to walk on it. as shown in Figure 1, the length of the pontic 2 that is linked to be by a plurality of pontic segmentations should be greater than the twice of the width of obstacle (being zanjon 4)
Establish pulley in pontic 2 bottoms, finish setting up of pedestrian overcrossing fast by promoting overline bridge toward opposite bank 4a at obstacle limit 4b.Half section power of toppling that deadweight causes before overline bridge promotes to overcome overline bridge in the erection process should be guaranteed in the position of pulley, finishes overline bridge smoothly and sets up, and realizes the purpose of leaping over obstacles.
After overline bridge is finished using, at first pull down the segmentation of a plurality of railing body, unclamp the connection of the flange portion between the adjacent pontic segmentation then, storage and carrying are convenient in a plurality of railing body segmentation under the dismounting and a plurality of pontic segmentation.

Claims (8)

1. large span ready-package pedestrian overcrossing is characterized in that comprising:
Pontic (2) is made up of a plurality of pontic segmentations;
Railing (3) is made up of a plurality of railing segmentations, is separately fixed in a plurality of pontic segmentations.
2. large span ready-package pedestrian overcrossing as claimed in claim 1 is characterized in that:
Also comprise pulley (1), be arranged on the bottom of pontic (2).
3. large span ready-package pedestrian overcrossing as claimed in claim 1 or 2 is characterized in that:
Each described pontic segmentation has last truss (6) and following truss (5), and the two ends of last truss (6) and following truss (5) have flange portion, interconnect by flange portion between the adjacent pontic segmentation.
4. large span ready-package pedestrian overcrossing as claimed in claim 3 is characterized in that: intubate (8) is established in described pontic side, and described railing segmentation has the montant in cross bar and the insertion intubate (8).
5. large span ready-package pedestrian overcrossing as claimed in claim 4 is characterized in that: the lower end of described intubate (8) baffled (9).
6. large span ready-package pedestrian overcrossing as claimed in claim 3 is characterized in that: go up diagonal control arm (7) interconnection by alternately tilting between truss (6) and the following truss (5).
7. large span ready-package pedestrian overcrossing as claimed in claim 2, it is characterized in that: described pulley (1) comprises front wheel (1a) and the rear wheel (1c) that is positioned at the pontic two ends, establish middle pulley (1b) between front wheel (1a) and the rear wheel (1c), the distance between front wheel (1a) and the middle pulley (1b) is greater than the width for the treatment of the leaping over obstacles ditch.
8. large span ready-package pedestrian overcrossing as claimed in claim 7, it is characterized in that: the distance between middle pulley and the rear wheel is greater than the distance between front wheel and the middle pulley.
CN2009201085181U 2009-06-05 2009-06-05 Wide-span rapid-assembling type pedestrian bridge Expired - Fee Related CN201459590U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009201085181U CN201459590U (en) 2009-06-05 2009-06-05 Wide-span rapid-assembling type pedestrian bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009201085181U CN201459590U (en) 2009-06-05 2009-06-05 Wide-span rapid-assembling type pedestrian bridge

Publications (1)

Publication Number Publication Date
CN201459590U true CN201459590U (en) 2010-05-12

Family

ID=42386943

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009201085181U Expired - Fee Related CN201459590U (en) 2009-06-05 2009-06-05 Wide-span rapid-assembling type pedestrian bridge

Country Status (1)

Country Link
CN (1) CN201459590U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106012854A (en) * 2016-06-22 2016-10-12 武汉市创先专利技术服务有限公司 Transportation equipment for prefabricated viaduct plates
CN107700333A (en) * 2017-10-13 2018-02-16 北京交通大学 A kind of composite material assembly type foot bridge
CN108149587A (en) * 2017-11-23 2018-06-12 湖北华舟重工应急装备股份有限公司 A kind of modularization bridge erecting device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106012854A (en) * 2016-06-22 2016-10-12 武汉市创先专利技术服务有限公司 Transportation equipment for prefabricated viaduct plates
CN107700333A (en) * 2017-10-13 2018-02-16 北京交通大学 A kind of composite material assembly type foot bridge
CN108149587A (en) * 2017-11-23 2018-06-12 湖北华舟重工应急装备股份有限公司 A kind of modularization bridge erecting device

Similar Documents

Publication Publication Date Title
CN105603860B (en) Prefabricated T beam and construction method
CN102108676B (en) Arch bridge construction method for combined beam-steel arch combined system
CN201459590U (en) Wide-span rapid-assembling type pedestrian bridge
CN100476076C (en) Mobile integral construction platform, construction method thereof and special sling for the same
CN205474784U (en) Prefabricated T roof beam
CN113323488A (en) Steel pipe concrete beam column connecting joint capable of being replaced after earthquake
CN206538672U (en) Novel fabricated truss steel trestle
CN203668857U (en) Walkable operating platform frame used for connection and reinforcement of SS-level guardrail templates
RU2476635C1 (en) Dismountable metal bridge
CN105839550A (en) Oppressive traveling mechanism used for cantilever hanging basket and cantilever hanging basket
CN204212059U (en) A kind of dilatory with large span heavy duty slipway beam
CN207469111U (en) A kind of construction Hanging Basket walking structure
CN207670619U (en) A kind of fishing device for bridge construction
CN209941469U (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN101942811B (en) Auxiliary travel device for bridge girder erection machine
CN203603013U (en) Newly-built railway small-angle over-crossing existing railway combined rigid frame structure
CN208870251U (en) A kind of precast floor slab for assembling type steel structure
CN104314007B (en) A kind of dilatory with large span heavy duty slipway beam
CN202520326U (en) Multifunctional construction platform
CN207597269U (en) The cable arrangement constructed by cross for the whole hole of steel reinforced concrete combination beam
CN203834740U (en) Assembly type steel beam joint T-shaped mixed limb wall
CN206319262U (en) Carry the Diamond-Shape Form Traveler of transport and Lift-on/Lift-off System
CN215364540U (en) Corridor lifting machine frame and corridor lifting machine
CN202829323U (en) Two multi-span precast prestressed crane beam
CN204753353U (en) Novel a portable emergent bridge for road construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100512