CN206538672U - Novel fabricated truss steel trestle - Google Patents
Novel fabricated truss steel trestle Download PDFInfo
- Publication number
- CN206538672U CN206538672U CN201720055908.1U CN201720055908U CN206538672U CN 206538672 U CN206538672 U CN 206538672U CN 201720055908 U CN201720055908 U CN 201720055908U CN 206538672 U CN206538672 U CN 206538672U
- Authority
- CN
- China
- Prior art keywords
- steel
- distribution beam
- truss
- trestle
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本实用新型涉及钢桥技术领域,尤其是一种在高速公路保通及应急抢险中用的新型装配式桁架栈桥。一种新型装配式桁架钢栈桥,包括栈桥和桥墩,所述栈桥两端为钢筋混凝土浇筑的桥台,所述桥墩为钢管桩,两钢管桩之间通过剪刀撑连接,所述钢管桩顶固定有横向承重梁,在所述横向承重梁上两端对称固定有纵向承重梁,所述纵向承重梁为装配式桁架,所述纵向承重梁上固定有横向分配梁,在所述横向分配梁上设置有纵向分配梁,所述纵向分配梁上铺设有桥面铺层。本实用新型装配方便,具有结构简单、经济合理、实施容易、整体稳定和承载能力强等特点,强度高、跨径大,适用于高速公路保通及应急抢险。
The utility model relates to the technical field of steel bridges, in particular to a novel assembled truss trestle bridge used in expressway protection and emergency rescue. A new type of prefabricated truss steel trestle bridge, including a trestle bridge and bridge piers, the two ends of the trestle bridge are abutments made of reinforced concrete, the bridge piers are steel pipe piles, and the two steel pipe piles are connected by scissors. A horizontal load-bearing beam is fixed on the top of the pile, and longitudinal load-bearing beams are symmetrically fixed at both ends of the horizontal load-bearing beam. A longitudinal distribution beam is arranged on the distribution beam, and a bridge deck layer is laid on the longitudinal distribution beam. The utility model is easy to assemble, has the characteristics of simple structure, reasonable economy, easy implementation, overall stability and strong bearing capacity, high strength and large span, and is suitable for expressway traffic protection and emergency rescue.
Description
技术领域technical field
本实用新型涉及钢桥技术领域,尤其是一种在高速公路保通及应急抢险中用的新型装配式桁架栈桥。The utility model relates to the technical field of steel bridges, in particular to a novel assembled truss trestle bridge used in highway traffic protection and emergency rescue.
背景技术Background technique
针对需上跨跨度较大的内河、公路及铁路等需通航或行车的道路,如:为了在高速公路保通及应急抢险中用需在高速公路上修建一座临时施工便桥,钢桥是最常见的临时桥梁结构,修建钢桥有利于工程的顺利进行。目前,钢便桥大都采用贝雷架,因为贝雷架强度高,架设较大跨度的便桥时比较经济合理,但是装配较麻烦。For inland rivers, highways and railways with large spans that need to be navigated or driven, such as: to build a temporary construction bridge on the expressway for expressway maintenance and emergency rescue, steel bridges are the most common The construction of steel bridges is conducive to the smooth progress of the project. At present, most of the steel temporary bridges use Bailey frame, because of the high strength of Bailey frame, it is more economical and reasonable to erect a large-span temporary bridge, but the assembly is more troublesome.
实用新型内容Utility model content
本实用新型要解决的技术问题是:克服现有技术中之不足,提供一种强度高、跨径大的新型装配式桁架栈桥。The technical problem to be solved by the utility model is: to overcome the deficiencies in the prior art and provide a new type of assembled truss trestle bridge with high strength and large span.
本实用新型解决其技术问题所采用的技术方案是:一种新型装配式桁架钢栈桥,包括栈桥和桥墩,所述栈桥两端为钢筋混凝土浇筑的桥台,所述桥墩为钢管桩,两钢管桩之间通过剪刀撑连接,所述钢管桩顶固定有横向承重梁,在所述横向承重梁上两端对称固定有纵向承重梁,所述纵向承重梁为装配式桁架,所述纵向承重梁上固定有横向分配梁,在所述横向分配梁上设置有纵向分配梁,所述纵向分配梁上铺设有桥面铺层。The technical solution adopted by the utility model to solve the technical problems is: a new type of assembled truss steel trestle bridge, including a trestle bridge and a bridge pier. The steel pipe piles are connected by scissor braces, the top of the steel pipe piles is fixed with a horizontal load-bearing beam, and the two ends of the horizontal load-bearing beam are symmetrically fixed with longitudinal load-bearing beams, and the longitudinal load-bearing beam is an assembled truss. A transverse distribution beam is fixed on the longitudinal load-bearing beam, and a longitudinal distribution beam is arranged on the transverse distribution beam, and a bridge deck layer is laid on the longitudinal distribution beam.
具体地,所述装配式桁架具有上、下对称设置的两层三角桁架,所述三角桁架由多个三角结构架并排连接而成,单个三角结构架包括端压杆、端弦杆、斜弦杆和撑杆,所述端弦杆、斜弦杆和撑杆的一端均连接在端压杆上,三者的另一端固定连接,且端弦杆和斜弦杆关于撑杆对称。Specifically, the prefabricated truss has two layers of triangular trusses arranged symmetrically up and down. The triangular truss is formed by connecting multiple triangular frames side by side. A single triangular frame includes end compression bars, end chords, oblique Rods and struts, one end of the end chord, the oblique chord and the strut are all connected to the end compression rod, the other ends of the three are fixedly connected, and the end chord and the oblique chord are symmetrical about the strut.
再具体地,所述端弦杆和斜弦杆的中点处分别固定有结构相同的中竖杆和斜腹杆,所述中竖杆与端压杆垂直,所述端弦杆上的斜腹杆与端弦杆垂直。More specifically, middle vertical rods and diagonal web rods with the same structure are respectively fixed at the midpoints of the end chords and oblique chords, the middle vertical rods are perpendicular to the end compression rods, and the oblique webs on the end chords The web is perpendicular to the end chord.
具体地,所述钢管桩为混凝土钢管桩,钢管桩采用螺旋钢管。Specifically, the steel pipe pile is a concrete steel pipe pile, and the steel pipe pile adopts a spiral steel pipe.
具体地,所述横向承重梁为工字钢,两侧焊有竖劲板。Specifically, the horizontal load-bearing beam is I-shaped steel, and vertical stiffeners are welded on both sides.
具体地,所述横向分配梁和纵向分配梁均为工字钢,所述桥面铺层为花纹钢板。Specifically, both the horizontal distribution beam and the longitudinal distribution beam are I-beams, and the bridge deck layer is patterned steel plate.
具体地,所述桥面铺层的两侧设置有型钢护栏,所述型钢护栏的下端固定在横向分配梁上。Specifically, shaped steel guardrails are arranged on both sides of the bridge deck, and the lower ends of the shaped steel guardrails are fixed on the transverse distribution beams.
本实用新型的有益效果是:本实用新型装配方便,具有结构简单、经济合理、实施容易、整体稳定和承载能力强等特点,强度高、跨径大,适用于高速公路保通及应急抢险。The beneficial effects of the utility model are: the utility model is easy to assemble, has the characteristics of simple structure, reasonable economy, easy implementation, overall stability and strong bearing capacity, high strength and large span, and is suitable for highway traffic protection and emergency rescue.
附图说明Description of drawings
下面结合附图和实施方式对本实用新型进一步说明。Below in conjunction with accompanying drawing and embodiment the utility model is further described.
图1是本实用新型的结构示意图。Fig. 1 is the structural representation of the utility model.
图2是图1的断面图。FIG. 2 is a sectional view of FIG. 1 .
图3是图2在A-A方向上的结构示意图。Fig. 3 is a schematic diagram of the structure of Fig. 2 along the direction A-A.
图4是本实用新型中装配式桁架的结构示意图。Fig. 4 is a structural schematic diagram of the assembled truss in the present invention.
图中:1.桥台,2.钢管桩,3.剪刀撑,4.横向承重梁,5.纵向承重梁,6.横向分配梁,7.纵向分配梁,8.桥面铺层,9.端压杆,10.端弦,11.斜弦杆,12.撑杆,13.中竖杆,14.斜腹杆,15.型钢护栏。In the figure: 1. abutment, 2. steel pipe pile, 3. scissor brace, 4. horizontal load-bearing beam, 5. longitudinal load-bearing beam, 6. horizontal distribution beam, 7. longitudinal distribution beam, 8. deck pavement, 9. End pressure bar, 10. End chord, 11. Inclined chord, 12. Strut, 13. Middle vertical bar, 14. Diagonal web bar, 15. Sectional steel guardrail.
具体实施方式detailed description
现在结合附图对本实用新型作进一步的说明。这些附图均为简化的示意图仅以示意方式说明本实用新型的基本结构,因此其仅显示与本实用新型有关的构成。The utility model is described further in conjunction with accompanying drawing now. These drawings are simplified schematic diagrams only to illustrate the basic structure of the utility model in a schematic way, so they only show the configurations related to the utility model.
如图1~2所示的一种新型装配式桁架钢栈桥,包括栈桥和桥墩,栈桥两端为钢筋混凝土浇筑的桥台1,桥墩为钢管桩2,两钢管桩2之间通过剪刀撑3连接,钢管桩2顶固定有横向承重梁4,在横向承重梁4上两端对称固定有纵向承重梁5,纵向承重梁5为装配式桁架,纵向承重梁5上固定有横向分配梁6,在横向分配梁6上设置有纵向分配梁7,纵向分配梁7上铺设有桥面铺层8。A new type of prefabricated truss steel trestle as shown in Figures 1-2, including trestle and bridge piers, the two ends of the trestle are reinforced concrete abutments 1, the bridge piers are steel pipe piles 2, and the two steel pipe piles 2 are separated by scissors. The support 3 is connected, the top of the steel pipe pile 2 is fixed with a horizontal load-bearing beam 4, and the two ends of the horizontal load-bearing beam 4 are symmetrically fixed with a longitudinal load-bearing beam 5, the longitudinal load-bearing beam 5 is an assembled truss, and a horizontal distribution The beam 6 is provided with a longitudinal distribution beam 7 on the transverse distribution beam 6 , and a bridge deck layer 8 is laid on the longitudinal distribution beam 7 .
如图4所示,装配式桁架具有上、下对称设置的两层三角桁架,三角桁架由多个三角结构架并排连接而成,单个三角结构架包括端压杆9、端弦杆10、斜弦杆11和撑杆12,端弦杆10、斜弦杆11和撑杆12的一端均连接在端压杆9上,三者的另一端固定连接,且端弦杆10和斜弦杆11关于撑杆12对称。端弦杆10和斜弦杆11的中点处分别固定有结构相同的中竖杆13和斜腹杆14,中竖杆13与端压杆9垂直,端弦杆10上的斜腹杆14与端弦杆10垂直。As shown in Figure 4, the prefabricated truss has two layers of triangular trusses arranged symmetrically up and down. The triangular truss is formed by connecting multiple triangular structures side by side. The chord 11 and the strut 12, one end of the end chord 10, the oblique chord 11 and the strut 12 are all connected to the end compression rod 9, and the other ends of the three are fixedly connected, and the end chord 10 and the oblique chord 11 Symmetrical about the strut 12 . The midpoints of the end chord 10 and the oblique chord 11 are respectively fixed with the middle vertical rod 13 and the oblique web rod 14 with the same structure, the middle vertical rod 13 is perpendicular to the end pressure rod 9, and the oblique web rod 14 Perpendicular to the end chord 10.
在本实施例中,钢管桩2为混凝土钢管桩,钢管桩2采用螺旋钢管。横向承重梁4为工字钢,两侧焊有竖劲板。横向分配梁6和纵向分配梁7均为工字钢,桥面铺层8为花纹钢板。桥面铺层8的两侧设置有型钢护栏15,型钢护栏15的下端固定在横向分配梁6上。In this embodiment, the steel pipe pile 2 is a concrete steel pipe pile, and the steel pipe pile 2 adopts a spiral steel pipe. The horizontal load-bearing beam 4 is an I-shaped steel, and vertical stiffeners are welded on both sides. Both the horizontal distribution beam 6 and the longitudinal distribution beam 7 are I-beams, and the deck layer 8 is patterned steel plate. Both sides of the deck layer 8 are provided with shaped steel guardrails 15 , and the lower ends of the shaped steel guardrails 15 are fixed on the transverse distribution beam 6 .
型钢护栏15焊接在装配式桁架上的横向分配梁6上,焊脚高度不小于8mm。栏杆的竖杆、扶手连续涂刷红白相间的警示反光油漆。栈桥钢管桩2在低潮位以上部分涂刷醒目的橘红色面漆,每隔15m设置有安全警示灯,在栈桥中央设置有一个高倍扬声器,一旦发生意外情况,可及时通知作业人员在最短时间内撤离。The section steel guardrail 15 is welded on the transverse distribution beam 6 on the assembled truss, and the height of the welding foot is not less than 8mm. The vertical bars and handrails of the railings are continuously painted with red and white warning reflective paint. The steel pipe pile 2 of the trestle bridge is painted with eye-catching orange-red topcoat on the part above the low tide level, safety warning lights are installed every 15m, and a high-power loudspeaker is set in the center of the trestle bridge. Evacuate inside.
装配式桁架的特点是全部装配式,最重杆件1.8t/件,安装方便,施工通用性好;可以全部拆卸回收使用,经济性好,克服了中国当前“移模”钢箱主梁重量大,安装运输困难,周转性差的弊病。The feature of the prefabricated truss is that it is fully assembled, the heaviest member is 1.8t/piece, it is easy to install, and has good construction versatility; it can be completely disassembled and recycled, and it is economical, overcoming the weight of the main girder of the steel box of the current "moving formwork" in China Large size, difficult installation and transportation, and poor turnover.
横向分配梁6安装位置需与装配式桁架的节点对应;纵向分配梁7横向须均匀布置,桥面铺层8的花纹钢板与纵向分配梁7间断焊接,确保其平整度。各层构件之间须密贴,以确保荷载有效传递。The installation position of the transverse distribution beam 6 must correspond to the node of the fabricated truss; the longitudinal distribution beam 7 must be evenly arranged in the horizontal direction, and the checkered steel plate of the deck layer 8 is intermittently welded with the longitudinal distribution beam 7 to ensure its flatness. The components of each layer must be closely bonded to ensure effective load transfer.
上述实施方式只为说明本实用新型的技术构思及特点,其目的在于让熟悉此项技术的人士能够了解本实用新型的内容并加以实施,并不能以此限制本实用新型的保护范围,凡根据本实用新型精神实质所作的等效变化或修饰,都应涵盖在本实用新型的保护范围内。The above-mentioned embodiments are only to illustrate the technical conception and characteristics of the present utility model. Equivalent changes or modifications made by the spirit of the present utility model shall be covered within the protection scope of the present utility model.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720055908.1U CN206538672U (en) | 2017-01-18 | 2017-01-18 | Novel fabricated truss steel trestle |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201720055908.1U CN206538672U (en) | 2017-01-18 | 2017-01-18 | Novel fabricated truss steel trestle |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN206538672U true CN206538672U (en) | 2017-10-03 |
Family
ID=59940159
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201720055908.1U Expired - Fee Related CN206538672U (en) | 2017-01-18 | 2017-01-18 | Novel fabricated truss steel trestle |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN206538672U (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107700337A (en) * | 2017-11-28 | 2018-02-16 | 北京中铁隧建筑有限公司 | It is a kind of quickly to pacify the light section suspension bridge torn open |
| CN108018867A (en) * | 2017-12-20 | 2018-05-11 | 国网福建省电力有限公司 | The method that coastal waters beach column foot construction is realized based on trestle method |
| CN110924286A (en) * | 2019-12-17 | 2020-03-27 | 中交路桥建设有限公司 | A protect and lead to steel landing stage structure for rebuilding and expanding engineering |
| CN112482202A (en) * | 2020-10-27 | 2021-03-12 | 中建三局基础设施建设投资有限公司 | Pull rod type multipurpose steel trestle bridge abutment and construction method thereof |
| CN113309132A (en) * | 2021-05-07 | 2021-08-27 | 中铁十一局集团第一工程有限公司 | Construction method based on steel trestle bridge anchoring pile |
| CN114214912A (en) * | 2021-12-08 | 2022-03-22 | 胡宗孝 | Portable assembled bridge and construction method |
| CN114277659A (en) * | 2021-03-02 | 2022-04-05 | 福州市规划设计研究院集团有限公司 | A modular steel truss trestle structure suitable for mountain parks |
| CN115637648A (en) * | 2022-10-31 | 2023-01-24 | 中国二十二冶集团有限公司 | Construction method of retractable steel trestle guardrail device |
-
2017
- 2017-01-18 CN CN201720055908.1U patent/CN206538672U/en not_active Expired - Fee Related
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107700337A (en) * | 2017-11-28 | 2018-02-16 | 北京中铁隧建筑有限公司 | It is a kind of quickly to pacify the light section suspension bridge torn open |
| CN108018867A (en) * | 2017-12-20 | 2018-05-11 | 国网福建省电力有限公司 | The method that coastal waters beach column foot construction is realized based on trestle method |
| CN110924286A (en) * | 2019-12-17 | 2020-03-27 | 中交路桥建设有限公司 | A protect and lead to steel landing stage structure for rebuilding and expanding engineering |
| CN112482202A (en) * | 2020-10-27 | 2021-03-12 | 中建三局基础设施建设投资有限公司 | Pull rod type multipurpose steel trestle bridge abutment and construction method thereof |
| CN114277659A (en) * | 2021-03-02 | 2022-04-05 | 福州市规划设计研究院集团有限公司 | A modular steel truss trestle structure suitable for mountain parks |
| CN113309132A (en) * | 2021-05-07 | 2021-08-27 | 中铁十一局集团第一工程有限公司 | Construction method based on steel trestle bridge anchoring pile |
| CN114214912A (en) * | 2021-12-08 | 2022-03-22 | 胡宗孝 | Portable assembled bridge and construction method |
| CN115637648A (en) * | 2022-10-31 | 2023-01-24 | 中国二十二冶集团有限公司 | Construction method of retractable steel trestle guardrail device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN206538672U (en) | Novel fabricated truss steel trestle | |
| CN202899015U (en) | Modular highway steel truss bridge | |
| CN111335142A (en) | Self-anchored cable-stayed arch bridge | |
| CN114214920B (en) | Large-span double-layer steel truss arch bridge and its construction method | |
| CN107227694A (en) | A kind of concrete-bridge transversely strengthening construction | |
| CN110373988A (en) | The big segment steel truss girder and manufacturing technology of a kind of band pair purlin | |
| CN106087711B (en) | Antinode work beam-steel concrete top plate-external prestressing combines T-shaped simply supported beam | |
| CN110344315A (en) | A kind of Long span steel reinforced concrete combined bridge structure and construction technology | |
| CN107841934B (en) | Wing-spreading arch cable-stayed bridge | |
| CN112796196B (en) | Bridge structure suitable for asymmetric swivel and construction method thereof | |
| CN201891069U (en) | Through steel pipe-concrete open type truss combination beam bridge | |
| CN108589512B (en) | A steel-concrete combined beam structure suitable for heavy-duty railways | |
| CN209652741U (en) | A long-span viaduct across railway stations | |
| CN112554031B (en) | Upper bearing type beam-arch combined rigid frame bridge for double-deck traffic | |
| CN210066504U (en) | Large-span cantilever truss type bent cap support system | |
| CN202644410U (en) | Protection canopy frame of triangle-shaped trusswork | |
| CN103758022A (en) | Extensible rapidly-assembled trussed deck type arch bridge | |
| CN214573257U (en) | Truss-suspension cable composite pedestrian bridge structure using cold-formed thin-wall steel | |
| CN112095798B (en) | Super high-rise double-layer super large cantilever steel structure | |
| CN108978432A (en) | A medium-span assembled steel hollow sandwich slab bridge and its manufacturing method | |
| CN210596966U (en) | Large-span steel-concrete composite bridge structure | |
| CN211472116U (en) | A railway assembled steel diagonal strut combined PC beam | |
| CN108316119B (en) | Steel construction overpass convenient to installation | |
| CN207210930U (en) | A kind of highway steel reinforced concrete combined beam structure based on assembling | |
| CN212175441U (en) | Long-span steel-concrete composite bridge large-segment steel truss girder transport beam trestle |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171003 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |