CN108842632A - A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method - Google Patents
A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method Download PDFInfo
- Publication number
- CN108842632A CN108842632A CN201810871151.2A CN201810871151A CN108842632A CN 108842632 A CN108842632 A CN 108842632A CN 201810871151 A CN201810871151 A CN 201810871151A CN 108842632 A CN108842632 A CN 108842632A
- Authority
- CN
- China
- Prior art keywords
- girder
- floorings
- girder steel
- leg
- cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C19/00—Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C5/00—Base supporting structures with legs
- B66C5/02—Fixed or travelling bridges or gantries, i.e. elongated structures of inverted L or of inverted U shape or tripods
- B66C5/04—Fixed or travelling bridges or gantries, i.e. elongated structures of inverted L or of inverted U shape or tripods with runways or tracks supported for movements relative to bridge or gantry
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/04—Cable-stayed bridges
Abstract
A kind of cable-stayed bridge girder steel of the present invention and floorings combined hanging equipment and hanging method, the hanging device of girder steel and floorings is combined into one, by erection crane hoisting steel beam, floorings loop wheel machine uses common cantilever gantry crane, it is mounted on erection crane, electric block can be moved into the cantilever end of gantry crane, to avoid suspension cable interference, the floorings being easy to lift on the outside of suspension cable;The present invention is used for municipal cable-stayed bridge girder steel and floorings lift, have many advantages, such as that installation speed is fast, safe effect is good, easy for construction in construction, construction cost is also controlled simultaneously, especially increase the safety in construction, and it is able to satisfy large-tonnage floorings lifting demand, reference is provided for later same type bridge girder steel and floorings lifting construction.
Description
Technical field
The present invention relates to CONSTRUCTION OF CABLE-STAYED BRIDGE technical fields, are related to a kind of for municipal cable-stayed bridge girder steel and floorings lifting
Combined hanging device and hanging method.
Background technique
Concrete-steel Beam cable-stayed bridge generally comprises the girder steel of composition bridge main body, and suspension cable is installed in girder steel two sides and bridge tower connects
It connects, concrete slab is laid on girder steel.When CONSTRUCTION OF CABLE-STAYED BRIDGE, girder steel is by erection crane segmental hoisting, by oblique after lifting
Drag-line is fixed, and floorings are lifted in girder steel section by floorings loop wheel machine piecemeal.In municipal road construction, encounter across lake, cross a river
Bridge construction, through mixing composite beam form municipal administration cable-stayed bridge frequently with large-span steel, to meet municipal works needs, bridge floor needs to be arranged
Non-motorized lane and pavement, therefore unjointed beam face is wider.Cable stress condition is considered in the design phase, generally by non-machine
Motor-car road and pavement design on the outside of suspension cable, based on this design, part floorings be located at suspension cable outside, and weight compared with
Suspension cable has been installed when greatly, due to lifting floorings, and by the blocking of suspension cable, floorings loop wheel machine can not walk on the outside of suspension cable
Construction, therefore the demand for lifting floorings is unable to satisfy using common floorings loop wheel machine.In addition, floorings and steel in the prior art
Beam section is lifted using special boom hoisting respectively, has both been influenced speed of application or has been increased construction cost.
Summary of the invention
It is an object of the invention to lift demand to meet big width cable-stayed bridge engineering construction floorings, and reduce mechanical throwing
Enter, a kind of combined hanging equipment and hanging method for cable-stayed bridge girder steel and floorings lifting is provided, to reduce difficulty of construction
And construction cost.
To achieve the above object, the present invention provides a kind of cable-stayed bridge girder steel and floorings combined hanging equipment, including
Erection crane for hoisting steel beam, it is characterised in that:The erection crane include two along bridges to being horizontally set on cable-stayed bridge
Girder on the inside of suspension cable is connected respectively by front beam with rear cross beam between the front-end and back-end of two girders, the girder and
Forward and backward crossbeam is truss structure, is equipped with two top booms and two lower booms;Each girder bottom rear end is equipped with rear support leg, rear to prop up
The lower boom of leg upper end and girder is bolted, and the lower end of rear support leg is supported on suitable bridge to the bridge floor for being laid on girder steel top surface
On loop wheel machine sliding rail, and anchored with the lifting lug on girder steel;Front leg strut, the front leg strut upper end and master are equipped among each girder bottom
Beam lower boom is bolted, and lower end is supported on the erection crane sliding rail, and it is horizontally disposed that front leg strut lower end is also connected with one
Pipe bending cylinder, described pipe bending cylinder one end connect with front leg strut by pin shaft, and the other end passes through with erection crane sliding rail
Connecting plate is anchored with bolt, and the anchored end of pipe bending cylinder and erection crane sliding rail is between front leg strut and rear support leg;Each
Girder bottom is set between front leg strut and girder front end there are two auxiliary leg, and two auxiliary legs are located at girder two sides,
It is supported on girder lower boom bottom by support axis connection between two auxiliary legs and by support shaft, two auxiliary leg upper ends are logical
Limit screw connection is crossed, the Limit screw is located at the top of girder lower boom, two auxiliary legs and girder is locked, two auxiliary branch
Leg lower end is supported on girder steel top surface;Girder top surface rear end is equipped with hoist engine, is equipped with suspender lifting close to girder front end of the top surface
System, and suspender is connected by suspender lifting system, the suspender lifting system is equipped with pulley blocks, the traction rope of the hoist engine
Front end around lifting system pulley blocks after be fixedly connected with girder front end;One is set at the top of the erection crane for lifting bridge floor
The gantry crane of plate, the gantry crane both ends are respectively equipped with two gantry crane supporting legs, and top boom is provided on the outside of erection crane girder
Gantry crane sliding rail, the lower end of the gantry crane supporting leg are supported on the gantry crane sliding rail on erection crane girder, gantry crane supporting leg
Upper end connect the horizontally disposed load bearing beam of direction across bridge, the both ends of the load bearing beam, which extend to, forms cantilever on the outside of suspension cable, holds
Carrier beam bottom is equipped with skid beam, and there are two can be along the electric block of skid beam longitudinal sliding motion for connection in the skid beam.
The present invention also provides a kind of methods of lifting cable-stayed bridge girder steel and floorings, using above-mentioned cable-stayed bridge girder steel and bridge floor
Board group closes hanging device, it is characterised in that includes the following steps:
(1) after cable-stayed bridge 0# block steel beam lifting is completed, installs 0# suspension cable and complete two times tensioning, on 0# block girder steel
It is located at the inside of two suspension cables to two sliding rails mobile for erection crane, two sliding rails are laid with along bridge, adjustment sliding rail is
Horizontality;
(2) in 0# block girder steel over-assemble cable-stayed bridge girder steel and floorings combined hanging equipment, by the rear support leg of erection crane
It is respectively supported on sliding rail with front leg strut;Auxiliary leg lower end is supported on girder steel top surface, and upper end is faced by Limit screw and girder
Shi Suoding;Rear support leg and the lifting lug of girder steel top surface are anchored;Gantry crane on erection crane is between rear support leg and front leg strut;
(3) 1# girder steel is lifted:Gantry crane move into heart line from erection crane front leg strut 3800mm at, the gantry crane
Center line refers to the cut-off rule that the longitudinal axis along load bearing beam does gantry crane;Then starting hoist engine transfers suspender, lifts by crane 1#
After girder steel section to design mounting height, hoist engine is locked;
(4) gantry crane is advanced again into from supporting leg 500mm;1# girder steel is docked with 0# girder steel, installation 1# girder steel is oblique
Drag-line, and carry out first time tensioning;
(5) floorings on 1# girder steel are installed:Gantry crane continues to move along between front leg strut and girder front end, and dragon
Gantry crane is away from front leg strut 1755mm;Floorings are transported on 1# beam with beam car, is first lifted and is located at jointly by two electric blocks
Intermediate floorings between suspension cable;Floorings on the outside of two suspension cables are lifted by single motor cucurbit, lifting left side suspension cable
When the floorings of outside, an electric block is first moved at the suspension cable of right side along load bearing beam and is hung with the bridge floor that suspension hook catches on lower section
Main beam is sling floorings by another electric block and is moved on the outside of the suspension cable of left side, and floorings are installed to specific bit
It sets;Then floorings on the outside of the suspension cable of right side are lifted in the same way;
(6) after floorings are installed, gantry crane moves back 1255mm, at from front leg strut 500mm;
(7) Limit screw between auxiliary leg and girder is released, manually auxiliary leg is pushed to close to girder front end, then
With girder Limit screw temporary locking;
(8) anchoring between rear support leg and girder lifting lug is released;
(9) pipe bending cylinder for starting front leg strut, by girder pushing tow 6m forward;During girder moves forward, girder
Top gantry crane, which synchronizes, to be moved backward;
(10) Limit screw of auxiliary leg and girder is released again, and after auxiliary leg is pushed 2m forward, with girder
It is locked with Limit screw;
(11) start the pipe bending cylinder of front leg strut for girder pushing tow 2m further along, in girder moving process, top gantry crane
It synchronizes and moves backward;
(12) (11) are arrived by step (9), girder moves forward in place;Rear support leg and girder lifting lug are anchored, 1# is carried out
Suspension cable two times tensioning on girder steel, then lifts the floorings on next girder steel and girder steel, applies by step (3) to (11) circulation
Work, until completing the lifting of all girder steels and floorings.
The hanging device of girder steel and floorings is combined into one by the present invention, realizes girder steel and floorings lifting shares one
The purpose of machine.By erection crane hoisting steel beam, floorings loop wheel machine uses common cantilever gantry crane, is mounted on erection crane,
Electric block can be moved into the cantilever end of gantry crane, can avoid suspension cable interference, the floorings being easy to lift on the outside of suspension cable;This
It invents and is lifted for municipal cable-stayed bridge girder steel and floorings, with installation speed is fast, safe effect is good, easy for construction in construction
The advantages that, while construction cost is also controlled, the safety in construction is especially increased, and be able to satisfy large-tonnage floorings and hang
Dress demand provides reference for later same type bridge girder steel and floorings lifting construction.
Detailed description of the invention
Fig. 1 is suitable bridge of the invention to structural schematic diagram;
Fig. 2 is direction across bridge structural schematic diagram of the invention;
Fig. 3 is the direction across bridge structural schematic diagram of erection crane rear support leg;
Fig. 4 is the direction across bridge structural schematic diagram of erection crane front leg strut;
Fig. 5 is the suitable bridge of erection crane front leg strut to structural schematic diagram;
Fig. 6 is the direction across bridge structural schematic diagram of erection crane auxiliary leg;
Fig. 7 is the suitable bridge of suspender lifting system to structural schematic diagram;
Fig. 8 is the direction across bridge structural schematic diagram of suspender lifting system;
Fig. 9 is the suitable bridge of gantry crane to structural schematic diagram.
Specific embodiment
As shown in Figure 1 and Figure 2, a kind of cable-stayed bridge girder steel provided by the invention and floorings combined hanging equipment, including be used for
The erection crane of hoisting steel beam, the erection crane include two along bridges to being horizontally set on the inside of stay cable of cable-stayed bridge 100
Girder 1 is connected respectively by front beam and rear cross beam 2 between the front-end and back-end of two girders 1, the girder 1 and front beam, after
Crossbeam 2 is truss structure, is equipped with two top booms and two lower booms;Each girder bottom rear end is equipped with rear support leg 3, rear support leg 3
Upper end and the lower boom of girder 1 are bolted, and the lower end of rear support leg is supported on suitable bridge to the bridge for being laid on 101 top surface of girder steel
On face loop wheel machine sliding rail 4, and anchored with the lifting lug on girder steel 101;Front leg strut 5, the front leg strut 5 are equipped among each girder bottom
Upper end and the lower boom of girder 1 are bolted, and lower end is supported on the erection crane sliding rail 4, and 5 lower end of front leg strut also connects
A horizontally disposed pipe bending cylinder 6 is connect, described 6 one end of pipe bending cylinder is connect with front leg strut 5 by pin shaft, and the other end is hung with bridge floor
Machine sliding rail 4 by connecting plate with bolt by being anchored, and the anchored end of pipe bending cylinder 6 and erection crane sliding rail is located at front leg strut 5
Between rear support leg 3;Each girder bottom is set between front leg strut and girder front end there are two auxiliary leg 7, and two auxiliary are propped up
Leg 7 is located at girder two sides, by support axis connection and is supported on girder lower boom by support shaft between two auxiliary legs
Bottom, two auxiliary leg upper ends are connected by Limit screw, and the Limit screw is located at the top of girder lower boom, by two auxiliary branch
Leg and girder lock, and two auxiliary leg lower ends are supported on girder steel top surface;Each girder top surface rear end is equipped with hoist engine 8, close to main
Top surface of the beam front end is equipped with suspender lifting system 9, and connects suspender 102, the suspender lifting system 9 by suspender lifting system 9
Equipped with pulley blocks, 10 front end of traction rope of the hoist engine 8 after the pulley blocks of lifting system with girder front end around being fixedly connected;
One is set at the top of the erection crane for lifting the gantry crane 11 of floorings, the gantry crane both ends are respectively equipped with two gantry crane branch
Leg 12, top boom is provided with gantry crane sliding rail 13 on the outside of erection crane girder, and the lower end of the gantry crane supporting leg is supported on bridge
On gantry crane sliding rail 13 on the loop wheel machine girder of face, the upper end of gantry crane supporting leg connects the horizontally disposed load bearing beam 14 of direction across bridge, institute
The both ends for stating load bearing beam 14 extend to and form cantilever on the outside of suspension cable, and load bearing beam bottom is equipped with skid beam, are connected in the skid beam
Two can be along the electric block 15 of skid beam longitudinal sliding motion.
As shown in figure 3, the rear support leg 3 includes horizontally disposed rear support leg stull 31,31 top of rear support leg stull
Two lower booms 16 that both ends pass through two rear support leg connecting plates 32 and girder 1 respectively are connected with, 31 bottom two of rear support leg stull
End sets a vertical rear support leg respectively and adjusts oil cylinder 33, and rear support leg adjusts the rear support leg pad that oil cylinder 33 is supported on setting girder steel top surface
On block 34;Two pieces of vertical anchor plates 35 are set among 31 bottom of rear support leg stull, the lifting lug 17 of girder steel top surface is placed in two anchor plates
Between 35, and two anchor plates 35 are anchored with lifting lug 17 by bolt;31 bottom of rear support leg stull is located at a rear support leg and adjusts oil
Rear support leg sliding slot 36 is equipped between cylinder 31 and anchor plate 35, the rear support leg sliding slot 36 is supported on the erection crane sliding rail 4.
As shown in figure 4, the front leg strut 5 includes horizontally disposed front leg strut stull 51,51 top of front leg strut stull
Two lower booms 16 that both ends pass through two front leg strut connecting plates 52 and girder 1 respectively are connected with, 51 bottom two of front leg strut stull
End sets a vertical front leg strut respectively and adjusts oil cylinder 53, and front leg strut adjusts the front leg strut pad that oil cylinder 53 is supported on setting girder steel top surface
On block 54;51 bottom of front leg strut stull is located at two front leg struts and adjusts equipped with front leg strut sliding slot 55 between oil cylinder, and the front leg strut is sliding
Slot 55 is supported on the erection crane sliding rail 4.
As shown in figure 5,5 lower end of front leg strut is also connected with a horizontally disposed pipe bending cylinder 6, described 6 one end of pipe bending cylinder with
Front leg strut 5 is connected by pin shaft, the other end with erection crane sliding rail 4 by being anchored by connecting plate with bolt, and pipe bending cylinder 6
Anchored end with erection crane sliding rail is between front leg strut 5 and rear support leg 3.
As shown in fig. 6, the two auxiliary legs 7 difference position that each girder bottom is arranged between front leg strut and girder front end
Between 1 two sides of girder, two auxiliary legs 7 by support shaft 71 connect and by support shaft support 71 girder 1 lower boom
16 bottoms, two auxiliary legs, 7 upper end are connected by Limit screw 72, and the Limit screw 72 is located at 16 top of girder lower boom,
Two auxiliary legs and girder are locked, two auxiliary leg lower ends are supported on 101 top surface of girder steel;7 bottom of auxiliary leg is equipped with
Height adjustment bolt 73,73 upper end of height adjustment bolt are spirally connected with 7 bottom of auxiliary leg, and lower end is supported on the top of girder steel 101
On face.
As shown in Figure 7, Figure 8, the suspender lifting system 9 includes a pedestal 91 that 1 top of girder is arranged in, the pedestal
A support 92 is set on 91, and the first fixed pulley 93 and the second fixed pulley 94 are fixedly installed on the support 92, is equipped with below girder
One movable pulley 95, two fixed pulleys 93,94 and movable pulley 95 form the pulley blocks of the suspender lifting system, and the hoist engine is led
After messenger 10 successively bypasses the first fixed pulley 93, movable pulley 95, the second fixed pulley 94, fixed with 1 front end of erection crane girder.
As shown in fig. 7, the suspender lifting system 9 is equipped with the longitudinally adjusted oil cylinder 96 of suspender;It is equipped in the girder top surface
Along bridge to the base slide 97 of setting, the base bottom is supported in the base slide 97, the longitudinally adjusted oil of suspender
96 one end of cylinder is connect with the rear end of suspender pedestal, and the other end is anchored along bridge to base slide 97.
As shown in figure 8, the suspender lifting system 9, which is equipped with suspender, laterally adjusts oil cylinder 98, set in 91 top surface of pedestal
The support sliding rail 99 for having direction across bridge to be arranged, the support 92 are supported on the support sliding rail 99, and the suspender laterally adjusts oil
98 one end of cylinder is fixedly connected with suspender support 92, and other end direction across bridge is fixedly connected with the side of the pedestal 91.
As shown in figure 9, setting one at the top of erection crane for lifting the gantry crane 11 of floorings.The gantry crane 11 is using existing
Some general cantilever gantry cranes, gantry crane both ends are respectively equipped with two gantry crane supporting legs 12, along 1 outside top boom of erection crane girder
It is provided with gantry crane sliding rail 13, the lower end of the gantry crane supporting leg is supported on the gantry crane sliding rail 13 on erection crane girder.
The upper end of gantry crane supporting leg 12 connects the horizontally disposed load bearing beam 14 of direction across bridge, and the both ends of the load bearing beam 14 extend to suspension cable
Outside forms cantilever, and load bearing beam bottom is equipped with skid beam, and there are two can be along the electronic calabash of skid beam longitudinal sliding motion for connection in the skid beam
Reed 15.
Using above-mentioned cable-stayed bridge girder steel and floorings combined hanging equipment hoisting cable-stayed bridge girder steel and floorings, Specific construction
Method process is as follows:
(1) after cable-stayed bridge 0# block steel beam lifting is completed, installs 0# suspension cable and complete two times tensioning, on 0# block girder steel
It is located at the inside of two suspension cables to two sliding rails mobile for erection crane, two sliding rails are laid with along bridge, adjustment sliding rail is
Horizontality;
(2) in 0# block girder steel over-assemble cable-stayed bridge girder steel and floorings combined hanging equipment, by the rear support leg of erection crane
It is respectively supported on sliding rail with front leg strut;Auxiliary leg lower end is supported on girder steel top surface, and upper end is faced by Limit screw and girder
Shi Suoding;Rear support leg and the lifting lug of girder steel top surface are anchored;Gantry crane on erection crane is between rear support leg and front leg strut;
(3) 1# girder steel is lifted:Gantry crane move into heart line from erection crane front leg strut 3800mm at, the gantry crane
Center line refers to the cut-off rule that the longitudinal axis along load bearing beam does gantry crane;Then starting hoist engine transfers suspender, lifts by crane 1#
After girder steel section to design mounting height, hoist engine is locked;
(4) gantry crane is advanced again into from supporting leg 500mm;1# girder steel is docked with 0# girder steel, installation 1# girder steel is oblique
Drag-line, and carry out first time tensioning;
(5) floorings on 1# girder steel are installed:Gantry crane continues to move along between front leg strut and girder front end, and dragon
Gantry crane is away from front leg strut 1755mm;Floorings are transported on 1# beam with beam car, is first lifted and is located at jointly by two electric blocks
Intermediate floorings between suspension cable;Floorings on the outside of two suspension cables are lifted by single motor cucurbit, lifting left side suspension cable
When the floorings of outside, an electric block is first moved at the suspension cable of right side along load bearing beam and is hung with the bridge floor that suspension hook catches on lower section
Main beam is sling floorings by another electric block and is moved on the outside of the suspension cable of left side, and floorings are installed to specific bit
It sets;Then floorings on the outside of the suspension cable of right side are lifted in the same way;
(6) after floorings are installed, gantry crane moves back 1255mm, at from front leg strut 500mm;
(7) Limit screw between auxiliary leg and girder is released, manually auxiliary leg is pushed to close to girder front end, then
With girder Limit screw temporary locking;
(8) anchoring between rear support leg and girder lifting lug is released;
(9) pipe bending cylinder for starting front leg strut, by girder pushing tow 6m forward;During girder moves forward, girder
Top gantry crane, which synchronizes, to be moved backward;
(10) Limit screw of auxiliary leg and girder is released again, and after auxiliary leg is pushed 2m forward, with girder
It is locked with Limit screw;
(11) start the pipe bending cylinder of front leg strut for girder pushing tow 2m further along, in girder moving process, top gantry crane
It synchronizes and moves backward;
(12) (11) are arrived by step (9), girder moves forward in place;Rear support leg and girder lifting lug are anchored, 1# is carried out
Suspension cable two times tensioning on girder steel, then lifts the floorings on next girder steel and girder steel, applies by step (3) to (11) circulation
Work, until completing the lifting of all girder steels and floorings.
Claims (8)
1. a kind of cable-stayed bridge girder steel and floorings combined hanging equipment, including the erection crane for hoisting steel beam, feature exists
In:The erection crane include two along bridges to the girder being horizontally set on the inside of stay cable of cable-stayed bridge, the front end of two girders and
It is connected respectively by front beam with rear cross beam between rear end, the girder and forward and backward crossbeam are truss structure, are winded up equipped with two
Bar and two lower booms;Each girder bottom rear end is equipped with rear support leg, and the lower boom of rear support leg upper end and girder is bolted,
The lower end of rear support leg is supported on along bridge on the erection crane sliding rail for being laid on girder steel top surface, and is anchored with the lifting lug on girder steel;
Front leg strut is equipped among each girder bottom, the front leg strut upper end is bolted with girder lower boom, and lower end is supported on
On the erection crane sliding rail, front leg strut lower end is also connected with a horizontally disposed pipe bending cylinder, and described pipe bending cylinder one end is with before
Supporting leg is connected by pin shaft, the other end with erection crane sliding rail by being anchored by connecting plate with bolt, and pipe bending cylinder and bridge
The anchored end of face loop wheel machine sliding rail is between front leg strut and rear support leg;Each girder bottom is between front leg strut and girder front end
If two auxiliary legs are located at girder two sides there are two auxiliary leg, pass through support axis connection between two auxiliary legs and lead to
It crosses support shaft and is supported on girder lower boom bottom, two auxiliary leg upper ends are connected by Limit screw, and the Limit screw is located at
At the top of girder lower boom, two auxiliary legs and girder are locked, two auxiliary leg lower ends are supported on girder steel top surface;The girder top
Surface rear end is equipped with hoist engine, is equipped with suspender lifting system close to girder front end of the top surface, and connect suspender by suspender lifting system,
The suspender lifting system is equipped with pulley blocks, the traction rope front end of the hoist engine around after the pulley blocks of lifting system with girder
Front end is fixedly connected;One is set at the top of the erection crane for lifting the gantry crane of floorings, the gantry crane both ends are set respectively
There are two gantry crane supporting legs, top boom is provided with gantry crane sliding rail, the lower end of the gantry crane supporting leg on the outside of erection crane girder
It is supported on the gantry crane sliding rail on erection crane girder, the upper end of gantry crane supporting leg connects the horizontally disposed carrying of direction across bridge
Beam, the both ends of the load bearing beam extend to and form cantilever on the outside of suspension cable, and load bearing beam bottom is equipped with skid beam, connect in the skid beam
There are two can be along the electric block of skid beam longitudinal sliding motion.
2. cable-stayed bridge girder steel according to claim 1 and floorings combined hanging equipment, it is characterised in that:The rear support leg
Including horizontally disposed rear support leg stull, both ends pass through two rear support leg connecting plates and girder respectively at the top of the rear support leg stull
Two lower booms are connected with, and rear support leg stull bottom both ends set a vertical rear support leg respectively and adjust oil cylinder, and rear support leg is adjusted
Oil cylinder is supported on the rear support leg cushion block of setting girder steel top surface;Two pieces of vertical anchor plates, steel are set among rear support leg stull bottom
The lifting lug of top surface of the beam is placed between two anchor plates, and is anchored two anchor plates and lifting lug by bolt;Rear support leg stull bottom position
It is adjusted in a rear support leg and is equipped with rear support leg sliding slot between oil cylinder and anchor plate, the rear support leg chute supported is in the erection crane
On sliding rail.
3. cable-stayed bridge girder steel according to claim 1 and floorings combined hanging equipment, it is characterised in that:The front leg strut
Including horizontally disposed front leg strut stull, both ends pass through two front leg strut connecting plates and girder respectively at the top of the front leg strut stull
Two lower booms are connected with, and front leg strut stull bottom both ends set a vertical front leg strut respectively and adjust oil cylinder, and front leg strut is adjusted
Oil cylinder is supported on the front leg strut cushion block of setting girder steel top surface;Front leg strut stull bottom, which is located between two front leg struts adjusting oil cylinder, to be set
There is front leg strut sliding slot, the front leg strut chute supported is on the erection crane sliding rail.
4. cable-stayed bridge girder steel according to claim 1 and floorings combined hanging equipment, it is characterised in that:The auxiliary branch
Leg bottom is equipped with height adjustment bolt, and the height adjustment bolt upper end is spirally connected with auxiliary leg bottom, and lower end is supported on girder steel
On top surface.
5. cable-stayed bridge girder steel according to claim 1 and floorings combined hanging equipment, it is characterised in that:The suspender mentions
Crane system includes a pedestal being arranged at the top of girder, and a support is set on the pedestal, and fixed setting first is fixed on the support
Pulley and the second fixed pulley are equipped with a movable pulley, fixed pulley and running block into the suspender lifting system below girder
Pulley blocks, it is solid with girder front end after the traction rope of the hoist engine successively bypasses the first fixed pulley, movable pulley, the second fixed pulley
It is fixed.
6. cable-stayed bridge girder steel according to claim 5 and floorings combined hanging equipment, it is characterised in that:The suspender mentions
Crane system is equipped with the longitudinally adjusted oil cylinder of suspender;It is equipped in the girder top surface along base slide of the bridge to setting, the pedestal bottom
Portion is supported in the base slide, and described longitudinally adjusted oil cylinder one end of suspender is connect with the rear end of suspender pedestal, and the other end is suitable
Bridge is anchored to base slide.
7. cable-stayed bridge girder steel according to claim 5 and floorings combined hanging equipment, it is characterised in that:The suspender mentions
Crane system is equipped with suspender and laterally adjusts oil cylinder, is equipped with the support sliding rail of direction across bridge setting, the support branch in the base top surface
Support on the support sliding rail, the suspender laterally adjusts oil cylinder one end and is fixedly connected with suspender support, other end direction across bridge and
The side of the pedestal is fixedly connected.
8. a kind of use cable-stayed bridge girder steel according to claim 1 and floorings combined hanging equipment hoisting cable-stayed bridge girder steel
And the method for floorings, it is characterised in that include the following steps:
(1) after cable-stayed bridge 0# block steel beam lifting is completed, installs 0# suspension cable and complete two times tensioning, along bridge on 0# block girder steel
To two sliding rails mobile for erection crane are laid with, two sliding rails are located at the inside of two suspension cables, and adjustment sliding rail is level
State;
(2) in 0# block girder steel over-assemble cable-stayed bridge girder steel and floorings combined hanging equipment, by the rear support leg of erection crane with before
Supporting leg is respectively supported on sliding rail;Auxiliary leg lower end is supported on girder steel top surface, and upper end is temporarily locked by Limit screw with girder
It is fixed;Rear support leg and the lifting lug of girder steel top surface are anchored;Gantry crane on erection crane is between rear support leg and front leg strut;
(3) 1# girder steel is lifted:Gantry crane move into heart line from erection crane front leg strut 3800mm at, the gantry crane center
Line refers to the cut-off rule that the longitudinal axis along load bearing beam does gantry crane;Then starting hoist engine transfers suspender, lifts by crane 1# girder steel
After section to design mounting height, hoist engine is locked;
(4) gantry crane is advanced again into from supporting leg 500mm;1# girder steel is docked with 0# girder steel, 1# girder steel suspension cable is installed,
And carry out first time tensioning;
(5) floorings on 1# girder steel are installed:Gantry crane continues to move along between front leg strut and girder front end, and gantry crane
Away from front leg strut 1755mm;Floorings are transported on 1# beam with beam car, is first lifted jointly by two electric blocks and is located at oblique pull
Intermediate floorings between rope;Floorings on the outside of two suspension cables are lifted by single motor cucurbit, on the outside of the suspension cable of lifting left side
When floorings, an electric block is first moved at the suspension cable of right side and is caught on suspension hook the erection crane master of lower section along load bearing beam
Beam is sling floorings by another electric block and is moved on the outside of the suspension cable of left side, and floorings are installed to designated position;So
Lift floorings on the outside of the suspension cable of right side in the same way afterwards;
(6) after floorings are installed, gantry crane moves back 1255mm, at from front leg strut 500mm;
(7) release the Limit screw between auxiliary leg and girder, manually auxiliary leg be pushed to close to girder front end, then with master
Beam Limit screw temporary locking;
(8) anchoring between rear support leg and girder lifting lug is released;
(9) pipe bending cylinder for starting front leg strut, by girder pushing tow 6m forward;During girder moves forward, girder top
Gantry crane, which synchronizes, to be moved backward;
(10) Limit screw of auxiliary leg and girder is released again, and after auxiliary leg is pushed 2m forward, with girder limit
Position screw lock;
(11) start the pipe bending cylinder of front leg strut for girder pushing tow 2m further along, in girder moving process, top gantry crane is synchronous
It moves backward;
(12) (11) are arrived by step (9), girder moves forward in place;Rear support leg and girder lifting lug are anchored, 1# girder steel is carried out
On suspension cable two times tensioning, then lift the floorings on next girder steel and girder steel, by step (3) to (11) circulation construction,
Until completing the lifting of all girder steels and floorings.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810871151.2A CN108842632A (en) | 2018-08-02 | 2018-08-02 | A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810871151.2A CN108842632A (en) | 2018-08-02 | 2018-08-02 | A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108842632A true CN108842632A (en) | 2018-11-20 |
Family
ID=64195319
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810871151.2A Pending CN108842632A (en) | 2018-08-02 | 2018-08-02 | A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108842632A (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629448A (en) * | 2019-01-28 | 2019-04-16 | 中铁大桥局集团有限公司 | The synchronous device and method for setting up girder and floorings |
CN111254831A (en) * | 2020-01-20 | 2020-06-09 | 中铁大桥局第七工程有限公司 | Hoisting method of steel structure frame beam of through arch bridge |
CN111620244A (en) * | 2020-06-05 | 2020-09-04 | 招商局重庆交通科研设计院有限公司 | Bridge floor crane |
CN113086827A (en) * | 2021-04-02 | 2021-07-09 | 山东省公路桥梁建设有限公司 | Lifting appliance system for transporting beam under beam and lifting method |
CN113682989A (en) * | 2021-07-20 | 2021-11-23 | 中铁建工集团有限公司 | Auxiliary hoisting device for bridge construction |
CN113832869A (en) * | 2020-06-23 | 2021-12-24 | 青岛同创旷远企业发展有限公司 | Urban overhead integrated operation process and assembly based on bridge-turning process |
CN114232487A (en) * | 2021-12-15 | 2022-03-25 | 中交路桥建设有限公司 | Construction system for erecting main beam of large-span cable-stayed bridge |
CN117286804A (en) * | 2023-11-27 | 2023-12-26 | 中交一公局第六工程有限公司 | Integrated equipment for paving and erecting beam and girder erecting method |
CN114232487B (en) * | 2021-12-15 | 2024-04-19 | 中交路桥建设有限公司 | Construction system for erecting main girder of large-span cable-stayed bridge |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108203934A (en) * | 2018-02-02 | 2018-06-26 | 中交二公局第工程有限公司 | Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading |
CN108217448A (en) * | 2017-12-29 | 2018-06-29 | 武汉理工大学 | A kind of integrated bridge floor device for hoisting for composite beam construction |
CN108265628A (en) * | 2018-02-01 | 2018-07-10 | 中交路桥建设有限公司 | One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method |
-
2018
- 2018-08-02 CN CN201810871151.2A patent/CN108842632A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108217448A (en) * | 2017-12-29 | 2018-06-29 | 武汉理工大学 | A kind of integrated bridge floor device for hoisting for composite beam construction |
CN108265628A (en) * | 2018-02-01 | 2018-07-10 | 中交路桥建设有限公司 | One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method |
CN108203934A (en) * | 2018-02-02 | 2018-06-26 | 中交二公局第工程有限公司 | Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629448A (en) * | 2019-01-28 | 2019-04-16 | 中铁大桥局集团有限公司 | The synchronous device and method for setting up girder and floorings |
CN109629448B (en) * | 2019-01-28 | 2023-10-20 | 中铁大桥局集团有限公司 | Device and method for synchronously erecting girder and bridge deck |
CN111254831A (en) * | 2020-01-20 | 2020-06-09 | 中铁大桥局第七工程有限公司 | Hoisting method of steel structure frame beam of through arch bridge |
CN111254831B (en) * | 2020-01-20 | 2021-05-14 | 中铁大桥局第七工程有限公司 | Hoisting method of steel structure frame beam of through arch bridge |
CN111620244A (en) * | 2020-06-05 | 2020-09-04 | 招商局重庆交通科研设计院有限公司 | Bridge floor crane |
CN111620244B (en) * | 2020-06-05 | 2021-08-10 | 招商局重庆交通科研设计院有限公司 | Bridge floor crane |
CN113832869A (en) * | 2020-06-23 | 2021-12-24 | 青岛同创旷远企业发展有限公司 | Urban overhead integrated operation process and assembly based on bridge-turning process |
CN113086827A (en) * | 2021-04-02 | 2021-07-09 | 山东省公路桥梁建设有限公司 | Lifting appliance system for transporting beam under beam and lifting method |
CN113682989A (en) * | 2021-07-20 | 2021-11-23 | 中铁建工集团有限公司 | Auxiliary hoisting device for bridge construction |
CN114232487A (en) * | 2021-12-15 | 2022-03-25 | 中交路桥建设有限公司 | Construction system for erecting main beam of large-span cable-stayed bridge |
CN114232487B (en) * | 2021-12-15 | 2024-04-19 | 中交路桥建设有限公司 | Construction system for erecting main girder of large-span cable-stayed bridge |
CN117286804A (en) * | 2023-11-27 | 2023-12-26 | 中交一公局第六工程有限公司 | Integrated equipment for paving and erecting beam and girder erecting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108842632A (en) | A kind of cable-stayed bridge girder steel and floorings combined hanging equipment and hanging method | |
CN104894979B (en) | Side coil feeding beam Bridge Erector and beam erecting method | |
CN102912730B (en) | Hoisting construction method for single-rib closure rope of large-span reinforced concrete arch bridge | |
CN105421249A (en) | Novel dragging- hoisting combined type hanging basket structure and construction method | |
CN108265628A (en) | One kind rides cable-styled erection crane lifting cable-stayed bridge girder steel and bridge floor board construction method | |
CN101831888B (en) | 1200 tonner water conservancy aqueduct transportation and erection equipment | |
CN109653105B (en) | Main truss system of box girder bridge cantilever construction hanging basket and use method thereof | |
CN103882812A (en) | Construction method for midspan main beams of cable-stayed bridge | |
CN106744351A (en) | The method that cable-stayed bridge main-beam lifting is carried out using cable crane | |
CN110258352A (en) | The steel reinforced concrete combined bridge construction method that two bridgings are done | |
JP3455660B2 (en) | Lifting device for bridge girder erection | |
CN109183620A (en) | Telescoping bracket, steel box-girder hanging device and hanging method | |
CN113120771A (en) | Double-side synchronous hoisting equipment suitable for rear cantilever arm of composite-section beam bridge and construction method | |
CN207987749U (en) | Ride cable-styled erection crane | |
CN105484166B (en) | A kind of ladder type masts type cantilever loop wheel machine | |
CN102071641B (en) | Cement beam packs bridge machine cloth supporting leg type integration of transporting and building Bridge Erector and bridge formation engineering method thereof | |
CN210368669U (en) | Hoisting equipment for two-span continuous construction of combined beam | |
CN110344334B (en) | Construction method for two-span continuous steel-concrete composite bridge by adopting back cable type bridge girder erection machine | |
CN108086168A (en) | Ride cable-styled erection crane | |
CN205529915U (en) | Ladder type masts type hangs pieces together loop wheel machine | |
CN112144401A (en) | Bridge girder erection machine over-span method based on curve track and large longitudinal slope environment | |
CN208995928U (en) | A kind of multi-functional erection crane suitable for composite beam construction | |
CN209065230U (en) | A kind of towed vertical transferring apparatus system | |
CN110616638A (en) | Bracket-free hoisting method for steel box girder in shallow beach area of suspension bridge | |
CN110316662A (en) | A kind of large span gantry crane construction method of installation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20181120 |
|
WD01 | Invention patent application deemed withdrawn after publication |