CN105986106A - Postweld heat treatment technology of steel tube - Google Patents

Postweld heat treatment technology of steel tube Download PDF

Info

Publication number
CN105986106A
CN105986106A CN201510047385.1A CN201510047385A CN105986106A CN 105986106 A CN105986106 A CN 105986106A CN 201510047385 A CN201510047385 A CN 201510047385A CN 105986106 A CN105986106 A CN 105986106A
Authority
CN
China
Prior art keywords
heat treatment
steel
pipe
less
wall thickness
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510047385.1A
Other languages
Chinese (zh)
Inventor
赵伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Qin Huang Machinery Manufacturing Co Ltd
Original Assignee
Chongqing Qin Huang Machinery Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Qin Huang Machinery Manufacturing Co Ltd filed Critical Chongqing Qin Huang Machinery Manufacturing Co Ltd
Priority to CN201510047385.1A priority Critical patent/CN105986106A/en
Publication of CN105986106A publication Critical patent/CN105986106A/en
Pending legal-status Critical Current

Links

Landscapes

  • Heat Treatment Of Articles (AREA)

Abstract

The invention discloses a postweld heat treatment technology of steel tube. The postweld heat treatment technology of steel tube comprises the following steps: 1) the postweld heat treatment requirements: the 15CrMo tube with wall thickness of greater than 10mm and the caliber of greater than 108 mm as well as 12Cr1MoV tube with wall thickness of greater than 8mm and the caliber of greater than 108 mm are subjected to heat treatment after being welded; wherein heat preservation and slow cooling should be carried out if the heat treatment is not required after welding; 2) the heat processing operation procedures are prescribed; 3) the heating and cooling speed of the 15CrMo and 12Cr1MoV tubes is calculated according to 6250/thickness(DEG C/h) and is no greater than 300 DEG C/h, the temperature during a cooling process is less than 300 DEG C and cannot be controlled, 4) the postweld heat treatment of a xenogenesis steel welded joint should be compressively considered according to steel and the used welding rod (welding wire) at two sides, the heat treatment temperature generally does not exceed a lower critical of lower side steel of an alloy component; and 5) the heating width of the heat treatment can be calculated from the center of the welded seam, the preheating width at each side is 3 times or above the thickness of the tube, and the thickness is no less than 60 mm. The heat treatment technology has the advantages of reasonable process and low manufacture cost.

Description

A kind of post weld heat treatment technique of steel pipe
Technical field
The present invention relates to the post weld heat treatment technique of a kind of steel pipe.
Background technology
The post weld heat treatment technique of existing steel pipe exists that procedure arrangement is unreasonable, operation is various, higher to operator's skill requirement so that production cost is higher.
Summary of the invention
Because the drawbacks described above of prior art, the technical problem to be solved be to provide a kind of operation rationally, the post weld heat treatment technique of the steel pipe of low cost of manufacture.
For achieving the above object, the invention provides
The post weld heat treatment technique of a kind of steel pipe, comprises the steps:
1), post weld heat treatment requirement
All wall thickness must carry out heat treatment more than the 15CrMo pipe of 108mm, wall thickness more than 8mm, the caliber 12Cr1MoV pipe postwelding more than 108mm more than 10mm, caliber.The postwelding that need not heat treatment should carry out being incubated slow cooling.
2), cooking schedule
3), 15CrMo, 12Cr1MoV pipe heating, cooling speed, typically can calculate by 6250/ wall thickness (DEG C/h), and no more than 300 DEG C/h, in temperature-fall period, less than 300 DEG C can not control.
4), the post weld heat treatment of Dissimilar Steel Welded Joint, should consider by both sides steel and welding rod used (welding wire).Heat treatment temperature is usually no more than the lower critical of alloy composition downside steel.
5), the width of heating of heat treatment, count from Weld pipe mill, every side is not less than three times of pipe wall thickness, and not less than 60mm.
6), the insulation width of heat treatment, count from Weld pipe mill, every side is not less than five times of pipe wall thickness, to reduce thermograde.Instrument used, thermocouple and adnexa should be demarcated according to the requirement of metering or verify.
7), the heating means of heat treatment, the method using remote control crawler type resistance heating, specifically used method is as follows:
7.1) thermocouple symmetry being fixed on weld seam both sides, horizontal tube is placed up and down, and standpipe is symmetrically placed, pops one's head in good with bead contact, then heating tape is wrapped in welded joints, bandages with insulation material, switch on power and process.
7.2), during heat treatment, the temporary support of pipeline should be removed after heat treatment, and the weld seam of weight bearing area should add temporary support at heat treatment, in case being deformed in processing procedure.The heating tape of standpipe should prevent it from falling.During constant temperature, in heated perimeter, the temperature difference of any two points should be less than 50 DEG C.
7.3) after heat treatment, should make a record and labelling, and stamp steel seal number or the permanent marker of heat treatment work.
7.4) weld seam after heat treatment need to carry out hardness test.Weld hardness after heat treatment is usually no more than mother metal Brinell hardness and adds 100, and less than 270.
The invention has the beneficial effects as follows: operation of the present invention is reasonable, low cost of manufacture.
Detailed description of the invention
Below in conjunction with embodiment, the invention will be further described:
The post weld heat treatment technique of a kind of steel pipe, comprises the steps:
1), post weld heat treatment requirement
All wall thickness must carry out heat treatment more than the 15CrMo pipe of 108mm, wall thickness more than 8mm, the caliber 12Cr1MoV pipe postwelding more than 108mm more than 10mm, caliber.The postwelding that need not heat treatment should carry out being incubated slow cooling.
2), cooking schedule
3), 15CrMo, 12Cr1MoV pipe heating, cooling speed, typically can calculate by 6250/ wall thickness (DEG C/h), and no more than 300 DEG C/h, in temperature-fall period, less than 300 DEG C can not control.
4), the post weld heat treatment of Dissimilar Steel Welded Joint, should consider by both sides steel and welding rod used (welding wire).Heat treatment temperature is usually no more than the lower critical of alloy composition downside steel.
5), the width of heating of heat treatment, count from Weld pipe mill, every side is not less than three times of pipe wall thickness, and not less than 60mm.
6), the insulation width of heat treatment, count from Weld pipe mill, every side is not less than five times of pipe wall thickness, to reduce thermograde.Instrument used, thermocouple and adnexa should be demarcated according to the requirement of metering or verify.
7), the heating means of heat treatment, the method using remote control crawler type resistance heating, specifically used method is as follows:
7.1) thermocouple symmetry being fixed on weld seam both sides, horizontal tube is placed up and down, and standpipe is symmetrically placed, pops one's head in good with bead contact, then heating tape is wrapped in welded joints, bandages with insulation material, switch on power and process.
7.2), during heat treatment, the temporary support of pipeline should be removed after heat treatment, and the weld seam of weight bearing area should add temporary support at heat treatment, in case being deformed in processing procedure.The heating tape of standpipe should prevent it from falling.During constant temperature, in heated perimeter, the temperature difference of any two points should be less than 50 DEG C.
7.3) after heat treatment, should make a record and labelling, and stamp steel seal number or the permanent marker of heat treatment work.
7.4) weld seam after heat treatment need to carry out hardness test.Weld hardness after heat treatment is usually no more than mother metal Brinell hardness and adds 100, and less than 270.

Claims (1)

1. the post weld heat treatment technique of a steel pipe, it is characterised in that comprise the steps:
1), post weld heat treatment requirement
All wall thickness must carry out heat treatment more than the 15CrMo pipe of 108mm, wall thickness more than 8mm, the caliber 12Cr1MoV pipe postwelding more than 108mm more than 10mm, caliber;
The postwelding that need not heat treatment should carry out being incubated slow cooling;
2), cooking schedule
3), 15CrMo, 12Cr1MoV pipe heating, cooling speed, typically can calculate by 6250/ wall thickness (DEG C/h), and no more than 300 DEG C/h, in temperature-fall period, less than 300 DEG C can not control;
4), the post weld heat treatment of Dissimilar Steel Welded Joint, should consider by both sides steel and welding rod used (welding wire);Heat treatment temperature is usually no more than the lower critical of alloy composition downside steel;
5), the width of heating of heat treatment, count from Weld pipe mill, every side is not less than three times of pipe wall thickness, and not less than 60mm;
6), the insulation width of heat treatment, count from Weld pipe mill, every side is not less than five times of pipe wall thickness, to reduce thermograde;Instrument used, thermocouple and adnexa should be demarcated according to the requirement of metering or verify;
7), the heating means of heat treatment, the method using remote control crawler type resistance heating, specifically used method is as follows:
7.1) thermocouple symmetry being fixed on weld seam both sides, horizontal tube is placed up and down, and standpipe is symmetrically placed, pops one's head in good with bead contact, then heating tape is wrapped in welded joints, bandages with insulation material, switch on power and process;
7.2), during heat treatment, the temporary support of pipeline should be removed after heat treatment, and the weld seam of weight bearing area should add temporary support at heat treatment, in case being deformed in processing procedure;The heating tape of standpipe should prevent it from falling;During constant temperature, in heated perimeter, the temperature difference of any two points should be less than 50 DEG C;
7.3) after heat treatment, should make a record and labelling, and stamp steel seal number or the permanent marker of heat treatment work;
7.4) weld seam after heat treatment need to carry out hardness test;Weld hardness after heat treatment is usually no more than mother metal Brinell hardness and adds 100, and less than 270.
CN201510047385.1A 2015-01-30 2015-01-30 Postweld heat treatment technology of steel tube Pending CN105986106A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510047385.1A CN105986106A (en) 2015-01-30 2015-01-30 Postweld heat treatment technology of steel tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510047385.1A CN105986106A (en) 2015-01-30 2015-01-30 Postweld heat treatment technology of steel tube

Publications (1)

Publication Number Publication Date
CN105986106A true CN105986106A (en) 2016-10-05

Family

ID=57035212

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510047385.1A Pending CN105986106A (en) 2015-01-30 2015-01-30 Postweld heat treatment technology of steel tube

Country Status (1)

Country Link
CN (1) CN105986106A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107122556A (en) * 2017-05-03 2017-09-01 柏诚工程股份有限公司 A kind of manufacture method of the integrated cold water computer room of monoblock type
CN107619922A (en) * 2017-09-29 2018-01-23 彭娟 A kind of intermediate-frequency induction heating technique of heat-resistant high alloy steel weld bond
CN111334649A (en) * 2020-04-15 2020-06-26 天津海运职业学院 G115 steel small-diameter pipe heat treatment method through flexible ceramic resistance heating

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107122556A (en) * 2017-05-03 2017-09-01 柏诚工程股份有限公司 A kind of manufacture method of the integrated cold water computer room of monoblock type
CN107619922A (en) * 2017-09-29 2018-01-23 彭娟 A kind of intermediate-frequency induction heating technique of heat-resistant high alloy steel weld bond
CN107619922B (en) * 2017-09-29 2019-01-25 彭娟 A kind of intermediate-frequency induction heating technique of heat-resistant high alloy steel weld bond
CN111334649A (en) * 2020-04-15 2020-06-26 天津海运职业学院 G115 steel small-diameter pipe heat treatment method through flexible ceramic resistance heating

Similar Documents

Publication Publication Date Title
CN205741134U (en) Tee pipe fitting scene local heat treatmet device
CN102839270B (en) Postwelding stress-releasing heat treatment technology for pressure bearing equipment
MX2009012146A (en) Method for manufacturing tanks.
CN105986106A (en) Postweld heat treatment technology of steel tube
CN101462190A (en) Low temperature welding method between cast steel and low-alloy structural steel
CN101462191A (en) Low temperature welding method between Q345D steel structure
US8735782B2 (en) System for forming brazed joint between tie wire and workpiece, and methods therefor
CN105603173A (en) Furnace tube welding heat-treatment technology
CN105986107A (en) Welded seam heat processing technology
CN105624387A (en) Heating and cooling method for post-weld heat treatment of pipe fittings
CN106270977A (en) A kind of steel plate low temperature environment welding procedure
CN104148841A (en) Tee joint main pipe butt joint local post weld heat treatment method
CN105714065A (en) Heat treatment process for pressure vessel
CN107868870A (en) A kind of post weld heat treatment technique of steel pipe
CN105983765A (en) Heat treatment process for alloy-steel pipes
CN103934548A (en) Welding method of pure nickel pipelines
CN105171261A (en) Welding method of large steel making converter body
CN105986110A (en) Postweld heat treatment process for steel pipe
CN104801872B (en) A kind of semiconductor refrigeration member bonding machine
CN104227187A (en) Large cardan shaft flange welding method
CN105081002B (en) X80 steel-grade D1422*30.8 Frequency Induction Heating simmers the manufacturing process of bend pipe processed
CN105714095A (en) Postweld heat treatment process
CN105986081A (en) Heat treatment process of steel TP92
CN105057907B (en) The assembled welding procedure of super-large diameter diamond circular saw film base body
CN104475929A (en) Inert gas arc welding process suitable for aluminum and aluminum alloy with plate thickness smaller than 4mm

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161005