CN105171261B - A kind of welding method of large-scale steelmaking converter body of heater - Google Patents

A kind of welding method of large-scale steelmaking converter body of heater Download PDF

Info

Publication number
CN105171261B
CN105171261B CN201510608032.4A CN201510608032A CN105171261B CN 105171261 B CN105171261 B CN 105171261B CN 201510608032 A CN201510608032 A CN 201510608032A CN 105171261 B CN105171261 B CN 105171261B
Authority
CN
China
Prior art keywords
welding
furnace shell
heater
weld
converter body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510608032.4A
Other languages
Chinese (zh)
Other versions
CN105171261A (en
Inventor
孔炯
施光涛
徐峥
高忠明
郭建华
汪柱兵
琚志海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510608032.4A priority Critical patent/CN105171261B/en
Publication of CN105171261A publication Critical patent/CN105171261A/en
Application granted granted Critical
Publication of CN105171261B publication Critical patent/CN105171261B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Arc Welding In General (AREA)

Abstract

The invention discloses a kind of welding method of large-scale steelmaking converter body of heater.It is comprised the following steps:1)Preparation of construction before welding body of heater:Escape way first is set up in converter body surrounding 11.5m elevation locations, finally the diameter to furnace shell is detected, the diameter deviation of furnace shell should meet design requirement;2)Tack welding;3)Formal welding:Locator card is first removed before formal welding, furnace body inside is welded afterwards, until weld joint on inner side untill when being welded to the 2/3 of its length;4)Post weld heat treatment;5)Final welding:The back chipping treatment of weld joint on inner side, then the external side of soldering furnace are first carried out, after the completion of outer side weld, the welding of furnace body inside residue weld seam is finally completed.The present invention compared to existing technology, by welding sequence and welding method efficient combination, improves the quality and operating efficiency of welding, reduces mass defect, increases a solder yield.

Description

A kind of welding method of large-scale steelmaking converter body of heater
Technical field
The invention belongs to converter body welding technology field, more particularly to a kind of welding side of large-scale steelmaking converter body of heater Method.
Background technology
At present, it is existing on steelmaking converter body of heater welding method, relevant information is not directly found, but title is relatively Patent design it is more;Such as " the baking oven furnace body welding robot double work of China national Patent Office's on October 2nd, 2013 issue Stand ", Patent No. CN201310292826, it is mainly baking oven furnace body welding robot double work station by constituting The each edge of workpiece is gripped, so as to preferably be shaped, is easy to welding.For another example China national Patent Office 2013 " attemperator of blast furnace welding under low temperature environment " of the issue of November 6, Patent No. CN201220473027, its is main Be to provide it is a kind of blast furnace is heated up at low temperature, is incubated, to ensure low temperature ring of the welding region temperature more than 0 DEG C The attemperator of blast furnace welding under border.But current, there is not the patent to form steel-making patent body of heater welding method also.
With the policy guidance that China's economy is developed rapidly and country's encouragement eliminates the backward production facilities, metallurgy industry is faced with life Production. art, renewal of the equipment, require newly-built or enlarging steelmaking system equipment accordingly, increase production capacity and quality assurance.Converter installation It is most to popularize general steel-making main equipment, is directly connected to the yield and quality of steel mill's molten steel.And steelmaking converter body of heater is segmented Site Welding of marching into the arena will directly affect the follow-up quality of production of converter body, and it is difficult that the special material of body of heater causes welding quality to control Degree is increased.
The content of the invention
It is an object of the invention to provide a kind of welding method of large-scale steelmaking converter body of heater, to solve above-mentioned background technology The problem of middle proposition.
To achieve the above object, present invention employs following technical scheme:
A kind of welding method of large-scale steelmaking converter body of heater, comprises the following steps:
1)Preparation of construction before welding body of heater:
Escape way first is set up in converter body surrounding 11.5m elevation locations, to facilitate applying for human users and cable If converter body includes upper furnace shell and lower furnace shell, finally the diameter to furnace shell is detected, the diameter deviation of furnace shell should meet and set Meter is required, and the difference of maximum gauge and minimum diameter cannot be greater than the 3/1000 of furnace shell intended diameter, and the limit of furnace shell height is inclined Difference is ± the 3/1000 of design height, and fire door plane is 1/1000 to the squareness tolerance of furnace shell axis;
2)Tack welding:
First the upper furnace shell of converter body and lower furnace shell are linked together by locator card, then by welder using formal weldering Material and welding procedure welding are connect, ensures that weld seam does not ftracture in welding process, postwelding inspection is carried out after the completion of last tack welding, gone out During existing defect, it is necessary to root out tack welding meat and re-start tack welding;
3)Formal welding:
Locator card is first removed before formal welding, furnace body inside is welded afterwards, until weld joint on inner side is being welded to the 2/3 of its length When untill, in formal welding process, some welders weldings simultaneously at same direction;
4)Post weld heat treatment:
After formal welding is finished, in the case where weld seam without cooling down completely, by heater energization come to weld seam Locate heat temperature raising up to temperature reaches 200 DEG C and is incubated 2 hours, to remove the hydrogen remained in weld seam;
5)Final welding:
The back chipping treatment of weld joint on inner side, then the external side of soldering furnace are first carried out, after the completion of outer side weld, is finally completed in body of heater The welding of side residue weld seam.
Preferably, step 2)Middle locator card is that the 16Mn steel plates that specification is 800 × 400 × 30mm are made, locator card Side opens up to ensure the semi-circular hole that locator card is consistent with upper furnace shell and lower furnace shell joint gap.
Preferably, step 2)Middle locator card is uniformly arranged on outside in furnace shell, and locator card on the outside of furnace shell avoids furnace shell Both sides gudgeon position.
Preferably, step 2)In when tack welding is carried out, outside carries out tack welding in body of heater, and fusion length is 300mm, adjacent weld spacing is 300mm.
Preferably, step 3)In being preheated with before formal welding after removing locator card, preheating temperature is 125 ± 25 DEG C interval.
Preferably, step 4)Wrap up heat-preservation cotton in heater periphery.
Compared with prior art, beneficial effects of the present invention are as follows:
The present invention compared to existing technology, by welding sequence and welding method efficient combination, improves the quality and work of welding Make efficiency, reduce mass defect, increase a solder yield.
Brief description of the drawings
Fig. 1 is the welding schematic diagram of upper furnace shell and lower furnace shell.
Fig. 2 is the arrangement schematic diagram of locator card.
Specific embodiment
Preferred embodiment of the invention is described in further detail with reference to embodiment.
As depicted in figs. 1 and 2, a kind of welding method of large-scale steelmaking converter body of heater, comprises the following steps:
1)Preparation of construction before welding body of heater:
Escape way first is set up in the surrounding 11.5m elevation locations of converter body 1, to facilitate applying for human users and cable If converter body 1 includes upper furnace shell 2 and lower furnace shell 3, finally the diameter to furnace shell detects that the diameter deviation of furnace shell should be accorded with Design requirement is closed, and the difference of maximum gauge and minimum diameter cannot be greater than the 3/1000 of furnace shell intended diameter, the pole of furnace shell height Limit deviation is ± the 3/1000 of design height, and fire door plane is 1/1000 to the squareness tolerance of furnace shell axis.
2)Tack welding:
First the upper furnace shell 2 of converter body 1 and lower furnace shell 3 are linked together by locator card 4, locator card 4 is uniformly arranged The outside in furnace shell, and locator card 4 on the outside of furnace shell avoids furnace shell both sides gudgeon position, locator card 4 is that specification is 800 × 400 The 16Mn steel plates of × 30mm are made, and the side of the locator card 4 opens up to ensure locator card 4 with upper furnace shell 2 and lower furnace shell 3 The consistent semi-circular hole of joint gap, then uses formal welding material and welding procedure welding by welder, in welding process really Protect weld seam not ftracture, postwelding inspection is carried out after the completion of last tack welding, when there is defect, it is necessary to root out tack welding meat and enter again Row tack welding, when carrying out tack welding, outside carries out tack welding in body of heater 1, and fusion length is 300mm, adjacent weld spacing It is 300mm.
3)Formal welding:
Locator card 4 is first removed before formal welding, the inner side of body of heater 1 is welded afterwards, until weld joint on inner side is being welded to its length Untill when 2/3, to be preheated with before formal welding after dismounting locator card 4, preheating temperature is formal to weld in 125 ± 25 DEG C of intervals In termination process, some welder's weldings simultaneously at same direction.
4)Post weld heat treatment:
After formal welding is finished, in the case where weld seam without cooling down completely, it is powered come to weld seam by heater 5 Place's heat temperature raising up to temperature reaches 200 DEG C and is incubated 2 hours, to remove the hydrogen remained in weld seam, protect by the periphery of heater 5 parcel Warm cotton 6.
5)Final welding:
The back chipping treatment of weld joint on inner side is first carried out, then welds the outside of body of heater 1, after the completion of outer side weld, finally complete body of heater 1 The welding of remaining inside weld seam.
The present invention proposes a kind of welding method of large-scale steelmaking converter body of heater, and the present invention is carried out successively by following operation: Confirm assembling quality, check tack weld, welding region cleaning, preheating is welded at groove 2/3 from converter, the polishing of outside back chipping, Back chipping quality determination, weld joint on inner side welding, outer side weld welding, face of weld cleaning, post weld heat treatment, visual examination of weld, UT checks that wherein weld joint on inner side welding and outer side weld are intended to preheating before welding and carrying out, and the present invention is by welding sequence and welds Method efficient combination, improves the quality and operating efficiency of welding, reduces mass defect, increases a solder yield.
Embodiment above is only that the preferred embodiment of the present invention is described, and not the scope of the present invention is entered Row is limited, and on the premise of design spirit of the present invention is not departed from, those of ordinary skill in the art make to technical scheme The various modifications for going out and improvement, all should fall into the protection domain of claims of the present invention determination.

Claims (6)

1. a kind of welding method of large-scale steelmaking converter body of heater, it is characterised in that comprise the following steps:
1)Preparation of construction before welding body of heater:
First in converter body(1)Surrounding 11.5m elevation locations set up escape way, to facilitate applying for human users and cable If, converter body(1)Including upper furnace shell(2)With lower furnace shell(3), finally the diameter to furnace shell detect that the diameter of furnace shell is inclined Difference should meet design requirement, and the difference of maximum gauge and minimum diameter cannot be greater than the 3/1000 of furnace shell intended diameter, and furnace shell is high The limit deviation of degree is ± the 3/1000 of design height, and fire door plane is 1/1000 to the squareness tolerance of furnace shell axis;
2)Tack welding:
First by converter body(1)Upper furnace shell(2)With lower furnace shell(3)By locator card(4)Link together, then adopted by welder With formal welding material and welding procedure welding, ensure that weld seam does not ftracture in welding process, welded after the completion of last tack welding After check, when there is defect, it is necessary to root out tack welding meat and re-start tack welding;
3)Formal welding:
Locator card is first removed before formal welding(4), body of heater is welded afterwards(1)Inner side, until weld joint on inner side is being welded to its length Untill when 2/3, in formal welding process, some welder's weldings simultaneously at same direction;
4)Post weld heat treatment:
After formal welding is finished, in the case where weld seam without cooling down completely, by heater(5)It is powered and comes to commissure Heat temperature raising until temperature reaches 200 DEG C and is incubated 2 hours, to remove the hydrogen of residual in weld seam;
5)Final welding:
The back chipping treatment of weld joint on inner side is first carried out, then welds body of heater(1)Outside, after the completion of outer side weld, finally completes body of heater(1) The welding of remaining inside weld seam.
2. the welding method of large-scale steelmaking converter body of heater according to claim 1, it is characterised in that step 2)Described in it is fixed Position card(4)For specification for the 16Mn steel plates of 800 × 400 × 30mm are made, the locator card(4)Side opens up to ensure Locator card(4)With upper furnace shell(2)With lower furnace shell(3)The consistent semi-circular hole of joint gap.
3. the welding method of large-scale steelmaking converter body of heater according to claim 1, it is characterised in that step 2)Described in it is fixed Position card(4)It is uniformly arranged on outside in furnace shell, and the locator card on the outside of furnace shell(4)Avoid furnace shell both sides gudgeon position.
4. the welding method of large-scale steelmaking converter body of heater according to claim 1, it is characterised in that step 2)In carry out During tack welding, body of heater(1)Interior outside carries out tack welding, and fusion length is 300mm, and adjacent weld spacing is 300mm.
5. the welding method of large-scale steelmaking converter body of heater according to claim 1, it is characterised in that step 3)In remove Locator card(4)To be preheated with before formal welding afterwards, preheating temperature is in 125 ± 25 DEG C of intervals.
6. the welding method of large-scale steelmaking converter body of heater according to claim 1, it is characterised in that step 4)Heater (5)Wrap up heat-preservation cotton in periphery(6).
CN201510608032.4A 2015-09-23 2015-09-23 A kind of welding method of large-scale steelmaking converter body of heater Active CN105171261B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510608032.4A CN105171261B (en) 2015-09-23 2015-09-23 A kind of welding method of large-scale steelmaking converter body of heater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510608032.4A CN105171261B (en) 2015-09-23 2015-09-23 A kind of welding method of large-scale steelmaking converter body of heater

Publications (2)

Publication Number Publication Date
CN105171261A CN105171261A (en) 2015-12-23
CN105171261B true CN105171261B (en) 2017-06-20

Family

ID=54893934

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510608032.4A Active CN105171261B (en) 2015-09-23 2015-09-23 A kind of welding method of large-scale steelmaking converter body of heater

Country Status (1)

Country Link
CN (1) CN105171261B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105755205A (en) * 2016-04-14 2016-07-13 中国十七冶集团有限公司 Combination-method mounting method of ultra-large converter
CN109385519B (en) * 2018-09-30 2020-07-28 上海宝冶集团有限公司 Modular installation method of aluminum ingot pushing type heating furnace
CN111360439A (en) * 2020-03-26 2020-07-03 中国十七冶集团有限公司 Online welding method for transverse welding seam of corner of large-scale blast furnace shell

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5947315A (en) * 1982-09-09 1984-03-17 Nippon Kokan Kk <Nkk> Method for reparing shell of converter body
JPH10216946A (en) * 1997-02-07 1998-08-18 Nkk Corp Welding equipment for fitting to sleeve brick at tap hole of converter
CN100526000C (en) * 2007-12-28 2009-08-12 中国第十七冶金建设有限公司 Combination method mounting technique for ultra-large type steel converter
CN103205526A (en) * 2013-03-04 2013-07-17 中国十七冶集团有限公司 Pushing installation method for large converter
CN103962808B (en) * 2014-05-16 2016-07-06 中国十九冶集团有限公司 Fabrication and installation method for last furnace shell

Also Published As

Publication number Publication date
CN105171261A (en) 2015-12-23

Similar Documents

Publication Publication Date Title
CN105195860B (en) Welding method is tiltedly found in back docking
CN102756235B (en) Field welding repair method especially for larger and penetrating defects in steel casting with heavy wall thickness
CN105171261B (en) A kind of welding method of large-scale steelmaking converter body of heater
CN105537791B (en) A kind of method of Site Welding large-size horizontal converter barrel axiality
CN102922085B (en) Manual electric arc welding prime coat is the application of arc extinguishing method in Q460 steel-pipe welding in a zigzag
CN103920967B (en) Absorption tower welding method
CN108176910A (en) A kind of nuclear power station Leak-tight liner siding band ceramic backing Lincoln weld method
CN107052701A (en) A kind of roll overlaying technique
CN107457473A (en) AP1000 main steam line welding methods
CN105665898A (en) Automatic submerged arc welding method for pearlitic heat-resistant steel composite board
CN102717225B (en) Method for repairing damage of non-work surface of roller
CN102248345A (en) End plate surfacing fixture and manufacturing method
CN105057905A (en) Welding method of large-pipe-diameter exhaust channel of gas turbine
CN104526133A (en) Method for preventing tearing of metal welding layers
CN103481008B (en) Deep-hole repair welding technology
CN102941403A (en) Welding process of narrow-gap submerged arc welding for shell flange
CN109202367A (en) Forging and pressing operating machine clamps cylinder renovation technique
CN104889519A (en) Highly-efficient, energy-saving and environmentally-friendly manufacturing method of metal ceramic X ray tube
CN106270977A (en) A kind of steel plate low temperature environment welding procedure
CN106424214A (en) Reverse deformation shaping tool for outward turnover of tower drum flange of wind generating set and method for reverse deformation shaping tool
CN105234533A (en) Steel welding technology
CN104526132B (en) Method for preventing trunnion welding from producing delayed cracks
CN107825085A (en) Aircraft engine tubular bracket integral welding method and aircraft engine tubular bracket
CN107186316A (en) It is a kind of to connect the distortion-free welding procedure of condenser welding for large-size steam turbine low pressure (LP) cylinder
CN109024903B (en) Hemispherical support joint and manufacturing process thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A welding method for large scale converter body

Effective date of registration: 20210519

Granted publication date: 20170620

Pledgee: Industrial and Commercial Bank of China Limited MAANSHAN Tuanjie square sub branch

Pledgor: CHINA MCC17 GROUP Co.,Ltd.

Registration number: Y2021980003566

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230810

Granted publication date: 20170620

Pledgee: Industrial and Commercial Bank of China Limited MAANSHAN Tuanjie square sub branch

Pledgor: CHINA MCC17 GROUP Co.,Ltd.

Registration number: Y2021980003566

PC01 Cancellation of the registration of the contract for pledge of patent right