CN105970988A - Construction method for installing elevator shaft side wall rebars in raft foundation - Google Patents

Construction method for installing elevator shaft side wall rebars in raft foundation Download PDF

Info

Publication number
CN105970988A
CN105970988A CN201610405377.4A CN201610405377A CN105970988A CN 105970988 A CN105970988 A CN 105970988A CN 201610405377 A CN201610405377 A CN 201610405377A CN 105970988 A CN105970988 A CN 105970988A
Authority
CN
China
Prior art keywords
crane
truck crane
elevator
raft foundation
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610405377.4A
Other languages
Chinese (zh)
Other versions
CN105970988B (en
Inventor
唐际宇
林忠和
陈勇辉
唐阁威
梁月利
张皆科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201610405377.4A priority Critical patent/CN105970988B/en
Publication of CN105970988A publication Critical patent/CN105970988A/en
Application granted granted Critical
Publication of CN105970988B publication Critical patent/CN105970988B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The invention discloses a construction method for installing elevator shaft side wall rebars in a raft foundation. The construction method comprises the steps that bottom-layer rebars and surface-layer rebars of the raft foundation are constructed, and the position of an elevator shaft is reserved in the raft foundation; a supporting bed-jig is arranged in the position, a certain distance away from the elevator shaft, between the bottom-layer rebars and the surface-layer rebars; an automobile crane is craned to the position, corresponding to the supporting bed-jig, of the surface-layer rebars through a tower crane; and the side wall rebars of the elevator shaft are craned and installed through the automobile crane. According to the construction method for installing the elevator shaft side wall rebars in the raft foundation, the automobile crane is placed on the raft foundation, the traditional tower crane is replaced with the automobile crane to complete heavy craning and installing tasks of the elevator shaft side wall rebars, and overuse of the tower crane is avoided; and meanwhile, the situation that risks exist due to the fact that a chain hoist is close to the side walls when the elevator shaft side wall rebars are craned and installed through the chain hoist in a super-thick raft is also avoided.

Description

The construction method of elevator sidewall reinforcing bar is installed in raft foundation
Technical field
The present invention relates to a kind of the realm of building construction, particularly relate to a kind of installation elevator in raft foundation The construction method of well sidewall reinforcing bar.
Background technology
Owing to land resource is limited, modern architecture, for meeting demand, mostly is high-rise building, Super High Building is inevitable with super thick raft foundation, and the thickness of raft foundation is relatively big, commonly reach 5 meters and more than, It is in raft foundation in the construction of installation elevator sidewall reinforcing bar, due to the raft thickness of slab of elevator sidewall Degree is relatively big, and the quantity of reinforcement of elevator sidewall reinforcing bar is big, and reinforcing bar deadweight is the most heavier, the weight of every reinforcing bar General 100kg~150kg to be reached, manually cannot install.
Due to elevator sidewall raft plate super thick, typically can reach more than 10m, use the lifting of calabash jack During reinforcing bar, near sidewall, excessively dangerous, and 1# and the 2# tower crane installed of foundation ditch (place size is relatively Little, and near urban district, 2 tower cranes can only be installed), 2# tower crane can not cover elevator position, 1# Tower crane is mainly responsible for handling scene steel, steel structure etc., uses 1# tower crane to install sidewall reinforcing bar and can cause tower The utilization rate hung is too low, and will have a strong impact on the duration.
Summary of the invention
The technical problem to be solved is to provide a kind of installation elevator sidewall in raft foundation The construction method of reinforcing bar, it is possible to be substantially reduced the reinforcement installation dependency to tower crane, it is adaptable to engineering field Narrow and small, the tower crane limited amount in ground and the lifting heavy operating mode of task.
For realizing above-mentioned technique effect, the invention discloses a kind of installation elevator side in raft foundation The construction method of wall reinforcing bar, including step:
The bottom layer of the reinforcing steel of construction raft foundation and surfacing steel bar, and reserve elevator in described raft foundation Well location is put;And in the described bottom layer of the reinforcing steel at a certain distance from described elevator and described surfacing steel bar Between support jig is set;
Utilize tower crane that truck crane winches to correspondence to have in the described surfacing steel bar of described support jig;
Described truck crane is utilized to lift the sidewall reinforcing bar of described elevator.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, the bottom layer of the reinforcing steel of construction raft foundation and surfacing steel bar, including:
The bottom layer of the reinforcing steel of colligation raft foundation;
Gluten supporting construction is installed on described bottom layer of the reinforcing steel;
Colligation surfacing steel bar in described gluten supporting construction, described surfacing steel bar is at described elevator well location Put formation concave domain.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, in described gluten supporting construction before surfacing steel bar described in colligation, also include:
In the described bottom layer of the reinforcing steel that colligation completes, moulding bed support pads is set;
Support jig is installed on described moulding bed support pads, and utilizes connecting rod by described support jig and institute State gluten supporting construction to be welded to connect.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, described truck crane includes vehicle body, the multiple wheels being positioned at described body bottom and is positioned at described vehicle body Multiple supporting legs of both sides;Described support jig includes being supported in correspondingly each described wheel and every By described company between the lattice support body of the lower section of individual described supporting leg, and multiple described lattice support body Bar connects.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, utilize tower crane to be winched to by truck crane in described surfacing steel bar by following steps:
Pack up the supporting leg of described truck crane, by tower crane lifting rope colligation at the leg location of described truck crane;
Suspension centre and the center of gravity finding out described truck crane is hung, it is ensured that all wheels of described truck crane by examination Lifting time the most liftoff;
After finding out suspension centre and center of gravity, tower crane lifts by crane described truck crane, and after described truck crane is liftoff Suspend lifting, make described truck crane remain static;
Tower crane continues to lift by crane described truck crane, and when the liftoff segment distance of described truck crane, suspends Hang, described truck crane is moved a segment distance to tower crane center position;
Tower crane crane arm starts to swing, and described truck crane winches to the top position of described support jig;
Transfer described automobile to winch to, at described surfacing steel bar one segment distance, debug;
After debugging, continue to transfer described truck crane, make the pressure wheel of described truck crane at described surface layer steel On muscle;
Put down the supporting leg of described truck crane.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, before described truck crane is transferred to described surfacing steel bar, also include: in described surface layer steel Lay supporting pad plate on muscle, and each lattice of described support jig is shown at described support backing plate subscript The position of formula support body.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, before utilizing described truck crane to lift the sidewall reinforcing bar of described elevator, also include: to described Support frame and described surfacing steel bar carry out Deformation checking.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, by following steps utilize described truck crane lift described elevator sidewall reinforcing bar:
Promoting the supporting leg of described truck crane, the wheel making described truck crane is the most liftoff;
By the sidewall reinforcing bar of root lifting elevator, after winching to the sidewall locations of elevator, manually carry out institute State the colligation of sidewall reinforcing bar.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, also include: after described sidewall reinforcement installation completes, utilize tower crane that described truck crane is hung institute State support backing plate.
The construction method installing elevator sidewall reinforcing bar in be set forth in raft foundation is further improved In, described support jig is arranged at the position apart from described elevator 10m~20m.
Due to the fact that and have employed above technical scheme so that it is have the advantages that
1) engineering ground is narrow and small, tower crane limited amount, and when tower crane lifting task is heavy, super thick raft plate Sidewall reinforcing bar uses truck crane to carry out lifting the installation method of reinforcing bar on raft slab muscle, greatly reduces The reinforcement installation dependency to tower crane;
2) convenient and quick construction, hence it is evident that decrease the set-up time of sidewall reinforcing bar, alleviate work simultaneously Intensity;
3) the raft plate reinforcing bar binding duration is shortened, it is possible to fulfil underplate concrete ahead of schedule and pour, it is to avoid rainy season Occur during construction that foundation pit collapse is dangerous;
4) reinforcing bar binding safety coefficient is high, it is to avoid reinforcing bar casualty accident occur.
Accompanying drawing explanation
Fig. 1 is the technique stream that the present invention installs the construction method of elevator sidewall reinforcing bar in raft foundation Cheng Tu.
Fig. 2 is that the present invention installs the preferable of the construction method of elevator sidewall reinforcing bar in raft foundation The schematic diagram of the raft foundation of embodiment.
Fig. 3 is that the present invention installs the preferable of the construction method of elevator sidewall reinforcing bar in raft foundation The process chart of embodiment.
Fig. 4 is that the present invention installs the preferable of the construction method of elevator sidewall reinforcing bar in raft foundation The site plan of the support jig of embodiment.
Fig. 5 is that the present invention installs the preferable of the construction method of elevator sidewall reinforcing bar in raft foundation The elevation of the support jig of embodiment.
Fig. 6 is that the present invention installs the preferable of the construction method of elevator sidewall reinforcing bar in raft foundation The elevation of another angle of the support jig of embodiment.
Fig. 7 is that the present invention installs the preferable of the construction method of elevator sidewall reinforcing bar in raft foundation The lifting construction schematic diagram of the elevator sidewall reinforcing bar of embodiment.
Detailed description of the invention
Below in conjunction with the accompanying drawings and detailed description of the invention the present invention is further detailed explanation.
Referring initially to shown in Fig. 1, the present invention installs the construction of elevator sidewall reinforcing bar in raft foundation Method mainly includes following construction technology:
S001: the bottom layer of the reinforcing steel of construction raft foundation and surfacing steel bar, and in raft foundation, reserve electricity Stair shaft position;And setting between bottom layer of the reinforcing steel and the surfacing steel bar at a certain distance from distance elevator Support frame;
S002: utilize tower crane to be winched to by truck crane having in the surfacing steel bar of support jig;
S003: utilize the sidewall reinforcing bar of truck crane lifting elevator.
The central idea of main employing is: is prevented by truck crane on raft foundation, utilizes truck crane generation Complete the lifting task of heavy elevator sidewall reinforcing bar for traditional tower crane, save the mistake of tower crane Degree uses;Meanwhile, it also avoid and use calabash jack to lift elevator sidewall steel in super thick raft plate During muscle, due near sidewall, the danger existed.Further, by arranging a support in raft foundation Frame, is made that improvement to raft board supporting structure, is supported truck crane and reinforces, and makes the truck crane can To be stably installed on raft foundation, and play the effect avoiding raft foundation to deform.
Illustrate with an embodiment below and how to realize the present invention elevator is installed in raft foundation The construction of sidewall reinforcing bar.
Coordinating shown in Fig. 2, in the present embodiment, raft foundation 11 is high building raft plate, and thickness is about 5m, and elevator 12 a size of 16250mm × 6850mm × 6800mm (H), elevator side The plank thickness of wall position reaches about 11.8m, elevator sidewall reinforcing bar 13 shape and size such as Fig. 2 institute Showing, in " 7 " font, this sidewall number of steel bars is many, and the weight of every is about 120 kilograms, manually Cannot install.Owing to the raft plate sidewall thickness of elevator position reaches 11.8m, calabash jack is used to hang During dress, near sidewall, excessively dangerous, and 1# and the 2# tower crane that foundation ditch is installed (place size is less, And near urban district, 2 tower cranes can only be installed), 2# tower crane can not cover elevator position, 1# tower Hanging main handling scene steel, the steel structure etc. be responsible for, sidewall reinforcing bar installed by employing 1# tower crane can cause tower crane Utilization rate too low, and the duration will be had a strong impact on.Therefore, the present invention is used to install in raft foundation The construction method of elevator sidewall reinforcing bar installs the sidewall reinforcing bar of elevator, is the most suitable.Tool The working procedure of body is refering to shown in Fig. 3, and construction item sees as follows:
1, truck crane position selects
Truck crane is selected in elevator north side, needs to avoid the moulding bed of steel construction pre embedded bolt, simultaneously need to 23m lifting radius side can meet the normal lifting of elevator sidewall reinforcing bar.Need in the range of 23m to hang Dress 0.12t lift heavy, selects QY12 truck crane, can meet requirement.
2, truck crane lifting analysis in place
Owing to truck crane is placed in the surfacing steel bar of raft foundation, it is impossible to directly reach specify position, The on-the-spot place intending first allowing truck crane reach foundation ditch east side, then uses 1# tower crane (S1200M64) Truck crane is hung appointment position, and truck crane supporting leg again is fixed.Require that truck crane to be placed accurately, really Protect and be placed on the reinforcement point specified, the lifting of elevator sidewall reinforcing bar can be carried out.
1# tower crane center is front place about 44m to Office Area, has 22m to lifting point, according to The lift heavy information of S1200M64,45m position maximum lift heavy is 26.6T, and middle QY12 truck crane Weight be 20T, lifting requirements can be met.Truck crane lifting point from the farthest angle of elevator away from From for 20m, the coverage that middle QY12 truck crane is arranged is 23m, can meet elevator institute There is the lifting requirements of sidewall reinforcing bar.
3, the support jig design and construction of truck crane lifting point surfacing steel bar
In order to ensure the stable of the support system of whole surfacing steel bar and safety, need truck crane in place Region carries out local stiffening, mainly 161, two trailing wheels 162 and four of two front-wheels to truck crane Individual supporting leg 163 position reinforces, the most as shown in Figure 4.
Wherein, two front-wheels 161 of truck crane and two trailing wheels 162 are positioned at the bottom of truck crane vehicle body, Four supporting legs 163 of truck crane are positioned at the both sides of vehicle body;Support jig includes being supported in correspondingly Between the lattice support body 14 of the lower section of each wheel and each supporting leg, and multiple lattice support body 14 Connected by connecting rod, refering to shown in Fig. 5 and Fig. 6.14 4 corners of lattice support body use 16#'s I-steel, a size of 1000mm × 1000mm, the height of moulding bed specifically combines the thickness of raft plate and determines. Connect between the I-steel at four angles and have cross bar and diagonal brace, it is contemplated that tower crane lifts big arm swing and produces relatively Big moment, cross bar and diagonal brace use 10# channel-section steel, arrange together every 1000mm height.
The bottom layer of the reinforcing steel 111 of construction raft foundation 11 and surfacing steel bar 112, specifically include:
The bottom layer of the reinforcing steel 111 of colligation raft foundation 11;
Gluten supporting construction 17 is installed on bottom layer of the reinforcing steel 111;
Colligation surfacing steel bar 112 in gluten supporting construction 17, surfacing steel bar 112 is at elevator 12 Position forms concave domain, and the sidewall reinforcing bar 13 of elevator is just installed on the surrounding of this concave domain.
Wherein, it is in gluten supporting construction, before colligation surfacing steel bar, also to include:
In the bottom layer of the reinforcing steel 111 that colligation completes, moulding bed support pads is set;
Support jig is installed on moulding bed support pads, and utilizes connecting rod 18 to be supported with gluten by support jig Structure 17 is welded to connect.
Moulding bed support pads therein uses 10# channel-section steel, pad to be located at each lattice support body of support jig Between bottom and the bottom layer of the reinforcing steel 111 of raft foundation 11 of 14, play supporting role;Raft foundation The surfacing steel bar 112 of 11 be placed directly on support jig and with the gluten supporting construction of raft foundation 11 Colligation is fixed.
Occur without accident in order to ensure this construction, need 8 lattice support bodys 14 of design are carried out Stability Checking, is mainly the stability in the large of support jig and the intensity of each component and stablizes Property check, it is desirable to the gluten in eight lattice support bodys bottom truck crane 14 and this region supports knot Structure is welded to connect and is fixed as an entirety, improves holistic resistant behavior.Gluten supporting construction typically uses Type steel support, bottom uses the 10# channel-section steel pad bottom layer of the reinforcing steel at raft foundation 11 of about 200mm length On 111;Connecting rod includes being connected to the cross bar between multiple lattice support body 14 and diagonal brace, uses 5# Angle steel, the gluten supporting construction with reinforcing area is welded to connect, as shown in Figure 6 simultaneously.
4, truck crane is in place
According to spot plane layout drawing, truck crane reaches specific bit and postpones the counterweight on car, chock etc. Foreign material all unload, foreign material falling from high altitude when preventing tower crane from allocating and transporting truck crane.Tower crane crane arm swings to vapour The overhead that car hangs, transfers suspension hook, and four sash-line diameter use 14mm, and every maximum bears weight Reach 20T.
5, utilize tower crane handling truck crane to the surfacing steel bar of raft foundation
(1) lifting point site layout project
Owing to the weight of truck crane is big, in order to reduce the truck crane local pressure to surfacing steel bar 112, To support backing plate 15 on one layer of the upper berth, lifting point of surfacing steel bar 112, as shown in Figure 5 and Figure 6, be somebody's turn to do Support backing plate 15 and can use heavy steel plate thick for 15mm, support backing plate 15 subscript with Calx simultaneously Go out the position of each lattice support body 14 of support jig, it is simple to truck crane is in place.
(2) truck crane colligation point selection
The area of truck crane is big, position of centre of gravity is more difficult determines, four lifting rope colligations of crane hook are at automobile Four leg location (supporting leg does not stretches out) hung, repeatedly check whether after colligation and meet the requirements.
(3) suspension centre and the center of gravity of truck crane are found out
Dynamic load is increased, it is necessary to find out suspension centre and center of gravity in order to prevent hoisting process truck crane from rocking After can lift by crane.Tower crane first slowly hoists, and checks that all of wheel of truck crane is the most liftoff.As Fruit not, is slowly transferred suspension hook, it is judged that deviation of gravity center direction at once, readjusts before and after's lifting rope Length.Owing to the colligation point of lifting rope is four leg location of truck crane, front leg strut due near headstock, Center of gravity can offset to front leg strut, and therefore colligation should compare the shorter of front leg strut, just at the lifting rope of rear support leg Can guarantee that all of wheel is the most liftoff.By regulate lifting rope length, find out truck crane suspension centre and Center of gravity.
(4) tower crane lifting
After finding out suspension centre, tower crane slowly hoists 300mm, hoisting until suspending after truck crane is liftoff, making Truck crane slowly remains static.Then, tower crane continues slowly to hoist, overhead after 3m, temporarily Stop hoisting, simultaneously tower crane amplitude variation trolley setting in motion, make truck crane be transported by 45m to tower crane centre distance Move 22m position.Last tower crane crane arm starts to swing, until truck crane rests on the upper of lifting point Sky, slowly transfers until automobile hangs gluten steel plate 300mm, by manual adjustment, makes truck crane Front and back wheel just with regard to site, is slowly transferred until pressure wheel is on steel plate.
Now, tower crane can't pine hook, site administrator observes the deformation of gluten and stable feelings After condition, it is ensured that after An Quan, tower crane could pine hook.
6, support jig and the Deformation checking of surfacing steel bar
The quantity of this elevator sidewall reinforcing bar is more, needs just can complete for two days, and therefore truck crane exists On gluten, residence time is longer.In order to ensure whole hoisting process surfacing steel bar, gluten supporting construction, The stability of support jig and safety, need to strengthen support jig, the inspection of gluten deformation and prison Control, the time interval of inspection can not be more than 2 hours every time, and inspection content is:
(1) vertical rod of support jig I-steel with or without deformation or deformation strengthen trend, vertical rod, cross bar, It is welded with without coming off scene, especially proximate to the moulding bed of elevator side between brace;
(2) trend that the surfacing steel bar that truck crane is pressed strengthens with or without deformation or deformation;
(3) the gluten supporting construction of surfacing steel bar is with or without situations such as song torsion, deformation.
7, truck crane lifting elevator sidewall reinforcing bar
Coordinate shown in Fig. 7, truck crane 16 in place stable after, truck crane opens supporting leg and prepares lifting reinforcing bar, Four supporting legs to be pressed in like clockwork with regard on site.Elevator sidewall reinforcing bar shape as it can be seen, in " 7 " font, sidewall reinforcing bar is to install one by one, and lift heavy is little, with car when four supporting legs promote Take turns the most liftoff being advisable, allow four supporting legs and all wheels stress simultaneously, reduce the face of raft foundation 11 The local pressure of layer reinforcing bar 111.After all of preparation is ready, sidewall reinforcing bar can be proceeded by The construction of 13, as shown in Figure 7.Lifting rope ties up the turning point at " 7 " font sidewall reinforcing bar 13, hangs After the sidewall locations of elevator 12, manually adjust spacing and fix with tied silk colligation.
The innovative point of the construction method that the present invention installs elevator sidewall reinforcing bar in raft foundation is as follows:
1) engineering ground is narrow and small, tower crane limited amount, and when tower crane lifting task is heavy, super thick raft plate Sidewall reinforcing bar uses truck crane to carry out lifting the installation method of reinforcing bar on raft slab muscle, greatly reduces The reinforcement installation dependency to tower crane;
2) convenient and quick construction, hence it is evident that decrease the set-up time of sidewall reinforcing bar, alleviate work simultaneously Intensity;
3) the raft plate reinforcing bar binding duration is shortened, it is possible to fulfil underplate concrete ahead of schedule and pour, it is to avoid rainy season Occur during construction that foundation pit collapse is dangerous;
4) reinforcing bar binding safety coefficient is high, it is to avoid reinforcing bar casualty accident occur.
Above in association with drawings and Examples, the present invention is described in detail, ordinary skill in this area The present invention can be made many variations example by personnel according to the above description.Thus, some in embodiment is thin Joint should not constitute limitation of the invention, the present invention by the scope that defines using appended claims as Protection scope of the present invention.

Claims (10)

1. the construction method installing elevator sidewall reinforcing bar in raft foundation, it is characterised in that Including step:
The bottom layer of the reinforcing steel of construction raft foundation and surfacing steel bar, and reserve elevator in described raft foundation Well location is put;And in the described bottom layer of the reinforcing steel at a certain distance from described elevator and described surfacing steel bar Between support jig is set;
Utilize tower crane that truck crane winches to correspondence to have in the described surfacing steel bar of described support jig;
Described truck crane is utilized to lift the sidewall reinforcing bar of described elevator.
2. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 1 Method, it is characterised in that the bottom layer of the reinforcing steel of construction raft foundation and surfacing steel bar, including:
The bottom layer of the reinforcing steel of colligation raft foundation;
Gluten supporting construction is installed on described bottom layer of the reinforcing steel;
Colligation surfacing steel bar in described gluten supporting construction, described surfacing steel bar is at described elevator well location Put formation concave domain.
3. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 2 Method, it is characterised in that in described gluten supporting construction before surfacing steel bar described in colligation, also include:
In the described bottom layer of the reinforcing steel that colligation completes, moulding bed support pads is set;
Support jig is installed on described moulding bed support pads, and utilizes connecting rod by described support jig and institute State gluten supporting construction to be welded to connect.
4. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 3 Method, it is characterised in that: described truck crane include vehicle body, the multiple wheels being positioned at described body bottom and It is positioned at multiple supporting legs of described vehicle body both sides;Described support jig includes being supported in correspondingly each The lattice support body of the lower section of described wheel and each described supporting leg, and multiple described lattice support body it Between connected by described connecting rod.
5. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 4 Method, it is characterised in that utilize tower crane to be winched to by truck crane in described surfacing steel bar by following steps:
Pack up the supporting leg of described truck crane, by tower crane lifting rope colligation at the leg location of described truck crane;
Suspension centre and the center of gravity finding out described truck crane is hung, it is ensured that all wheels of described truck crane by examination Lifting time the most liftoff;
After finding out suspension centre and center of gravity, tower crane lifts by crane described truck crane, and after described truck crane is liftoff Suspend lifting, make described truck crane remain static;
Tower crane continues to lift by crane described truck crane, and when the liftoff segment distance of described truck crane, suspends Hang, described truck crane is moved a segment distance to tower crane center position;
Tower crane crane arm starts to swing, and described truck crane winches to the top position of described support jig;
Transfer described automobile to winch to, at described surfacing steel bar one segment distance, debug;
After debugging, continue to transfer described truck crane, make the pressure wheel of described truck crane at described surface layer steel On muscle;
Put down the supporting leg of described truck crane.
6. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 5 Method, it is characterised in that before described truck crane is transferred to described surfacing steel bar, also include: In described surfacing steel bar, lay supporting pad plate, and at described support backing plate subscript, described support is shown The position of each lattice support body of frame.
7. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 1 Method, it is characterised in that before utilizing described truck crane to lift the sidewall reinforcing bar of described elevator, also wrap Include: described support jig and described surfacing steel bar are carried out Deformation checking.
8. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 1 Method, it is characterised in that utilize described truck crane to lift the sidewall steel of described elevator by following steps Muscle:
Promoting the supporting leg of described truck crane, the wheel making described truck crane is the most liftoff;
By the sidewall reinforcing bar of root lifting elevator, after winching to the sidewall locations of elevator, manually carry out institute State the colligation of sidewall reinforcing bar.
9. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 8 Method, it is characterised in that also include: after described sidewall reinforcement installation completes, utilizes tower crane by described Truck crane hangs described support backing plate.
10. the construction party installing elevator sidewall reinforcing bar in raft foundation as claimed in claim 1 Method, it is characterised in that: described support jig is arranged at the position apart from described elevator 10m~20m.
CN201610405377.4A 2016-06-08 2016-06-08 The construction method of elevator sidewall reinforcing bar is installed in raft foundation Active CN105970988B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610405377.4A CN105970988B (en) 2016-06-08 2016-06-08 The construction method of elevator sidewall reinforcing bar is installed in raft foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610405377.4A CN105970988B (en) 2016-06-08 2016-06-08 The construction method of elevator sidewall reinforcing bar is installed in raft foundation

Publications (2)

Publication Number Publication Date
CN105970988A true CN105970988A (en) 2016-09-28
CN105970988B CN105970988B (en) 2018-02-06

Family

ID=57011643

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610405377.4A Active CN105970988B (en) 2016-06-08 2016-06-08 The construction method of elevator sidewall reinforcing bar is installed in raft foundation

Country Status (1)

Country Link
CN (1) CN105970988B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984170A (en) * 2019-11-25 2020-04-10 上海水务建设工程有限公司 Semi-automatic foundation pit steel support installation method and steel support installation auxiliary device
CN115030205B (en) * 2022-06-07 2024-04-26 上海城建市政工程(集团)有限公司 Integrated rapid construction method for raft, water collecting well and elevator shaft of deep foundation pit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4883462B1 (en) * 2011-08-22 2012-02-22 昌之 宗清 Reinforcement construction method for deep foundation piles and ladder reinforcement of the reinforcing bar unit.
JP2013096117A (en) * 2011-10-31 2013-05-20 Asahi Kasei Homes Co Building construction method
CN204920174U (en) * 2015-06-26 2015-12-30 中天建设集团有限公司 Elevartor shaft regularization operation platform
CN204940874U (en) * 2015-07-13 2016-01-06 山西建筑工程(集团)总公司 For the servicing unit of beam column core space reinforcement installation
CN105421476A (en) * 2015-11-30 2016-03-23 中国建筑第八工程局有限公司 Construction method for installing tower crane embedded parts on raft foundation and installation structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4883462B1 (en) * 2011-08-22 2012-02-22 昌之 宗清 Reinforcement construction method for deep foundation piles and ladder reinforcement of the reinforcing bar unit.
JP2013096117A (en) * 2011-10-31 2013-05-20 Asahi Kasei Homes Co Building construction method
CN204920174U (en) * 2015-06-26 2015-12-30 中天建设集团有限公司 Elevartor shaft regularization operation platform
CN204940874U (en) * 2015-07-13 2016-01-06 山西建筑工程(集团)总公司 For the servicing unit of beam column core space reinforcement installation
CN105421476A (en) * 2015-11-30 2016-03-23 中国建筑第八工程局有限公司 Construction method for installing tower crane embedded parts on raft foundation and installation structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘晓宇等: "超高层建筑施工中塔吊的选型分析", 《工程质量》 *
李琰等: "300t汽车吊临近深基坑坑边吊装作业施工技术", 《建筑施工》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984170A (en) * 2019-11-25 2020-04-10 上海水务建设工程有限公司 Semi-automatic foundation pit steel support installation method and steel support installation auxiliary device
CN115030205B (en) * 2022-06-07 2024-04-26 上海城建市政工程(集团)有限公司 Integrated rapid construction method for raft, water collecting well and elevator shaft of deep foundation pit

Also Published As

Publication number Publication date
CN105970988B (en) 2018-02-06

Similar Documents

Publication Publication Date Title
CN103075025B (en) Wholly lifting construction method for asymmetric structure of huge overhang steel of high-rise building
CN201228206Y (en) Self-made small-sized hoisting machine
CN102493352B (en) Method for bridge-spanning construction by using tyre carrier
CN103086279B (en) Vertical transportation construction method for building construction
CN104649128B (en) Special sling for hoisting extra-large structural modules for nuclear power plants
CN205955237U (en) Plug -type platform of unloading of encorbelmenting
CN205772984U (en) A kind of hanging apparatus of monolithic steel truss
CN108455451B (en) A kind of 600 tons of gantry cranes hold the method for hanging installation superelevation flare tower
CN102979313A (en) High-altitude lifting construction method for overweight steel truss of transferring layer
CN102049335B (en) Installation and construction method of large-sized ball mill
CN206538126U (en) The large-scale overweight equipment handling constructing device of Super High
CN106544959B (en) The construction method of king-tower lifting segment and bridge main tower saddle containing saddle
CN103086276B (en) Construction method for hoisting bridge type crane in high-rise well tower type building
CN106315426A (en) Block form tower crane mounting and jacking method for assembled building
CN104775363B (en) The spelling method of upper king-post strut reinforcing bar sections
CN105970988A (en) Construction method for installing elevator shaft side wall rebars in raft foundation
CN105776011A (en) Mounting method for crane beam on blast furnace top
CN206590793U (en) Connect arm assembly and the movable arm tower crane comprising the device in the air
CN105540433B (en) One kind tilts installation site overweight equipment hanging method
CN104234636A (en) Installation method for self-elevating platform derrick
CN103848333B (en) Door frame Lift-on/Lift-off System and using method thereof
CN207047703U (en) A kind of beam piece prestressed stretch-draw jack easy device in place
CN201722621U (en) Integral hoisting frame of pre-fabricated box beam
CN108518071A (en) The installation method of the double-deck large-span steel vestibule
CN211949528U (en) Double-deck operation platform of high-rise building elevartor shaft

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant