CN105951707B - An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method - Google Patents

An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method Download PDF

Info

Publication number
CN105951707B
CN105951707B CN201610473303.4A CN201610473303A CN105951707B CN 105951707 B CN105951707 B CN 105951707B CN 201610473303 A CN201610473303 A CN 201610473303A CN 105951707 B CN105951707 B CN 105951707B
Authority
CN
China
Prior art keywords
preliminary bracing
compaction pile
cement
construction
soil compaction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610473303.4A
Other languages
Chinese (zh)
Other versions
CN105951707A (en
Inventor
邵正辉
彭小兵
吴韩飞
张湘
周再升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201610473303.4A priority Critical patent/CN105951707B/en
Publication of CN105951707A publication Critical patent/CN105951707A/en
Application granted granted Critical
Publication of CN105951707B publication Critical patent/CN105951707B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/08Improving by compacting by inserting stones or lost bodies, e.g. compaction piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of an ultra shallow to bury collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method, it is characterized in that:Collapsible loess tunnel is buried for an ultra shallow to excavate to form excavation face using the interim inverted arch of three steps, three steps refer in tunnel excavating process, it the top bar that sequentially forms step by step, middle step and gets out of a predicament or an embarrassing situation, it is set in the outside of the top bar arch springing of top bar preliminary bracing steelframe and expands arch springing, top bar arch springing is up arranged at intervals stiffness connection;Construction inverted arch preliminary bracing first, installs compaction pile position provided pipe in inverted arch preliminary bracing, and cement-soil compaction pile of constructing in the provided pipe of compaction pile position forms cement-soil compaction pile ruggedized construction.The present invention is effective against surrouding rock deformation, is reached preliminary bracing entirety stress using the stiffness connection expanded between arch springing and increase top bar preliminary bracing steelframe;First construction inverted arch preliminary bracing, installs compaction pile position provided pipe, reaches and first close preliminary bracing, slow down surrouding rock deformation in the early stage between supporting, can ensure that country rock safety.

Description

An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction Method
Technical field
The present invention relates to bury in collapsible loess tunnel, the ruggedized construction of consolidation process is carried out for ground and apply in an ultra shallow Work method.
Background technology
In recent years, with the rapid development of economic construction of China, the construction of high-speed railway more develops rapidly.Circuit sinks Drop deformation directly affects the comfort level of passenger and the operation security of high-speed railway and development.
Collapsible loess is very wide in branch of China, and main branch is in Shanxi, Shaanxi, Gansu most area and He Nanxi Portion.It is limited with reference to above area by geographical conditions, for road mostly with tunnel transition, the base collapsibility in tunnel is after influencing railway An important factor for phase operation security.In limited construction space, how deformation controlling for rock surrounding gateways, accelerate cement-soil compaction pile reinforcing and apply Work progress is a collapsible loess tunnel construction important topic urgently to be resolved hurrily.
Five-pointed star level ground tunnel outlet section, under wear a local peasant household orchard, tunnel top earthing buried depth is 2.4~11.3m, original state Native foundation bearing capacity is 140~220KP.Tunnel exit end chiltern loess has very serious IV grade of self-weight collapsible, saturated yielding soil Layer thickness is about 32m.This section of tunnel surrounding grade is V e, and design is constructed using the interim inverted arch engineering method of three steps, Tunnel Mouth carries out advance supports using hundred meters of bimetallic tube canopies, and preliminary bracing uses I 25a+ in-network processing supportings.
136m scopes domestic demand carries out consolidation process using cement-soil compaction pile to ground in tunnel, is applied according to its routine is designed Work method is to get out of a predicament or an embarrassing situation after construction, i.e., carries out cement-soil compaction pile base construction using electronic Luoyang Spade cooperation block stamp.But because Limited space in tunnel, interference are more;Shake larger during the construction of electronic Luoyang Spade, effect is very slow;And buried section of construction of an ultra shallow, Surrouding rock deformation is larger, and there are certain security risks.
The content of the invention
The present invention is for shortcoming existing for avoiding above-mentioned technology, provides a kind of an ultra shallow and buries collapsible loess tunnel ground Cement-soil compaction pile ruggedized construction and construction method, it is full to be effective against surrouding rock deformation, improve construction efficiency, reduction vibrations Sufficient tunnel space requirement.
The present invention adopts the following technical scheme that solve technical problem:
An ultra shallow of the present invention, which buries the characteristics of collapsible loess tunnel ground cement-soil compaction pile ruggedized construction, is:It is buried for an ultra shallow Collapsible loess tunnel excavates to form excavation face using the interim inverted arch of three steps, and three step refers in tunnel excavating process In, it the top bar that sequentially forms step by step, middle step and gets out of a predicament or an embarrassing situation, in the outside of the top bar arch springing of top bar preliminary bracing steelframe It sets and expands arch springing, top bar arch springing is up arranged at intervals stiffness connection;Construction inverted arch preliminary bracing first, in inverted arch initial stage branch Compaction pile position provided pipe is installed in shield, it is compacted to form soil cement for cement-soil compaction pile of constructing in the provided pipe of the compaction pile position Stake ruggedized construction.
An ultra shallow of the present invention is buried the characteristics of collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and is lain also in:On described The outside of step preliminary bracing steelframe expands inclined 0.8m outside arch springing, and tangent with the outer of the top bar preliminary bracing steelframe.
An ultra shallow of the present invention is buried the characteristics of collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and is lain also in:In inverted arch After the installing of compaction pile position provided pipe is completed in preliminary bracing, backfill to form operation platform using the soil body, be applied described in recycling Work platform carries out the construction of cement-soil compaction pile.
An ultra shallow of the present invention, which buries the characteristics of collapsible loess tunnel ground cement-soil compaction pile reinforced construction method, is:
Collapsible loess tunnel is buried for an ultra shallow to excavate to form excavation face using the interim inverted arch of three steps, three step is Refer in tunnel excavating process, the top bar that sequentially forms step by step, middle step and get out of a predicament or an embarrassing situation, in top bar preliminary bracing steelframe The outside of top bar arch springing, which is set, expands arch springing, and top bar arch springing is up arranged at intervals stiffness connection;As follows in tunnel It constructs in ground cement-soil compaction pile, forms cement-soil compaction pile ruggedized construction:
Step a:Cement-soil compaction pile stake position is reserved according to test pile spacing between each road inverted arch preliminary bracing steelframe, is gone forward side by side Row first time inverted arch preliminary bracing concrete construction;
Step b:After first time inverted arch preliminary bracing concrete construction, the backfill soil body to inverted arch filled layer top surface mark Height forms operation platform;
Step c:On the operation platform, first using extension drill rod in crawler type screw drilling machine and setting in each stake position Place is molded stake holes by designing pile length, and tamping machine is recycled to be molded cement-soil compaction pile for each stake holes, is completed at the reinforcing to substrate Reason, effective stake top face of the cement-soil compaction pile is in the bottom of inverted arch preliminary bracing steelframe;
Step d:The soil body that secondary excavation is filled in the reserved cement-soil compaction pile stake position is filled in preliminary bracing and is mixed Solidifying soil, completes inverted arch preliminary bracing concrete construction;
Step e:Inverted arch secondary lining and Concrete Filled layer construct to designed elevation.
An ultra shallow of the present invention is buried the characteristics of collapsible loess tunnel ground cement-soil compaction pile reinforced construction method and is lain also in:
Inverted arch is excavated per secondary control in 1.2~1.8m drilling depths, 5 after first time inverted arch preliminary bracing concrete construction Carry out cement-soil compaction pile construction within~7 days;
Control construction speed enables the tunnel to reach preliminary bracing closing cyclization in 12 days;
Depth of the inverted arch preliminary bracing away from top bar face is 15~20m, and top bar face is away from the cyclic distance of two linings No more than 55m.
An ultra shallow of the present invention is buried the characteristics of collapsible loess tunnel ground cement-soil compaction pile reinforced construction method and is lain also in:Tunnel Minimum effective operation height 6.5m in road, cement-soil compaction pile design length are 9.0m, and drilling machine uses 6.0m long spire formula drill bits, Brill footpath is 0.35m, and interior extension drill rod is not less than 3m.
Extension drill rod is structurally characterized in that in the present invention:
The auger stem of screw drilling machine is set to be set with extension bar in one section in the sleeve type drill rod for sleeve type drill rod; The interior extension bar is the polished rod with the auger stem clearance fit, and interior extension bar can freely plug in the auger stem;
It is connected with the interior extension bar with the power output shaft of screw drilling machine;The auger stem being sleeved on interior extension bar can Pin joint is carried out using the top pin hole and interior extension bar upper pin hole of auger stem, forms non-extension bar;The auger stem or Pin joint is carried out using the top pin hole and interior extension bar lower pin hole of auger stem, forms extension bar;The interior extension bar upper pin hole The upper end of interior extension bar is in, the interior extension bar lower pin hole is in the lower end of interior extension bar.
The design feature of extension drill rod is lain also in the present invention:The power output shaft of the interior extension bar and screw drilling machine it Between use pin joint.
Compared with the prior art, the present invention has the beneficial effect that:
1st, the present invention sets pre- pile anchoring position between steelframe when inverted arch preliminary bracing is constructed according to test pile spacing;By inverted arch Tunnel is first constructed, and preliminary bracing is made to form ring body, and whole stress resists surrouding rock deformation, it is ensured that tunnel safety.
2nd, the present invention sets the method that stiffness connects that country rock is controlled to become using expansion arch springing and between top bar steelframe Shape makes preliminary bracing entirety stress, it is ensured that the stabilization of country rock.
3rd, the present invention uses crawler type screw drilling machine, and extension drill rod in setting, meets construction site spatial altitude It is required that, it is ensured that foundation treatment depth reduces the vibration during pile foundation construction, improves work efficiency.
Description of the drawings
Fig. 1 expands arch springing schematic diagram for Tunnel in the present invention;
Fig. 2 stiffness connection diagrams between top bar preliminary bracing steelframe in the present invention;
Fig. 3 arranges schematic diagram for cement-soil compaction pile stake position facade in the present invention;
Fig. 4 arranges schematic diagram for cement-soil compaction pile stake bit plane in the present invention;
Fig. 5 is the interim inverted arch digging mode schematic diagram of three steps in the present invention.
Fig. 6 is interior extension drill rod structure diagram in the present invention;
Fig. 7 is Fig. 6 close-up schematic views;
Fig. 8 is interior extension drill rod use state diagram in the present invention;
Figure label:1 gets out of a predicament or an embarrassing situation, step in 2,3 top bars, 4 top bar preliminary bracing steelframes, and 5 expand arch springing, 6 stiffnesses Connection, 7 inverted arch preliminary bracing steelframes, 8 cement-soil compaction pile stake positions, 9 inverted arch filled layer top surface absolute altitudes, 11 first sections, 12 the Two sections, 13 the 3rd sections, 21 auger stems, 21a helical blades, extension bar in 22, extension bar top pin hole in 22a, extension bar in 22b Top pin hole, extension bar lower pin hole in 22c, 23 screw drilling machines, 23a power output shafts.
Specific embodiment
Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4 and Fig. 5, it is compacted to bury collapsible loess tunnel ground soil cement for an ultra shallow in the present embodiment Stake ruggedized construction, it is characterized in that:Collapsible loess tunnel is buried for an ultra shallow to excavate to form excavation face using the interim inverted arch of three steps, Three step refers in tunnel excavating process, the top bar 3 that sequentially forms step by step, middle step 2 and gets out of a predicament or an embarrassing situation 1, is appearing on the stage The outside of the top bar arch springing of rank preliminary bracing steelframe 4, which is set, expands arch springing 5, and top bar arch springing is up arranged at intervals stiffness connection 6;Construction inverted arch preliminary bracing first, compaction pile position provided pipe is installed in inverted arch preliminary bracing, then backfills to be formed with the soil body and apply Work platform is constructed cement-soil compaction pile using the operation platform in the provided pipe of the compaction pile position, and it is compacted to form soil cement Stake ruggedized construction.Super shallow depth loess tunnels are mostly new loess, and soil property is more loose, and foundation bearing capacity is relatively low, set and expand arch springing The forced area of arch springing can effectively be increased, surrouding rock deformation is resisted, between steelframe stiffness is set to connect, improve steelframe globality, Ensure steelframe entirety stress.
As depicted in figs. 1 and 2, in specific implementation, the outside of top bar preliminary bracing steelframe 4 expands inclined 0.8m outside arch springing 5, It is and tangent with the outer of top bar preliminary bracing steelframe 4;It is connected in tetra- stiffnesses of both sides Ge You of top bar preliminary bracing steelframe 4 6, stiffness connection 6 is spaced 50cm along longitudinal direction and in being horizontally disposed with using I-steel, stiffness connection 6 between adjacent stiffness connection 6.
An ultra shallow, which buries collapsible loess tunnel ground cement-soil compaction pile reinforced construction method, in the present embodiment is:
Collapsible loess tunnel is buried for an ultra shallow to excavate to form excavation face using the interim inverted arch of three steps, three steps refer to In tunnel excavating process, the top bar 3 that sequentially forms step by step, middle step 2 and 1 is got out of a predicament or an embarrassing situation, in top bar preliminary bracing steelframe 4 The outside of top bar arch springing, which is set, expands arch springing 5, and top bar arch springing is up arranged at intervals stiffness connection 6;As follows in tunnel It constructs in road ground cement-soil compaction pile, forms cement-soil compaction pile ruggedized construction:
Step a:Cement-soil compaction pile stake position 8 is reserved according to test pile spacing between each road inverted arch preliminary bracing steelframe 7, and First time inverted arch preliminary bracing concrete construction is carried out, as shown in the first section 11 in Fig. 5.
The spacing of top bar preliminary bracing steelframe 4 is arranged to 60cm, the laying of cement-soil compaction pile stake position 8 is straight using stake Footpath is 40cm, and stake spacing 70cm × 70cm is laid in equilateral triangle;Inverted arch preliminary bracing steelframe 7 is first installed, then during construction It is in a row between adjacent inverted arch preliminary bracing steelframe 7 using the pvc pipe of φ 45cm × 8mm, according to test pile spacing, reserved stake is set Position, by the connection reinforcing bar between inverted arch preliminary bracing steelframe 7 by the casing fixation of stake position.
Step b:After first time inverted arch preliminary bracing concrete construction, the backfill soil body to inverted arch filled layer top surface mark It is high by 9, operation platform is formed, carries out rolling compacting using excavator during filling, avoids collapse hole occur during pile foundation construction.
Step c:On the operation platform, first using extension drill rod in crawler type screw drilling machine and setting in each stake position Place is molded stake holes by designing pile length, and tamping machine is recycled to be molded cement-soil compaction pile for each stake holes, is completed at the reinforcing to substrate Reason, effective stake top face of the cement-soil compaction pile is in the bottom of inverted arch preliminary bracing steelframe 7.Using two tamping machines and one Crawler type screw drilling machine combination construction, avoids adjacent bores position from caving in, and constructs every hole;During construction, inverted arch backfill length will meet 6 Rice, should ensure to leave equipment construction space shorten again the Second Lining Construction after stiffening basic ground apart from excavation face away from From.
Step d:The soil body that secondary excavation is filled fills in preliminary bracing in the reserved cement-soil compaction pile stake position 8 Concrete completes inverted arch preliminary bracing concrete construction, as shown in the second section 12 in Fig. 5;Secondary excavation fills the soil body Length control can fill in preliminary bracing concrete and subsequent inverted arch after 6m, excavation to reserved cement-soil compaction pile stake position The construction of secondary lining and Concrete Filled layer.
Step e:Construction inverted arch secondary lining and Concrete Filled layer are to designed elevation, as shown in the 3rd section 13 in Fig. 5.
In construction, in order to effectively slow down surrouding rock deformation and ensure the intensity of inverted arch preliminary bracing concrete, step is excavated in control Away from interval time and preliminary bracing off-period after, inverted arch preliminary bracing, including:Inverted arch is excavated per secondary control in 1.2~1.8m Drilling depth carries out cement-soil compaction pile construction in 5~7 days after first time inverted arch preliminary bracing concrete construction;Control construction Progress enables tunnel to reach preliminary bracing closing cyclization in 12 days;Depth of the inverted arch preliminary bracing away from top bar face For 15~20m, top bar face is no more than 55m away from two lining cyclization distances.
In specific implementation, because of minimum effective operation height 6.5m in tunnel, cement-soil compaction pile design length is 9.0m, is bored Machine uses 6.0m long spire formula drill bits, and brills footpath is 0.35m, and extension drill rod is not less than 3m in setting, to meet designing pile length and hole Hole space requirement.
The present invention is connected by using the stiffness expanded between arch springing, increase top bar preliminary bracing steelframe, is effective against Surrouding rock deformation reaches preliminary bracing entirety stress;Using inverted arch preliminary bracing of first constructing, compaction pile position is installed between supporting in the early stage Provided pipe reaches and first closes preliminary bracing, slows down surrouding rock deformation, it is ensured that country rock safety.
Structure type referring to interior extension drill rod in Fig. 6, Fig. 7 and Fig. 8 the present embodiment is:
The auger stem 21 of screw drilling machine is set to be set with extension bar 22 in one section in sleeve type drill rod for sleeve type drill rod; Interior extension bar 22 is the polished rod with 21 clearance fit of auger stem, and interior extension bar 22 can freely plug in auger stem 21.
Extension bar 22 is connected with the power output shaft of screw drilling machine in the present embodiment;The spiral shell being sleeved on interior extension bar 22 Rotary drill bar 21 can carry out pin joint using the top pin hole of auger stem 21 with interior extension bar upper pin hole 22b, form such as Fig. 6 and figure Non- extension bar shown in 7;Auger stem 21 or top pin hole and the interior extension bar lower pin hole 22c of auger stem 21 is utilized to carry out Pin joint forms extension bar as shown in Figure 8;Wherein, interior extension bar upper pin hole 22b is in the upper end of interior extension bar 22, that is, is near One end where power output shaft 23a, interior extension bar lower pin hole 22c are in the lower end of interior extension bar 22, in interior extension bar 22 and screw rod Pin joint is similarly used between the power output shaft 23a of drilling machine 23.
Easily operated in order to avoid disturbing, corresponding structure type is:The interior extension bar top pin being arranged on interior extension bar 22 For hole 22a and interior extension bar upper pin hole 22b in " ten " word on horizontal plane, interior extension bar top pin hole 22a is including being used for The pin hole of pin joint is carried out between extension bar 22 and the power output shaft 23a of screw drilling machine 23.
In construction:
First, pin joint is carried out between the top pin hole of auger stem 21 and the top pin hole of interior extension bar 22, makes interior extension bar 22 keep being sleeved in the sleeve of auger stem 21, start drilling machine;When auger stem 21 reaches depth of pore forming, auger is kept Connection of the bar 21 between bottom hole position, releasing auger stem 21 and interior extension bar 22.
Then, extension bar 22 in being extracted from auger stem 21, and the top pin hole using auger stem 21 and interior extension bar 22 Lower part pin hole carry out pin joint, form extension bar, be again started up drilling machine and implement drilling.
Since interior extension bar 22 is polished rod, no casting helical blade 21a after every drilling certain depth, promotes drilling rod extremely Helical blade on auger stem 21 is higher by aperture, is discharged the soil body on helical blade 21a using the rotation of auger stem 21, Such cycle operation, until reaching design stake bottom position.
The present invention using crawler type screw drilling machine and interior extension drill rod meet minimum effective operation height in tunnel will It asks, effectively reduces influence of the vibration to country rock during pile foundation construction, improve construction efficiency, it is ensured that the construction peace in tunnel Entirely;By adjusting tunnel safety step pitch and preliminary bracing closing cyclic time, safe construction environment is provided for constructing tunnel.

Claims (3)

1. a kind of an ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile reinforced construction method, it is characterized in that:
Collapsible loess tunnel is buried for an ultra shallow to excavate to form excavation face using the interim inverted arch of three steps, three step refers to It in tunnel excavating process, the top bar (3) that sequentially forms step by step, middle step (2) and gets out of a predicament or an embarrassing situation (1), in top bar preliminary bracing The outside of the top bar arch springing of steelframe (4), which is set, expands arch springing (5), and top bar arch springing is up arranged at intervals stiffness connection (6);It presses Following steps are constructed cement-soil compaction pile in tunnel foundation, form cement-soil compaction pile ruggedized construction:
Step a:Cement-soil compaction pile stake position (8) is reserved according to test pile spacing between each road inverted arch preliminary bracing steelframe (7), and Carry out first time inverted arch preliminary bracing concrete construction;
Step b:After first time inverted arch preliminary bracing concrete construction, the backfill soil body to inverted arch filled layer top surface absolute altitude (9), operation platform is formed;
Step c:On the operation platform, pressed first using extension drill rod in crawler type screw drilling machine and setting at each stake position Designing pile length is molded stake holes, and tamping machine is recycled to be molded cement-soil compaction pile for each stake holes, completes the consolidation process to substrate, institute The effective stake top face for stating cement-soil compaction pile is in the bottom of inverted arch preliminary bracing steelframe (7);
Step d:The soil body that secondary excavation is filled in the reserved cement-soil compaction pile stake position (8) is filled in preliminary bracing and is mixed Solidifying soil, completes inverted arch preliminary bracing concrete construction;
Step e:Inverted arch secondary lining and Concrete Filled layer construct to designed elevation.
2. an ultra shallow according to claim 1 buries collapsible loess tunnel ground cement-soil compaction pile reinforced construction method, It is characterized in:
Inverted arch is excavated per secondary control in 1.2~1.8m drilling depths, 5~7 after first time inverted arch preliminary bracing concrete construction It carries out cement-soil compaction pile construction;
Control construction speed enables the tunnel to reach preliminary bracing closing cyclization in 12 days;
Depth of the inverted arch preliminary bracing away from top bar face is 15~20m, and top bar face does not surpass away from two lining cyclization distances Cross 55m.
3. an ultra shallow according to claim 1 buries collapsible loess tunnel ground cement-soil compaction pile reinforced construction method, It is characterized in:Minimum effective operation height 6.5m in tunnel, cement-soil compaction pile design length are 9.0m, and drilling machine uses 6.0m long spiral shells Rotating drill bit, brill footpath are 0.35m, and interior extension drill rod is not less than 3m.
CN201610473303.4A 2016-06-23 2016-06-23 An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method Active CN105951707B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610473303.4A CN105951707B (en) 2016-06-23 2016-06-23 An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610473303.4A CN105951707B (en) 2016-06-23 2016-06-23 An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method

Publications (2)

Publication Number Publication Date
CN105951707A CN105951707A (en) 2016-09-21
CN105951707B true CN105951707B (en) 2018-05-18

Family

ID=56904037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610473303.4A Active CN105951707B (en) 2016-06-23 2016-06-23 An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method

Country Status (1)

Country Link
CN (1) CN105951707B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108331530A (en) * 2018-03-05 2018-07-27 嘉兴市恒创电力设备有限公司 A kind of portable electric pole earth boring machine
CN108533296B (en) * 2018-06-11 2023-09-15 中铁二局第一工程有限公司 Butt joint structure of reserved deformation units of large deformation tunnel steel frame and construction method
CN110792440B (en) * 2019-11-07 2021-02-05 中铁二十局集团有限公司 Construction method of water-rich loess tunnel penetrating through loess towards valley
CN112901208B (en) * 2021-05-06 2021-07-30 中铁九局集团第七工程有限公司 Comprehensive construction method for shallow buried section of urban railway mining method tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000337093A (en) * 1999-05-26 2000-12-05 Nihon Samicon Kk Arched hollow structure
CN101598028A (en) * 2009-06-29 2009-12-09 中铁二院工程集团有限责任公司 Lining structure for super large section water-rich loess tunnel of high-speed railroad
CN101603282A (en) * 2009-06-29 2009-12-16 中铁二院工程集团有限责任公司 High speed railway collapsible loess tunnel foundation base configuration
CN201486568U (en) * 2009-06-29 2010-05-26 中铁二院工程集团有限责任公司 Primary support structure of shallow underpass highway loess strata super-large section tunnel
CN201915385U (en) * 2010-08-09 2011-08-03 中铁第一勘察设计院集团有限公司 Compacted pile for foundation treatment of collapsed loess in tunnel
CN105673025A (en) * 2014-11-19 2016-06-15 山东科技大学 Underground engineering loess tunnel ground surface settlement control construction process
CN205688426U (en) * 2016-06-23 2016-11-16 中铁四局集团有限公司 An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000337093A (en) * 1999-05-26 2000-12-05 Nihon Samicon Kk Arched hollow structure
CN101598028A (en) * 2009-06-29 2009-12-09 中铁二院工程集团有限责任公司 Lining structure for super large section water-rich loess tunnel of high-speed railroad
CN101603282A (en) * 2009-06-29 2009-12-16 中铁二院工程集团有限责任公司 High speed railway collapsible loess tunnel foundation base configuration
CN201486568U (en) * 2009-06-29 2010-05-26 中铁二院工程集团有限责任公司 Primary support structure of shallow underpass highway loess strata super-large section tunnel
CN201915385U (en) * 2010-08-09 2011-08-03 中铁第一勘察设计院集团有限公司 Compacted pile for foundation treatment of collapsed loess in tunnel
CN105673025A (en) * 2014-11-19 2016-06-15 山东科技大学 Underground engineering loess tunnel ground surface settlement control construction process
CN205688426U (en) * 2016-06-23 2016-11-16 中铁四局集团有限公司 An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction

Also Published As

Publication number Publication date
CN105951707A (en) 2016-09-21

Similar Documents

Publication Publication Date Title
CN105951707B (en) An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction and construction method
CN103628894B (en) Method is repaiied in a kind of rich water fault belt based on angle umbrella pre-grouting lane, tunnel of collapsing
CN103758123B (en) The construction method of manually digging hole filling pile retaining wall lining
CN102660955B (en) Quick construction method for foundation pit slope support
CN107620600A (en) A kind of MJS engineering methods and pipe-roof method combined supporting big cross section small interval tunneling engineering method
CN104532714B (en) Roadbed structure for treating deep soft soil karst foundation
CN107044293A (en) A kind of construction method in tunnel
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
KR101039554B1 (en) Combination pile having a cast in place concrete pile combined with a phc or steel pile and the construction method using the same
CN110284885A (en) Shield inspection-pit construction method
CN106609509A (en) Self-balancing foundation pit enclosure structure and construction method thereof
CN108149696B (en) A kind of construction method for the composite supporting construction that gib soil nail wall is combined with permanent anti-float anchor rod
CN105156123B (en) A kind of open type shield excavation machine and its application method
CN109853399A (en) Big section for arch bridge tilts tunnel type skewback structure and its construction method
JP2010255237A (en) Method and structure for tunnel reinforcement
JP4132442B2 (en) Tunnel construction method
CN204311456U (en) Foundation ditch strengthening structure
CN107604931A (en) The breakage mountain body restorative procedure and structure that a kind of friction pile is combined with GSZ
CN107339122A (en) A kind of steel pipe column handles goaf engineering method
CN105019431B (en) Crush and complete alternate steep dip stratified rock masses Large Diameter Super-long Bored Piles construction method
CN207513614U (en) Shallow tunnel subsurface excavation method advance support structure and combined type advanced tubule
CN107060778B (en) Pass through super high-rise building group back filled region method for tunnel construction
CN105735383A (en) Partial underground obstacle removing construction method capable of reserving structural system
CN205688426U (en) An ultra shallow buries collapsible loess tunnel ground cement-soil compaction pile ruggedized construction
CN107143149A (en) A kind of existing masonry structure building sets up the construction method of basement

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant