CN105926630A - 一种加快深大地下结构施工的环形换撑及跳仓施工方法 - Google Patents
一种加快深大地下结构施工的环形换撑及跳仓施工方法 Download PDFInfo
- Publication number
- CN105926630A CN105926630A CN201610269743.8A CN201610269743A CN105926630A CN 105926630 A CN105926630 A CN 105926630A CN 201610269743 A CN201610269743 A CN 201610269743A CN 105926630 A CN105926630 A CN 105926630A
- Authority
- CN
- China
- Prior art keywords
- construction
- storehouse
- annular
- foundation ditch
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Abstract
本发明公开了一种加快深大地下结构施工的环形换撑及跳仓施工方法,基坑上方基础底板或者楼层板施工时,先将基坑周边沿环向划分成若干个区块,然后采用跳仓间隔或顺次施工所述的若干个区块,提前在基坑周边形成环形的换撑板带,使上道支撑梁具备拆除条件,在上道支撑梁拆除后进入下一层结构的施工。因此,本发明可以达到节省工期的目的。
Description
技术领域
本发明涉及建筑地下结构施工领域,适用于基坑工程采用围护桩加内支撑的地下结构施工。
背景技术
在采用围护桩(墙)结合内支撑支护体系的深大基坑工程中,当土方开挖至坑底逐层向上施工地下结构时,一般需要支撑梁下所有楼(底)板全部完成并达到设计强度要求,能够有效抵抗土压力,才能拆除上一道支撑。
当地下室楼(底)板超长时,一般需要每隔40m左右留设800~1000mm后浇带,待后浇带两侧混凝土收缩完成(一般60d)后方可封闭。在封闭前由于两侧楼板断开,无法有效传递土压力。跳仓法将地下室基础底板或楼板划分为40m左右的小块,相邻区块浇筑时间间隔不小于7天,区块与区块之间连成整体,可避免超长结构留设后浇带,起到连续传力作用。
对于大面积深基坑,由于垂直运输、劳动力布置等原因往往要占用很长工期,传统施工方法难以加快施工进度,影响了工期。
发明内容
本发明所要解决的技术问题就是提供一种加快深大地下结构施工的环形换撑及跳仓施工方法,加快施工进度,缩短工期。
为解决上述技术问题,本发明采用如下技术方案:一种加快深大地下结构施工的环形换撑及跳仓施工方法,基坑上方基础底板或者楼层板施工时,先将基坑周边沿环向划分成若干个区块,然后采用跳仓间隔或顺次施工所述的若干个区块,提前在基坑周边形成环形的换撑板带,使上道支撑梁具备拆除条件,在上道支撑梁拆除后进入下一层结构的施工。
优选的,该施工方法具体包括如下步骤:
步骤一、圆环区段的划分,以基坑中心为圆点画圆,将基础底板或楼层板划分为宽度不大于40m的圆环板带;
步骤二、圆环区域的划分,根据跳仓法仓块最长段不宜大于40m的原则,以圆环圆心为中心,向基坑四周引直线,划分各个圆环内的区块;
步骤三、合理选择施工顺序,按先外环后里环,控制相邻区块的施工间隔时间不少于7天;
步骤四、分块间隔施工,采用跳仓法间隔浇筑环形区块;
步骤五、拆除支撑梁、施工下一层结构,待支撑梁下环形周边部分所有基础底板或楼层换撑板完成后,且混凝土强度达到设计要求,即可拆除支撑梁,同时补足洞口内楼板/底板,施工下一层结构。
作为优选,当深大基坑形状近似矩形时,设置多个后补洞口。
本发明方法的环形换撑及跳仓,只要在下一层楼板施工中先施工周边部分,中间形成较大开洞,只要周边剩余部分能够起到支撑围护桩的作用,周边换撑达到强度后就可以拆除其上方的支撑,拆除支撑同时完成开洞部分楼板,从而达到加快施工进度,节省工期的目的。
附图说明
下面结合附图和具体实施方式对本发明作进一步描述:
图1为基坑形状示意图;
图2为基础底板区块划分示意图。
具体实施方式
本发明在楼(底)板施工时,先将基坑周边沿环向划分成若干个区块,然后采用跳仓间隔或顺次施工所述的若干个区块,提前在基坑周边形成环形的换撑板带,使上道支撑梁具备拆除条件,在上道支撑梁拆除后进入下一层结构的施工。
实施例1,下面以某地下结构工程为例,对本发明做进一步说明。
如图1所示,该项目基坑为多边形结构,基坑面积约2.1万m2,地下一层,开挖深度约6m,基坑围护结构为钻孔灌注桩结合一道环形混凝土内支撑,环形内支撑半径75.0m,筏板基础。其具体施工步骤如下:
(一)圆环区段划分
以环形支撑的圆心为中心画圆,将基础底板划分为若干环形区块,此例为2个环形区块,外层为环形,内层为圆形。
(二)圆环区域划分
如图2所示,根据跳仓法仓块最长段不宜大于40m的原则,以圆环圆点为中心,向基坑四周引直线,划分各个圆环内的区块,共划分为17个区块。
(三)混凝土施工
采用跳仓法间隔或顺次浇筑环形区块,此例中,如图2所示,浇筑顺序为Ⅰ→Ⅱ→Ⅲ→Ⅳ,相邻区块之间浇筑间隔时间不少于7天。施工中应优化混凝土配合比、加强振捣与养护,养护时间不应低于14天。
(四)支撑梁拆除,施工负一层
待Ⅰ、Ⅱ区块完成以后,且混凝土强度带到设计要求,便可拆除环形支撑,施工负一层结构。
实施例2,当深大基坑形状近似矩形或细长不规则时,可设置多个后补洞口,只要周边部分能够抵抗土的压力,本方法同样适用。
Claims (3)
1.一种加快深大地下结构施工的环形换撑及跳仓施工方法,其特征在于:基坑上方基础底板或者楼层板施工时,先将基坑周边沿环向划分成若干个区块,然后采用跳仓间隔或顺次施工所述的若干个区块,提前在基坑周边形成环形的换撑板带,使上道支撑梁具备拆除条件,在上道支撑梁拆除后进入下一层结构的施工。
2.根据权利要求1所述的一种加快深大地下结构施工的环形换撑及跳仓施工方法,其特征在于包括如下步骤:
步骤一、圆环区段的划分,以基坑中心为圆点画圆,将基础底板或楼层板划分为宽度不大于40m的圆环板带;
步骤二、圆环区域的划分,根据跳仓法仓块最长段不大于40m的原则,以圆环圆心为中心,向基坑四周引直线,划分各个圆环内的区块;
步骤三、合理选择施工顺序,按先外环后里环,控制相邻区块的施工间隔时间不少于7天;
步骤四、分块间隔施工,采用跳仓法间隔浇筑环形区块;
步骤五、拆除支撑梁、施工下一层结构,待支撑梁下环形周边部分所有基础底板或楼层换撑板完成后,且混凝土强度达到设计要求,即可拆除支撑梁,同时补足洞口内楼板/底板,施工下一层结构。
3.根据权利要求1或者2所述的一种加快深大地下结构施工的环形换撑及跳仓施工方法,其特征在于:当深大基坑形状近似矩形时,设置多个后补洞口。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610269743.8A CN105926630B (zh) | 2016-04-27 | 2016-04-27 | 一种加快深大地下结构施工的环形换撑及跳仓施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610269743.8A CN105926630B (zh) | 2016-04-27 | 2016-04-27 | 一种加快深大地下结构施工的环形换撑及跳仓施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105926630A true CN105926630A (zh) | 2016-09-07 |
CN105926630B CN105926630B (zh) | 2018-03-13 |
Family
ID=56837571
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610269743.8A Active CN105926630B (zh) | 2016-04-27 | 2016-04-27 | 一种加快深大地下结构施工的环形换撑及跳仓施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105926630B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109139055A (zh) * | 2018-10-29 | 2019-01-04 | 中铁十二局集团有限公司 | 全圆小断面隧洞针梁台车衬砌施工方法 |
CN111395350A (zh) * | 2020-04-15 | 2020-07-10 | 中国建筑第七工程局有限公司 | 一种软土深基坑挖土施工工法 |
CN112609701A (zh) * | 2020-11-30 | 2021-04-06 | 中国建筑第八工程局有限公司 | 深基坑内支撑拆除方法 |
CN112627197A (zh) * | 2021-01-06 | 2021-04-09 | 上海建工一建集团有限公司 | 基坑支撑拆除及地下室结构回筑的施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090047074A1 (en) * | 2007-08-13 | 2009-02-19 | Meyer John W | Center beam connection assembly for temporary shoring |
CN103590406A (zh) * | 2013-11-29 | 2014-02-19 | 中船第九设计研究院工程有限公司 | 一种超大型深基坑分区同步开挖的施工方法 |
CN104947681A (zh) * | 2015-07-07 | 2015-09-30 | 中建三局第二建设工程有限责任公司 | 一种超大超深地下室基坑的施工方法 |
CN104963357A (zh) * | 2015-07-08 | 2015-10-07 | 中国十七冶集团有限公司 | 大面积rc地下室结构跳仓施工法 |
-
2016
- 2016-04-27 CN CN201610269743.8A patent/CN105926630B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20090047074A1 (en) * | 2007-08-13 | 2009-02-19 | Meyer John W | Center beam connection assembly for temporary shoring |
CN103590406A (zh) * | 2013-11-29 | 2014-02-19 | 中船第九设计研究院工程有限公司 | 一种超大型深基坑分区同步开挖的施工方法 |
CN104947681A (zh) * | 2015-07-07 | 2015-09-30 | 中建三局第二建设工程有限责任公司 | 一种超大超深地下室基坑的施工方法 |
CN104963357A (zh) * | 2015-07-08 | 2015-10-07 | 中国十七冶集团有限公司 | 大面积rc地下室结构跳仓施工法 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109139055A (zh) * | 2018-10-29 | 2019-01-04 | 中铁十二局集团有限公司 | 全圆小断面隧洞针梁台车衬砌施工方法 |
CN111395350A (zh) * | 2020-04-15 | 2020-07-10 | 中国建筑第七工程局有限公司 | 一种软土深基坑挖土施工工法 |
CN112609701A (zh) * | 2020-11-30 | 2021-04-06 | 中国建筑第八工程局有限公司 | 深基坑内支撑拆除方法 |
CN112627197A (zh) * | 2021-01-06 | 2021-04-09 | 上海建工一建集团有限公司 | 基坑支撑拆除及地下室结构回筑的施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105926630B (zh) | 2018-03-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105926630A (zh) | 一种加快深大地下结构施工的环形换撑及跳仓施工方法 | |
CN108005084A (zh) | 深基坑复合式支护及施工方法 | |
CN104594361B (zh) | 一种工字型围护桩以及围护结构兼做主体结构的施工方法 | |
CN102383433A (zh) | 一种超高层建筑深大基坑的设计方法 | |
CN106013167A (zh) | 用于长大深基坑的分块支护结构及支护方法 | |
CN103603358A (zh) | 一种多平台围护结构及施工方法 | |
CN102444130A (zh) | 深基坑工程中的快速换撑施工方法 | |
CN208685703U (zh) | 一种装配式预制钢筋混凝土取水头结构 | |
CN103669284A (zh) | 水上拼装的箱筒型基础防波堤结构及其拼装方法 | |
CN102493488A (zh) | 基坑工程逆梁顺板施工方法 | |
CN107503355B (zh) | 外排后插型钢式双排桩基坑支护体系及其施工方法 | |
CN103603357A (zh) | 一种多平台无内支撑自防水基坑围护结构及其施工方法 | |
CN105350575A (zh) | 一种地下连续墙的逆作施工方法 | |
JP5872724B1 (ja) | 水中の仮締切構造の施工方法 | |
US4232491A (en) | Swimming pool deck | |
KR101212578B1 (ko) | 수직구의 돔 설치방법과 그 돔세그먼트 | |
CN103572762B (zh) | 基坑支护结构的斜内撑下端的牛腿及制造工具和施工方法 | |
CN107313454A (zh) | 一种地下车库的施工方法 | |
CN203821398U (zh) | 基坑支护结构的斜内撑下端的牛腿及制造工具 | |
CN108612129B (zh) | 基于可周转钢平台的逆作法施工方法 | |
JP5506057B2 (ja) | 建物の構築方法 | |
CN104674796B (zh) | 一种地下防空洞灌注桩的模板系统及其施工方法 | |
CN105297758A (zh) | 预应力方桩与钢格构柱集成立柱 | |
CN217629966U (zh) | 一种临地铁的大跨度半逆作法基坑内支撑结构 | |
CN202247905U (zh) | 一种深基坑的快速换撑结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Yutao Inventor after: Xu Shuangquan Inventor after: Chen Liang Inventor after: Gong Xufeng Inventor after: Gong Yongqing Inventor after: Gu Xin Inventor before: Liu Yutao Inventor before: Xu Shuangquan Inventor before: Chen Liang Inventor before: Gong Xufeng |
|
GR01 | Patent grant | ||
GR01 | Patent grant |