CN105909306A - Super-long large dip angle tunnel anchorage double-track slag removal construction method - Google Patents

Super-long large dip angle tunnel anchorage double-track slag removal construction method Download PDF

Info

Publication number
CN105909306A
CN105909306A CN201610452453.7A CN201610452453A CN105909306A CN 105909306 A CN105909306 A CN 105909306A CN 201610452453 A CN201610452453 A CN 201610452453A CN 105909306 A CN105909306 A CN 105909306A
Authority
CN
China
Prior art keywords
track
mine car
slag
hole
hoist engine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610452453.7A
Other languages
Chinese (zh)
Inventor
唐中波
徐国挺
胡盼
张磊
段羽
李清培
代道芬
陈刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Original Assignee
SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN LUQIAO HUADONG BUILDING CO Ltd filed Critical SICHUAN LUQIAO HUADONG BUILDING CO Ltd
Priority to CN201610452453.7A priority Critical patent/CN105909306A/en
Publication of CN105909306A publication Critical patent/CN105909306A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Abstract

The invention discloses a super-long large dip angle tunnel anchorage double-track slag removal construction method which is characterized by comprising the following steps: (1) mounting a track; (2) arranging a safety device; (3) loading slag in a tramcar; and (4) pulling by a winch. The previous tunnel anchorage slag removal is performed by adopting a single-track slag removal system generally, and the method mainly aims at tunnel anchorage with small length and small sectional area. For a long or super-long tunnel anchorage, compared with the single-track slag removal construction method, the double-track slag removal construction method is short in used time and high in efficiency. Particularly for a super-long tunnel anchorage with a larger sectional area, the utilization value can be reflected.

Description

A kind of overlength, the method for high inclination-angle tunnel anchorage two-orbit tap cinder construction
Technical field
The present invention relates to field of civil engineering, be specifically related to a kind of realize overlength, construction method that high inclination-angle tunnel anchorage is slagged tap.
Background technology
At present, domestic Tunnel-Type Anchorage of Suspension Bridge is slagged tap and general is used monorail slag-tapping system, the method mainly for shorter in length, the tunnel anchorage that basal area is less.If using monorail slag-tapping system for longer or Super Long Tunnel anchor, its effect is relatively low, and utilizes two-orbit tap cinder construction method will to be greatly improved in effect than monorail tap cinder construction method, and the time shortens greatly.The tunnel anchor watch the longest, cross-sectional area is the biggest can embody its value.
Summary of the invention
It is an object of the invention to provide a kind of method utilizing two-orbit that overlength, high inclination-angle tunnel anchorage are slagged tap at this;Making its time used of slagging tap short, efficiency is high.The tunnel anchor watch the longest, cross-sectional area is the biggest can embody its value.
The present invention is achieved in that and utilizes the device of simple and convenient to realize high efficiency installation method, it is characterised in that: comprise the following steps:
Step one: track installation: track is made up of shaped steel, after concrete construct until inverted arch spray, utilizes backfill hole slag, installs sleeper, lay track of slagging tap, and two tracks are laid side by side, and track laying fills at slag to hole from hole;
Step 2: safety device is arranged: be provided with electric-controlled switch stop in orbit, when mine car is beyond leakage hole, touches this device, and hoist engine will stop continuing to lift up mine car at once, arrives braking purpose.Track end is provided with pressure arresting stop, prevents hoist engine generation chance failure from promoting mine car beyond track.After having slagged tap every time, mine car is parked in mine car and parks at platform, for preventing mine car from surprisingly gliding, anti-skidding restriction is set at mine car two-wheeled and blocks;
Step 3: mine car dress slag: use digging machine to be filled in mine car by slag, have special messenger to command when track is slagged tap in hole, links up in time with operation hoist engine personnel with transmitter receiver, preferably guarantees the safety of construction;
Step 4: hoist engine draws;Two hoist engines are arranged, for the traction of mine car of slagging tap outside hole.After mine car installs slag, utilize hoist engine trailer wagon to topple over place to slag, then unload.
Overlength of the present invention, the method for high inclination-angle tunnel anchorage two-orbit tap cinder construction;Comprise the following steps: (1) track installation;(2) safety device is arranged;(3) mine car dress slag;(4) hoist engine traction;In the past tunnel anchorage was slagged tap and general was used monorail slag-tapping system, the method pin mainly for shorter in length, the tunnel anchorage that basal area is less.Using two-orbit tap cinder construction method shorter than the time used by monorail tap cinder construction method for longer or Super Long Tunnel anchor, efficiency is high.The tunnel anchor watch the longest, cross-sectional area is the biggest can embody its value.
The present invention slags tap relative to conventional tunnel anchorage from the point of view of general employing monorail slag-tapping system, has the advantage that
1, by the enforcement of the present invention, can high efficiency slag transhipment in hole be appeared in overlength, high inclination-angle tunnel anchorage.
2, monorail efficiency is high than ever, and the time used is short, and safety device consolidates, it is not easy to security incident occurs.
Accompanying drawing explanation
Fig. 1 is track involved in the present invention and dolly schematic diagram
Fig. 2 is two-orbit schematic diagram involved in the present invention.
Wherein: operating platform 1, material loading platform 2, winch 3, the horizontal hole of tunnel anchorage 4, track 5 of slagging tap, dolly 6 of slagging tap, excavator 7, electric wire 8, execute brill airduct 9, water pipe 10, People's Bank of China's ladder step 11, ventilation duct 12.
Detailed description of the invention
Below in conjunction with accompanying drawing 1-2, the present invention is described in detail, is clearly and completely described the technical scheme in the embodiment of the present invention, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments.Based on the embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained under not making creative work premise, broadly fall into the scope of protection of the invention.
It is an object of the invention to provide a kind of overlength, the method for high inclination-angle tunnel anchorage fast slag tapping so that it is the time used of slagging tap is short, efficiency is high, and can safely and effectively construct;The specific embodiment of the invention be expanded on further below in conjunction with the accompanying drawings:
A kind of overlength, the method for high inclination-angle tunnel anchorage two-orbit tap cinder construction, improve speed, and can safely and effectively construct, comprise the following steps:
Step one: track installation: track is made up of shaped steel, after concrete construct until inverted arch spray, utilizes backfill hole slag, installs sleeper, lay track of slagging tap, and two tracks are laid side by side, and track laying fills at slag from hole to hole, as shown in Figure 1;
Step 2: safety device is arranged: be provided with electric-controlled switch stop in orbit, when mine car is beyond leakage hole, touches this device, and hoist engine will stop continuing to lift up mine car at once, arrives braking purpose.Track end is provided with pressure arresting stop, prevents hoist engine generation chance failure from promoting mine car beyond track.After having slagged tap every time, mine car is parked in mine car and parks at platform, for preventing mine car from surprisingly gliding, anti-skidding restriction is set at mine car two-wheeled and blocks.
Step 3: mine car dress slag: use digging machine to be filled in mine car by slag, have special messenger to command when track is slagged tap in hole, links up in time with operation hoist engine personnel with transmitter receiver, preferably guarantees the safety of construction.
Step 4: hoist engine draws;Two hoist engines are arranged, for the traction of mine car of slagging tap outside hole.After mine car installs slag, utilize hoist engine trailer wagon to topple over place to slag, then unload.
Present invention have the advantage that
1, by the enforcement of the present invention, can high efficiency slag transhipment in hole be appeared in overlength, high inclination-angle tunnel anchorage.
2, monorail efficiency is high than ever, and the time used is short, and safety device consolidates, it is not easy to security incident occurs.
Described above to the disclosed embodiments, makes professional and technical personnel in the field be capable of or uses the present invention.Multiple amendment to these embodiments will be apparent from for those skilled in the art, and generic principles defined herein can realize without departing from the spirit or scope of the present invention in other embodiments.Therefore, the present invention is not intended to be limited to the embodiments shown herein, and is to fit to the widest scope consistent with principles disclosed herein and features of novelty.

Claims (1)

1. an overlength, the method for high inclination-angle tunnel anchorage two-orbit tap cinder construction, it is characterised in that: comprise the following steps:
Step one: track installation: track is made up of shaped steel, after concrete construct until inverted arch spray, utilizes backfill hole slag, installs sleeper, lay track of slagging tap, and two tracks are laid side by side, and track laying fills at slag to hole from hole;
Step 2: safety device is arranged: be provided with electric-controlled switch stop in orbit, when mine car is beyond leakage hole, touches this device, and hoist engine will stop promoting mine car at once, arrives braking purpose;Track end is provided with pressure arresting stop, prevents hoist engine generation chance failure from promoting mine car beyond track;After having slagged tap every time, mine car is parked in mine car and parks at platform, for preventing mine car from surprisingly gliding, anti-skidding restriction is set at mine car two-wheeled and blocks;
Step 3: mine car dress slag: use digging machine to be filled in mine car by slag, have special messenger to command when track is slagged tap in hole, links up in time with operation hoist engine personnel with transmitter receiver, preferably guarantees the safety of construction;
Step 4: hoist engine draws;Two hoist engines are arranged, for the traction of mine car of slagging tap outside hole;After mine car installs slag, utilize hoist engine trailer wagon to topple over place to slag, then unload.
CN201610452453.7A 2016-06-22 2016-06-22 Super-long large dip angle tunnel anchorage double-track slag removal construction method Pending CN105909306A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610452453.7A CN105909306A (en) 2016-06-22 2016-06-22 Super-long large dip angle tunnel anchorage double-track slag removal construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610452453.7A CN105909306A (en) 2016-06-22 2016-06-22 Super-long large dip angle tunnel anchorage double-track slag removal construction method

Publications (1)

Publication Number Publication Date
CN105909306A true CN105909306A (en) 2016-08-31

Family

ID=56759125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610452453.7A Pending CN105909306A (en) 2016-06-22 2016-06-22 Super-long large dip angle tunnel anchorage double-track slag removal construction method

Country Status (1)

Country Link
CN (1) CN105909306A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111074781A (en) * 2019-12-31 2020-04-28 中铁大桥局集团有限公司 Method for quickly excavating suspension bridge tunnel anchor
CN112901201A (en) * 2021-02-02 2021-06-04 中铁大桥局集团第五工程有限公司 Construction method for large-capacity rapid slag tapping of tunnel anchor with ultra-large inclination angle
CN112901223A (en) * 2021-02-02 2021-06-04 中铁大桥局集团第五工程有限公司 Tunnel anchor mechanical equipment with ultra-large inclination angle and method for automatically transporting materials
CN115110958A (en) * 2022-06-23 2022-09-27 保利长大工程有限公司 Multi-arch tunnel group safe tunneling construction process under complex geological conditions

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060030389A (en) * 2004-10-05 2006-04-10 (주) 철도안전연구소 Constructing apparatus for reforming plate girder bridge of railway and engineering method of reforming thereof
CN101363324A (en) * 2008-09-24 2009-02-11 中国水利水电第五工程局有限公司 Improved process for tap cinder construction for main hole incline shaft
CN203321581U (en) * 2013-06-21 2013-12-04 中国葛洲坝集团国际工程有限公司 Material conveying device for inclined shaft

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060030389A (en) * 2004-10-05 2006-04-10 (주) 철도안전연구소 Constructing apparatus for reforming plate girder bridge of railway and engineering method of reforming thereof
CN101363324A (en) * 2008-09-24 2009-02-11 中国水利水电第五工程局有限公司 Improved process for tap cinder construction for main hole incline shaft
CN203321581U (en) * 2013-06-21 2013-12-04 中国葛洲坝集团国际工程有限公司 Material conveying device for inclined shaft

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
吴庆鸣等: "全断面隧洞掘进机配套出渣列车优化调度的研究", 《矿山机械》 *
范水木: "双洞平行开挖轨道出渣施工技术探讨", 《福建建筑》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111074781A (en) * 2019-12-31 2020-04-28 中铁大桥局集团有限公司 Method for quickly excavating suspension bridge tunnel anchor
CN112901201A (en) * 2021-02-02 2021-06-04 中铁大桥局集团第五工程有限公司 Construction method for large-capacity rapid slag tapping of tunnel anchor with ultra-large inclination angle
CN112901223A (en) * 2021-02-02 2021-06-04 中铁大桥局集团第五工程有限公司 Tunnel anchor mechanical equipment with ultra-large inclination angle and method for automatically transporting materials
CN115110958A (en) * 2022-06-23 2022-09-27 保利长大工程有限公司 Multi-arch tunnel group safe tunneling construction process under complex geological conditions

Similar Documents

Publication Publication Date Title
CN105909306A (en) Super-long large dip angle tunnel anchorage double-track slag removal construction method
CN108678785B (en) Box culvert crane for hoisting railway tunnel prefabricated inverted arch side box culvert
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN106012855B (en) One kind realizes overlength, high inclination-angle tunnel anchorage reinforcing pull rod quick-mount system and operating method
CN103046933B (en) Shield station-crossing tunneling and station parallel construction method
CN103711499A (en) Shield tunneling machine split starting construction method
CN107237649A (en) The long steep inclined shaft transportation system of light section and construction method
CN206987883U (en) The long steep inclined shaft transportation system of light section
CN205448857U (en) Portable safety device of rock bar foundation ditch blasting excavation
CN106194214B (en) A kind of lining template trolley for baffle and its method walked safely on ramp
CN106593454B (en) The shield side that boring construction starting well and lifting well combine originates tunneling construction method and structure
CN208137972U (en) A kind of box culvert loop wheel machine for the prefabricated inverted arch side box culvert lifting of railway tunnel
CN103775734B (en) Gas drainage pipeline system construction method under large-diameter well
CN106285019A (en) A kind of overhead traveling crane installation method under confined space
CN203321581U (en) Material conveying device for inclined shaft
CN206915369U (en) Hopper bend tilting device
CN205858409U (en) A kind of structure of slagging tap of low-angle dip inclined shaft
CN109083020A (en) A kind of change of lower guide fixed-point sling erecting bridge machine is across method
CN203306018U (en) Special vehicle for automatically laying subway cable
CN201851160U (en) Traffic lamp under mining well
CN104018474B (en) The method in a working tunnel backfill reconstruction maintenance hole
CN203127962U (en) Material transportation device for hot blast stove
CN203246992U (en) Inclined-mine forking uncoupling field
CN205769328U (en) Type Protection Device for Inclined Shaft Runaway Car
CN205369182U (en) A fill water energy absorber that is used for geomembrane storehouse basin prevention of seepage system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160831