CN105908625A - Construction method for adding frame bridge under existing railway line based on dragging method - Google Patents
Construction method for adding frame bridge under existing railway line based on dragging method Download PDFInfo
- Publication number
- CN105908625A CN105908625A CN201610227511.6A CN201610227511A CN105908625A CN 105908625 A CN105908625 A CN 105908625A CN 201610227511 A CN201610227511 A CN 201610227511A CN 105908625 A CN105908625 A CN 105908625A
- Authority
- CN
- China
- Prior art keywords
- frame bridge
- main body
- construction
- existing railway
- slide plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
A construction method for adding a frame bridge under an existing railway line based on a dragging method relates to a frame bridge construction method. The method provided by the invention solves the problems in existing addition of a frame bridge based on a jacking method that the construction cost is high; construction is slow; a horizontal position and an elevation of the frame bridge cannot be controlled easily during the jacking course; and large deviations often appear. The method provided by the invention comprises the steps including the first step of foundation pit excavation, the second step of slide plate construction, the third step of isolating layer construction, the fourth step of frame bridge main body prefabrication, the fifth step of construction of a waterproof layer and a protective layer of the frame bridge main body, the sixth step of construction of a retaining wall or an anti-slide pile, the seventh step of horizontal directional drilling, the eighth step of penetration of multiple tension bars, the ninth step of line reinforcement, the tenth step of frame bridge main body dragging, the eleventh step of abutment back backfilling and the twelfth step of digging and external transport of soil between the retaining wall or the anti-slide pile and the frame bridge main body. The method provided by the invention is used to add the frame bridge under the existing railway line.
Description
Technical field
The present invention relates to a kind of frame bridge construction method, set up executing of frame bridge particularly to method dilatory under a kind of existing railway line
Work method.
Background technology
Under existing railway line during newly-built frame bridge, existing construction method is to use pipe jacking method.What jacking existed lacks
Point has: 1) force-transmitting pole and distribution beam are in pressured state in use, owing to the slenderness ratio of rod member is relatively big, and easy unstability,
The pressure that can bear is less, therefore can not give full play to the mechanical property of material, and the usage amount causing force-transmitting pole and distribution beam is non-
Chang great, has bad luck relatively costly by the most up to tens tons;2) haul distance of every one jack of jacking in jack-in process,
Being accomplished by the force-transmitting pole using crane constantly to change different length, the job demand of outward transport of cutting the earth in period frame bridge stops,
Speed of application is relatively slow, relatively costly;3) jack-in process center is built bridge horizontal level and elevation are not easily controlled, and often go out
The biggest deviation.
Summary of the invention
The present invention is to solve that when existing jacking sets up frame bridge, construction cost is higher, speed of application is relatively slow, and jacking
Horizontal level and elevation that journey center is built bridge are not easily controlled, problem relatively large deviation often occur, it is provided that a kind of existing railway
Under line, dilatory method sets up the construction method of frame bridge.
The present invention is to solve that above-mentioned technical problem adopts the technical scheme that: dilatory method under a kind of existing railway line of the present invention
The construction method setting up frame bridge comprises the following steps:
Step one, excavation of foundation pit: in the both sides of existing railway circuit, take the mode putting slope excavation or supporting excavation to dig foundation ditch,
Foundation ditch is dug the substrate absolute altitude of design;
Step 2, slide plate are constructed:
Detection foundation bearing capacity, detect qualified after, carry out the construction of slide plate, slide plate is made up of armored concrete, first at railway
Lay blotter in the foundation ditch substrate of circuit wherein side, then carry out colligation or the welding of slide plate reinforcing bar, finally pour mixed
Solidifying soil makes slide plate, strictly to control the flatness of slide plate end face during slide plate construction;
Step 3, sealing coat are constructed:
At slide plate end face coated with paraffin layer, paraffin layer is laid laminated plastics cloth, between every layer of Polypropylence Sheet, uniformly spills Pulvis Talci;
Step 4, prefabricated frame bridge formation main body:
Prefabricated frame bridge formation main body above the sealing coat of step 3, frame bridge main body is made up of armored concrete, frame bridge main body
Casting concrete at twice, for the first time base plate of pouring frame bridge main body, for the second time pouring frame bridge main body two sides side wall,
Wall is drawn on top board and two sides, and every Orly tie wall of frame bridge main body is all reserved multiple first duct, the plurality of first duct
The most right, the rear side of every Orly tie wall arranges multiple built-in fitting, the position of built-in fitting and the first duct one_to_one corresponding,
Between frame bridge main body and existing aileron, at the concrete crack of frame bridge main body, take measures of preventing water according to construction requirement;
Step 5, the waterproof layer of frame bridge main body and protective layer construction:
Treat that the concrete surface of frame bridge main body prefabricated in step 4 is fully dried, prevent at frame bridge body outer surface
The construction of water layer, after construction of waterproof layer completes, carries out the construction of protective layer outside waterproof layer;
Step 6, retaining wall or friction pile construction:
In the foundation ditch of rail track opposite side, according to topographic features, concrete gravity type retaining wall or armored concrete are set
Reserved multiple second ducts on friction pile, retaining wall or friction pile, multiple second ducts are that two row are arranged, multiple on two row
Multiple first ducts that second duct and two sides are drawn on wall are the most right;
Step 7, horizontal orientation are holed:
Using horizontal directional drilling machine to bore multiple 3rd duct under existing railway circuit, multiple 3rd ducts are that two row are arranged, and two
Multiple 3rd ducts on row are the most right with multiple first ducts that two sides is drawn on wall;
Step 8, penetrate many pulling force rod members:
Pulling force rod member is horizontally disposed with, many pulling force rod members and multiple first duct one_to_one corresponding, one end one of every pulling force rod member
After one passes corresponding first duct, using anchoring piece to be anchored on corresponding built-in fitting, the other end of every pulling force rod member depends on
Secondary through front and corresponding first duct just to the 3rd duct and the second duct after, penetrate horizontal conveyor device;
Step 9, track strengthening:
D type just beam or I-steel is used to lift beam method in length and breadth and existing railway circuit is carried out track strengthening;
Step 10, dilatory frame bridge main body:
Start horizontal conveyor device, many pulling force rod members are synchronized continuously elongated, makes frame bridge main body at pulling force rod member
Pull lower being continuously advanced, along with the advance of frame bridge main body, excavator or loader enter from rear to existing railway circuit direction
Cut the earth in entering frame bridge main body and transport outward, until frame bridge main body is dragged to the design attitude below existing railway circuit;
Step 11, back filling behind abutment:
Infiltration soil or concrete is used to carry out back filling behind abutment, it is ensured that the degree of compaction of backfill is qualified;
Step 12, the soil between retaining wall or friction pile and frame bridge main body is scooped away and transports outward, make frame bridge main body with both
The foundation ditch having rail track both sides connects.
The invention has the beneficial effects as follows:
1, the stayed mast number of packages amount that the present invention uses is about force-transmitting pole and the quantity of distribution beam that jacking uses
10%~20%, save turnover expense about 50%~70%;
2, the frame bridge main body of the present invention is about the 20% of jacking with regard to bit time, and speed of application is fast, improves simultaneously and digs
The service efficiency of soil machinery, saves expense for using mechanical equipment about 60%~80%;
3, the present invention is compared with jacking, it is not necessary to use crane, eliminates the usage charges of crane and coordinates the labour cost of crane;
4, the present invention arranges duct in advance under frame bridge main body, railway line and on retaining wall, and ensure duct position and
Elevation is consistent, ensures that the horizontal level of frame bridge and the accuracy of elevation;
5, the invention enables frame bridge to be continuously advanced, railway bed can be effectively reduced and cave in the front skylight and clerestory caused,
Decrease stablizing of the quantity of backfill soil, beneficially circuit;
6, the present invention is without putting into special equipment, puts into little, and strong operability is applied widely, has the biggest promotion price
Value.
Accompanying drawing explanation
Fig. 1 is the construction schematic diagram of the present invention;
Fig. 2 is the left view of Fig. 1 center bridge formation main body;
Fig. 3 is the front view of the slide plate corresponding with detailed description of the invention five;
Fig. 4 is the enlarged drawing of a-quadrant in Fig. 1.
Detailed description of the invention
Detailed description of the invention one: combine Fig. 1 to Fig. 3 and present embodiment is described, under a kind of existing railway line of present embodiment
Dilatory method is set up the construction method of frame bridge and is comprised the following steps:
Step one, excavation of foundation pit: in the both sides of existing railway circuit 1, take the mode putting slope excavation or supporting excavation to dig base
Hole 2, digs the substrate absolute altitude of design by foundation ditch 2;
Step 2, slide plate are constructed:
Detection foundation bearing capacity, detect qualified after, carry out the construction of slide plate 4, slide plate 4 is made up of armored concrete, first exists
Lay blotter in foundation ditch 2 substrate of rail track wherein side, then carry out colligation or the welding of slide plate reinforcing bar, finally
Casting concrete makes slide plate 4, strictly to control the flatness of slide plate 4 end face during slide plate construction;
Step 3, sealing coat are constructed:
At the end face coated with paraffin layer of slide plate 4, paraffin layer is laid laminated plastics cloth, between every layer of Polypropylence Sheet, uniformly spills Talcum
Powder;
Step 4, prefabricated frame bridge formation main body 3:
Prefabricated frame bridge formation main body 3 above the sealing coat of step 3, frame bridge main body 3 is made up of armored concrete, frame bridge
Main body 3 casting concrete at twice, for the first time the base plate 3-1 of pouring frame bridge main body 3, for the second time pouring frame bridge main body
Two sides side wall 3-2, top board 3-3 and two sides draw wall 3-4, all reserved many on every Orly tie wall 3-4 of frame bridge main body 3
Individual first duct 3-5, the plurality of first duct 3-5 is the most right, and the rear side of every Orly tie wall 3-4 arranges multiple
Built-in fitting, the position of built-in fitting and the first duct 3-5 one_to_one corresponding, between frame bridge main body 3 and existing aileron, frame bridge
Measures of preventing water is taked according to construction requirement at the concrete crack of main body 3;
Step 5, the waterproof layer of frame bridge main body 3 and protective layer construction:
Treat that the concrete surface of frame bridge main body 3 prefabricated in step 4 is fully dried, enter at frame bridge main body 3 outer surface
The construction of row waterproof layer, after construction of waterproof layer completes, carries out the construction of protective layer outside waterproof layer;
Step 6, retaining wall or friction pile 6 are constructed:
In the foundation ditch 2 of rail track opposite side, according to topographic features, concrete gravity type retaining wall or reinforced concrete are set
Soil friction pile, reserved multiple second ducts on retaining wall or friction pile 6, multiple second ducts are that two row are arranged, on two row
Multiple second ducts are the most right with multiple first duct 3-5 that two sides is drawn on wall 3-4;
Step 7, horizontal orientation are holed:
Using horizontal directional drilling machine to bore multiple 3rd ducts 1 time at existing railway circuit, multiple 3rd ducts are that two row are arranged,
Multiple 3rd ducts on two row are the most right with multiple first duct 3-5 that two sides is drawn on wall 3-4;
Step 8, penetrate many pulling force rod members 7:
Pulling force rod member 7 is horizontally disposed with, many pulling force rod members 7 and multiple first duct 3-5 one_to_one corresponding, every pulling force rod member
After one end of 7 passes corresponding first duct 3-5 one by one, anchoring piece is used to be anchored on corresponding built-in fitting, every pulling force
The other end of rod member 7 sequentially pass through front and corresponding first duct 3-5 just to the 3rd duct and the second duct after, penetrate water
Flat actuating device;
Step 9, track strengthening:
D type just beam or I-steel is used to lift beam method in length and breadth and existing railway circuit 1 is carried out track strengthening;
Step 10, dilatory frame bridge main body 3:
Start horizontal conveyor device, many pulling force rod members 7 are synchronized continuously elongated, makes frame bridge main body 3 draw at many
Be continuously advanced to existing railway circuit 1 direction under the pulling of power rod member 7, along with the advance of frame bridge main body 3, excavator or
Loader enters from rear and cuts the earth in frame bridge main body 3 and transport outward, until frame bridge main body 3 is dragged to existing railway circuit
Design attitude below 1;
Step 11, back filling behind abutment:
Infiltration soil or concrete is used to carry out back filling behind abutment, it is ensured that the degree of compaction of backfill is qualified;
Step 12, the soil between retaining wall or friction pile 6 and frame bridge main body 3 scooped away and transports outward, making frame bridge main body
3 connect with the foundation ditch 2 of existing railway circuit 1 both sides.
The flatness of slide plate 4 end face concrete is crossed senior general and is strengthened resistance when frame bridge main body 3 starts, therefore during slide plate construction
Strictly to control the flatness of slide plate 4 end face.
Frame bridge main body 3 is the frame structure front and back connected, and the front opening of frame bridge main body 3 points to existing railway circuit 1,
Every side wall outside vertical of frame bridge main body 3 is connected with the dilatory wall 3-4 of one side, and two sides is drawn wall 3-4 and is arranged on frame bridge
The rear end of main body 3;During prefabricated frame bridge formation main body 3, it should be noted that avoid steel bar end to scratch Polypropylence Sheet;Preventing of frame bridge main body 3
When water layer and protective layer construction, it should be noted that avoid concrete protective layer pad to scratch Polypropylence Sheet.
Pvc pipe can be used on retaining wall or friction pile 6 to reserve multiple second duct, be used for wearing pulling force rod member 7.
During horizontal orientation boring, the diameter in the 3rd duct, quantity are according to the pulling force calculated and the specifications and models meter of pulling force rod member 7
Determine;
During track strengthening, D type just beam basis uses artificial digging pile or the pattern of Extended chemotherapy.
The dilatory of frame bridge main body 3 must be carried out in the train interval on existing railway circuit 1, and track strengthening is not removed
Before, same speed limit is driven a vehicle, and train F-Zero is not to be exceeded 45km/h.
It is ensured that the degree of compaction of backfill is qualified during back filling behind abutment, prevent line sinking.
When frame bridge main body 3 is stowed to when overlapping with frame bridge main body 3 shown in dotted lines in Figure 1, i.e. representational framework bridge master
Body 3 is in place.
Detailed description of the invention two: the excavation of foundation pit in the step one of present embodiment takes excavator operation, digs to higher than design
Substrate absolute altitude 0.3m~0.5m time, use the substrate absolute altitude manually continuing to be excavated to design instead.So excavation, a rate of advance
Hurry up, hand excavation is easy to repair the shape of foundation ditch 2.Other step is identical with detailed description of the invention one.
, there is subsoil water when detecting at foundation ditch 2 in detailed description of the invention three: in the step one of present embodiment before excavation of foundation pit
Time, withdrawal, well-points dewatering or water-stop curtain need to be taked to carry out precipitation.Above dewatering measure will be according to soil property situation and ground
Lower water water level, the water yield, foundation ditch size perform.Other step is identical with detailed description of the invention two.
Detailed description of the invention four: combine Fig. 1 and present embodiment is described, in the step 2 of present embodiment, the bottom of slide plate 4
It is provided with multiple rows of ground anchor beam 5, is often vertically connected with multiple shear reinforcement between row's ground anchor beam 5 and slide plate 4.It is arranged such, can
Ensure that when frame bridge main body 3 starts, slide plate 4 will not move, and meets design and use requirement.Other step be embodied as
Mode one, two or three are identical.
Detailed description of the invention five: combine Fig. 3 and present embodiment is described, the slide plate 4 in the step 2 of present embodiment is to existing
Rail track 1 direction is provided with slope than the upward slope being 5 ‰, is provided with the ship of 2%~4% in the front end k length range of slide plate 4
Head slope, wherein k is 1m.Fore slope refers to: the thickness of slide plate 4 front end is h1, the cunning at distance slide plate 4 front end 1m
Plate thickness be the difference of h2, h2 and h1 be h3, h3/h2=2%~4%.It is so designed that, meets construction requirement.Other step
Rapid identical with detailed description of the invention four.
Detailed description of the invention six: in the step 3 of present embodiment, the thickness of paraffin layer is 2cm, the number of plies of Polypropylence Sheet is 2
Layer.It is so designed that, the resistance in frame bridge main body 3 moving process can be reduced.Other step is identical with detailed description of the invention five.
Detailed description of the invention seven: the waterproof layer in the step 5 of present embodiment is water-repellent paint, protective layer is concrete.Protect
The setting of sheath can prevent frame bridge main body 3 from being destroyed by sandstone under railway line during advancing.Other step is real with concrete
Execute mode five or six identical.
Detailed description of the invention eight: the pulling force rod member 7 in the step 8 of present embodiment is fining twisted steel.Can realize framework
Pulling of bridge main body 3, simultaneously compared with conventional steel strand wires, fining twisted steel intensity is bigger, even and if unexpected fracture,
Also workmen will not be caused personal injury, it is ensured that work progress safe and reliable.Other step and detailed description of the invention
Seven is identical.
Detailed description of the invention nine: every pulling force rod member 7 of present embodiment is by the detachably head and the tail connection of multistage fining twisted steel
Become, a length of 1.5m~2.0m of every section of fining twisted steel.Along with dilatory process, pulling force rod member 7 is constantly from horizontal conveyor
It is drawn out in device, is so designed that, it is simple to along with dilatory process carries out segmentation dismounting to the pulling force rod member having been pulled out, thus
Can reduce the tap length of foundation ditch 2, use manpower and material resources sparingly financial resources.Other step is identical with detailed description of the invention eight.
Detailed description of the invention ten: combine Fig. 4 and present embodiment is described, the horizontal conveyor device in the step 8 of present embodiment
For multiple centre-hole jacks 8, multiple centre-hole jacks about 8, the most just to being arranged on jack stand, each are worn
One end of core type jack 8 acts against on retaining wall or friction pile 6, before the other end of each centre-hole jack 8 acts against
Side leans on plate 9, leans plate 9 the most affixed on the ground, multiple respective entrances of centre-hole jack 8 and multiple the
Two ducts are the most right, and every pulling force rod member 7 is after corresponding second duct passes, then sequentially passes through the punching thousand in front
Jin pushes up 8 and leans plate 9.Start multiple centre-hole jack 8 simultaneously, many pulling force rod members 7 can be synchronized continuous print to
Front stretching, is pulled forward to design attitude by frame bridge main body 3.Other step is identical with detailed description of the invention nine.
Claims (10)
1. under an existing railway line, dilatory method sets up the construction method of frame bridge, it is characterised in that: it comprises the following steps:
Step one, excavation of foundation pit: in the both sides of existing railway circuit (1), take the mode putting slope excavation or supporting excavation to dig
Foundation ditch (2), digs the substrate absolute altitude of design by foundation ditch (2);
Step 2, slide plate are constructed:
Detection foundation bearing capacity, detect qualified after, carry out the construction of slide plate (4), slide plate (4) is made up of armored concrete,
In foundation ditch (2) substrate of rail track wherein side, first lay blotter, then carry out colligation or the welding of slide plate reinforcing bar,
Last casting concrete makes slide plate (4), strictly to control the flatness of slide plate (4) end face during slide plate construction;
Step 3, sealing coat are constructed:
At the end face coated with paraffin layer of slide plate (4), paraffin layer is laid laminated plastics cloth, between every layer of Polypropylence Sheet, uniformly spills cunning
Stone powder;
Step 4, prefabricated frame bridge formation main body (3):
Prefabricated frame bridge formation main body (3) above the sealing coat of step 3, frame bridge main body (3) is made up of armored concrete, frame
Bridge formation main body (3) casting concrete at twice, for the first time base plate (3-1) of pouring frame bridge main body (3), second time is watered
Build the two sides side wall (3-2) of frame bridge main body, top board (3-3) and two sides and draw wall (3-4), frame bridge main body (3) every
All reserving multiple first duct (3-5) on Orly tie wall (3-4), the plurality of first duct (3-5) is the most right,
The rear side of every Orly tie wall (3-4) arranges multiple built-in fitting, the position of built-in fitting and the first duct (3-5) one_to_one corresponding, frame
Between bridge formation main body (3) and existing aileron, at the concrete crack of frame bridge main body (3), take sealing according to construction requirement
Measure;
Step 5, the waterproof layer of frame bridge main body (3) and protective layer construction:
Treat that the concrete surface of frame bridge main body (3) prefabricated in step 4 is fully dried, in frame bridge main body (3) outward
Surface carries out the construction of waterproof layer, after construction of waterproof layer completes, carries out the construction of protective layer outside waterproof layer;
Step 6, retaining wall or friction pile (6) construction:
In the foundation ditch (2) of rail track opposite side, according to topographic features, concrete gravity type retaining wall is set or reinforcing bar mixes
Upper reserved multiple second ducts of solidifying soil friction pile, retaining wall or friction pile (6), multiple second ducts are that two row are arranged, two row
On multiple second ducts the most right with multiple first ducts (3-5) that two sides is drawn on wall (3-4);
Step 7, horizontal orientation are holed:
Using horizontal directional drilling machine to bore multiple 3rd duct under existing railway circuit (1), multiple 3rd ducts are that two row are arranged,
Multiple 3rd ducts on two row are the most right with multiple first ducts (3-5) that two sides is drawn on wall (3-4);
Step 8, penetrate many pulling force rod members (7):
Pulling force rod member (7) is horizontally disposed with, many pulling force rod members (7) and multiple first duct (3-5) one_to_one corresponding, every
After one end of pulling force rod member (7) passes corresponding first duct (3-5) one by one, anchoring piece is used to be anchored at the most pre-buried
On part, the other end of every pulling force rod member (7) sequentially pass through front and corresponding first duct (3-5) just to the 3rd duct
Behind the second duct, penetrate horizontal conveyor device;
Step 9, track strengthening:
D type just beam or I-steel is used to lift beam method in length and breadth and existing railway circuit (1) is carried out track strengthening;
Step 10, dilatory frame bridge main body (3):
Start horizontal conveyor device, many pulling force rod members (7) are synchronized continuously elongated, makes frame bridge main body (3) exist
It is continuously advanced to existing railway circuit (1) direction under the pulling of many pulling force rod members (7), along with frame bridge main body (3)
Advancing, excavator or loader enter from rear and cut the earth in frame bridge main body (3) and transport outward, until frame bridge main body (3)
It is dragged to the design attitude of existing railway circuit (1) lower section;
Step 11, back filling behind abutment:
Infiltration soil or concrete is used to carry out back filling behind abutment, it is ensured that the degree of compaction of backfill is qualified;
Step 12, the soil between retaining wall or friction pile (6) and frame bridge main body (3) scooped away and transports outward, making framework
Bridge main body (3) connects with the foundation ditch (2) of existing railway circuit (1) both sides.
Under a kind of existing railway line the most according to claim 1, dilatory method sets up the construction method of frame bridge, and its feature exists
In: the excavation of foundation pit in step one takes excavator operation, digs to during higher than the substrate absolute altitude 0.3m~0.5m designed, uses instead
Manually continue to be excavated to the substrate absolute altitude of design.
Under a kind of existing railway line the most according to claim 2, dilatory method sets up the construction method of frame bridge, and its feature exists
In: in step one before excavation of foundation pit, when detecting that foundation ditch (2) place exists subsoil water, withdrawal, well point fall need to be taked
Water or water-stop curtain carry out precipitation.
4. the construction method of frame bridge is set up according to method dilatory under a kind of existing railway line described in claim 1,2 or 3,
It is characterized in that: in step 2, the bottom of slide plate (4) is provided with multiple rows of ground anchor beam (5), often row ground anchor beam (5) and slide plate
(4) multiple shear reinforcement vertically it is connected with between.
Under a kind of existing railway line the most according to claim 4, dilatory method sets up the construction method of frame bridge, and its feature exists
In: the slide plate (4) in step 2 is provided with slope to existing railway circuit (1) direction than the upward slope being 5 ‰, slide plate (4)
Being provided with the fore slope of 2%~4% in the k length range of front end, wherein k is 1m.
Under a kind of existing railway line the most according to claim 5, dilatory method sets up the construction method of frame bridge, and its feature exists
In: in step 3, the thickness of paraffin layer is 2cm, and the number of plies of Polypropylence Sheet is 2 layers.
7. set up the construction method of frame bridge according to method dilatory under a kind of existing railway line described in claim 5 or 6, it is special
Levying and be: the waterproof layer in step 5 is water-repellent paint, protective layer is concrete.
Under a kind of existing railway line the most according to claim 7, dilatory method sets up the construction method of frame bridge, and its feature exists
In: the pulling force rod member (7) in step 8 is fining twisted steel.
Under a kind of existing railway line the most according to claim 8, dilatory method sets up the construction method of frame bridge, and its feature exists
In: every pulling force rod member (7) is formed by connecting by multistage fining twisted steel detachably head and the tail, every section of fining twisted steel a length of
1.5m~2.0m.
Under a kind of existing railway line the most according to claim 9, dilatory method sets up the construction method of frame bridge, its feature
Being: the horizontal conveyor device in step 8 is multiple centre-hole jack (8), multiple centre-hole jacks (8) go up next
One just to being arranged on jack stand, and one end of each centre-hole jack (8) acts against retaining wall or friction pile (6)
On, the other end of each centre-hole jack (8) acts against the leaning on plate (9) of front, leans plate (9) the most affixed
On the ground, multiple centre-hole jacks (8) respective entrance is the most right with multiple second ducts, every pulling force rod member (7)
After corresponding second duct passes, then sequentially pass through the centre-hole jack (8) in front and lean plate (9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610227511.6A CN105908625B (en) | 2016-04-13 | 2016-04-13 | The construction method that method adds frame bridge is drawn under a kind of existing railway line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610227511.6A CN105908625B (en) | 2016-04-13 | 2016-04-13 | The construction method that method adds frame bridge is drawn under a kind of existing railway line |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105908625A true CN105908625A (en) | 2016-08-31 |
CN105908625B CN105908625B (en) | 2018-04-17 |
Family
ID=56745923
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610227511.6A Active CN105908625B (en) | 2016-04-13 | 2016-04-13 | The construction method that method adds frame bridge is drawn under a kind of existing railway line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105908625B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587515A (en) * | 2017-09-19 | 2018-01-16 | 辽宁工程技术大学 | A kind of across railway line bridge bearing platform foundation construction method |
CN108611985A (en) * | 2018-06-22 | 2018-10-02 | 中铁六局集团天津铁路建设有限公司 | Framed underpass bridge construction method that special geology is overweight |
CN108930226A (en) * | 2018-08-20 | 2018-12-04 | 中铁六局集团天津铁路建设有限公司 | The construction method of jacked frame bridge upper box in the way of spreading slide plate |
CN109706848A (en) * | 2018-12-26 | 2019-05-03 | 中铁十局集团第一工程有限公司 | A kind of construction method using centre-hole jack jacking bridge and culvert |
CN109944167A (en) * | 2019-03-19 | 2019-06-28 | 中建一局集团建设发展有限公司 | A kind of interim sliding supporting structure and its construction method of the jacking of large span lower frame |
CN110055896A (en) * | 2019-04-22 | 2019-07-26 | 同济大学 | A kind of just beam discharging method when boring across underneath high-speed railway road-bridge transition section |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111764286B (en) * | 2020-06-16 | 2021-04-02 | 中铁二十四局集团有限公司 | Frame bridge jacking construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6857156B1 (en) * | 2000-04-05 | 2005-02-22 | Stanley J. Grossman | Modular bridge structure construction and repair system |
CN101736692A (en) * | 2008-11-20 | 2010-06-16 | 中铁十六局集团有限公司 | Construction technology for passenger railway line spanning existing railway cast-in-place box beam bracket |
CN101845793A (en) * | 2009-12-23 | 2010-09-29 | 中铁大桥局集团第一工程有限公司 | Construction method of small-angle skew multi-span portal frame pier cast-in-situ beam for crossing highway or railway line |
CN102808381A (en) * | 2012-08-21 | 2012-12-05 | 中铁十局集团有限公司 | High-water-level silty-soil underneath-pass multi-track railway frame bridge jacking and butting construction method |
CN103643640A (en) * | 2013-12-19 | 2014-03-19 | 中铁六局集团天津铁路建设有限公司 | Jacking-first and line-reinforcement-second jacking construction method for frame bridge |
-
2016
- 2016-04-13 CN CN201610227511.6A patent/CN105908625B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6857156B1 (en) * | 2000-04-05 | 2005-02-22 | Stanley J. Grossman | Modular bridge structure construction and repair system |
CN101736692A (en) * | 2008-11-20 | 2010-06-16 | 中铁十六局集团有限公司 | Construction technology for passenger railway line spanning existing railway cast-in-place box beam bracket |
CN101845793A (en) * | 2009-12-23 | 2010-09-29 | 中铁大桥局集团第一工程有限公司 | Construction method of small-angle skew multi-span portal frame pier cast-in-situ beam for crossing highway or railway line |
CN102808381A (en) * | 2012-08-21 | 2012-12-05 | 中铁十局集团有限公司 | High-water-level silty-soil underneath-pass multi-track railway frame bridge jacking and butting construction method |
CN103643640A (en) * | 2013-12-19 | 2014-03-19 | 中铁六局集团天津铁路建设有限公司 | Jacking-first and line-reinforcement-second jacking construction method for frame bridge |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107587515A (en) * | 2017-09-19 | 2018-01-16 | 辽宁工程技术大学 | A kind of across railway line bridge bearing platform foundation construction method |
CN108611985A (en) * | 2018-06-22 | 2018-10-02 | 中铁六局集团天津铁路建设有限公司 | Framed underpass bridge construction method that special geology is overweight |
CN108611985B (en) * | 2018-06-22 | 2019-07-30 | 中铁六局集团天津铁路建设有限公司 | Framed underpass bridge construction method that special geology is overweight |
CN108930226A (en) * | 2018-08-20 | 2018-12-04 | 中铁六局集团天津铁路建设有限公司 | The construction method of jacked frame bridge upper box in the way of spreading slide plate |
CN109706848A (en) * | 2018-12-26 | 2019-05-03 | 中铁十局集团第一工程有限公司 | A kind of construction method using centre-hole jack jacking bridge and culvert |
CN109944167A (en) * | 2019-03-19 | 2019-06-28 | 中建一局集团建设发展有限公司 | A kind of interim sliding supporting structure and its construction method of the jacking of large span lower frame |
CN110055896A (en) * | 2019-04-22 | 2019-07-26 | 同济大学 | A kind of just beam discharging method when boring across underneath high-speed railway road-bridge transition section |
CN110055896B (en) * | 2019-04-22 | 2021-02-26 | 同济大学 | Temporary beam unloading method during underpass of high-speed railway road and bridge transition section |
Also Published As
Publication number | Publication date |
---|---|
CN105908625B (en) | 2018-04-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105908625A (en) | Construction method for adding frame bridge under existing railway line based on dragging method | |
CN104533446B (en) | Construction method and its structure that a kind of big cross section Support System in Soft Rock Tunnels bilayer pre- Geological disaster prevention of preliminary bracing occurs | |
CN108442382B (en) | In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method | |
CN104612162A (en) | Subway station deep foundation pit excavation construction method | |
CN103452561B (en) | Vertical in-tunnel construction method of multilayer transverse channel of underground excavation station of metro, and construction method on east side and west side | |
CN105274922B (en) | A kind of antiskid key steel-pipe pile composite construction and method for repairing landslide roadbed | |
CN108547639B (en) | Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings | |
CN103696784B (en) | Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure | |
CN102305075A (en) | Vertical shaft construction method under unfavorable geological condition | |
CN107130613A (en) | Large span tunnel is just wearing the retaining structure and its construction method of existing barricade | |
CN102979039B (en) | Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream | |
CN102953341A (en) | Overhead trestle structure built on non-covering steep bare rocks in deep rapids | |
CN106869969A (en) | A kind of excavation supporting construction method of soft rock large section tunnel | |
CN106522235A (en) | Narrow site deep foundation pit excavation supporting construction method | |
CN110359540A (en) | A kind of shallow earthing Large Diameter Pipeline high water level wears the artificial jacking construction engineering method of existing road | |
CN100513705C (en) | Underground Beam-Pile Frame Structure for Slope Reinforcement | |
CN109898521A (en) | A kind of anchored pile supporting and construction method for foundation pit external corner | |
CN109706945A (en) | Come down fracture belt tunnel construction method | |
CN206888990U (en) | A kind of Shallow Covered Metro Station separates open type structure | |
CN210263062U (en) | Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom | |
CN103174131A (en) | Underground engineering guiding-cavity-excavating small-diameter pile construction complete equipment system | |
CN101994314A (en) | Longhole rectangular terraced antiskid pile jump-preventing excavating construction | |
CN107587511B (en) | For preventing and administering the long-short pile ruggedized construction and reinforcement means of foundation pit bottom heave | |
CN210263075U (en) | Arrange bars formula tubular pile post back slip casting internal anchor outer stagnant water support system | |
CN105239573B (en) | The interplantation tube anchor rock construction method of shaped steel trestle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |