CN107587515A - A kind of across railway line bridge bearing platform foundation construction method - Google Patents

A kind of across railway line bridge bearing platform foundation construction method Download PDF

Info

Publication number
CN107587515A
CN107587515A CN201710844914.XA CN201710844914A CN107587515A CN 107587515 A CN107587515 A CN 107587515A CN 201710844914 A CN201710844914 A CN 201710844914A CN 107587515 A CN107587515 A CN 107587515A
Authority
CN
China
Prior art keywords
railway
steel sheet
steel
sheet pile
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710844914.XA
Other languages
Chinese (zh)
Other versions
CN107587515B (en
Inventor
李永靖
张淑坤
王树达
张鸿达
马启郁
高迎松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Technical University
Original Assignee
Liaoning Technical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Technical University filed Critical Liaoning Technical University
Priority to CN201710844914.XA priority Critical patent/CN107587515B/en
Publication of CN107587515A publication Critical patent/CN107587515A/en
Application granted granted Critical
Publication of CN107587515B publication Critical patent/CN107587515B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

一种跨铁路线桥梁承台基础施工方法,在承台基坑开挖前先构筑铁路路基防护结构,路基防护结构包括一组沿铁路线方向插入路基一侧地面中的地锚和一组插入路基另一侧地面中的钢板桩;钢板桩外露端由槽钢连成一体;对拉钢筋一端与地锚焊接,另一端沿铁路碎石道床面穿过铁路钢轨底部,按公式计算的张拉力张拉锚固在槽钢上;根据承台基坑挖掘过程中地锚焊接点、槽钢锚固点、钢板桩顶端水平位移及铁路钢轨标高监测结果调整基坑开挖方式;完成桥梁基础构筑后拆除路基防护结构。该施工方法可使路基稳定性不受桥梁基础施工影响;对拉钢筋按限定的张拉力张拉可达到最佳保护效果;防护结构施工工艺简单,钢板桩、对拉钢筋和钢垫板可重复利用,工程造价低。

A construction method for the cap foundation of a bridge spanning a railway line. Before excavating the foundation pit of the cap platform, a railway embankment protection structure is first constructed. The steel sheet piles in the ground on the other side of the subgrade; the exposed ends of the steel sheet piles are integrated by channel steel; one end of the tension steel bar is welded to the ground anchor, and the other end passes through the bottom of the railway rail along the gravel bed of the railway, and the tensile force calculated according to the formula Tension and anchoring on the channel steel; adjust the excavation method of the foundation pit according to the ground anchor welding point, channel steel anchor point, horizontal displacement of the top of the steel sheet pile and the monitoring results of the railway rail elevation during the excavation of the foundation pit of the cap; Roadbed protection structure. This construction method can make the stability of the subgrade unaffected by the construction of the bridge foundation; stretching the tensioned steel bars according to the limited tension can achieve the best protection effect; the construction process of the protective structure is simple, and the steel sheet piles, the tensioned steel bars and the steel backing plate can be repeated Utilization, the engineering cost is low.

Description

一种跨铁路线桥梁承台基础施工方法A construction method for the foundation of a bridge spanning a railway line

技术领域technical field

本发明涉及铁路路基防护和桥梁基础施工,具体为跨铁路线桥梁承台基础施工时先构筑铁路路基防护结构、然后进行基坑挖掘的桥梁承台基础施工方法。The invention relates to railway subgrade protection and bridge foundation construction, in particular to a bridge cap foundation construction method in which a railway subgrade protection structure is constructed first and then foundation pits are excavated during bridge cap foundation construction across railway lines.

背景技术Background technique

跨铁路线桥梁承台基础施工中,临近铁路线桥梁承台基坑开挖会影响到铁路路基的稳定性。基于铁路线对于路基的变形要求非常严格,为保证承台基坑开挖施工中铁路路基变形在容许范围内,必须对铁路路基进行必要的主动防护。目前的路基防护常采用挡土墙或抗滑桩等措施。但单一的挡土墙或抗滑桩不能施加主动的防护力,难以抑制基坑开挖施工对铁路路基的影响,极易导致路基变形超限。增加了预应力的锚杆(索)挡土墙或抗滑桩虽然可以减轻基坑开挖施工对路基的影响程度,但设置过长的锚杆(索)施工本身会对铁路线会造成一定程度的破坏,且先开挖后防护预应力损失过大,防护效果不好,此外,该方法还存在施工工艺复杂、施工工程量大和造价高的问题。During the construction of the bridge cap foundation across the railway line, the excavation of the foundation pit of the bridge cap adjacent to the railway line will affect the stability of the railway subgrade. Based on the strict requirements on the deformation of the subgrade by the railway line, in order to ensure that the deformation of the railway subgrade is within the allowable range during the excavation of the foundation pit of the cap platform, necessary active protection must be carried out on the railway subgrade. At present, measures such as retaining walls or anti-slide piles are often used for roadbed protection. However, a single retaining wall or anti-slide pile cannot exert active protective force, and it is difficult to restrain the impact of foundation pit excavation on the railway subgrade, which can easily lead to subgrade deformation exceeding the limit. Although the prestressed anchor (cable) retaining wall or anti-slide pile can reduce the impact of foundation pit excavation on the subgrade, the construction of too long anchor (cable) itself will cause certain damage to the railway line. degree of damage, and the loss of protective prestress after excavation is too large, and the protective effect is not good. In addition, this method also has the problems of complicated construction technology, large construction work volume and high cost.

发明内容Contents of the invention

针对上述现有技术存在的问题,本发明的目的是提供一种可有效保护铁路路基稳定性不受承台基坑施工影响、且施工工艺比较简单、施工工程量较小、工程造价较低和材料可循环利用的跨铁路线桥梁承台基础施工方法。Aiming at the problems existing in the above-mentioned prior art, the object of the present invention is to provide a method that can effectively protect the stability of the railway embankment from being affected by the construction of the cap foundation pit, and the construction process is relatively simple, the construction quantity is small, and the construction cost is low and The invention relates to a construction method for the cap foundation of a bridge spanning a railway line with recyclable materials.

本发明提供的跨铁路线桥梁承台基坑施工方法,包括以下步骤:The method for constructing foundation pits of bridge caps across railway lines provided by the invention comprises the following steps:

步骤1、构筑路基防护结构Step 1. Build roadbed protection structure

在承台基坑开挖前先对桥梁跨越的铁路路基构筑路基防护结构,该路基防护结构包括一组沿铁路线方向插入铁路路基一侧地面中的地锚和一组插入铁路路基另一侧地面中的钢板桩(地锚和钢板桩的数量根据承台基坑沿铁路线方向的长度确定);所述地锚横向分别对应相邻铁路轨枕之间;所述钢板桩由与钢板桩外露端焊接的槽钢连成一体;地锚与槽钢通过对拉钢筋以以下方式相互连接:Before the excavation of the foundation pit of the cap platform, the subgrade protection structure is constructed for the railway subgrade spanned by the bridge. Steel sheet piles in the ground (the number of ground anchors and steel sheet piles is determined according to the length of the cap foundation pit along the direction of the railway line); the horizontal direction of the ground anchors corresponds to between adjacent railway sleepers; The channel steel welded at the end is integrated; the ground anchor and the channel steel are connected to each other through the tension reinforcement in the following way:

对拉钢筋沿铁路碎石道床的上表面从铁路轨枕之间的铁路钢轨底部穿过,对拉钢筋与铁路碎石道床上表面之间有宽度与相邻铁路轨枕的间距相同的钢垫板,对拉钢筋的一端与地锚的外露端焊接,对拉钢筋的另一端按下式计算出的张拉力F张拉后锚固在槽钢上:The opposite-tensioned steel bars pass through the bottom of the railway rail between the railway sleepers along the upper surface of the railway crushed stone bed, and there is a steel backing plate with the same width as the distance between the adjacent railway sleepers between the opposite-drawn steel bars and the surface of the railway crushed stone bed. One end of the tensioned steel bar is welded to the exposed end of the ground anchor, and the other end of the tensioned steel bar is anchored on the channel steel after stretching with the tension F calculated by the following formula:

式中:In the formula:

Eak—桥梁承台基坑外侧主动土压力合力标准值(kN/m),E ak —Standard value of resultant force of active earth pressure outside the foundation pit of bridge cap (kN/m),

Epk—桥梁承台基坑内侧被动土压力合力标准值(kN/m),E pk —Standard value of resultant force of passive earth pressure inside the foundation pit of bridge cap (kN/m),

Za—桥梁承台基坑外侧主动土压力合力到钢板桩下端的距离(m),Z a — the distance from the resultant force of active earth pressure outside the foundation pit of the bridge cap to the lower end of the steel sheet pile (m),

Zp—桥梁承台基坑内侧被动土压力合力到钢板桩下端的距离(m),Z p — the distance from the resultant force of passive earth pressure inside the foundation pit of the bridge cap to the lower end of the steel sheet pile (m),

e—对拉钢筋锚固点到钢板桩下端的距离(m),e—the distance from the anchor point of the tensioned reinforcement to the lower end of the steel sheet pile (m),

m—桥梁承台基坑内撑数量,m—the number of braces in the foundation pit of the bridge cap,

n—沿铁路线每延米对拉钢筋的根数(与地锚数量相同);n—the number of tensioned steel bars per linear meter along the railway line (same as the number of ground anchors);

构筑该路基防护结构时,先清理铁路路基两侧地面的表层土,按施工图设计通过放线定位确定钢板桩的位置;利用打桩机在铁路路基一侧沿铁路线走向按设定间隔和标高插打钢板桩,在钢板桩的外露端横向焊接槽钢,将各钢板桩连成一体,槽钢对应地锚位置布设预留孔;然后在铁路路基另一侧钻孔、注浆布设地锚;将对拉钢筋沿铁路碎石道床的表面从铁路轨枕之间的铁路钢轨底部穿过,并在对拉钢筋与铁路碎石道床上表面之间铺设所述钢垫板;将对拉钢筋的一端与地锚焊接;将对拉钢筋的另一端按所述计算公式计算得出的张拉力张拉,并通过所述预留孔将其锚固在槽钢上;When constructing the protective structure of the roadbed, the surface soil on the ground on both sides of the railway roadbed should be cleaned first, and the position of the steel sheet piles should be determined by laying out positioning according to the design of the construction drawing; Insert and drive steel sheet piles, weld the channel steel horizontally at the exposed end of the steel sheet piles, connect the steel sheet piles into one, and lay out reserved holes corresponding to the ground anchor positions of the channel steel; then drill holes and grout the ground anchors on the other side of the railway subgrade ; Pass the opposite tension reinforcement along the surface of the railway gravel track bed from the bottom of the railway rail between the railway sleepers, and lay the steel backing plate between the opposite tension reinforcement and the surface of the railway gravel track bed; One end is welded with the ground anchor; the other end of the tensioned steel bar is stretched according to the tension calculated by the calculation formula, and anchored to the channel steel through the reserved hole;

当桥梁跨越的铁路线为电气化铁路时,需在所述路基防护结构中的对拉钢筋外部套橡胶管,使钢筋与铁路钢轨绝缘;When the railway line spanned by the bridge is an electrified railway, rubber tubes need to be placed on the outside of the tension reinforcement in the subgrade protection structure to insulate the reinforcement from the railway rail;

步骤2、挖掘桥梁承台基坑Step 2. Excavate the foundation pit of the bridge cap

完成上述路基防护结构构筑施工后进行桥梁承台基坑挖掘:桥梁承台基坑开挖由远离铁路线侧开始,逐渐向铁路路基推进,采取分段分层开挖,并在每一层开挖完毕后对应设置内撑;挖掘过程中实时观察地锚焊接点、槽钢锚固点及垫板有无扭曲变形或破裂,并以每天一次的监测频率测量钢板桩的顶端水平位移及铁路钢轨的标高;当地锚焊接点、槽钢锚固点发生破裂时必须暂停施工,对焊点和锚固点进行补焊和加固,当钢板桩的顶端水平位移达到0.002倍基坑深度警戒值或钢轨竖向位移累计达到4mm警戒值时,必须立即停止开挖并将已开挖的基坑回填夯实,然后修正铁路碎石道床,矫正铁路轨道几何型位,使铁路钢轨回复原状;然后对铁路路基防护结构用加密对拉钢筋的方法(相应增加地锚的数量)提高其防护性能;采取分区块减小每层开挖厚度并及时增设内撑的方法重新对桥梁承台基坑进行开挖和监测,直至完成整个桥梁承台基坑的挖掘,最后在承台基坑内设置基坑内撑;Excavation of the foundation pit of the bridge cap is carried out after the construction of the above roadbed protection structure is completed: the excavation of the foundation pit of the bridge cap starts from the side away from the railway line, and gradually advances towards the railway embankment. After the excavation is completed, set up the corresponding internal support; during the excavation process, observe in real time whether the ground anchor welding point, the channel steel anchor point and the backing plate are distorted, deformed or broken, and measure the horizontal displacement of the top of the steel sheet pile and the position of the railway rail at a monitoring frequency of once a day. Elevation; when the local anchor welding points and channel steel anchor points break, the construction must be suspended, and the welding and anchor points should be repaired and reinforced. When the horizontal displacement of the top of the steel sheet pile reaches 0.002 times the warning value of the depth of the foundation pit or the vertical displacement of the rail When the accumulative warning value of 4mm is reached, the excavation must be stopped immediately and the excavated foundation pit shall be backfilled and compacted, and then the gravel bed of the railway shall be corrected, the geometric shape of the railway track shall be corrected, and the railway rail shall return to its original state; then the protective structure of the railway subgrade shall be used The method of enlarging the tensioned steel bars (correspondingly increasing the number of ground anchors) improves its protective performance; adopting the method of reducing the excavation thickness of each layer in blocks and adding internal supports in time to excavate and monitor the foundation pit of the bridge cap until Complete the excavation of the foundation pit of the entire bridge cap, and finally set the inner support of the foundation pit in the foundation pit of the cap;

步骤3、构筑桥梁基础Step 3. Build the bridge foundation

完成桥梁承台基坑挖掘后,按照常规方法进行桥梁承台、墩身及回填土施工,完成桥梁基础构筑;After the excavation of the foundation pit of the bridge cap is completed, the bridge cap, pier body and backfilling shall be carried out according to the conventional method to complete the construction of the bridge foundation;

步骤4:拆除路基防护结构Step 4: Remove roadbed protective structure

完成桥梁基础构筑后,切断与槽钢锚固的对拉钢筋,焊割拆除钢梁;采用振动锤振动钢板桩,同时利用起重机吊力将钢板桩拔出,修整钢板桩以备再利用,然后回填钢板桩桩孔并用振动锤夯实;再用钢锯沿地面锯断地锚外露端(插入地面中的地锚可不必拔出),避免其影响正常生产和生活;将对拉钢筋从钢轨底部抽出,将钢垫板移出,完成拆除路基防护结构。After completing the construction of the bridge foundation, cut off the opposite tension reinforcement anchored with the channel steel, weld and cut to remove the steel beam; use a vibrating hammer to vibrate the steel sheet pile, and use the lifting force of a crane to pull out the steel sheet pile, trim the steel sheet pile for reuse, and then backfill The pile hole of the steel sheet pile is compacted with a vibrating hammer; then the exposed end of the ground anchor is sawed off along the ground with a hacksaw (the ground anchor inserted into the ground does not need to be pulled out), so as to avoid it affecting normal production and life; pull out the opposite tension steel bar from the bottom of the rail , remove the steel backing plate to complete the dismantling of the subgrade protective structure.

与现有技术相比,本发明的优点是:Compared with prior art, the advantage of the present invention is:

1、本发明中的路基防护结构,是在桥梁承台基坑开挖之前通过对拉钢筋预应力对铁路路基进行预先主动防护,该防护结构设计原理基于基坑开挖施工中开挖卸荷应力重新分布规律,维护路基针对性强,效果好。按照本发明方法进行桥梁基础施工,可使铁路路基的稳定性基本不受桥梁基础施工影响。1. The subgrade protection structure in the present invention is to actively protect the railway subgrade in advance by prestressing the tensioned steel bars before excavating the foundation pit of the bridge cap. The design principle of the protection structure is based on the excavation and unloading during the excavation of the foundation pit Stress redistribution is regular, and the maintenance of subgrade is highly targeted and effective. The bridge foundation construction is carried out according to the method of the invention, so that the stability of the railway embankment is basically not affected by the bridge foundation construction.

2、本发明路基防护结构中的对拉钢筋按照限定的张拉力计算公式进行张拉,可使路基防护结构对路基达到最佳保护效果:既不会因张拉力太小达不到有效防护路基的作用;又不会因张拉力过大对路基原有结构造成损伤。2. The anti-stretching steel bars in the roadbed protection structure of the present invention are stretched according to the limited tension calculation formula, so that the roadbed protection structure can achieve the best protection effect on the roadbed: neither can the effective protection of the roadbed be achieved because the tension force is too small The role; and will not cause damage to the original structure of the subgrade due to excessive tension.

3、本发明中的路基防护结构及其施工工艺简单,工程造价显著降低。3. The roadbed protection structure and its construction technology in the present invention are simple, and the engineering cost is significantly reduced.

4、本发明中的钢板桩、对拉钢筋和钢垫板在桥梁基础施工回填完成后可以回收重复利用,节省材料。4. The steel sheet piles, anti-tension steel bars and steel backing plates in the present invention can be recycled and reused after the backfilling of the bridge foundation construction is completed, saving materials.

附图说明Description of drawings

图1为本发明中路基防护结构及桥梁承台基坑的示意图(横断面图);Fig. 1 is the schematic diagram (cross-sectional view) of subgrade protection structure and bridge cap foundation pit among the present invention;

图2为图1的俯视图;Fig. 2 is the top view of Fig. 1;

图3为图2的A-A剖面图;Fig. 3 is the A-A sectional view of Fig. 2;

图4为图2的B-B剖面图;Fig. 4 is the B-B sectional view of Fig. 2;

图5为图2的C-C剖面图。Fig. 5 is a C-C sectional view of Fig. 2 .

图中:1-钢板桩,2-对拉钢筋,3-橡胶管,4-铁路钢轨,5-铁路轨枕,6-铁路碎石道床,7-铁路路基,8-地锚,9-地面。10-槽钢,11-钢垫板,12-承台基坑,13-基坑内撑,14-腰梁,15-顶靠桩。In the figure: 1-steel sheet pile, 2-tie steel bar, 3-rubber tube, 4-railway rail, 5-railway sleeper, 6-railway gravel bed, 7-railway subgrade, 8-ground anchor, 9-ground. 10-channel steel, 11-steel backing plate, 12-cap foundation pit, 13-support inside the foundation pit, 14-waist beam, 15-top pile.

具体实施方式detailed description

以下结合附图和实施例对本发明做进一步说明。The present invention will be further described below in conjunction with drawings and embodiments.

本实施例为跨越电气化铁路线的某桥梁基础施工。This embodiment is the foundation construction of a certain bridge across the electrified railway line.

该桥梁的承台基坑12沿铁路线方向长15m,横向宽11m,开挖深度6m,距离铁路路基基坡脚5m。基坑开挖深度5m,主要以粉质粘土、细砂为主,5m以下以砂砾石土为主。The cap foundation pit 12 of the bridge is 15m long along the railway line direction, 11m wide laterally, and has an excavation depth of 6m, and is 5m away from the slope foot of the railway embankment. The excavation depth of the foundation pit is 5m, mainly composed of silty clay and fine sand, and below 5m mainly composed of sandy gravel.

基坑外侧主动土压力合力标准值Eak=454.25kN/m,基坑内侧被动土压力合力标准值Epk=883kN/m(两项标准值是根据土的重度、粘聚力及内摩擦角等参数,利用主动土压力计算公式求出主动土压力强度及分布后求得)。基坑外侧主动土压力合力到钢板桩下端距离Za=3.83m,基坑内侧被动土压力合力到钢板桩下端距离Zp=2.15m,桥梁承台基坑内撑数量m=1。The standard value of the resultant force of active earth pressure on the outside of the foundation pit is E ak454.25kN /m, and the standard value of the resultant force of passive earth pressure on the inside of the foundation pit is Epk=883kN/m (the two standard values are based on the weight, cohesion and internal friction angle of the soil and other parameters, obtained after calculating the active earth pressure intensity and distribution using the active earth pressure calculation formula). The distance from the resultant active earth pressure outside the foundation pit to the lower end of the steel sheet pile is Z a =3.83m, the distance from the resultant passive earth pressure inside the foundation pit to the lower end of the steel sheet pile is Z p =2.15m, and the number of braces in the foundation pit of the bridge cap is m=1.

为确保铁路路基稳定性不受该跨铁路线桥梁基础施工影响,该桥梁基础施工按以下步骤进行:In order to ensure that the stability of the railway embankment is not affected by the bridge foundation construction across the railway line, the bridge foundation construction is carried out according to the following steps:

步骤1、在桥梁的承台基坑开挖之前先进行铁路路基防护结构构筑Step 1. Construction of the railway subgrade protection structure before excavation of the foundation pit of the bridge cap

结合图1至图5,利用打桩机在铁路路基7一侧的地面9上沿铁路线方向相互间隔1000mm竖直打插由1根直径φ30-40mm、长度10m的钢筋构成的地锚8(如图3所示),共16根,地锚横向分别与相邻铁路轨枕5之间相对应,其上端外露0.5m。在铁路路基7的另一侧地面上沿铁路线方向以每延米2.5根的密度打插38根长度为12m、宽度为500mm、厚度为200mm的钢板桩1,钢板桩上端外露0.5m。距离钢板桩的顶端0.4m横向焊接槽钢10,将钢板桩连成一体,槽钢的尺寸(腰高×腿宽×腰厚)为120mm×53mm×5mm,槽钢对应地锚位置布设预留孔(未图示)。地锚通过φ10mm对拉钢筋2与槽钢相互连接,对拉钢筋沿铁路线每延米根数n=1,对拉钢筋锚固点距离钢板桩下端距离e=11.6m,在对拉钢筋与铁路碎石道床6贴靠的中间段外部套内径φ12mm、外径φ16mm的橡胶管3(如图5所示),且使橡胶管两端与铁路钢轨的距离在1m以上(如图1、2所示),以确保对拉钢筋与铁路钢轨绝缘。使对拉钢筋沿铁路碎石道床6的表面从铁路轨枕5之间的铁路钢轨4底部穿过,并在对拉钢筋与铁路碎石道床上表面之间铺设宽度与相邻铁路轨枕的间距相同、厚度为10mm的钢垫板11。In conjunction with Fig. 1 to Fig. 5, utilize pile driver on the ground 9 on one side of railway subgrade 7 and vertically drive and insert the ground anchor 8 that is made of a steel bar with a diameter of φ30-40mm and a length of 10m along the direction of the railway line at intervals of 1000mm (such as Shown in Figure 3), there are 16 in total, and the ground anchor horizontally corresponds to the adjacent railway sleeper 5 respectively, and its upper end exposes 0.5m. Insert 38 steel sheet piles 1 with a length of 12m, a width of 500mm, and a thickness of 200mm along the direction of the railway line at a density of 2.5 per linear meter on the ground on the other side of the railway subgrade 7, with 0.5m exposed at the upper end of the steel sheet piles. Weld channel steel 10 horizontally from the top of the steel sheet pile 0.4m to connect the steel sheet piles together. The size of the channel steel (waist height×leg width×waist thickness) is 120mm×53mm×5mm, and the channel steel is equipped with reserved holes corresponding to the ground anchor position (not shown). The ground anchor is connected to the channel steel through the φ10mm anti-tension steel bar 2. The number of anti-tension steel bars along the railway line is n=1, and the distance between the anchor point of the anti-tension steel bar and the lower end of the steel sheet pile is e=11.6m. The middle section of the crushed stone track bed 6 is covered with a rubber tube 3 with an inner diameter of φ12mm and an outer diameter of φ16mm (as shown in Figure 5), and the distance between the two ends of the rubber tube and the railway rail is more than 1m (as shown in Figures 1 and 2). shown) to ensure that the tension reinforcement is insulated from the railway rails. Make the opposite-tensioned steel bars pass through the bottom of the railway rail 4 between the railway sleepers 5 along the surface of the railway crushed stone bed 6, and lay the same distance between the opposite-drawn steel bars and the surface of the railway crushed stone bed with the same spacing as the adjacent railway sleepers 1. A steel backing plate 11 with a thickness of 10mm.

然后将对拉钢筋的一端与地锚的外露端焊接,另一端以张拉力Then weld one end of the tension steel bar to the exposed end of the ground anchor, and the other end is tensioned

张拉后锚固在槽钢10上,并加以锁定,完成路基防护结构构筑施工。After being stretched, it is anchored on the channel steel 10 and locked to complete the construction of the subgrade protection structure.

步骤2、完成路基防护结构构筑施工后进行桥梁承台基坑挖掘施工Step 2. Excavate the foundation pit of the bridge cap after completing the construction of the roadbed protection structure

基坑开挖由远离铁路路基侧开始,逐渐向铁路路基推进,前后分3段、每段上下分2层开挖;挖掘过程中,随时观察地锚焊接点、槽钢锚固点有无扭曲变形及裂缝,并以每天一次的监测频率测量钢板桩的顶端水平位移及铁路钢轨的标高。施工过程中经实际监测,地锚焊接点、槽钢锚固点均无破裂,钢轨累计竖向位移2.5mm,满足继续开挖条件,直至达到开挖标高,在基坑远离路基的一侧对应钢板桩1设置与钢板桩相同的顶靠桩15,在距离钢板桩顶端4m处水平位置横向设置数量m=1、由直径650mm钢管构成的桥梁承台基坑内撑13,基坑内撑的两端分别通过由350*350mm H型钢构成的腰梁14顶靠在钢板桩和顶靠桩上。The excavation of the foundation pit starts from the side away from the railway embankment, and gradually advances towards the railway embankment. It is divided into 3 sections, and each section is divided into 2 layers. During the excavation process, observe whether the ground anchor welding points and channel steel anchor points are twisted or deformed. and cracks, and measure the horizontal displacement of the top of the steel sheet pile and the elevation of the railway rail with a monitoring frequency of once a day. According to the actual monitoring during the construction process, the ground anchor welding point and the channel steel anchor point have no cracks, and the cumulative vertical displacement of the rail is 2.5mm, which meets the conditions for continued excavation until the excavation elevation is reached. The side of the foundation pit away from the subgrade corresponds to the steel plate Pile 1 is equipped with the same supporting pile 15 as the steel sheet pile, and the number m = 1 is installed horizontally at the horizontal position 4m from the top of the steel sheet pile. The inner support 13 of the bridge cap foundation pit composed of steel pipes with a diameter of 650mm, the two ends of the inner support of the foundation pit are respectively A waist beam 14 made of 350*350mm H-shaped steel leans against the steel sheet pile and the pile against the pile.

步骤3、完成桥梁承台基坑挖掘施工后按照常规方法进行桥梁承台、墩身及回填土施工,完成桥梁基础施工。Step 3. After the excavation of the foundation pit of the bridge cap is completed, the bridge cap, pier body and backfilling are carried out according to the conventional method, and the bridge foundation construction is completed.

步骤4、完成桥梁基础施工后,切断与槽钢锚固的对拉钢筋,焊割拆除钢梁;采用振动锤振动钢板桩,同时利用起重机吊力将钢板桩拔出,修整钢板桩以备再利用,然后回填钢板桩桩孔并用振动锤夯实;再用钢锯沿地面锯断地锚外露端(插入地面中的地锚不拔出),避免其影响正常生产和生活;将对拉钢筋从钢轨底部抽出,将钢垫板移出,完成路基防护结构拆除。Step 4. After the completion of the bridge foundation construction, cut off the opposite tension bars anchored with channel steel, weld and cut and remove the steel beams; use a vibrating hammer to vibrate the steel sheet piles, and at the same time use the lifting force of a crane to pull out the steel sheet piles, and repair the steel sheet piles for reuse , then backfill the steel sheet pile pile hole and tamp it with a vibrating hammer; then use a hacksaw to cut off the exposed end of the ground anchor along the ground (the ground anchor inserted into the ground will not be pulled out), so as to avoid it affecting normal production and life; Pull out the bottom, remove the steel backing plate, and complete the demolition of the roadbed protection structure.

路基防护结构拆除后,经过实际检测,此段铁路路基的稳定性未因桥梁基础施工受大影响。After the protective structure of the subgrade was removed, the stability of the subgrade of this section of the railway was not greatly affected by the construction of the bridge foundation.

Claims (1)

  1. A kind of 1. across railway line bridge bearing platform foundation construction method, it is characterized in that comprising the following steps:
    Step 1, construct subgrade protection structure
    The railway bed first crossed over before cushion cap excavation of foundation pit to bridge constructs subgrade protection structure, and the subgrade protection structure includes Earth anchor (8) in insertion railway bed (7) the side ground of one group of downline direction and one group of insertion railway bed opposite side Steel sheet pile (1) in face;The earth anchor laterally corresponds between adjacent railway sleeper (5) respectively;The steel sheet pile by with steel sheet pile The channel-section steel (10) of exposed junction welding is connected;Earth anchor passes through to drawing reinforcing bar (2) to be connected with each other in the following manner with channel-section steel:
    To drawing upper surface of the reinforcing bar along railway ballast bed (6) to be passed through from railway track (4) bottom between railroad sleeper (5), There is the spacing identical billet (11) of width and adjacent railway sleeper between reinforcing bar and the ballast bed upper surface of railway to drawing, it is right One end of reinforcing bar and the exposed junction of earth anchor is drawn to weld, anchor after the stretching force F tensioning that the other end for drawing reinforcing bar is calculated as follows out Gu on channel-section steel:
    <mrow> <mi>F</mi> <mo>=</mo> <mn>0.6</mn> <mo>&amp;times;</mo> <mfrac> <mrow> <mn>1.25</mn> <msub> <mi>E</mi> <mrow> <mi>a</mi> <mi>k</mi> </mrow> </msub> <mo>&amp;CenterDot;</mo> <msub> <mi>Z</mi> <mi>a</mi> </msub> <mo>-</mo> <msub> <mi>E</mi> <mrow> <mi>p</mi> <mi>k</mi> </mrow> </msub> <mo>&amp;CenterDot;</mo> <msub> <mi>Z</mi> <mi>p</mi> </msub> </mrow> <mrow> <mi>n</mi> <mo>&amp;CenterDot;</mo> <mi>e</mi> <mrow> <mo>(</mo> <mi>m</mi> <mo>+</mo> <mn>1</mn> <mo>)</mo> </mrow> </mrow> </mfrac> </mrow>
    In formula:
    EakActive earth pressure is made a concerted effort standard value on the outside of-bridge bearing platform foundation ditch,
    EpkPassive earth pressure is made a concerted effort standard value on the inside of-bridge bearing platform foundation ditch,
    ZaActive earth pressure is made a concerted effort to the distance of steel sheet pile lower end on the outside of-bridge bearing platform foundation ditch,
    ZpPassive earth pressure is made a concerted effort to the distance of steel sheet pile lower end on the inside of-bridge bearing platform foundation ditch,
    E-to draw Bar Anchorage point to steel sheet pile lower end distance,
    M-bridge bearing platform foundation ditch inner support quantity,
    N-downline is per linear meter(lin.m.) to the radical of drawing reinforcing bar;
    When constructing the subgrade protection structure, the topsoil on railway bed both sides ground is first cleared up, passes through unwrapping wire by construction drawing design Positioning determines the position of steel sheet pile;Using piling machine in railway bed side downline trend by setting interval and absolute altitude inserting piling Steel sheet pile, in the exposed junction transverse weld channel-section steel of steel sheet pile, each steel sheet pile is connected, channel-section steel accordingly lay in advance by anchor location Box out;Then earth anchor is laid in the drilling of railway bed opposite side, slip casting;By to drawing reinforcing bar along the ballast bed surface of railway from iron Railway track bottom between rail pillow passes through, and is laying the steel pad between reinforcing bar and the ballast bed upper surface of railway to drawing Plate;By to drawing one end of reinforcing bar and earth anchor to weld;By the tensioning to drawing the other end of reinforcing bar to be calculated by the calculation formula Power tensioning, and be anchored at by the preformed hole on channel-section steel;
    When bridge cross over railway line be electric railway when, need to be in the subgrade protection structure to drawing reinforcing bar outer cover rubber Sebific duct, reinforcing bar is set to be insulated with railway track;
    Step 2, excavate bridge bearing platform foundation ditch
    Bridge bearing platform foundation ditch excavation is carried out after completing above-mentioned subgrade protection structure construction:Bridge bearing platform excavation of foundation pit is by remote Railway line side starts, and is gradually promoted to railway bed, takes staged and layered to excavate, and is correspondingly arranged after being excavated at each layer Inner support;Real Time Observation earth anchor pad, channel-section steel anchor point and backing plate whether there is torsional deformation or rupture in mining process, and with daily The upper horizontal displacement of monitoring frequency measurement steel sheet pile once and the absolute altitude of railway track;When earth anchor pad, channel-section steel anchor Necessary suspension of works when point ruptures, butt welding point and anchor point carry out repair welding and reinforcing, when the upper horizontal displacement of steel sheet pile Reach 0.002 times of foundation depth warning value or when rail vertical displacement has reached 4mm warning values, it is necessary to stop excavating simultaneously immediately The foundation ditch excavated is backfilling and compacted, then amendment railway is ballast bed, correction railroad track geometric type position, returns railway track Restore shape;Then its barrier propterty is improved to the method for drawing reinforcing bar with encryption to railway bed safeguard structure;Blockette is taken to subtract Small every layer is excavated thickness and sets up the method for inner support in time bridge bearing platform foundation ditch is excavated and monitored again, until completion is whole The excavation of individual bridge bearing platform foundation ditch, foundation ditch inner support (13) is finally set in cushion cap foundation ditch;
    Step 3, construct bridge foundation
    After completing the excavation of bridge bearing platform foundation ditch, bridge bearing platform, pier shaft and backfill construction are conventionally carried out, completes bridge Basic construct;
    Step 4:Remove subgrade protection structure
    After completion bridge foundation is constructed, cut-out is with channel-section steel anchoring to drawing reinforcing bar, welding dismounting girder steel;Steel is vibrated using vibration hammer Sheet pile, while hang power using crane and extract steel sheet pile, then finishing steel sheet pile backfills steel sheet pile stake holes simultaneously in case recycling Tamped with vibration hammer;Again it is avoided with hacksaw along the sawed-off earth anchor exposed junction in ground (earth anchor in insertion ground need not can be extracted) Influence normal production and life;Billet will be removed, complete to remove subgrade protection knot to drawing reinforcing bar to be extracted out from rail foot Structure.
CN201710844914.XA 2017-09-19 2017-09-19 A construction method for bridge cap foundation across railway lines Expired - Fee Related CN107587515B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710844914.XA CN107587515B (en) 2017-09-19 2017-09-19 A construction method for bridge cap foundation across railway lines

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710844914.XA CN107587515B (en) 2017-09-19 2017-09-19 A construction method for bridge cap foundation across railway lines

Publications (2)

Publication Number Publication Date
CN107587515A true CN107587515A (en) 2018-01-16
CN107587515B CN107587515B (en) 2019-04-09

Family

ID=61047571

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710844914.XA Expired - Fee Related CN107587515B (en) 2017-09-19 2017-09-19 A construction method for bridge cap foundation across railway lines

Country Status (1)

Country Link
CN (1) CN107587515B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2599298B2 (en) * 1989-01-31 1997-04-09 財団法人鉄道総合技術研究所 How to correct the slope
DE202006007142U1 (en) * 2006-04-27 2006-08-03 Sächsische Bau GmbH Edge way sheeting for railway lines has infill, pressed stakes and back anchorages, whereby infill is hot-dip galvanized or galvanically coated crimped heavy plate
CN105908625A (en) * 2016-04-13 2016-08-31 中铁建大桥工程局集团第四工程有限公司 Construction method for adding frame bridge under existing railway line based on dragging method
CN205776253U (en) * 2016-05-31 2016-12-07 中国十九冶集团有限公司 Foundation pit counter-pulling supporting structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2599298B2 (en) * 1989-01-31 1997-04-09 財団法人鉄道総合技術研究所 How to correct the slope
DE202006007142U1 (en) * 2006-04-27 2006-08-03 Sächsische Bau GmbH Edge way sheeting for railway lines has infill, pressed stakes and back anchorages, whereby infill is hot-dip galvanized or galvanically coated crimped heavy plate
CN105908625A (en) * 2016-04-13 2016-08-31 中铁建大桥工程局集团第四工程有限公司 Construction method for adding frame bridge under existing railway line based on dragging method
CN205776253U (en) * 2016-05-31 2016-12-07 中国十九冶集团有限公司 Foundation pit counter-pulling supporting structure

Also Published As

Publication number Publication date
CN107587515B (en) 2019-04-09

Similar Documents

Publication Publication Date Title
CN106638673B (en) A kind of construction method of compound retaining structure
WO2021000444A1 (en) Foundation reinforcement structure and method for hoisting heavy equipment close to unclosed building
CN104846840B (en) A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method
CN114000524A (en) Steel sheet pile cofferdam structure of deep silt geological adjacent structure and construction method
CN205776273U (en) Tall earth fill balance weight retaining wall and prestress anchorage cable combined support structure
CN111335923B (en) Construction method for large deformation of soft rock of tunnel with unfavorable geology
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN203284708U (en) Subgrade structure of deep-layer loose and soft soil region
CN105862930A (en) Protection structure on existing tunnel below new underground engineering
JP6170268B1 (en) Ballast track subbase formation method
CN117966617A (en) A jacking construction method and device for a frame bridge under a railway
CN115012393A (en) Construction method for bearing platform under weakly weathered rock stratum riverbed
CN115434191B (en) Deep deformation renovation method for ballast track subgrade of operation railway
CN114961336B (en) Protective demolition construction method for foundation pile of basement close to existing subway line
EP2744942B1 (en) Railway track support system
CN212077496U (en) railway reinforcement
CN115929399B (en) Construction protection device and construction protection method for electric power tunnel
CN110241863B (en) Soft soil foundation pit excavation process pipe gallery deformation control device and control method thereof
CN107587515A (en) A kind of across railway line bridge bearing platform foundation construction method
CN216515676U (en) Steel sheet pile cofferdam structure of deep silt geology closes on structure
RU2374392C1 (en) Method for stabilisation of embankment with retaining structures from steel corrugated sheets
CN115897426A (en) A construction method for shield tunneling of stacked tunnels safely crossing existing bridge piles and intruding into tunnel areas
CN210561510U (en) Railway line protection device
CN212983933U (en) Structure for preventing and treating differential settlement of roadbed at edge of linear underground structure
CN111235968B (en) Railway reinforcement roadbed and reinforcement method of railway settlement roadbed

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant