CN105888664A - Mining method for extremely-thick hard coal - Google Patents
Mining method for extremely-thick hard coal Download PDFInfo
- Publication number
- CN105888664A CN105888664A CN201610210154.2A CN201610210154A CN105888664A CN 105888664 A CN105888664 A CN 105888664A CN 201610210154 A CN201610210154 A CN 201610210154A CN 105888664 A CN105888664 A CN 105888664A
- Authority
- CN
- China
- Prior art keywords
- coal
- layering
- thick hard
- layer
- extremely thick
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/02—Supporting means, e.g. shuttering, for filling-up materials
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Remote Sensing (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention discloses a mining method for extremely-thick hard coal. The method includes the following steps that the extremely-thick hard coal is divided into at least two layers; roadway tunneling is performed on the first layer; fully-mechanized mining equipment is installed in a roadway of the first layer; fully-mechanized stoping is performed on the first layer; roadway tunneling is performed on the second layer, and top coal is reserved on a roadway of the second layer; fully-mechanized caving equipment is installed in the roadway of the second layer; a coal mining machine is adopted for cutting coal on the lower portion of the second layer; the top coal of the second layer is recycled in a top coal caving mode; all the mining steps of the second layer are repeated on all the layers below the second layer. The method has the advantages of being suitable for mining extremely-thick hard coal, high in resource recycling rate, low in cost and high in safety and reducing the probability of spontaneous combustion in goafs.
Description
Technical field
The present invention relates to the technical field of coal mining, particularly relate to the extremely thick hard coal recovery method of one.
Background technology
China typically has high working face to open for the recovery method of the super high seam that thickness is 5-10m at present
Adopt, separate zone production, top coal caving and strip mining transformation totally four kinds, these recovery methods have respectively respectively
From different features and applicable elements.
The comprehensive large cutting height workface adopting full-seam mining is to use high working face hydraulic support and major diameter cylinder
Super high seam is exploited by the supporting fully-mechanized mining equipment such as coal-winning machine.China's full-seam mining is adopted greatly at present
The maximum height in high comprehensive mining face is only 8.8m, there is no method for more than the 8.8m coal seam that thickness is bigger real
The large cutting height workface of existing full-seam mining.
Separate zone production refers to super high seam is used the method being the most gradually layered fully-mechnized mining,
Higher slice to be that manufacture of intraocular vacation top is exploited in lower leaf in base plate paving mesh sheet during back production,
Deng back production lower leaf again after higher slice back production.Although this recovery method high stoping rate, but need
Sufficiently complex in base plate lapping, production practice, back production efficiency is low, and stoping cost is high.General
Adopt 2 layers, every layer of mining height 4-5m, the most domestic precedent the most not adopting 3 layers, say, that at present
The coal of domestic separate zone production is thick at below 10m.
Longwall top coal caving is to adopt coal-winning machine coal cutting and reclaim behind certain thickness coal seam with combining, and residue top coal is complete
Portion uses caving to reclaim.This recovery method Sub-Level Caving height is restricted, if top coal is the thickest too
Firmly, caving ability is the most very poor, and resource recovery is the lowest, causes the substantial amounts of wasting of resources, and adopts
It is many that coal is lost in dead zone, brings the hidden danger of spontaneous fire, and put coal excessively after, be vented above support,
Easily cause and cut top pressure rack accident.Therefore, the coal seam thickness that this recovery method is suitable for is the most limited,
It is usually no more than 10m, and for the thickness coal seam more than 10m, longwall top coal caving method is also difficult to fit
Should.
Strip mining transformation is the method by exploiting super high seam after peeling off earth's surface overlying strata again, this exploitation
The method scope of application is the least, is only applicable to shallow buried coal seam, and requires that stripping-to-ore ratio can not be too big, and one
Denier stripping-to-ore ratio is excessive, uneconomical on cost, and ground surface environment also can be caused serious broken by Lu Cai
Bad.Therefore, strip mining transformation can not adapt to the special thick and pole high seam that buried depth is bigger.
In sum, current China all can not for all recovery methods of the super high seam of 5-10m
Individually solve the mining problem of pole high seam thick for 11-217m.Therefore, it is necessary to design one money
Source response rate height, low cost, safety preferably and reduce spontaneous combustion in goaf probability
Extremely thick hard coal recovery method.
Summary of the invention
It is an object of the invention to overcome the deficiencies in the prior art, it is provided that a kind of resource recovery height,
Low cost, safety preferably and reduce the extremely thick hard coal exploitation of spontaneous combustion in goaf probability
Method.
Technical scheme provides one extremely thick hard coal recovery method, comprises the following steps:
Described extremely thick hard coal is divided at least two-layer layering;
First layer is carried out tunnelling;
Fully-mechanized mining equipment is installed in the described tunnel of described first layer;
Carry out described first layer combining and adopt back production;
Second layering is carried out tunnelling, top coal reserve on the described tunnel of described second layering;
Install to combine in the described tunnel of described second layering and put equipment;
The bottom of described second layering is used coal-winning machine coal cutting;
Sub-Level Caving is used to reclaim in the described top coal of described second layering;
Following all layerings are repeated all stages of mining of described second layering.
Further, described first layer is combined and adopted the coal seam thickness of back production is 3-5m, described second point
The coal cutting of the longwall top coal caving of layer is highly 3-5m, the Sub-Level Caving of the longwall top coal caving of described second layering
Thickness is 2-4m.
Further, described first layer is combined and adopted the coal seam thickness of back production is 4m, described second layering
The coal cutting of longwall top coal caving be highly 4m, the thickness of the Sub-Level Caving of the longwall top coal caving of described second layering
For 3m.
Further, combine while adopting or combine and putting back to and adopt, just help along haulage gate to install soft mould coagulation
Cob wall.
Further, the step of described supporting soft mould concrete walls, farther include:
Combine while adopting or combine and putting back to and adopt, along the haulage gate at the support rear of stope just
Side installs soft mould;
By concrete unit and conveying pipe, concrete grout is injected in described soft mould;
After solidification, then whitewash, form described soft mould concrete walls.
Further, the thickness of described soft mould concrete walls is 1-1.5m.
Further, while installing soft mould concrete walls, to the district of just exploitation on stope
Territory carries out gib.
Further, described gib comprises the following steps:
Hydraulic prop for moving suspended top beam, monomer is used to join girder steel and carry out Lagging support in lane;
Caterpillar track travelling hydraulic support, monomer, wood point post and wire netting is used to carry out supporting;
Termination 1-5 frame is taked paving top net supporting, is used for keeping off cash.
Further, before installing soft mould concrete walls, the top board in described tunnel is carried out reinforcement and props up
Protect.
Further, while described tunnelling, described tunnel is carried out combined supporting.
After using technique scheme, have the advantages that
The set of the present invention advantage of fully-mechnized mining, longwall top coal caving and separate zone production, and by second
Layer and later top coal stablize entity coal seam as the top board in tunnel, it is not necessary to manufacturing artificial vacation top.
Therefore, the present invention has and is applicable to extremely thick hard coal exploitation, resource recovery height, low cost, safety
Property preferably and the advantage that reduces spontaneous combustion in goaf probability.
Accompanying drawing explanation
Fig. 1 is the flow chart of extremely thick hard coal recovery method in one embodiment of the invention;
Fig. 2 is the exploitation schematic diagram of extremely thick hard coal recovery method in one embodiment of the invention;
Fig. 3 is the flow chart of extremely thick hard coal recovery method in highly preferred embodiment of the present invention;
Fig. 4 is supporting soft mould concrete in extremely thick hard coal recovery method in highly preferred embodiment of the present invention
The construction technology floor map of wall;
Fig. 5 is the exploitation schematic diagram of extremely thick hard coal recovery method in highly preferred embodiment of the present invention.
Detailed description of the invention
Further illustrate the detailed description of the invention of the present invention below in conjunction with the accompanying drawings.
Seeing Fig. 1-2, Fig. 1 is the flow chart of extremely thick hard coal recovery method in one embodiment of the invention;
Fig. 2 is the exploitation schematic diagram of extremely thick hard coal recovery method in one embodiment of the invention, and Fig. 2 is exploitation
Coal seam longitudinal sectional drawing.This recovery method specifically includes following steps:
Step S101: extremely thick hard coal is divided into two-layer layering;
Step S102: first layer is carried out tunnelling;
Step S103: install fully-mechanized mining equipment in the tunnel of first layer;
Step S104: carry out first layer combining and adopt back production;
Step S105: the second layering is carried out tunnelling, reserved top on the tunnel of the second layering
Coal;
Wherein, this top coal is as the stability of cavern roof entity coal seam of digging laneway, owing to first layer is combined
After adopting face back production, the roadway layout of comprehensive coal face below upper strata fully mechanized coal face formed mined out
Under district, the pressure that overlying rock is formed is released, and top does not exist concentration coal column and avoids down
There is the problem of focus pressure during layer driving, also avoid surge problem, advantageously in
The Roof Control of driving face.
Step S106: install to combine in the tunnel of the second layering and put equipment;
Step S107: the bottom of the second layering is used coal-winning machine coal cutting;
Step S108: use Sub-Level Caving to reclaim in the top coal on the top of the second layering.
The set of the present invention advantage of fully-mechnized mining, longwall top coal caving and separate zone production, and by second
Layer and later top coal stablize entity coal seam as the second back being layered, it is not necessary to as existing
Some separate zone productions such manufacturing artificial vacation top.Therefore, the present invention has and is applicable to extremely thick hard coal and opens
Adopt, resource recovery height, low cost, safety preferably and reduce spontaneous combustion in goaf can
The advantage of energy property.
Seeing Fig. 3-5, Fig. 3 is the flow process of extremely thick hard coal recovery method in highly preferred embodiment of the present invention
Figure;Fig. 4 is supporting soft mould concrete in extremely thick hard coal recovery method in highly preferred embodiment of the present invention
The construction technology floor map of wall;Fig. 5 is extremely thick hard coal exploitation in highly preferred embodiment of the present invention
The exploitation schematic diagram of method, Fig. 5 is working seam longitudinal sectional drawing.This recovery method specifically includes
Following steps:
Step S201: extremely thick hard coal is divided into three layers of layering;
Step S202: first layer is carried out tunnelling;
Wherein, the driving height in tunnel is about 3.5m, and during driving, base plate is strictly along this layer thickness end
Portion is tunneled, and forbids with in the mind pricking, thus avoids damage to underlying seam, it is to avoid digs lower slicing roadway
Enter the Roof Control with back production and bring difficulty.
Step S203: while tunnelling, carries out combined supporting to tunnel;
Wherein, " anchor pole+anchor cable+mesh sheet " combined supporting is used.
Step S204: the top board in tunnel is carried out reinforcement supporting;
Wherein, before installing soft mould concrete walls, the top board in tunnel is carried out anchor cable steel band reinforcement
Supporting.
Step S205: install fully-mechanized mining equipment in the tunnel of first layer;
Step S206: carry out first layer combining and adopt back production;
The coal seam thickness of first layer fully mechanized coal face back production is 4m, and such thickness had both facilitated tunnelling
It is easy to again combine adopt back production, also helps soft mould concrete support gob side entry retaining.First layer is combined and is adopted back
When adopting, along roof back production, mining height 4m, during back production, strictly control mining height, forbid with in the mind pricking,
Avoid the Roof Control of lower slicing roadway driving and back production is brought difficulty.
Step S207: combine while adopting back production, just help along haulage gate to install soft mould concrete walls;
Wherein, the step of supporting soft mould concrete walls, farther include:
Combine while adopting back production, just help to install along the haulage gate at the support rear of stope
Soft mould;
By concrete unit and conveying pipe, concrete grout is injected in soft mould;
After solidification, then whitewash, form soft mould concrete walls.
The thickness of soft mould concrete walls can be 1-1.5m.
Soft mould concrete walls form the isolation that goaf is caving spoil, and have certain to top board
Support effect.So stay new crossheading that lane formed (i.e. in Fig. 4 just at face haulage crossheading)
Just can continue as next work surface to use, as the air return way of next work surface.Soft mould
Concrete walls achieve without coal pillar mining, as shown in Figure 4, only have one between two Adjacent Working Faces
Bar crossheading, tunnelling engineering amount reduces about 50% than existing coal pillar mining, ten thousand tons of drivage ratios
Being substantially reduced, cost reduces, and efficiency improves, and coal recovery rate reaches about 87%,
About 12 percentage points are exceeded than the rate of extraction of national requirements 75%.
Step S208: the second layering is carried out tunnelling, reserved top on the tunnel of the second layering
Coal;
Wherein, along being adopted the bottom driving that layering coal is thick during tunnelling, head-room is 3.5m,
Remaining thickness (3.5m) gives over to push up coal, as the stability of cavern roof entity coal seam of digging laneway.Due to
After first layer fully mechanized coal face back production, the roadway layout of comprehensive coal face below is at upper strata fully mechanized coal face
Under the goaf formed, the pressure that overlying rock is formed is released, and top does not exist concentration coal column
Avoid to exist during lower floor's driving the problem of focus pressure, also avoid surge problem,
Advantageously in the Roof Control of driving face.
Step S209: while tunnelling, carries out combined supporting to tunnel;
Wherein, operation here is identical with first layer.
Step S210: the top board in tunnel is carried out reinforcement supporting;
Wherein, operation here is also identical with first layer.
Step S211: install to combine in the tunnel of the second layering and put equipment;
Step S212: the bottom of the second layering is used coal-winning machine coal cutting;
Wherein, the thickness of the second layering coal-winning machine coal cutting is 4m, and operation requires the phase with first layer
With.
Step S213: combine while putting back to and adopting, just help along haulage gate to install soft mould concrete walls;
Wherein, operation here is also identical with first layer.
Step S214: carry out Sub-Level Caving recovery to pushing up coal described in the second top being layered;
The coal seam thickness of the second layering is 7m, adopts 4m and puts 3m, tunnelling height 3.5m, combines
Tapping coal height 4m, residual thickness 3m is as top coal, and top coal can be development end and comprehensive coal face carries
For stable Man-made False, and can reclaim after frame, both can improve back production to greatest extent
Rate, can guarantee that again the roof safety of fully mechanized coal face.
During comprehensive coal face coal cutting, strengthen visiting top coal work, it is ensured that stay the top coal thickness set to meet design and want
Ask, forbid lower bundle equally, it is to avoid the Roof Control of lower slicing roadway driving and back production is brought difficulty.
Support should select the hydraulic support with telescopic top beam and face guard, uses a cutter once putting, seeing cash
The caving mode stopped.
Step S215: the 3rd layering is repeated all stages of mining of the second layering.
Multi-segment coal push to adopt and can be divided into two ways: one is after first layer has all been adopted,
Adopting the second layering again, the second layering adopts the 3rd layering after all having adopted again, the like, until will
Pole high seam has all been adopted;Another kind be upper and lower two layering push to adopt simultaneously, higher slice front, under
Layering is rear, and the higher slice roof caving such as lower leaf pushes to adopt after stablizing a segment distance again.
It is preferred that first layer is combined, to adopt the coal seam thickness of back production can be 3-5m, and the second layering is combined and decontroled
Adopting coal-winning machine coal cutting height can be 3-5m, and the thickness of the Sub-Level Caving of the longwall top coal caving of the second layering can be
2-4m。
It is preferred that while installing soft mould concrete walls, to the region of just exploitation on stope
Carry out gib.
Further, described gib comprises the following steps:
Hydraulic prop for moving suspended top beam, monomer is used to join girder steel and carry out Lagging support in lane;
Caterpillar track travelling hydraulic support, monomer, wood point post and wire netting is used to carry out supporting;
Termination 1-5 frame is taked paving top net supporting, is used for keeping off cash.
The invention have the advantages that
(1) new technique, new way are provided for extremely thick hard coal exploitation.In terms of the whole country, extremely thick
Hard coal seam employing multi-segment gob side entry retaining is combined and is put without coal pillar mining technology, the whole nation beyond example, this skill temporarily
The innovation of art solves the mining problem of the extremely thick hard coal of 11-217m, has certain popularization and application valency
Value.
(2) owing to have employed without coal pillar mining, between two work surfaces, only have 1 crossheading, tunnel
Excavation work amount ratio has coal pillar mining to reduce about 50%, and ten thousand tons of drivage ratios are substantially reduced, cost
Reducing, efficiency improves, and coal recovery rate reaches about 87%, than national requirements 75%
The rate of extraction exceed about 12 percentage points.
(3) generation of bump is effectively prevented.All use without coal owing to pole high seam is respectively layered
Post is exploited, and there is not coal column after exploitation, will not form focus pressure, thus also avoid impact
The problem of ground pressure.
(4) this technology coal recovery rate is greatly improved, and makes the something lost coal in goaf greatly reduce, thus
The hidden danger making the spontaneous combustion in goaf is substantially reduced.
(5) tunnelling is about 3.5m due to top coal thickness, takes anchor cable, anchor pole, mesh sheet to combine
Supporting, it is not necessary to frame canopy, supporting is simple, and supporting expense is low, and cost of ton coal is low.
(6) have certain destruction due to higher slice after exploiting to lower leaf coal, lower leaf is exploited
Time support repeatedly support to top coal also have certain destruction, it is thus possible to ensure top good the emitting of coal
Putting property, it is not necessary to top coal is carried out presplit blasting, and put also without carrying out pressure when just adopting
Top.
(7) use Longwall top coal caving technology technique to achieve and be just not required to lapping under this special geologic condition
Can solve very well to combine the Roof Control problem adopting tip to face distance scope, also eliminate periodic weighting simultaneously,
Face pressure is less, has effectively stopped to leak cash and the generation of roof fall accident.
(8) this technology has fully been drawn fully-mechnized mining, longwall top coal caving, separate zone production and has opened without coal column
Adopt the advantage of four kinds of recovery methods.Compared with separate zone production, extremely thick hard coal multi-segment is combined and is put without coal column
Exploitation need not lapping manufacture of intraocular vacation top, and technique is simpler.Compared with Sub-Level Caving, Mei Gefen
The gross thickness of layer only has 7m, Sub-Level Caving to only have 3m, it is ensured that emitting and put effect, the response rate is higher,
And avoid and high seam top, pole coal is failed to lay down or be vented cradle top coal seam cause work
Make face periodic weighting roof fall and cut the problem that top cannot advance.
(9) the thickness subject range for pole high seam is wider, and this technology uses except first layer
Outside fully-mechnized mining, bottom is respectively layered and all uses longwall top coal caving, for the coal that 11-217m is even thicker
Layer can be suitable for.
(10) driving is without frame canopy, and back production, without lapping, is mined and driving speed is all very fast, efficiency
Height, profitable, popularizing application prospect is good.
The present invention can solve the problem that the safety and high efficiency problem of the extremely thick hard coal of 11-217m, here
Hard coal refers generally to Protodyakonov coefficient f >=3, and joint fissure aplasia, the preferable coal seam of toughness.Significantly
Improving resource recovery, safety is preferable, and reduces the probability of Study on Protection of Spontaneous Combustion,
Provide multi-segment for the extremely thick hard coal of thickness 11-217m to combine and put the new technique without coal pillar mining.This
Outward, the present invention can also apply to the exploitation of super high seam of 8-10m.
Above-described is only principle and the preferred embodiment of the present invention.It should be pointed out that, for this
For the those of ordinary skill in field, on the basis of the principle of the invention, it is also possible to make some its
Its modification, also should be regarded as protection scope of the present invention.
Claims (10)
1. an extremely thick hard coal recovery method, it is characterised in that comprise the following steps:
Described extremely thick hard coal is divided at least two-layer layering;
First layer is carried out tunnelling;
Fully-mechanized mining equipment is installed in the described tunnel of described first layer;
Carry out described first layer combining and adopt back production;
Second layering is carried out tunnelling, top coal reserve on the described tunnel of described second layering;
Install to combine in the described tunnel of described second layering and put equipment;
The bottom of described second layering is used coal-winning machine coal cutting;
Sub-Level Caving is used to reclaim in the described top coal of described second layering;
Following all layerings are repeated all stages of mining of described second layering.
Extremely thick hard coal recovery method the most according to claim 1, it is characterised in that described the
The one comprehensive coal seam thickness adopting back production of layering is 3-5m, and the coal cutting of the longwall top coal caving of described second layering is high
Degree is 3-5m, and the thickness of the Sub-Level Caving of the longwall top coal caving of described second layering is 2-4m.
Extremely thick hard coal recovery method the most according to claim 2, it is characterised in that described the
The one comprehensive coal seam thickness adopting back production of layering is 4m, the coal cutting height of the longwall top coal caving of described second layering
For 4m, the thickness of the Sub-Level Caving of the longwall top coal caving of described second layering is 3m.
Extremely thick hard coal recovery method the most according to claim 1, it is characterised in that combine adopt or
Combine while putting back to and adopting, just help along haulage gate to install soft mould concrete walls.
Extremely thick hard coal recovery method the most according to claim 4, it is characterised in that described
Protect the step of soft mould concrete walls, farther include:
Combine while adopting or combine and putting back to and adopt, along the haulage gate at the support rear of stope just
Side installs soft mould;
By concrete unit and conveying pipe, concrete grout is injected in described soft mould;
After solidification, then whitewash, form described soft mould concrete walls.
Extremely thick hard coal recovery method the most according to claim 4, it is characterised in that described soft
The thickness of mould concrete walls is 1-1.5m.
Extremely thick hard coal recovery method the most according to claim 4, it is characterised in that install soft
While mould concrete walls, the region of just exploitation on stope is carried out gib.
Extremely thick hard coal recovery method the most according to claim 7, it is characterised in that described in face
Time supporting comprise the following steps:
Hydraulic prop for moving suspended top beam, monomer is used to join girder steel and carry out Lagging support in lane;
Caterpillar track travelling hydraulic support, monomer, wood point post and wire netting is used to carry out supporting;
Termination 1-5 frame is taked paving top net supporting, is used for keeping off cash.
Extremely thick hard coal recovery method the most according to claim 4, it is characterised in that install soft
Before mould concrete walls, the top board in described tunnel is carried out reinforcement supporting.
Extremely thick hard coal recovery method the most according to claim 1, it is characterised in that described
While tunnelling, described tunnel is carried out combined supporting.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610210154.2A CN105888664A (en) | 2016-04-06 | 2016-04-06 | Mining method for extremely-thick hard coal |
CN202110205826.1A CN113153295A (en) | 2016-04-06 | 2016-04-06 | Mining method for extremely thick hard coal |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610210154.2A CN105888664A (en) | 2016-04-06 | 2016-04-06 | Mining method for extremely-thick hard coal |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110205826.1A Division CN113153295A (en) | 2016-04-06 | 2016-04-06 | Mining method for extremely thick hard coal |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105888664A true CN105888664A (en) | 2016-08-24 |
Family
ID=57013455
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610210154.2A Pending CN105888664A (en) | 2016-04-06 | 2016-04-06 | Mining method for extremely-thick hard coal |
CN202110205826.1A Pending CN113153295A (en) | 2016-04-06 | 2016-04-06 | Mining method for extremely thick hard coal |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110205826.1A Pending CN113153295A (en) | 2016-04-06 | 2016-04-06 | Mining method for extremely thick hard coal |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN105888664A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106939789A (en) * | 2017-03-20 | 2017-07-11 | 中国神华能源股份有限公司 | A kind of separate zone production technique that separate zone production is carried out to super high seam |
CN110630265A (en) * | 2018-12-26 | 2019-12-31 | 中国矿业大学 | Layered mining method for controlling subsidence of surface steps of huge thick coal seam |
CN114017119A (en) * | 2021-10-27 | 2022-02-08 | 国能神东煤炭集团有限责任公司 | Coal seam thickness detection equipment and control method thereof |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113653489A (en) * | 2021-08-31 | 2021-11-16 | 中煤科工开采研究院有限公司 | Mining method and net laying mechanism for soft surrounding rock extra-thick coal seam |
CN114320298B (en) * | 2022-01-05 | 2024-03-01 | 国家能源集团国源电力有限公司 | Coal mining method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102094646A (en) * | 2010-11-18 | 2011-06-15 | 新汶矿业集团有限责任公司协庄煤矿 | Process process for comprehensively mining extra-hard inter-band coal seams with complex texture |
CN102900438A (en) * | 2012-10-12 | 2013-01-30 | 山西焦煤集团有限责任公司 | Residual coal full-mechanized repeated mining method of near-distance inflammable seam gob |
CN103291304A (en) * | 2013-06-28 | 2013-09-11 | 中国矿业大学 | Recovery method of super mining height top coal on fully mechanized coal mining face |
CN105134212A (en) * | 2015-08-10 | 2015-12-09 | 河南理工大学 | Method for ensuring fully-mechanized top coal caving recovery rate of three-soft thick coal seam roadway tunneling along top |
CN105317438A (en) * | 2015-11-09 | 2016-02-10 | 中国矿业大学(北京) | Middle pre-mining slicing top-coal breaking coal mining method for super high seams |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1224793A (en) * | 1999-01-29 | 1999-08-04 | 王晓利 | Method of recovering coal from blasted down roof |
CN101498216A (en) * | 2009-03-06 | 2009-08-05 | 太原理工大学 | Thick coal seam large height workface step coal wall coal mining method |
CN103233740B (en) * | 2013-04-22 | 2015-07-08 | 中国矿业大学(北京) | Top-cutting roadway coal-pillar-free mining method of close-range thin coal seam |
-
2016
- 2016-04-06 CN CN201610210154.2A patent/CN105888664A/en active Pending
- 2016-04-06 CN CN202110205826.1A patent/CN113153295A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102094646A (en) * | 2010-11-18 | 2011-06-15 | 新汶矿业集团有限责任公司协庄煤矿 | Process process for comprehensively mining extra-hard inter-band coal seams with complex texture |
CN102900438A (en) * | 2012-10-12 | 2013-01-30 | 山西焦煤集团有限责任公司 | Residual coal full-mechanized repeated mining method of near-distance inflammable seam gob |
CN103291304A (en) * | 2013-06-28 | 2013-09-11 | 中国矿业大学 | Recovery method of super mining height top coal on fully mechanized coal mining face |
CN105134212A (en) * | 2015-08-10 | 2015-12-09 | 河南理工大学 | Method for ensuring fully-mechanized top coal caving recovery rate of three-soft thick coal seam roadway tunneling along top |
CN105317438A (en) * | 2015-11-09 | 2016-02-10 | 中国矿业大学(北京) | Middle pre-mining slicing top-coal breaking coal mining method for super high seams |
Non-Patent Citations (1)
Title |
---|
孟国胜: "公务素矿大倾角特厚煤层长壁综放开采工艺研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅰ辑》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106939789A (en) * | 2017-03-20 | 2017-07-11 | 中国神华能源股份有限公司 | A kind of separate zone production technique that separate zone production is carried out to super high seam |
CN110630265A (en) * | 2018-12-26 | 2019-12-31 | 中国矿业大学 | Layered mining method for controlling subsidence of surface steps of huge thick coal seam |
CN110630265B (en) * | 2018-12-26 | 2021-07-09 | 中国矿业大学 | Layered mining method for controlling subsidence of surface steps of huge thick coal seam |
CN114017119A (en) * | 2021-10-27 | 2022-02-08 | 国能神东煤炭集团有限责任公司 | Coal seam thickness detection equipment and control method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN113153295A (en) | 2021-07-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103470261B (en) | The method of gob side entry driving under the former back in mining goaf | |
CN102080518B (en) | Method for extracting gas from coal seam roof complex branched well | |
CN103742149B (en) | A kind of combining puts the method that second mining remains ground coal | |
CN105888664A (en) | Mining method for extremely-thick hard coal | |
CN104234749B (en) | A kind of fully-mechanized mining working big cross section return channel surrounding rock control method | |
CN111594258A (en) | Technical method for quickly extracting gas to reach standard by using broken soft low-permeability outburst coal seam instead of roadway through holes | |
CN108049896B (en) | A kind of fully mechanized coal face gob-side entry retaining method | |
CN103382844B (en) | A kind of tracked hydraulic sectional shelf-unit temporary lining and permanent support parallel operations piercing technique and equipment | |
CN102953732A (en) | Room-and-pillar major-diameter longhole inverted-step-like segmented lateral caving subsequent filling mining method | |
CN104847355A (en) | Continuous mining method for hollow ground of medium-thickness steeply inclined ore body | |
CN103104259A (en) | Inclination fragmentation ore body segment top board reconstruction middle-deep hole ore break down filling mining method | |
CN108756885A (en) | A kind of high-dipping ore block that ore-rock is smashed to pieces it is lower to or on to consolidated fill mechanized mining method | |
CN108590747B (en) | Wall type full-face extraction hydraulic column temporary support subsequent filling method | |
AU2021106168A4 (en) | High-gas Coal Seam Group Pressure Relief Mining Method Based on Gob-side Entry Retaining in the First Mining Whole Rock Pressure Relief Working Face | |
CN103147761A (en) | Filling mining method of gently inclined thin mineral deposit with soft roof | |
CN102644464A (en) | Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine | |
CN103643979A (en) | Hydraulic support used for roadway temporary support and erecting and use method of hydraulic support | |
CN105649630A (en) | Mining technology for gold ore | |
CN108266189A (en) | A kind of lane top Tunnelling Along Goaf goaf isolation method | |
CN104533419B (en) | Method for partial recovery of residual coal from wide coal pillar | |
CN113216963B (en) | Stoping method for gallery ore in transition mining by caving method to filling method | |
CN110410076A (en) | A kind of filling mining method for leaving Pillar Recovery for old pillars of a house goaf | |
CN106988760A (en) | Facility-sliding strata tunnel portal reinforcing construction and construction method | |
CN107862106B (en) | Without coal column along empty caving at lane feasibility discrimination method | |
CN109630112A (en) | A kind of N00 mining codes for cutting top filling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160824 |
|
RJ01 | Rejection of invention patent application after publication |