CN105862589A - Manufacturing method for broken-line-shaped double-joint stud welded chord member with anchor boxes - Google Patents
Manufacturing method for broken-line-shaped double-joint stud welded chord member with anchor boxes Download PDFInfo
- Publication number
- CN105862589A CN105862589A CN201610106421.1A CN201610106421A CN105862589A CN 105862589 A CN105862589 A CN 105862589A CN 201610106421 A CN201610106421 A CN 201610106421A CN 105862589 A CN105862589 A CN 105862589A
- Authority
- CN
- China
- Prior art keywords
- unit
- line
- broken line
- plate
- band
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/14—Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Butt Welding And Welding Of Specific Article (AREA)
Abstract
The invention relates to a manufacturing method for a broken-line-shaped double-joint stud welded chord member with anchor boxes. The broken-line-shaped double-joint stud welded chord member with the anchor boxes is manufactured according to the sequence of manufacturing of elements, manufacturing of box bodies, installation and welding of cross beam connector plates, drilling of stud holes, and installation and welding of the anchor boxes. The broken-line-shaped double-joint stud welded chord member with the anchor boxes is applied to the Shanghai-to-Nantong Bridge. Broken-line-shaped double-joint chord members are arranged in the positions, where stay cables are installed, of the Shanghai-to-Nantong Bridge to meet the requirement for setting the pre-camber. In the past, stud welded single-joint chord members are adopted to achieve arch cambering by relying on connection of staggered holes and deformation of the chord members. The double-joint chord members are applied to the Shanghai-to-Nantong Bridge, and break points are arranged at joints, so that the cambering requirement is met more easily.
Description
Technical field
The present invention relates to bridge field, particularly to a kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method.
Background technology
The research of this bridge is that Shanghai leads to bridge, and in the middle of the manufacture of bridge, this Shanghai leads to bridge part-structure and uses suspension cable,
Thus needing to process some band anchor case truss and fix suspension cable, anchor case is arranged on the chord member of truss, common band anchor case
Bolt weldering chord member manufacture method all use the bolt to level weldering chord member make, and Shanghai lead to bridge install suspension cable position adopt
Be the binodal chord member of fold-line-shaped, this is the demand in order to arrange camber, used in the past bolt weldering form single node
Chord member relies on and connects wrong hole and chord member deformation arch camber, and Shanghai leads to bridge and uses binode form chord member, arranges folding at node
Point makes it be more easy to the demand reaching to arch upward, and the production method of common chord member cannot meet band anchor case fold-line-shaped binode bolt weldering chord member
Making requirement.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method, energy
Enough lead to the band anchor case fold-line-shaped binode bolt weldering chord member used on bridge bridge to producing Shanghai.
For solving above-mentioned technical problem, the technical scheme is that
A kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method, its innovative point is: this band anchor case fold-line-shaped binode
Bolt weldering chord member according to unit piece making, casing making, assembly welding beam joint plate, keyhole drill, the order of assembly welding anchor case is carried out, its
Specifically comprise the following steps that
S1. unit piece makes and includes that band broken line riser unit makes, upper cover plate unit makes, lower cover unit makes;
S1.1 band broken line riser unit makes: first by the broken line unit needed for band broken line riser, gusset plate unit, connecting plate list
Unit uses Numerical control cutting will cut down, then by broken line unit, gusset plate unit and connecting plate unit from raw steel
Carry out leveling process, secondly carry out, on broken line unit, gusset plate unit, connecting plate unit, the model as region to be processed of ruling
Contain system, the slope needing welding is carried out the PROCESS FOR TREATMENT of machine milling the most again, then by broken line riser unit according to from left to right
Broken line unit a, gusset plate unit a, connecting plate unit, gusset plate unit b, broken line unit b edge and groove are docked and weld
Get up, then is detected a flaw in welding position, it is to avoid weld defective, subsequently the band broken line riser unit welded is rectified
Flat process, carries out machine miller sequence to top margin and groove according to drawn line, the most again finally along on band broken line riser unit
Bearing of trend assembly welding floor a, then the floor a to assembly welding repairs the making being achieved that band broken line riser unit;
S1.2 upper cover plate unit makes: first used from raw steel by upper cover plate unit under the method cutting of accurate cutting
Come, then the upper cover plate unit cut down is carried out leveling process, secondly rule as work area to be added on upper cover plate unit
The scope control in territory, carries out machine milling process to the groove and slope needing welding according to drawn line, then by floor b along upper cover
Bearing of trend on Slab element welds, and finally the floor b welded is repairing the system being achieved that upper cover plate unit
Make;
The making of S1.3 lower cover unit: first lower cover unit is used from raw steel under the method cutting of accurate cutting
Come, then the lower cover unit cut down is carried out leveling process, secondly the both sides and groove needing welding are carried out machine
Milling, welds floor c along the bearing of trend of lower cover unit the most again, finally repairs the floor c of welding just
Achieve the making of lower cover unit;
S2. the making of casing: the making of casing uses fetalism inversion to assemble, and first upper cover plate unit is placed on fetalism platform
On, on the basis of the longitudinal rib keyhole of the above cover plate unit of bearing of trend of the floor b installed along upper cover plate unit and longitudinal axis
Line carries out the assembling of dividing plate, and the riser unit of band broken line is arranged on the both sides of upper cover plate unit, and the riser list of band broken line
Floor a in unit is embedded in groove one trench structure of interior formation that the both sides of dividing plate are opened, then is welded by this trench structure and repair
Whole, finally lower cover unit cover and is welded on the breach of cell body, form body structure;
S3. assembly welding beam joint plate: beam joint plate includes cantilever diaphragm adapter plate, crossbeam edge of a wing adapter plate, first by crossbeam
Web plate joint plate is the most assembled, by the centre of cantilever diaphragm adapter plate along the bearing of trend of floor a on band broken line riser unit
Position is welded on floor a, and its one end is welded on adapter plate upper surface, the crossbeam edge of a wing, and the other end is welded on the rib of upper cover plate unit
On plate b;
S4. keyhole drills: drilling of keyhole uses double gantry Three-dimensional numerical control driller, utilizes the precise linkage at double gantry the most once
Property completes the keyhole at chord member two ends and drills, and two band broken line riser unit can be avoided longitudinally, laterally to misplace, it is ensured that two band broken line risers
The concentricity of unit keyhole, each unit head of double gantry numerical control drilling machine all uses high speed drill and can be with accurate linkage, thus effectively
Ensure relative positional accuracy and the drilling efficiency of variant Kong Qun, after rod member utilizes the numerical control drilling machine boring of double gantry, it is no longer necessary to
Large-scale cover type connects brill model, significantly simplifies the bore process of integrated node member;
S5. assembly welding anchor case: on the basis of above, lower cover unit and riser unit keyhole, mark vertical at upper cover plate cell surface
To axis and node center line, inside anchor slab, then mark anchor case system line assembly welding anchor tie plate, the most again bond pads anchor case
Part, controls the position of anchor case anchor point, anchor plate and anchor tube angle, the welding quality of anchor case melt-through weld, and anchor case assembly welding completes
After, line flame cuts upper cover plate unit and bridge floor butt joint edge and butting grooves thereof, it is ensured that the width of upper cover plate unit, and line flame cuts joint
The web member joint of some Slab element and butting grooves thereof.
Further, described gusset plate cell width is relatively big, entirety journey cut blanking again after first completing steel plate splicing and detecting a flaw
To ensure gusset plate unit profile, filling position notes avoiding rod member principal weld position.
Further, precise scoring lines after blanking leveling, including oblique montant axis, put more energy into string center line of the bar, horizontal center line
And butt end machining line.
Further, the outer all kinds of adapter plates of case can complete assembly welding before casing is holed, thus thoroughly avoids welding point
During plate on casing linearity and keyhole the most lateral opening away from impact.
Further, the when of casing welding in the making of casing, four main weld balanced weldings on platform
Connect, prevent torsional deformation.
It is an advantage of the current invention that: this band anchor case fold-line-shaped binode bolt weldering chord member is applied to Shanghai and leads to bridge, and Shanghai leads to bridge
Using the binodal chord member of fold-line-shaped in the position installing suspension cable, this is the demand in order to arrange camber, adopts in the past
Be that bolt weldering form single node chord member relies on and connects wrong hole and chord member deformation arch camber, Shanghai leads to bridge and uses binode form
Chord member, arranges break at node and makes it be more easy to the demand reaching to arch upward, and reduces original employing linear type single node and arranges pre-
The difficulty of camber, the band anchor case fold-line-shaped binode bolt weldering chord member of the present invention compared with the technology that existing bridge arranges camber
Manufacture method complies fully with design requirement, uses the manufacture method of the present invention, can more easily arrange the camber of bridge, it is possible to
Reduction of erection time.
Accompanying drawing explanation
The present invention is further detailed explanation with detailed description of the invention below in conjunction with the accompanying drawings.
Fig. 1 band anchor case fold-line-shaped binode bolt weldering chord member integral installation figure.
Fig. 2 band anchor case broken line binode bolt weldering chord member entirety master regards view.
The manufacture schematic flow diagram of Fig. 3 riser unit.
Fig. 4 riser cellular construction figure.
The manufacture schematic flow diagram of Fig. 5 upper cover plate unit.
The manufacture schematic flow diagram of Fig. 6 lower cover unit.
Fig. 7 diaphragm structure figure.
The schematic diagram that Fig. 8 casing makes.
Fig. 9 keyhole drills flow chart.
Figure 10 is groove type and the dimensional drawings such as anchor case bearing plate and anchor tie plate penetration angle welding.
Figure 11 is anchor case weld seam welding variables figure.
As shown in Figures 1 to 9: 1, riser unit;11, broken line unit;12, gusset plate unit;13, connecting plate unit;14、
Floor a;2, upper cover plate unit;21, floor b;3, lower cover unit;31, floor c;4, casing;41, dividing plate;5, beam joint
Plate;51, cantilever diaphragm adapter plate;52, crossbeam edge of a wing adapter plate;6, anchor case.
Detailed description of the invention
The following examples can make professional and technical personnel that the present invention is more fully understood, but the most therefore by this
Bright it is limited among described scope of embodiments.
A kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method as shown in Figures 1 to 9, this band anchor case fold-line-shaped
Binode bolt weldering chord member according to unit piece make, casing 4 makes, assembly welding beam joint plate 5, keyhole drill, assembly welding anchor case 6 suitable
Sequence is carried out, and it specifically comprises the following steps that
S1. unit piece makes and includes that band broken line riser unit 1 makes, upper cover plate unit 2 makes, lower cover unit 3 makes;
S1.1 band broken line riser unit 1 makes: first by the broken line unit 11 needed for band broken line riser, gusset plate unit 12, company
Fishplate bar unit 13 uses Numerical control cutting to cut down from raw steel, then by broken line unit 11, gusset plate unit 12 with
And connecting plate unit 13 carries out leveling process, secondly carry out drawing on broken line unit 11, gusset plate unit 12, connecting plate unit 13
Line, as the scope control in region to be processed, carries out the PROCESS FOR TREATMENT of machine milling the most again to the slope needing welding, then by broken line
Riser unit 1 according to from left to right by broken line unit 11a, gusset plate unit 12a, connecting plate unit 13, gusset plate unit 12b,
Broken line unit 11b edge and groove dock and weld, then detect a flaw welding position, it is to avoid weld defective, subsequently
The band broken line riser unit 1 welded is carried out leveling process, the most again top margin and groove is carried out machine according to drawn line
Miller sequence, finally along the bearing of trend assembly welding floor 14a on band broken line riser unit 1, then enters the floor 14a of assembly welding
Row finishing is achieved that the making of band broken line riser unit 1.
S1.2 upper cover plate unit 2 makes: first upper cover plate unit 2 uses from raw steel the method for accurate cutting cut
Cutting off, then the upper cover plate unit 2 cut down is carried out leveling process, secondly on upper cover plate unit 2, line conduct is treated
The scope control of machining area, carries out machine milling process to the groove and slope needing welding according to drawn line, then by floor 21b
Weld along the bearing of trend on upper cover plate unit 2, finally the floor 21b of welding is being carried out finishing is achieved that upper cover
The making of Slab element 2.
The making of S1.3 lower cover unit 3: the method that first lower cover unit 3 is used from raw steel accurate cutting
Cut down, then the lower cover unit 3 cut down is carried out leveling process, secondly to both sides and the groove needing welding
Carry out machine milling, the most again floor 31c is welded along the bearing of trend of lower cover unit 3, finally the floor 31c to welding
Carry out repairing the making being achieved that lower cover unit 31.
S2. the making of casing 4: the making of casing 4 uses fetalism inversion to assemble, and first upper cover plate unit 2 is placed on tire
On type platform, the longitudinal rib keyhole of the above cover plate unit of bearing of trend 2 of the floor 21b installed along upper cover plate unit 2 and longitudinal direction
On the basis of axis, line carries out the assembling of dividing plate 41, and the riser unit 1 of band broken line is arranged on the both sides of upper cover plate unit 2, and
It is embedded in groove one trench structure of interior formation that the both sides of dividing plate 41 are opened with the floor 14a on the riser unit 1 of broken line, then will
The welding of this trench structure and finishing, finally cover on the breach of cell body by lower cover unit 3 and weld, and forms casing knot
Structure.
S3. assembly welding beam joint plate 5: beam joint plate 5 includes cantilever diaphragm adapter plate 51, crossbeam edge of a wing adapter plate 52,
First cantilever diaphragm adapter plate 51 is the most assembled, by crossbeam abdomen along the bearing of trend of floor 14a on band broken line riser unit 1
The centre position of plate adapter plate 51 is welded on floor 14a, and its one end is welded on adapter plate 52 upper surface, the crossbeam edge of a wing, the other end
It is welded on the floor 21b of upper cover plate unit 2.
S4. keyhole drills: drilling of keyhole uses double gantry Three-dimensional numerical control driller, utilizes the precise linkage at double gantry simultaneously
The keyhole disposably completing chord member two ends drills, and two band broken line riser unit 1 can be avoided longitudinally, laterally to misplace, it is ensured that two band foldings
The concentricity of line riser unit keyhole, each unit head of double gantry numerical control drilling machine all use high speed drill and can with accurate linkage, from
And relative positional accuracy and the drilling efficiency of variant Kong Qun is effectively ensured, after rod member utilizes the numerical control drilling machine boring of double gantry, no
Need large-scale cover type to connect brill model again, significantly simplify the bore process of integrated node member.
S5. assembly welding anchor case 6: on the basis of above, lower cover unit and riser unit 1 keyhole, on upper cover plate unit 2 surface
Mark longitudinal axis and node center line, inside anchor slab, then mark anchor case system line assembly welding anchor tie plate, assembly welding the most again
Connect anchor case part, control the position of anchor case anchor point, anchor plate and anchor tube angle, the welding quality of anchor case melt-through weld, anchor case group
After being soldered into, line flame cuts upper cover plate unit and bridge floor butt joint edge and butting grooves thereof, it is ensured that the width of upper cover plate Slab element 2,
Line flame cuts web member joint and the butting grooves thereof of gusset plate unit 12.
Gusset plate unit 12 width is relatively big, after first completing steel plate splicing and detecting a flaw again entirety journey cut blanking to ensure gusset plate
Unit profile, filling position notes avoiding rod member principal weld position.
Precise scoring lines after blanking leveling, including oblique montant axis, string center line of the bar of putting more energy into, horizontal center line and docking terminal
Processing line.
The outer all kinds of adapter plates of casing 4 can complete assembly welding before casing is holed, thus when thoroughly avoiding welding point plate pair
Casing 4 linearity and keyhole the most lateral opening away from impact.
The when of welding casing in the making of casing 4, four main welds are symmetrically welded on platform, prevent from turning round
Bent deformation.
As shown in Figure 10, groove type and the size such as anchor case bearing plate and anchor tie plate penetration angle welding.Unit: mm is due to anchor
Case position weld groove is deep, and loading is relatively big, should use little heat input, and coordinate flame to repair, to reduce welding during welding
Deformation, it is ensured that the position of anchor case and angle accurate.
As shown in figure 11, in anchor case weld seam welding variables figure:
1.WH70Q welding wire uses rich argon shield weldering, and other welding wire uses CO2 gas shield;
The most first welding backside angle weld seam, then from groove side back chipping, is careful not to leak clearly, welds, groove after polishing is clean
After weldering is full, cover plate side is even is not less than 8mm leg along welding.
Skilled person will appreciate that of the industry, the present invention is not restricted to the described embodiments, in above-described embodiment and description
The principle that the present invention is simply described described, without departing from the spirit and scope of the present invention, the present invention also has various
Changes and improvements, these changes and improvements both fall within scope of the claimed invention.Claimed scope is by institute
Attached claims and equivalent thereof define.
Claims (5)
1. a band anchor case fold-line-shaped binode bolt weldering chord member manufacture method, it is characterised in that: this band anchor case fold-line-shaped binode
Bolt weldering chord member according to unit piece making, casing making, assembly welding beam joint plate, keyhole drill, the order of assembly welding anchor case is carried out, its
Specifically comprise the following steps that
S1. unit piece makes and includes that band broken line riser unit makes, upper cover plate unit makes, lower cover unit makes;
S1.1 band broken line riser unit makes: first by the broken line unit needed for band broken line riser, gusset plate unit, connecting plate list
Unit uses Numerical control cutting will cut down, then by broken line unit, gusset plate unit and connecting plate unit from raw steel
Carry out leveling process, secondly carry out, on broken line unit, gusset plate unit, connecting plate unit, the model as region to be processed of ruling
Contain system, the slope needing welding is carried out the PROCESS FOR TREATMENT of machine milling the most again, then by broken line riser unit according to from left to right
Broken line unit a, gusset plate unit a, connecting plate unit, gusset plate unit b, broken line unit b edge and groove are docked and weld
Get up, then is detected a flaw in welding position, it is to avoid weld defective, subsequently the band broken line riser unit welded is rectified
Flat process, carries out machine miller sequence to top margin and groove according to drawn line, the most again finally along on band broken line riser unit
Bearing of trend assembly welding floor a, then the floor a to assembly welding repairs the making being achieved that band broken line riser unit;
S1.2 upper cover plate unit makes: first used from raw steel by upper cover plate unit under the method cutting of accurate cutting
Come, then the upper cover plate unit cut down is carried out leveling process, secondly rule as work area to be added on upper cover plate unit
The scope control in territory, carries out machine milling process to the groove and slope needing welding according to drawn line, then by floor b along upper cover
Bearing of trend on Slab element welds, and finally the floor b welded is repairing the system being achieved that upper cover plate unit
Make;
The making of S1.3 lower cover unit: first lower cover unit is used from raw steel under the method cutting of accurate cutting
Come, then the lower cover unit cut down is carried out leveling process, secondly the both sides and groove needing welding are carried out machine
Milling, welds floor c along the bearing of trend of lower cover unit the most again, finally repairs the floor c of welding just
Achieve the making of lower cover unit;
S2. the making of casing: the making of casing uses fetalism inversion to assemble, and first upper cover plate unit is placed on fetalism platform
On, on the basis of the longitudinal rib keyhole of the above cover plate unit of bearing of trend of the floor b installed along upper cover plate unit and longitudinal axis
Line carries out the assembling of dividing plate, and the riser unit of band broken line is arranged on the both sides of upper cover plate unit, and the riser list of band broken line
Floor a in unit is embedded in groove one trench structure of interior formation that the both sides of dividing plate are opened, then is welded by this trench structure and repair
Whole, finally lower cover unit cover and is welded on the breach of cell body, form body structure;
S3. assembly welding beam joint plate: beam joint plate includes cantilever diaphragm adapter plate, crossbeam edge of a wing adapter plate, first by crossbeam
Web plate joint plate is the most assembled, by the centre of cantilever diaphragm adapter plate along the bearing of trend of floor a on band broken line riser unit
Position is welded on floor a, and its one end is welded on adapter plate upper surface, the crossbeam edge of a wing, and the other end is welded on the rib of upper cover plate unit
On plate b;
S4. keyhole drills: drilling of keyhole uses double gantry Three-dimensional numerical control driller, utilizes the precise linkage at double gantry the most once
Property completes the keyhole at chord member two ends and drills, and two band broken line riser unit can be avoided longitudinally, laterally to misplace, it is ensured that two band broken line risers
The concentricity of unit keyhole, each unit head of double gantry numerical control drilling machine all uses high speed drill and can be with accurate linkage, thus effectively
Ensure relative positional accuracy and the drilling efficiency of variant Kong Qun, after rod member utilizes the numerical control drilling machine boring of double gantry, it is no longer necessary to
Large-scale cover type connects brill model, significantly simplifies the bore process of integrated node member;
S5. assembly welding anchor case: on the basis of above, lower cover unit and riser unit keyhole, mark vertical at upper cover plate cell surface
To axis and node center line, inside anchor slab, then mark anchor case system line assembly welding anchor tie plate, the most again bond pads anchor case
Part, controls the position of anchor case anchor point, anchor plate and anchor tube angle, the welding quality of anchor case melt-through weld, and anchor case assembly welding completes
After, line flame cuts upper cover plate unit and bridge floor butt joint edge and butting grooves thereof, it is ensured that the width of upper upper cover plate unit, and line flame is cut
The web member joint of gusset plate unit and butting grooves thereof.
A kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method the most according to claim 1, it is characterised in that: institute
State gusset plate cell width relatively big, outside overall journey cut blanking is with guarantee gusset plate unit again after first completing steel plate splicing and detecting a flaw
Shape, filling position notes avoiding rod member principal weld position.
A kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method the most according to claim 1, it is characterised in that under:
Precise scoring lines after material leveling, machines line including oblique montant axis, string center line of the bar of putting more energy into, horizontal center line and butt end.
A kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method the most according to claim 1, it is characterised in that: case
Outer all kinds of adapter plate can complete assembly welding before casing is holed, thus to casing linearity and bolt when thoroughly avoiding welding point plate
Hole the most lateral opening away from impact.
A kind of band anchor case fold-line-shaped binode bolt weldering chord member manufacture method the most according to claim 1, it is characterised in that:
The when of in the making of casing welding casing, four main welds are symmetrically welded on platform, prevent torsional deformation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610106421.1A CN105862589B (en) | 2016-02-26 | 2016-02-26 | A kind of band anchor case fold-line-shaped binode bolt weldering chord member preparation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610106421.1A CN105862589B (en) | 2016-02-26 | 2016-02-26 | A kind of band anchor case fold-line-shaped binode bolt weldering chord member preparation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105862589A true CN105862589A (en) | 2016-08-17 |
CN105862589B CN105862589B (en) | 2017-08-25 |
Family
ID=56625464
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610106421.1A Active CN105862589B (en) | 2016-02-26 | 2016-02-26 | A kind of band anchor case fold-line-shaped binode bolt weldering chord member preparation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105862589B (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107253026A (en) * | 2017-06-23 | 2017-10-17 | 江苏中铁山桥重工有限公司 | A kind of multidirectional four anchor heads overall steel anchor beam preparation method |
CN108797361A (en) * | 2018-06-28 | 2018-11-13 | 中铁山桥集团有限公司 | A kind of stock method of steel truss girder bridge gusset plate |
CN109024217A (en) * | 2018-07-17 | 2018-12-18 | 中铁大桥勘测设计院集团有限公司 | The connection structure and welding method of web member and chord member |
CN109208454A (en) * | 2018-10-19 | 2019-01-15 | 江苏京沪重工有限公司 | Joining section structure between a kind of Steel Bridge top plate |
CN109972492A (en) * | 2019-04-26 | 2019-07-05 | 江苏京沪重工有限公司 | A kind of bridge floor segmentation module and joining section module assembled system |
CN111119051A (en) * | 2019-12-24 | 2020-05-08 | 江苏中铁山桥重工有限公司 | Novel penetrating type chord structure |
CN112605620A (en) * | 2020-12-31 | 2021-04-06 | 江苏京沪重工有限公司 | Method for machining upper chord of Hualun-shaped truss with vertical rods |
CN114211150A (en) * | 2021-12-30 | 2022-03-22 | 武船重型工程股份有限公司 | Node welding method for double-layer truss bridge |
CN114434105A (en) * | 2022-01-28 | 2022-05-06 | 中铁宝桥(扬州)有限公司 | Method for manufacturing hyperbolic chord member of bridge bolted steel truss girder |
CN115351447A (en) * | 2022-09-15 | 2022-11-18 | 中国五冶集团有限公司 | Welding forming method for cable tower steel anchor box |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2178037C1 (en) * | 2001-03-21 | 2002-01-10 | Закрытое акционерное общество "Интертрансстрой" | Span (alternatives) |
KR100965750B1 (en) * | 2009-05-29 | 2010-06-24 | 안경수 | Joint unit structure of pipe truss for temporary assembly and method constructing the truss bridge with it |
CN201924271U (en) * | 2010-12-30 | 2011-08-10 | 上海市城市建设设计研究院 | Fully-welded integral node |
CN102704395A (en) * | 2012-06-01 | 2012-10-03 | 中铁大桥勘测设计院集团有限公司 | Internal inhaul cable and steel anchor box anchoring structure |
CN102966033A (en) * | 2012-12-12 | 2013-03-13 | 中铁山桥集团有限公司 | Multi-joint chord member of all-welded railway continuous steel truss girder, and manufacturing method of multi-joint chord member |
CN103397593A (en) * | 2013-08-12 | 2013-11-20 | 中铁大桥勘测设计院集团有限公司 | Web member intersecting and split joint connector structure in positions of steel truss girder bridge nodes |
CN203603022U (en) * | 2013-11-25 | 2014-05-21 | 中铁第四勘察设计院集团有限公司 | Butt joint type joint of railway steel truss girder |
CN104878699A (en) * | 2015-06-18 | 2015-09-02 | 上海振华重工(集团)股份有限公司 | Pitching type truss bridge manufacturing method |
CN204644873U (en) * | 2015-01-23 | 2015-09-16 | 中铁四局集团钢结构有限公司 | A kind of novel box type rod piece assembly jig |
-
2016
- 2016-02-26 CN CN201610106421.1A patent/CN105862589B/en active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2178037C1 (en) * | 2001-03-21 | 2002-01-10 | Закрытое акционерное общество "Интертрансстрой" | Span (alternatives) |
KR100965750B1 (en) * | 2009-05-29 | 2010-06-24 | 안경수 | Joint unit structure of pipe truss for temporary assembly and method constructing the truss bridge with it |
CN201924271U (en) * | 2010-12-30 | 2011-08-10 | 上海市城市建设设计研究院 | Fully-welded integral node |
CN102704395A (en) * | 2012-06-01 | 2012-10-03 | 中铁大桥勘测设计院集团有限公司 | Internal inhaul cable and steel anchor box anchoring structure |
CN102966033A (en) * | 2012-12-12 | 2013-03-13 | 中铁山桥集团有限公司 | Multi-joint chord member of all-welded railway continuous steel truss girder, and manufacturing method of multi-joint chord member |
CN103397593A (en) * | 2013-08-12 | 2013-11-20 | 中铁大桥勘测设计院集团有限公司 | Web member intersecting and split joint connector structure in positions of steel truss girder bridge nodes |
CN203603022U (en) * | 2013-11-25 | 2014-05-21 | 中铁第四勘察设计院集团有限公司 | Butt joint type joint of railway steel truss girder |
CN204644873U (en) * | 2015-01-23 | 2015-09-16 | 中铁四局集团钢结构有限公司 | A kind of novel box type rod piece assembly jig |
CN104878699A (en) * | 2015-06-18 | 2015-09-02 | 上海振华重工(集团)股份有限公司 | Pitching type truss bridge manufacturing method |
Non-Patent Citations (1)
Title |
---|
刘洋: "重庆新白沙沱长江特大桥主桁钢梁制作方法", 《钢结构》 * |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107253026B (en) * | 2017-06-23 | 2019-03-19 | 江苏中铁山桥重工有限公司 | A kind of multidirectional four anchor heads overall steel anchor beam production method |
CN107253026A (en) * | 2017-06-23 | 2017-10-17 | 江苏中铁山桥重工有限公司 | A kind of multidirectional four anchor heads overall steel anchor beam preparation method |
CN108797361A (en) * | 2018-06-28 | 2018-11-13 | 中铁山桥集团有限公司 | A kind of stock method of steel truss girder bridge gusset plate |
CN109024217A (en) * | 2018-07-17 | 2018-12-18 | 中铁大桥勘测设计院集团有限公司 | The connection structure and welding method of web member and chord member |
CN109208454B (en) * | 2018-10-19 | 2023-12-22 | 江苏京沪重工有限公司 | Inlaid segmented structure between steel bridge roof |
CN109208454A (en) * | 2018-10-19 | 2019-01-15 | 江苏京沪重工有限公司 | Joining section structure between a kind of Steel Bridge top plate |
CN109972492A (en) * | 2019-04-26 | 2019-07-05 | 江苏京沪重工有限公司 | A kind of bridge floor segmentation module and joining section module assembled system |
CN111119051A (en) * | 2019-12-24 | 2020-05-08 | 江苏中铁山桥重工有限公司 | Novel penetrating type chord structure |
CN112605620A (en) * | 2020-12-31 | 2021-04-06 | 江苏京沪重工有限公司 | Method for machining upper chord of Hualun-shaped truss with vertical rods |
CN114211150A (en) * | 2021-12-30 | 2022-03-22 | 武船重型工程股份有限公司 | Node welding method for double-layer truss bridge |
CN114211150B (en) * | 2021-12-30 | 2023-06-27 | 武船重型工程股份有限公司 | Node welding method for double-layer truss bridge |
CN114434105A (en) * | 2022-01-28 | 2022-05-06 | 中铁宝桥(扬州)有限公司 | Method for manufacturing hyperbolic chord member of bridge bolted steel truss girder |
CN114434105B (en) * | 2022-01-28 | 2023-08-22 | 中铁宝桥(扬州)有限公司 | Manufacturing method of bridge bolt welded steel truss girder hyperbolic chord member |
CN115351447A (en) * | 2022-09-15 | 2022-11-18 | 中国五冶集团有限公司 | Welding forming method for cable tower steel anchor box |
CN115351447B (en) * | 2022-09-15 | 2024-01-23 | 中国五冶集团有限公司 | Welding forming method for cable tower steel anchor box |
Also Published As
Publication number | Publication date |
---|---|
CN105862589B (en) | 2017-08-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105862589A (en) | Manufacturing method for broken-line-shaped double-joint stud welded chord member with anchor boxes | |
CN102277825B (en) | Steel truss bridge and method for fabricating same | |
CN108049302B (en) | A kind of manufacturing method of full welding steel case and full bolt truss combined bridge lower edge steel box-girder | |
CN107498269B (en) | A kind of large-scale ship reception chamber manufacturing method suitable for dry type ship compartment room | |
CN106884498A (en) | A kind of special-shaped box column and its processing technology | |
CN107199437B (en) | A kind of steel anchor beam segment preparation method | |
CN105421586B (en) | A kind of profile steel concrete column at urban rail transit elevated station and preparation method thereof | |
CN108103938B (en) | A kind of double deck module solid trial assembly method of large steel girder | |
CN105735129A (en) | Full-welding truss section modularized splicing method | |
CN105081595A (en) | Fillet weld welding structure for K-type grooves of moderately-thick plate without back chipping and welding technology of fillet weld welding structure | |
CN102839747A (en) | Construction method for steel structure truss of super high-rise special structure | |
CN105171354B (en) | A kind of pipe turns box column and its processing method | |
CN104695624A (en) | Large-cross-section box column and processing technology thereof | |
CN105290724B (en) | A kind of bridge lower boom manufacture craft | |
CN101186003A (en) | Firstly hole drilling construction method in girder steel hole-drilling | |
CN104110069B (en) | Box-type section X-type cross node, jig frame special, fixture and processing method thereof | |
CN103711066B (en) | Novel steel box girder top plate unit structure and preparation method | |
CN202099719U (en) | Steel truss bridge | |
JP2018053626A (en) | Welding method of building steel pipe column | |
CN106760195A (en) | A kind of preparation method of large span, the wide-angle tower hat huge post of connection | |
CN103418994A (en) | Method for equal-strength butt joint of steel tubes | |
CN103495793A (en) | Improved construction method for hoisting and welding large-tonnage cast steel component complex joints | |
CN212793489U (en) | Composite cushion block for butt joint of U-shaped rib embedding sections | |
CN102936963A (en) | GRC (Glass-fiber Reinforced Cement) member mounting method and mounting structure thereof | |
CN101812856B (en) | Production process of steel pile structure of cutter suction dredger |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 226500 Wenjin Road, Yangtze River Town, Rugao City, Nantong City, Jiangsu Province Patentee after: China Railway Shanqiao (Nantong) Co.,Ltd. Address before: 226500 Wenjin Road, Yangtze River Town, Rugao City, Nantong City, Jiangsu Province Patentee before: JIANGSU CHINA RAILWAY SHANHAIGUAN BRIDGE HEAVY INDUSTRY Co.,Ltd. |