CN105290724B - A kind of bridge lower boom manufacture craft - Google Patents

A kind of bridge lower boom manufacture craft Download PDF

Info

Publication number
CN105290724B
CN105290724B CN201510646454.0A CN201510646454A CN105290724B CN 105290724 B CN105290724 B CN 105290724B CN 201510646454 A CN201510646454 A CN 201510646454A CN 105290724 B CN105290724 B CN 105290724B
Authority
CN
China
Prior art keywords
unit
riser
welding
line
top plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510646454.0A
Other languages
Chinese (zh)
Other versions
CN105290724A (en
Inventor
张平
冯志敏
岳长勇
刘洋
关勇
谈发帮
常元鹏
陈方能
郑毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Shanqiao Nantong Co ltd
Original Assignee
Jiangsu Zhongtie Shanqiao Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Zhongtie Shanqiao Heavy Industry Co Ltd filed Critical Jiangsu Zhongtie Shanqiao Heavy Industry Co Ltd
Priority to CN201510646454.0A priority Critical patent/CN105290724B/en
Publication of CN105290724A publication Critical patent/CN105290724A/en
Application granted granted Critical
Publication of CN105290724B publication Critical patent/CN105290724B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges

Abstract

The present invention relates to a kind of bridge lower boom manufacture craft, its key step is as follows:Step one:Group weldering top plate unit, bottom board unit and riser unit;Step 2:Group weldering riser unit parts;Step 3:Assemble top plate unit and bottom board unit;Step 4:Main weldering seam welding and part are installed;Step 5:Bore positioning hole and bolt hole;Assemble remainder.The advantage of the invention is that:Assembling unit is progressively decomposed, rationally connection precision is high for order, and rod member is taken into full account the shape of part, more complicated structure and higher precision prescribed are all taken into full account and met using the method assembling of paperback and flip bonded.

Description

A kind of bridge lower boom manufacture craft
Technical field
The present invention relates to a kind of bridge field, more particularly to a kind of bridge lower edge manufacture craft.
Background technology
Orthotropic plate integrated deck structure, floorings are with lower boom, beam is connected as a single entity in length and breadth, and structure detail is complicated, system Fixed rational welding procedure, strict control welding quality are particularly important;The control stress point of lower boom manufacture, which is removed, includes lower boom weight Outside point control point, rational group weldering and drilling order are even more the key for ensureing this rod member geometric accuracy.
The content of the invention
The technical problem to be solved in the present invention is to provide the complete high-quality bridge lower boom manufacture craft of one kind.
In order to solve the above technical problems, the technical scheme is that:A kind of bridge lower boom manufacture craft, its innovative point It is:Its step is as follows:
1) group weldering top plate unit, bottom board unit and riser unit:Top plate unit is a rectangle, and one is welded at its center The ribbed stiffener extended along long axis direction;Bottom board unit is similar to top plate unit structure, procedure of processing is identical, only bottom board unit Width is less than top plate unit width;Riser unit is two pieces of identicals and flat board in irregular shape, and system is first drawn on flat board The position line such as line and ribbed stiffener, dividing plate and node, and center-punching, ribbed stiffener is welded by line;
2) group weldering riser unit parts:Riser is placed on platform and surveys flat, repetition measurement dividing plate, chord of arch level board, chord member water Flat position line, it is ensured that the accuracy of positioning and the perpendicularity of riser, and ensure chord of arch level board bolt hole concentricity;Will be each Part is welded on riser by line;Two risers are welded assembled by riser system line perpendicularity above and below guarantee;
3) assembling top plate unit and bottom board unit:Top plate unit is divided into two pieces of size, is vertically disposed on riser list First both sides, are in integrally groove profile, and weld the main weld of chord of arch level board and riser after welding by both sides flat board spot welding in place;Bottom Slab element is divided into two pieces of size, and two pieces of bottom board units are put respectively and are welded in the riser opposite side parallel with top plate, overall after welding In box;
4) main weldering seam welding and part are installed:It is placed on platform, can be carried out with special frock in inversion by overall It is fixed, convenient processing;The side sway of each part, vertical curved, distortion are first detected, a series of finishings are then carried out according to testing result, repaiied Group weldering lateral roof unit after whole, group postwelding is in integrally box, the rear welding for carrying out box main weld;After the completion of main weldering seam welding Continue to weld lower chord of arch ribbed stiffener, lower chord of arch dividing plate and anticollision barrier connector;180 ° of upsets will be integrally done, are noted in switching process Meaning prevents collision, is in integrally normotopia placement location after upset, and same recruitment clamping is fixed, and carries out top plate unit penetration weld seam weld Connect, postwelding need to detect a flaw to ensure welding quality, after the completion of the flaw detection of top plate unit melt-through weld, continuation group burn-on chord of arch ribbed stiffener, The upper embedding benefit section of chord of arch dividing plate and each floor;
5) positioning hole and bolt hole are bored:After rod member finishing is qualified, node when being rule on platform using riser unit is base Standard draws system line;Node side chord member and chord of arch positioning hole line are drawn on the basis of node center, with gantry numerical control drilling positioning hole, it is ensured that Both sides riser bolt hole is concentric;Then not a node side chord member positioning hole line is drawn on the basis of node center again, gantry is used after rotation Numerical control drilling positioning hole;Card model connects brill riser remaining bolt hole, and line card model bores two bottom plate hole, number hole drill spilled water hole, so Group welds top plate ribbed stiffener afterwards;
6) remainder is assembled:On the basis of system line line group weldering both sides beam joint plate lateral adapter plate and other Part, the secondary part of group weldering on the basis of system line, rule on the basis of hole crop and hand hole, and by drawing to privileged sites Putty is sealed.
Further, the step(2)And step(3)Middle electric welding is spot welding, and solder joint is closeer.
Further, the step(4)Symmetrical welding in the same direction is required during middle welding main weld.
Further, the step(5)Must be detected after the finishing of middle rod member it is qualified can upper mounting plate line, otherwise forbidden Marking on slab and upper lathe drill positioning hole.
The advantage of the invention is that:
1) assembling unit is progressively decomposed, rationally connection precision is high for order, and rod member is using paperback and the side of flip bonded Method is assembled, and takes into full account the shape of part, more complicated structure and higher precision prescribed are all taken into full account and met;
2) first positioned using spot welding, determine component locations, facilitate follow-up adjustment and the welding of miscellaneous part;Comparatively dense Solder joint proof strength, it is to avoid deformed in subsequent operation;
3) it is symmetrically welded to reduce torsional deformation in the same direction;
4) can rule drilling after rod member is qualified, improve product quality reduction in the numbers of seconds.
Brief description of the drawings
Fig. 1 is a kind of schematic diagram of bridge lower boom riser unit of the invention.
Fig. 2 is a kind of bridge lower boom schematic diagram of the invention.
Embodiment
As shown in Figure 1 and Figure 2, the invention discloses a kind of bridge lower edge manufacture craft, orthotropic plate integrated deck knot Structure, floorings are with lower boom, beam is connected as a single entity in length and breadth, and structure detail is complicated, formulate rational welding procedure, strict control welding Quality is particularly important;The control stress point of lower boom manufacture is in addition to comprising lower boom priority control point, and rational group weldering and drilling are suitable Sequence is even more the key for ensureing this rod member geometric accuracy.In addition to the CCP for taking the manufacture of common lower boom, take as Lower major measure:
1. rod member is assembled using the method for paperback and flip bonded;
2. to avoid chord of arch level board 2 from can not being drilled after box composition, chord of arch level board 2 drills before group weldering;
3. system line 6 must be marked in outside in node before assembling, due to the subdrilling of chord of arch level board 2 when box is assembled Hole, must implement measures to ensure that the concentricity of chord of arch level board 2 during assembling, while also must assure that bolt hole and system line 6 Relativeness;
4. during drilling, gantry numerical control drilling positioning hole, card model, which connects, bores other Kong Qun.
Overall procedure is as follows:
Top plate unit 7, bottom board unit 4, the 5 groups of welderings of riser unit, draw system line, chord of arch level board list on riser unit 5 First card sample bores two bolt hole, reserves welding contracted quantity.
During assembling on the basis of riser system line 6, dividing plate 1, the unit of chord of arch level board 2, chord member level board 3, then group are first spread Riser unit 5 and the formation groove profile of top plate unit 7, then the formation box of bottom board unit 4 is organized, after group repair welding is whole on the basis of system line 6 Line, gantry numerical control drilling positioning hole, card model bore remaining hole, and the secondary part of group weldering, is rule on the basis of hole and cut on the basis of system line 6 Head and hand hole, and privileged sites putty is sealed by drawing.
Concrete operation step is:
1) group weldering top plate unit 7, bottom board unit 4 and riser unit 5:Top plate unit 7 is a rectangle, is welded at its center Connect a ribbed stiffener extended along long axis direction;Bottom board unit 4 is similar to the structure of top plate unit 7, and procedure of processing is identical, only bottom plate The width of unit 4 is less than the width of top plate unit 7;Riser unit 5 is two pieces of identicals and flat board in irregular shape, first in flat board It is upper to draw system line 6 and ribbed stiffener, the position line and node of dividing plate 1, and center-punching, weld ribbed stiffener by line;
2) group weldering riser unit parts:Riser unit 5 is placed on platform and surveys flat, repetition measurement dividing plate 1, chord of arch level board 2, The position line of chord member level board 3, it is ensured that the accuracy of positioning and the perpendicularity of riser unit 5, and ensure the bolt of chord of arch level board 2 Hole concentricity;Each part is welded on riser cell board 5 by line;The perpendicularity of riser cellular system line 6 above and below guarantee, by two Riser element solder is assembled;
3) assembling top plate unit 7 and bottom board unit 4:7 points of top plate unit is two pieces of size, is vertically disposed on riser The both sides of unit 5, are in integrally groove profile after welding, and weld chord of arch level board 2 and riser unit 5 by both sides flat board spot welding in place Main weld;4 points of bottom board unit is two pieces of size, by two pieces of bottom board units 4 respectively point to be welded in the riser parallel with top plate unit 7 another Side, is in integrally box after welding;
4) main weldering seam welding and part are installed:It is placed on platform, can be carried out with special frock in inversion by overall It is fixed, convenient processing;The side sway of each part, vertical curved, distortion are first detected, a series of finishings are then carried out according to testing result, repaiied Group weldering lateral roof unit 7 after whole, group postwelding is in integrally box, the rear welding for carrying out box main weld;Main weldering seam welding is completed Continue to weld lower chord of arch ribbed stiffener, lower chord of arch dividing plate and anticollision barrier connector afterwards;180 ° of upsets will be integrally done, in switching process Note preventing collision, be in integrally normotopia placement location after upset, same recruitment clamping is fixed, and carries out the melt-through weld of top plate unit 7 Welding, postwelding need to be detected a flaw to ensure welding quality, after the completion of the flaw detection of the melt-through weld of top plate unit 7, and the continuation group chord of arch of burn-oning is put more energy into Rib, upper chord of arch dividing plate and the embedding benefit section of each floor;
5) positioning hole and bolt hole are bored:After rod member finishing is qualified, node when being rule on platform using riser unit 5 is base Standard draws system line 6;Node side chord member and chord of arch positioning hole line are drawn on the basis of node center, with gantry numerical control drilling positioning hole, is protected Demonstrate,prove both sides riser bolt hole concentric;Then not a node side chord member positioning hole line is drawn on the basis of node center again, with dragon after rotation Door numerical control drilling positioning hole;Card model connects brill riser remaining bolt hole, and line card model bores two bottom plate hole, number hole drill spilled water hole, Then group welds top plate ribbed stiffener;
6) remainder is assembled:On the basis of system line 6 line group weldering both sides beam joint plate lateral adapter plate and its His part, the secondary part of group weldering on the basis of system line 6, rule on the basis of hole crop and hand hole, and by drawing to special Position putty sealing.
In step(2)And step(3)Middle electric welding is spot welding, and solder joint is closeer, so as to follow-up correction, miscellaneous part Install and prevent deformation;In step(4)Symmetrical welding in the same direction is required during middle welding main weld, to reduce torsional deformation;In step Suddenly(5)Must be detected after the finishing of middle rod member it is qualified can upper mounting plate line, otherwise forbidden upper mounting plate line and upper lathe to drill fixed Position hole;Monitoring step is strictly observed, product quality is improved, defect is checked in time and is corrected, reduction in the numbers of seconds.
The general principle and principal character of the present invention has been shown and described above.It should be understood by those skilled in the art that, The present invention is not limited to the above embodiments, merely illustrating the principles of the invention described in above-described embodiment and specification, Without departing from the spirit and scope, various changes and modifications of the present invention are possible, and these changes and improvements all fall Enter in scope of the claimed invention.The scope of the present invention is defined by the appended claims and its equivalents.

Claims (4)

1. a kind of bridge lower boom manufacture craft, it is characterised in that:Its step is as follows:
(1)Group weldering top plate unit, bottom board unit and riser unit:Top plate unit is a rectangle, and an edge is welded at its center The ribbed stiffener of long axis direction extension;Bottom board unit is similar to top plate unit structure, and procedure of processing is identical, only the width of bottom board unit Degree is less than top plate unit width;Riser unit is two pieces of identicals and flat board in irregular shape, and system line is first drawn on flat board And ribbed stiffener, partition position line and node, and center-punching, weld ribbed stiffener by line;
(2)Group weldering riser unit parts:Riser is placed on platform and surveys flat, repetition measurement dividing plate, chord of arch level board, chord member level board The position line, it is ensured that the accuracy of positioning and the perpendicularity of riser, and ensure chord of arch level board bolt hole concentricity;By each part It is welded on by line on riser;Two risers are welded assembled by riser system line perpendicularity above and below guarantee;
(3)Assemble top plate unit and bottom board unit:Top plate unit is divided into two pieces of size, is vertically disposed on riser unit two Side, is in integrally groove profile, and weld the main weld of chord of arch level board and riser after welding by both sides flat board spot welding in place;Bottom plate list Member is divided into two pieces of size, and two pieces of bottom board units are put respectively and are welded in the riser opposite side parallel with top plate, is in integrally case after welding Type;
(4)Main weldering seam welding and part are installed:It is placed on platform, can be consolidated with special frock in inversion by overall It is fixed, convenient processing;The side sway of each part, vertical curved, distortion are first detected, a series of finishings, finishing are then carried out according to testing result Group weldering lateral roof unit, organizes postwelding integrally in box, the rear welding for carrying out box main weld afterwards;After the completion of main weldering seam welding after The lower chord of arch ribbed stiffener of continuous welding, lower chord of arch dividing plate and anticollision barrier connector;180 ° of upsets will be integrally done, are noted in switching process Collision is prevented, is in integrally normotopia placement location after upset, same recruitment clamping is fixed, and carries out top plate unit melt-through weld welding, Postwelding need to be detected a flaw to ensure welding quality, after the completion of the flaw detection of top plate unit melt-through weld, and continuation group is burn-on chord of arch ribbed stiffener, arch String dividing plate and the embedding benefit section of each floor;
(5)Bore positioning hole and bolt hole:After rod member finishing is qualified, drawn on the basis of node when being rule on platform by riser unit System line;Node side chord member and chord of arch positioning hole line are drawn on the basis of node center, with gantry numerical control drilling positioning hole, it is ensured that both sides Riser bolt hole is concentric;Then not a node side chord member positioning hole line is drawn on the basis of node center again, gantry numerical control is used after rotation Bore positioning hole;Card model connects brill riser remaining bolt hole, and line card model bores two bottom plate hole, number hole drill spilled water hole, then group Weld top plate ribbed stiffener;
Assemble remainder:Line group weldering both sides beam joint plate lateral adapter plate and miscellaneous part on the basis of system line, The secondary part of group weldering on the basis of system line, rule on the basis of hole crop and hand hole, and by drawing to privileged sites putty Sealing.
2. a kind of bridge lower boom manufacture craft according to claim 1, it is characterised in that:The step(2)And step Suddenly(3)Middle electric welding is spot welding, and solder joint is closeer.
3. a kind of bridge lower boom manufacture craft according to claim 1, it is characterised in that:The step(4)Middle welding Symmetrical welding in the same direction is required during main weld.
4. a kind of bridge lower boom manufacture craft according to claim 1, it is characterised in that:The step(5)Middle rod member Must be detected after finishing it is qualified can upper mounting plate line, otherwise forbidden upper mounting plate line and upper lathe drill positioning hole.
CN201510646454.0A 2015-10-09 2015-10-09 A kind of bridge lower boom manufacture craft Active CN105290724B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510646454.0A CN105290724B (en) 2015-10-09 2015-10-09 A kind of bridge lower boom manufacture craft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510646454.0A CN105290724B (en) 2015-10-09 2015-10-09 A kind of bridge lower boom manufacture craft

Publications (2)

Publication Number Publication Date
CN105290724A CN105290724A (en) 2016-02-03
CN105290724B true CN105290724B (en) 2017-08-25

Family

ID=55188904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510646454.0A Active CN105290724B (en) 2015-10-09 2015-10-09 A kind of bridge lower boom manufacture craft

Country Status (1)

Country Link
CN (1) CN105290724B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105729063B (en) * 2016-02-26 2017-11-10 江苏中铁山桥重工有限公司 A kind of box external node chord member preparation method of double anchors
CN107199437B (en) * 2016-03-16 2019-06-07 中铁十五局集团有限公司 A kind of steel anchor beam segment preparation method
CN107253026B (en) * 2017-06-23 2019-03-19 江苏中铁山桥重工有限公司 A kind of multidirectional four anchor heads overall steel anchor beam production method
CN111119051B (en) * 2019-12-24 2021-04-27 江苏中铁山桥重工有限公司 Wear out formula chord member structure
CN114211150B (en) * 2021-12-30 2023-06-27 武船重型工程股份有限公司 Node welding method for double-layer truss bridge

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101186003A (en) * 2007-11-26 2008-05-28 中铁大桥局集团第七工程有限公司 Firstly hole drilling construction method in girder steel hole-drilling
CN102179540A (en) * 2011-04-22 2011-09-14 海波重型工程科技股份有限公司 Sample mold drilling method for steel truss girder whole node rod
CN102277825A (en) * 2011-05-23 2011-12-14 江苏沪宁钢机股份有限公司 Steel truss bridge and method for fabricating same
CN103321152A (en) * 2012-07-23 2013-09-25 上海振华重工(集团)股份有限公司 Telescopic truss crossbeam and manufacture method thereof
CN103321350A (en) * 2013-06-03 2013-09-25 江苏沪宁钢机股份有限公司 Multi-connection and large-cross-section combination-box-type thick-plate side column and construction method therefor

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011174352A (en) * 2010-02-25 2011-09-08 Masatake Oshima Culvert side ditch with top surface slit
JP5984131B2 (en) * 2012-01-30 2016-09-06 株式会社富士ピー・エス Prestressed concrete truss girder formwork equipment

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101186003A (en) * 2007-11-26 2008-05-28 中铁大桥局集团第七工程有限公司 Firstly hole drilling construction method in girder steel hole-drilling
CN102179540A (en) * 2011-04-22 2011-09-14 海波重型工程科技股份有限公司 Sample mold drilling method for steel truss girder whole node rod
CN102277825A (en) * 2011-05-23 2011-12-14 江苏沪宁钢机股份有限公司 Steel truss bridge and method for fabricating same
CN103321152A (en) * 2012-07-23 2013-09-25 上海振华重工(集团)股份有限公司 Telescopic truss crossbeam and manufacture method thereof
CN103321350A (en) * 2013-06-03 2013-09-25 江苏沪宁钢机股份有限公司 Multi-connection and large-cross-section combination-box-type thick-plate side column and construction method therefor

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《南京大胜关长江大桥钢桁梁下弦杆制作工艺》;刘志刚;《钢结构》;20100522;论文第22、59-62页 *

Also Published As

Publication number Publication date
CN105290724A (en) 2016-02-03

Similar Documents

Publication Publication Date Title
CN105290724B (en) A kind of bridge lower boom manufacture craft
CN108049302B (en) A kind of manufacturing method of full welding steel case and full bolt truss combined bridge lower edge steel box-girder
CN102277825B (en) Steel truss bridge and method for fabricating same
Van Wingerde The fatigue behaviour of T-and X-joints made of square hollow sections
CN105862589B (en) A kind of band anchor case fold-line-shaped binode bolt weldering chord member preparation method
CN107253026B (en) A kind of multidirectional four anchor heads overall steel anchor beam production method
CN106884498A (en) A kind of special-shaped box column and its processing technology
CN107964864A (en) A kind of trapezoidal bending component of gradual change and manufacture method of anchoringwire in vivo
CN103711066B (en) Novel steel box girder top plate unit structure and preparation method
CN107199437B (en) A kind of steel anchor beam segment preparation method
CN202099719U (en) Steel truss bridge
CN106436924A (en) Steel pipe concrete column variable section broken-line-shaped steel bracket and connecting construction method thereof
CN109190177A (en) A kind of vehicle body of railway vehicle weld fatigue reliability estimation method and system
CN104801836B (en) Oversea wind power generation jacket basis flange installation method
CN110877674A (en) Positioning process of double rudder horn on subsection
CN102937402B (en) A kind of parallelogram web member hole group's detection method
CN105848427A (en) PCB drilling method, method for detecting drilling deviation of PCB, PCB, and equipment
CN114043171B (en) Manufacturing method of curve cable tower steel anchor box
CN101992356A (en) Joined turbine rotor components and method thereof
CN207610903U (en) A kind of metal T-type welding point tension test part
Chiew et al. Experimental and numerical stress analyses of tubular XT-joint
CN110820942A (en) Construction method for roof overlong overhanging lotus flower modeling steel structure
CN106043593A (en) Stiffening-U-rib both-side welding structure of orthotropic stiffening plate
CN110282078A (en) A kind of accuracy control method of self-discharging ship tank top W type segmentation
CN208167491U (en) A kind of trapezoidal bending component of gradual change of internal anchoringwire

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 226500 Wenjin Road, Yangtze River Town, Rugao City, Nantong City, Jiangsu Province

Patentee after: China Railway Shanqiao (Nantong) Co.,Ltd.

Address before: 226500 Wenjin Road, Yangtze River Town, Rugao City, Nantong City, Jiangsu Province

Patentee before: JIANGSU CHINA RAILWAY SHANHAIGUAN BRIDGE HEAVY INDUSTRY Co.,Ltd.