CN105839920A - Construction method for station-end temporary steel support replacement - Google Patents

Construction method for station-end temporary steel support replacement Download PDF

Info

Publication number
CN105839920A
CN105839920A CN201610377579.2A CN201610377579A CN105839920A CN 105839920 A CN105839920 A CN 105839920A CN 201610377579 A CN201610377579 A CN 201610377579A CN 105839920 A CN105839920 A CN 105839920A
Authority
CN
China
Prior art keywords
support
cast
bearing
situ continuous
support system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610377579.2A
Other languages
Chinese (zh)
Other versions
CN105839920B (en
Inventor
武鹏燕
章忠
沈灵友
李伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 15th Bureau Group Co Ltd
Priority to CN201610377579.2A priority Critical patent/CN105839920B/en
Publication of CN105839920A publication Critical patent/CN105839920A/en
Application granted granted Critical
Publication of CN105839920B publication Critical patent/CN105839920B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a construction method for station-end temporary steel support replacement. A second supporting system is arranged on one side of a first supporting system which bears cast-in-situ continuous beams; jacks on the first supporting system jack up the cast-in-situ continuous beams to realize arrangement of temporary supporting seats on the second supporting system, gaps between the temporary supporting seats and the cast-in-situ continuous beams are filled by steel plates, and the beams are descended slowly to complete first-time supporting system replacement; a third supporting system on a bearing platform is constructed, jacks on the third supporting system jack up the cast-in-situ continuous beams to realize arrangement of supporting seats on the third supporting system, steel plates are placed to fill gaps between the supporting seats and the cast-in-situ continuous beams, and the beams are descended slowly to complete second-time supporting system replacement. By the construction method, twice stress conversion in a steel support replacement process can be guaranteed, safety in the steel support replacement process is guaranteed, and accordingly stability and reliability of station ends after replacement are further guaranteed.

Description

The construction method of end temporary steel support support replacement of standing
Technical field
The invention belongs to end temporary steel support support replacement technical field of standing, be specifically related to the construction method of a kind of end temporary steel support support replacement of standing.
Background technology
When closing on the in-situ beam casting at station, station structure has to construction to station hall layer, end, station is positioned at above station hall layer for the bracket supporting Cast-in-situ Beam, miss the stop needs according to beam car, in the case of bracket is not constructed, beam body is held up by the bracing members that Cast-in-situ Beam temporarily uses arrangement form to be single nine, after prefabricated box beam is all transported and set up, station end position is constructed bracket component again, is then fallen within the bracket that station is stretched out the end of continuous beam.
In order to ensure beam car stablizing through temporary steel support beam body stress, and can there be reliable and stable temporary support beam body end during construction in later period bracket, the arrangement form of single nine bracing members is changed to double 10, but lack the construction method of bracing members support replacement at present, it is impossible to complete more reliable and more stable bracing members.
Summary of the invention
In view of this, present invention is primarily targeted at the construction method of a kind of end temporary steel support support replacement of standing is provided.
For reaching above-mentioned purpose, the technical scheme is that and be achieved in that:
The embodiment of the present invention provides the construction method of a kind of end temporary steel support support replacement of standing, and the method is realized by following steps:
Step one: the second support system is set in the side of the first support system bearing cast-in-situ continuous beam weight;
Step 2: prop up cast-in-situ continuous beam by the jack on the first support system, then temporary support is set on described second bearing system, and place steel plate for the space filling up between temporary support and cast-in-situ continuous beam, now, slowly fall beam body after rise, the load-bearing making described cast-in-situ continuous beam is positioned on described second support system, completes bearing system conversion for the first time;
Step 3: remove described first support system and be excavated to be positioned at the cushion cap face of platform drilled pile, afterwards, carrying out the construction of the 3rd support system on described cushion cap face;
Step 4: after described 3rd support system construction, cast-in-situ continuous beam is propped up by the jack on described 3rd support system, then bearing is set on described 3rd bearing system, and place steel plate for the space filling up between bearing and cast-in-situ continuous beam, now, slowly fall beam body after rise so that the load-bearing of described cast-in-situ continuous beam is positioned on described 3rd support system, complete second time bearing system conversion;
Step 5: remove described second support system.
In such scheme, described first support system is nine steel support structures of single setting.
In such scheme, described second support system is 2 steel support structures of single setting and reinforces diagonal brace.
In such scheme, described 3rd support system is ten steel support structures of double setting.
In such scheme, 2 steel support structures of described second support system are arranged on original ground and extend to 40 meters, underground.
In such scheme, described jack is four groups of 200t jack, is laid in both sides of the edge 20cm at the bottom of the beam of distance cast-in-situ continuous beam.
In such scheme, described cast-in-situ continuous beam is less than or equal to 1cm by jack stand, the settling data of the most static observation beam body, after determining situation without exception, then carries out placing steel plate for filling up the space between temporary support or bearing and cast-in-situ continuous beam and slowly falling beam body after rise.
Compared with prior art, beneficial effects of the present invention:
The present invention is able to ensure that the two times transfer of stress during bracing members support replacement, it is ensured that the security of support replacement process, and then ensures the reliable and stable of the station end after changing into.
Accompanying drawing explanation
Fig. 1 provides the initial schematic diagram of a kind of end temporary steel support support replacement of standing for the embodiment of the present invention;
Fig. 2 provides the schematic diagram of the step one of the construction method of a kind of end temporary steel support support replacement of standing for the embodiment of the present invention;
Fig. 3 provides the schematic diagram of the step 3 of the construction method of a kind of end temporary steel support support replacement of standing for the embodiment of the present invention
Fig. 4 provides the schematic diagram of the step 5 of the construction method of a kind of end temporary steel support support replacement of standing for the embodiment of the present invention.
Detailed description of the invention
In order to make the purpose of the present invention, technical scheme and advantage clearer, below in conjunction with drawings and Examples, the present invention is further elaborated.Should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not intended to limit the present invention.
The embodiment of the present invention provides the construction method of a kind of end temporary steel support support replacement of standing, and as Figure 1-4, the method is realized by following steps:
Step one: the second support system is set in the side of the first support system bearing cast-in-situ continuous beam weight, as shown in Figure 1, 2;
Step 2: prop up cast-in-situ continuous beam by the jack on the first support system, then temporary support is set on described second bearing system, and place steel plate for the space filling up between temporary support and cast-in-situ continuous beam, now, slowly fall beam body after rise, the load-bearing making described cast-in-situ continuous beam is positioned on described second support system, completes bearing system conversion for the first time;
Step 3: remove described first support system and be excavated to be positioned at the cushion cap face of platform drilled pile, afterwards, carries out the construction of the 3rd support system, as shown in Figure 3 on described cushion cap face;
Step 4: after described 3rd support system construction, by described theThreeCast-in-situ continuous beam propped up by jack on support system, then bearing is set on described 3rd bearing system, and place steel plate for the space filling up between bearing and cast-in-situ continuous beam, now, slowly fall beam body after rise, the load-bearing making described cast-in-situ continuous beam is positioned on described 3rd support system, completes second time bearing system conversion;
Step 5: remove described second support system, as shown in Figure 4.
Described first support system is nine steel support structures of single setting.
Described second support system is 2 steel support structures of single setting and reinforces diagonal brace.
Described 3rd support system is ten steel support structures of double setting.
2 steel support structures of described second support system are arranged on original ground and extend to 40 meters, underground.
Described jack is four groups of 200t jack, is laid in both sides of the edge 20cm at the bottom of the beam of distance cast-in-situ continuous beam.
Described cast-in-situ continuous beam, after determining situation without exception then is carried out placing steel plate for filling up the space between temporary support or bearing and cast-in-situ continuous beam and slowly falling beam body after rise less than or equal to 1cm, the settling data of the most static observation beam body by jack stand.
The above, only presently preferred embodiments of the present invention, it is not intended to limit protection scope of the present invention.

Claims (7)

1. the construction method of an end temporary steel support support replacement of standing, it is characterised in that the method is realized by following steps:
Step one: the second support system is set in the side of the first support system bearing cast-in-situ continuous beam weight;
Step 2: prop up cast-in-situ continuous beam by the jack on the first support system, then temporary support is set on described second bearing system, and place steel plate for the space filling up between temporary support and cast-in-situ continuous beam, now, slowly fall beam body after rise, the load-bearing making described cast-in-situ continuous beam is positioned on described second support system, completes bearing system conversion for the first time;
Step 3: remove described first support system and be excavated to be positioned at the cushion cap face of platform drilled pile, afterwards, carrying out the construction of the 3rd support system on described cushion cap face;
Step 4: after described 3rd support system construction, cast-in-situ continuous beam is propped up by the jack on described 3rd support system, then bearing is set on described 3rd bearing system, and place steel plate for the space filling up between bearing and cast-in-situ continuous beam, now, slowly fall beam body after rise so that the load-bearing of described cast-in-situ continuous beam is positioned on described 3rd support system, complete second time bearing system conversion;
Step 5: remove described second support system.
The construction method of station the most according to claim 1 end temporary steel support support replacement, it is characterised in that: described first support system is nine steel support structures of single setting.
The construction method of station the most according to claim 1 and 2 end temporary steel support support replacement, it is characterised in that: described second support system is 2 steel support structures of single setting and reinforces diagonal brace.
The construction method of station the most according to claim 3 end temporary steel support support replacement, it is characterised in that: described 3rd support system is ten steel support structures of double setting.
The construction method of station the most according to claim 4 end temporary steel support support replacement, it is characterised in that: 2 steel support structures of described second support system are arranged on original ground and extend to 40 meters, underground.
The construction method of station the most according to claim 5 end temporary steel support support replacement, it is characterised in that: described jack is four groups of 200t jack, is laid in both sides of the edge 20cm at the bottom of the beam of distance cast-in-situ continuous beam.
The construction method of station the most according to claim 6 end temporary steel support support replacement, it is characterized in that: described cast-in-situ continuous beam is less than or equal to 1cm by jack stand, the settling data of the most static observation beam body, after determining situation without exception, then carry out placing steel plate for filling up the space between temporary support or bearing and cast-in-situ continuous beam and slowly falling beam body after rise.
CN201610377579.2A 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing Active CN105839920B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610377579.2A CN105839920B (en) 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610377579.2A CN105839920B (en) 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing

Publications (2)

Publication Number Publication Date
CN105839920A true CN105839920A (en) 2016-08-10
CN105839920B CN105839920B (en) 2017-10-20

Family

ID=56595436

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610377579.2A Active CN105839920B (en) 2016-05-31 2016-05-31 The construction method for end temporary steel support support replacement of standing

Country Status (1)

Country Link
CN (1) CN105839920B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437157A (en) * 2016-11-11 2017-02-22 上海市机械施工集团有限公司 Axial force grouping and regulating method for steel support structure
CN109457708A (en) * 2018-12-14 2019-03-12 中冶天工集团有限公司 The construction method of temporary support in a kind of deep foundation ditch concrete structure construction procedure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001159232A (en) * 1999-12-01 2001-06-12 Hitachi Building Systems Co Ltd Moving scaffold device and installation method using moving scaffold device
JP4191235B1 (en) * 2007-12-28 2008-12-03 株式会社Just.Will Temporary support joint, temporary structure, and multi-story slab construction method
CN201762667U (en) * 2010-09-16 2011-03-16 中铁十九局集团第二工程有限公司 Fine adjustment system for moving beam
CN103075163A (en) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 Support change process of second liner construction of large-cross-section tunnel
CN104141383A (en) * 2014-07-16 2014-11-12 北京万兴建筑集团有限公司 Bailey beam suspension formwork supporting system and construction method thereof
CN105507168A (en) * 2015-12-30 2016-04-20 中交第三航务工程局有限公司 Multi-span box girder integral ultrahigh alternate jacking construction system and method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001159232A (en) * 1999-12-01 2001-06-12 Hitachi Building Systems Co Ltd Moving scaffold device and installation method using moving scaffold device
JP4191235B1 (en) * 2007-12-28 2008-12-03 株式会社Just.Will Temporary support joint, temporary structure, and multi-story slab construction method
CN201762667U (en) * 2010-09-16 2011-03-16 中铁十九局集团第二工程有限公司 Fine adjustment system for moving beam
CN103075163A (en) * 2012-12-28 2013-05-01 成都中铁隆工程集团有限公司 Support change process of second liner construction of large-cross-section tunnel
CN104141383A (en) * 2014-07-16 2014-11-12 北京万兴建筑集团有限公司 Bailey beam suspension formwork supporting system and construction method thereof
CN105507168A (en) * 2015-12-30 2016-04-20 中交第三航务工程局有限公司 Multi-span box girder integral ultrahigh alternate jacking construction system and method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437157A (en) * 2016-11-11 2017-02-22 上海市机械施工集团有限公司 Axial force grouping and regulating method for steel support structure
CN106437157B (en) * 2016-11-11 2020-02-21 上海市机械施工集团有限公司 Grouping regulation and control method for axial force of steel support structure
CN109457708A (en) * 2018-12-14 2019-03-12 中冶天工集团有限公司 The construction method of temporary support in a kind of deep foundation ditch concrete structure construction procedure

Also Published As

Publication number Publication date
CN105839920B (en) 2017-10-20

Similar Documents

Publication Publication Date Title
CN109778721A (en) Synchronization of jacking up bridge top and the bottom structure carries out the method that bridge increases transformation
CN104562924B (en) Bridge pad from jacking backing plate replacing options
CN108265618B (en) Underground reverse storey-adding construction method for viaduct pier foundation
CN103912010A (en) Construction method of open excavation prefabricated underground structure
ITBO20060414A1 (en) METHOD FOR LIFTING A BUILDING AFT.
CN103981816A (en) Construction method for underpinning of overpass framework pier columns
CN103821090A (en) Deviation correcting and resetting method for inclined bridge pier
CN109208610B (en) Dynamic adjusting method for pre-stress of lateral support for excavation of close-connection large-load bias foundation pit
CN103216114B (en) The translation construction method of building
CN111259478B (en) Method for inhibiting deformation of existing cutting gravity type retaining wall
CN104294769B (en) A kind of piling and the construction method increasing the built bridge abutment structure of platform cap composite reinforcement
CN105133856A (en) Method for integrally displacing building by utilizing assembly trailer
CN106320737A (en) Integral lifting method for ancient building
CN103469732B (en) Construction method of preformed holes for foundation bolts of bridge support
CN105839920A (en) Construction method for station-end temporary steel support replacement
CN209855277U (en) Conversion layer structure for underground added layer of existing building
CN103290851A (en) Prestressed steel support used for controlling internal and external differential displacement of foundation pit enclosure wall and construction method
CN204875481U (en) Arched bridge of main mound thrust can balance
CN102936897A (en) Steel bridge capable of being used as supporting and reinforcing structure
CN104652842B (en) Building integral error correcting and position, raise method for improving and its equipment
CN204097889U (en) A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement
JP2004316100A (en) Construction method for building
CN106812065A (en) A kind of concrete freely-supported pre-stressed box girder construction process
CN205012596U (en) Defense sector face is uniform settlement structure not
CN108330762A (en) A kind of structural adjustment system and method for the reply backfilled roadbed supported sedimentation of super thick

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant