CN105807749A - Test platform and test method for power dispatching automatic master station system - Google Patents

Test platform and test method for power dispatching automatic master station system Download PDF

Info

Publication number
CN105807749A
CN105807749A CN201410838561.9A CN201410838561A CN105807749A CN 105807749 A CN105807749 A CN 105807749A CN 201410838561 A CN201410838561 A CN 201410838561A CN 105807749 A CN105807749 A CN 105807749A
Authority
CN
China
Prior art keywords
test
power
control
main station
simulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410838561.9A
Other languages
Chinese (zh)
Other versions
CN105807749B (en
Inventor
杨清波
李立新
狄方春
花静
李宇佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, China Electric Power Research Institute Co Ltd CEPRI filed Critical State Grid Corp of China SGCC
Priority to CN201410838561.9A priority Critical patent/CN105807749B/en
Publication of CN105807749A publication Critical patent/CN105807749A/en
Application granted granted Critical
Publication of CN105807749B publication Critical patent/CN105807749B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a test platform and a test method for a power dispatching automatic master station system. A supporting layer, a power system simulation layer, a dispatching automatic system simulation layer, a test verification layer and an interface adapting layer are organically integrated into the test platform, so that a set of standard test environment configuration is provided, and test items including source code test, control software closed-loop test, power system avalanche test, protocol test and the like can be provided for the dispatching automatic master station system. The creation of the test platform for the dispatching automatic master station system effectively integrates various test verification resources, and the test platform realizes standard and automatic test on tested objects. The tested system or functional module is connected to the test verification platform in a mode of 'plug and play', so that the debugging time for connecting the tested system to the test system is reduced, the test resource utilization efficiency and the working efficiency are improved, and the automation level of the test work is improved.

Description

A kind of power dispatching automation main station system test platform and method of testing thereof
Technical field
The present invention relates to the test platform in a kind of power dispatching automation field and method of testing thereof, in particular to a kind of power dispatching automation main station system test platform and method of testing thereof.
Background technology
Along with the development of software industry, the quality control of software product and quality management are increasingly becoming the core of software enterprise's survival and development.Software test plays vital effect as the important step of speed measuring with software controlling unit, and its necessity has been entirely policy maker in the industry and has been received.Software test is a kind of technological means promoting software quality and region be directly facing application, its objective is to find the defect that software exists, with the hidden danger gone wrong after reducing running software, is a technical process in software detection activity.
From whether being concerned about software inhouse structure and the angular divisions implemented, software test ripe at present is theoretical and method, mainly has following three kinds:
1) Black-box Testing is theoretical.The function that known product should have, detecting each function by test is
No can normally use.When test, software system is regarded as a black basin that can not open, when giving no thought to program internal structure and bulk properties, in the test that routine interface carries out, it only checks that whether as desired the regulation of program function description normally uses, whether can suitably receive input number saw and produce correct output information, and keep the integrity of external information.
2) white-box testing is theoretical.Known product inner workings, detects interiors of products action by testing
Whether it is normally carried out according to the regulation of description.Construction test procedure within program, whether every path in testing procedure has correctly can work by pre-provisioning request, and the main method of white-box testing has logical drive, base drive test examination etc., is mainly used in software verification.
3) grey box testing is theoretical.A kind of method of testing between Black-box Testing and white-box testing.To possessing
The test of software platform character product, has been difficult to by black box manual test.And white-box testing carries out in unit testing, it is clear that the test of product is brought significant limitation, the problem that product brings in integrating process also cannot be tested.Grey box testing pays close attention to the output correctness for inputting, and also pays close attention to internal performance simultaneously, but this concern is detailed unlike whitepack, complete, judge internal running status simply by some representational phenomenons, event, mark.
Along with intelligent grid enters the propelling that all-round construction stage and State Grid Corporation of China big operation architecture is built, the new system of a large amount of grid automations, new equipment will put into operation in succession, need it is carried out comprehensive, detailed assessment and test, to guarantee that new system, new equipment disclosure satisfy that the requirement of standardization while reliable and stable operation.But, dispatching automation main station system is many due to system complex, function, not yet carries out test assessment for total system both at home and abroad, and its basis is weaker.The current scheduling station test job carried out is mainly the test to scattered dispatching automation main website subsystem or functional module and the integration testing of system.Scattered test, cannot adapt to enforcement and the upgrading needs of complex large-sized system.
The test of dispatching automation main station system software has following demand:
1) need to carry out source code test:
Dispatching automation main station system produced problem in actual moving process, has major part to be disguised very strong software code mass defect and causes, and traditional Black-box Testing mode cannot effectively find problems.For the practical problem that dispatching automation main station system runs in exploitation and the process that puts into operation, the source code of the nucleus module of scheduling automatic main station system need to be carried out white-box testing.
2) need power system is emulated:
AVC, AGC of dispatching automation main station system etc. control class software and to realize needing the closed loop control of power system practical power systems is emulated, mainly include power system primary equipment such as unit, bus, circuit, capacity reactance device, transformator, and Real-Time Power System Operation States, behavior and response are emulated.
3) need power plant and monitoring system of electric substation are emulated:
Power plant and monitoring system of electric substation are the Data Sources of dispatching automation main station system, it is necessary to communicate with dispatching automation main station system, also to receive the control command issued of dispatching automation main station system, it is achieved the control to electrical network simultaneously.
4) need multi-stage scheduling mechanism is emulated:
Under the regulation and administration system of fractional distribution, the dispatching of power netwoks of China controls the industrial control system that system is system-level (multistage power grid dispatching patcher), it is necessary to realize multilevel coordination control, especially electrical network closed loop control (AGC, AVC etc.);
5) need electrical network snowslide data are emulated:
Millions of electric network datas to be processed by power network schedule automation main station system test platform in real time, and especially when accident occurs in electrical network, real-time data of power grid amount can occur avalanche type to increase.
Building of power network schedule automation main station system test platform can effectively integrate various test resource, it is achieved to the standardization of system under test (SUT), automatization's examination test.
Summary of the invention
For solving deficiency of the prior art, the goal of the invention of the present invention is the operation characteristic according to power dispatching automation main station system, based on software testing technology, Object-Oriented Design Technology, emulation technology and system integration technology, a kind of power dispatching automation main station system test platform is proposed, it is provided that electrically-based dispatching automation main station system test platform realizes electric power scheduling automatization system carries out source code test, the method controlling class software closed loop test, electrical network snowslide data test.
It is an object of the invention to adopt following technical proposals to realize:
The present invention provides a kind of power dispatching automation main station system test platform, and it thes improvement is that, described test platform is bottom-up to be included successively:
(1) supporting layer: include computer hardware equipment, operating system and data base, for supporting the operation of power network schedule automation main station system test platform;
(2) electric system simulation layer: electric power system model, device model and electrical network behavior and response are emulated, is used for simulating real power system environment;
(3) dispatch automated system simulation layer: include main station simulation system and plant stand analogue system, wherein main station simulation system includes coordination control and the security protection system of multistage main website, it is used for docking with each ingredient of tested main station system, plant stand analogue system includes supervisory control of substation analogue system and power plant supervisory control simulation system, it is achieved the multilevel coordination closed loop control function of system is carried out verification experimental verification;
(4) verification experimental verification layer: by the testing tool of integrated specialty and subsystem, realize source code, function, performance, stability, standard compliance, compatibility, safety etc. are carried out verification experimental verification while, it is achieved that to multilevel coordination closed loop control, snowslide environmental simulation typical complex power grid control function, performance test.
(5) interface adaptation layer: adopt many general standard interface, it is ensured that the measurand of dispatching automation main station system can the access interface adaptation layer of " plug and play " without any amendment.
The present invention also provides for the method for testing of a kind of power dispatching automation main station system test platform, and it thes improvement is that, described method includes following aspect: 1. dispatching automation main station system source code test;2. dispatching automation main station system controls closed loop test and the 3. electrical network snowslide test of generic module.
Further, described 1. realized by verification experimental verification layer, adopt and realize scheduling automatic main station system source code is carried out static structure analysis, rest mass tolerance and rule check analysis checking based on semantic Static Analysis Technology;
Static analysis includes:
1) data-flow analysis: represented by source code figure, node is the basic block of source code, while be describe to control to transfer to another basic block from a brick;
2) based on the analysis of constraint: produce local restriction from source code, by resolving the constraint checking all properties produced.
3) type and interpretation of result: type and interpretation of result are the combinations of the type system of result system and annotation, the execution result of one statement of result system expression, and the type system of annotation provides the semanteme of result system.
Further, described 2. in, dispatching automation main station system control generic module include automatism voltage control AVC module and Automation generation control module;
Wherein:
<1>closed loop test of automatism voltage control AVC module comprises the steps:
A, plant stand analogue system are positioned at the dispatch automated system simulation layer of verification experimental verification platform and include power plant control system and transformer station's integrated monitoring system, and receive and perform the control command for unit, bus, reactive power compensator or load tap changer that the automatism voltage control AVC module of main station simulation system issues, and the locking information of unit, bus, reactive power compensator or load tap changer is returned main website;
After B, execution control command, unit is idle exerts oneself, the change reflection of reactive power compensator switching state and transformer gear is in the generating set model of electric system simulation layer, capacity reactance device model and transformer model, electric system simulation layer calculates the operation of power networks state after control command performs, and it is fed back in dispatching automation main station system, it is achieved the closed loop test to automatism voltage control AVC module;
For provincial and above electrical network automatism voltage control AVC module, the subordinate's scheduling automatism voltage control AVC module simulated by being positioned at the main station simulation system of the dispatch automated system simulation layer of verification experimental verification platform receives the control target that its (it refers to provincial and above electrical network automatism voltage control AVC module) issues, it is controlled order again decompose and issue operation, it is achieved multi-stage scheduling coordinates the verification experimental verification controlled;
<2>closed loop test of Automation generation control module comprises the steps:
A, plant stand analogue system include power plant control system and transformer station's integrated monitoring system, receive and perform the control command for unit that the Automation generation control module of main station simulation system issues, and by the meritorious return main website of exerting oneself of unit;
After B, execution control command, the change reflection of unit output is in the generating set model of electric system simulation layer, electric system simulation layer calculates the operation of power networks state after control command performs, and it is fed back in dispatching automation main station system simulation layer, it is achieved the closed loop test to Automation generation control module.
Further, described 3. in, electrical network snowslide test for checking because of power grid accident cause electric network information to increase severely time, power system process accident ability;Tested power system is passed through in proof procedure the plant stand analogue system of standard interface adaptation layer access dispatching automated system simulation layer, and the simulation of plant stand analogue system generates the snowslide data of multiple plant stands;Electric network information includes remote signalling displacement information, sequence of events recording SOE information and telemetry intelligence (TELINT);
Plant stand analogue system provides real time mass data, simulation plant-station accesses number no less than 1000, need the normal of power system simulation amount, quantity of state, the varied number of sequence of events recording SOE, period of change, variation pattern, quality of data flag bit and remote terminal control system RTU and abnormal operation are emulated according to test simultaneously, support remote control, remote regulating, channel operation, multi-source data craft and switching at runtime;
When the information change amount set, whether checking power system processes normally, and whether the process including remote measurement and remote signalling real time data is normal;Whether sequence of events recording SOE transmits in time;Whether remote regulating and guidance command process correct, utilize network test subsystem that verification experimental verification layer provides and computing power test analysis subsystem to monitor whether system performance index meets the requirements simultaneously.
Compared with immediate prior art, the excellent effect that technical scheme provided by the invention has is:
A kind of dispatching automation main station system test platform provided by the invention and method of testing, supporting layer, electric system simulation layer, dispatch automated system simulation layer, verification experimental verification layer, interface adaptation layer are organically integrated into a test platform, provide the configuration of standard set test environment, can for test events such as the offer source code test of dispatching automation main station system, control class software closed loop test, power system snowslide test, protocol convert.The establishment of dispatching automation main station system test platform effectively incorporates various verification experimental verification resource, it is achieved to the standardization of measurand, automatic test.System under test (SUT) or functional module access test platform in the way of " plug and play ", while reducing the debugging time that system under test (SUT) accesses test system, improve test resource utilization ratio and work efficiency, promote the automatization level of test job.
Accompanying drawing explanation
Fig. 1 is power network schedule automation main station system test platform Organization Chart provided by the invention;
Fig. 2 is AVC/AGC closed loop control logic flow chart provided by the invention.
Detailed description of the invention
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is described in further detail.
The present invention is used technical term and carries out description below:
1) dispatch automated system: dispatch automated system is a computer system integrating data acquisition, control, communication and analysis decision function, by dispatching automation main station system, dispatching automation substation system and connect the two communication system and constitute.
2) dispatching automation main station system: comprise front-end system, basic platform and monitor in real time and the application of early warning class, the application of operation plan class, the application of Security Checking class, management and running class application four big class application.The functions such as the main realization each plant stand RTU data of reception, data process, operation monitoring, control command issue.
3) closed loop control: be also feedback control, is by the measured value of system output compared with desired set-point, thus produces a deviation signal, utilizes this deviation signal to be adjusted controlling, makes output valve as far as possible close to expected value.
4) AVC: automatism voltage control (AutomaticVoltageControl) utilizes computer and communication technology, idle resource in electrical network and voltage adjusting device are automatically controlled, under the effect and given voltage constraints of automaton, the excitation of electromotor, transformer station reactive power compensator exert oneself and the tap of transformator can automatically carry out closed loop adjustment by instruction, it is made to inject the idle optimal value moving closer to grid requirements of electrical network, to reach to ensure the purpose of power grid security, high-quality and economical operation.
5) AGC: it is a critical function in EMS EMS that automatic generation amount controls AGC (AutomaticGenerationControl), it controls exerting oneself of frequency modulation unit, to meet the electricity needs being continually changing, and system is made to be in the running status of economy.
It is provided by the invention that a kind of power network schedule automation main station system test platform is bottom-up includes supporting layer, electric system simulation layer, dispatch automated system simulation layer, verification experimental verification layer and interface adaptation layer successively.Power network schedule automation main station system test platform framework is as shown in Figure 1.Wherein:
(1) supporting layer includes computer hardware equipment, operating system, database basis software and hardware, is used for supporting the operation of whole power network schedule automation main station system test platform;
(2) electric power system model, device model and electrical network behavior and response are emulated by electric system simulation layer, are used for simulating real power system environment.
(3) dispatch automated system simulation layer includes main station simulation system and plant stand analogue system, wherein main station simulation system includes coordination control and the security protection system of multistage main website, it is used for docking with each ingredient of tested main station system, plant stand analogue system includes supervisory control of substation analogue system and power plant supervisory control simulation system, it may be achieved the multilevel coordination closed loop control function of system is carried out verification experimental verification.
(4) validation layer testing tool by integrated specialty and subsystem are tested, while realizing source code, function, performance, stability, standard compliance, compatibility, safety etc. are carried out verification experimental verification, it is achieved that the test to the typical complex power grid control functions such as multilevel coordination closed loop control, snowslide environmental simulation, performance.
(6) interface adaptation layer adopt many general standard interface, it is ensured that the measurand of dispatching automation main station system without any amendment just can " plug and play " be linked into verification experimental verification platform.
The present invention also provides for the method for testing of a kind of power network schedule automation main station system test platform, including:
1. source code detection method: program source code is as the least unit constituting software system, and its quality is the basic guarantee of software system quality.Source code validation technology can at the software development initial stage, it is not necessary to code runs, and just can find quality and the safety problem of source code.
Can realize source code carries out the analysis verification that static structure analysis, rest mass tolerance and rule check based on semantic Static Analysis Technology.Abstract program constraint is used to carry out the structure of map source code based on semantic static analysis, when program is performed, the set of state and behavior is predicted, adopt substitution method, simplifying all of program problem analysis is the problem can followed the tracks of and calculate, use abstract tree (AbstractSyntaxTree), source code is built an AST by the method utilizing technique of compiling, is simultaneously introduced the description of semantic state.
Described static structure analysis refers to and need not perform tested code, by using testing tool to analyze the system authority of program source code, data structure, data-interface and inner control logic, generating function call graph, module controlling stream graph, internal file call graph, subroutine table, grand and function's parameter list, can clearly identify the composition structure of whole software system, check, by analysis diagram, the defect that software exists.
Rest mass tolerance is that the program code to tested software carries out code file type, size of code, annotation rate, number of modules and module cyclomatic complexity aspect and measures, analyzes and add up, and from functional, reliability, availability, effectiveness, maintainability, six convenience of portability, software is carried out quality metric.
Use software rules checking tool, according to country, industry or company standard, program code is programmed inspection and the analysis of criterion, and add up thousand row and run counter to rate.
Static analysis mainly uses following four basic skills:
1) data-flow analysis.Being represented by program figure, node is the basic block of program, while be describe to control how to transfer to another basic block from a brick, as drawn equation with the abstract of limit in scheming, it is possible to the Reachability question of settlement procedure.
2) based on the analysis of constraint.A series of local restriction is produced, by resolving the constraint checking all properties produced from program documentaion.
3) abstract parsing.Program maps being become more abstract territory (Domain), makes analysis more have trackability and have the effect of inspection code, abstract parsing immediately arrives at analysis result by calculating consolidation, rather than uses the mode of checking to be analyzed.
4) type and interpretation of result.Type and interpretation of result are the combinations of the type system of result system and annotation, the execution result of one statement of result system expression, and the type system of annotation provides the semanteme of result system.Type and interpretation of result are widely used in all kinds of compiler.
2. class software closed loop test method is controlled:
Dispatching automation main station system controls class software and mainly includes automatism voltage control (AVC) and Automatic Generation Control (AGC) etc..Main website of application schedules automatization system test platform, it is possible to analogue simulation control command issue after action and state, it is achieved the closed loop test of power grid control class software.Can being emulated by multi-stage scheduling, the effectiveness and the correctness that control are coordinated in checking, and power grid control class software closed-loop control logical flow chart is as shown in Figure 2 simultaneously.
<1>AVC software pilot verification method comprises the steps:
A, plant stand analogue system part include power plant control system and transformer station's integrated monitoring system, the control command for unit or bus and reactive power compensator or load tap changer that AVC main website issues can be received and perform, and the locking information of this equipment etc. main website can be returned.
After B, control command perform, unit is idle exerts oneself, the change of reactive power compensator switching state and transformer gear can reflect in the models such as the generating set of electric system simulation layer, capacity reactance device, transformator, electric system simulation layer calculates the operation of power networks state after control command performs, and it is fed back in dispatching automation main station system, it is achieved the closed loop test to AVC software.
For provincial and above electrical network AVC software, it is possible to the subordinate scheduling AVC being emulated partial simulation by main station system receives its control target issued, then it is controlled order and decomposes and wait operation with issuing, it is achieved multi-stage scheduling coordinates the verification experimental verification of control.
<2>AGC software pilot verification method
The verification experimental verification of a, AGC software is similar to AVC, and the control system of power plant of plant stand system emulation part receives and perform the control command to unit that AGC main website issues, and the locking information of this equipment etc. can be returned main website.
After b, control command perform, unit is gained merit to exert oneself and is changed in the generating set model that can reflect electric system simulation layer, electric system simulation layer calculates the operation of power networks state after control command performs, and it is fed back in power network schedule automation main station system, it is achieved the closed loop test to AGC software.
3. electrical network snowslide method of testing
The power grid environment of real time execution is complicated and changeable, and the power grid accident caused because of grid equipment or system problem is inevitable.Snowslide test for checking because of power grid accident cause electric network information (remote signalling displacement and SOE, telemetry intelligence (TELINT) etc.) to increase severely time, system processes the ability of accident.In verification experimental verification process, by standard adaptable interface, system under test (SUT) being accessed plant stand analogue system, the simulation of plant stand analogue system generates the snowslide data of multiple plant stands.
Plant stand analogue system can provide real time mass data, simulation plant-station accesses number no less than 1000, can need the normal of analog quantity, quantity of state, the varied number of SOE, period of change, variation pattern, quality of data flag bit and RTU and abnormal operation are emulated according to test simultaneously, support remote control, remote regulating, channel operation, multi-source data craft and switching at runtime etc..
When the information change amount set, whether checking system processes normally, whether the process including the real time data such as remote measurement, remote signalling is normal, whether SOE can transmit in time, whether remote regulating, guidance command process correct, utilize network test subsystem that verification experimental verification layer provides and computing power test analysis subsystem to monitor whether system property indices meets the requirements simultaneously.
Embodiment
Controlling class hapalonychia closed loop test selects the Historic Section that certain provincial power network is spaced apart 5 minutes to carry out power grid control class software closed-loop control functional verification, and sectional model magnitude is as shown in table 1.Power dispatching automation main station system test platform adopts two kinds of control conditions that the closed loop control function of AVC software is verified.
Table 1 sectional model magnitude
Control condition one be pointed to load center single power plant bus (certain economize. west city steam power plant/220kV. east bus) be controlled, control condition two is that the bus to 22 power plant is controlled.Control voltage course to consider to control voltage flatness, need each adjustment step-length is limited (220kV and above busbar voltage adjust step-length < 2kV, 110kV and following electric pressure mother's pressure-wire adjust step-length < the 1.5% of corresponding voltage grade).Table 2 arrives the checking data that table 4 is Intelligent electric network control system AVC software closed-loop control function.
Table 2AVC closed loop checking network loss optimizes data
Data that the checking of table 3AVC closed loop (controls condition one)
Data that the checking of table 4AVC closed loop (controls condition two)
By whole control process is carried out analogue simulation, it can be seen that the quantity of controllable device is notable on dropping the impact of damage amount.Participating in the damage amount that drops when controlling at 22 power plant's buses is about 10 times during the bus participation control of single power plant, as shown in table 2.Table 3 shows that certain being positioned at load center is economized. west city steam power plant/220kV. east busbar voltage adjustment amount is maximum, along with the increase Voltage Cortrol amount of the bus physics wiring of controlled power plant Yu load center distance progressively reduces.Table 4 shows when controllable device is sufficient, AVC makes full use of the idle resource of load center in the scope ensureing voltage reasonable, owing to certain is economized. neat heat plant/220kV. bis-bus electrical distance is distant with load center, the idle abundance in local, carry out turning down process to voltage, met voltage and automatically control Controlling principle on the spot.
Above test data shows, power dispatching automation main station system test platform achieves the analysis verification to power grid control class software AVC closed loop control function.
Finally should be noted that: above example is only in order to illustrate that technical scheme is not intended to limit; although the present invention being described in detail with reference to above-described embodiment; the specific embodiment of the present invention still can be modified or equivalent replacement by those of ordinary skill in the field; these are without departing from any amendment of spirit and scope of the invention or equivalent replace, within the claims of the present invention all awaited the reply in application.

Claims (5)

1. a power dispatching automation main station system test platform, it is characterised in that described test platform is bottom-up to be included successively:
(1) supporting layer: include computer hardware equipment, operating system and data base, for supporting the operation of power network schedule automation main station system test platform;
(2) electric system simulation layer: electric power system model, device model and electrical network behavior and response are emulated, is used for simulating real power system environment;
(3) dispatch automated system simulation layer: include main station simulation system and plant stand analogue system, wherein main station simulation system includes coordination control and the security protection system of multistage main website, it is used for docking with each ingredient of tested main station system, plant stand analogue system includes supervisory control of substation analogue system and power plant supervisory control simulation system, it is achieved the multilevel coordination closed loop control function of system is carried out verification experimental verification;
(4) verification experimental verification layer: by the testing tool of integrated specialty and subsystem, realize source code, function, performance, stability, standard compliance, compatibility, safety etc. are carried out verification experimental verification while, it is achieved that to multilevel coordination closed loop control, snowslide environmental simulation typical complex power grid control function, performance test;
(5) interface adaptation layer: adopt many general standard interface, it is ensured that the measurand of dispatching automation main station system can the access interface adaptation layer of " plug and play " without any amendment.
2. the method for testing of a power dispatching automation main station system test platform as claimed in claim 1, it is characterised in that described method includes following aspect: 1. dispatching automation main station system source code test;2. dispatching automation main station system controls closed loop test and the 3. electrical network snowslide test of generic module.
3. method of testing as claimed in claim 2, it is characterized in that, described 1. realized by verification experimental verification layer, adopt and realize scheduling automatic main station system source code is carried out static structure analysis, rest mass tolerance and rule check analysis checking based on semantic Static Analysis Technology;
Static analysis includes:
1) data-flow analysis: represented by source code figure, node is the basic block of source code, while be describe to control to transfer to another basic block from a brick;
2) based on the analysis of constraint: produce local restriction from source code, by resolving the constraint checking all properties produced;
3) type and interpretation of result: type and interpretation of result are the combinations of the type system of result system and annotation, the execution result of one statement of result system expression, and the type system of annotation provides the semanteme of result system.
4. method of testing as claimed in claim 2, it is characterised in that described 2. in, dispatching automation main station system controls generic module and includes automatism voltage control AVC module and Automation generation control module;
Wherein:
<1>closed loop test of automatism voltage control AVC module comprises the steps:
A, plant stand analogue system are positioned at the dispatch automated system simulation layer of verification experimental verification platform and include power plant control system and transformer station's integrated monitoring system, and receive and perform the control command for unit, bus, reactive power compensator or load tap changer that the automatism voltage control AVC module of main station simulation system issues, and the locking information of unit, bus, reactive power compensator or load tap changer is returned main website;
After B, execution control command, unit is idle exerts oneself, the change reflection of reactive power compensator switching state and transformer gear is in the generating set model of electric system simulation layer, capacity reactance device model and transformer model, electric system simulation layer calculates the operation of power networks state after control command performs, and it is fed back in dispatching automation main station system, it is achieved the closed loop test to automatism voltage control AVC module;
For provincial and above electrical network automatism voltage control AVC module, the subordinate's scheduling automatism voltage control AVC module simulated by being positioned at the main station simulation system of the dispatch automated system simulation layer of verification experimental verification platform receives the control target that its (it refers to provincial and above electrical network automatism voltage control AVC module) issues, it is controlled order again decompose and issue operation, it is achieved multi-stage scheduling coordinates the verification experimental verification controlled;
<2>closed loop test of Automation generation control module comprises the steps:
A, plant stand analogue system include power plant control system and transformer station's integrated monitoring system, receive and perform the control command for unit that the Automation generation control module of main station simulation system issues, and by the meritorious return main website of exerting oneself of unit;
After B, execution control command, unit output change reflection is in the generating set model of electric system simulation layer, electric system simulation layer calculates the operation of power networks state after control command performs, and it is fed back in dispatching automation main station system simulation layer, it is achieved the closed loop test to Automation generation control module.
5. method of testing as claimed in claim 2, it is characterised in that described 3. in, electrical network snowslide test for checking because of power grid accident cause electric network information to increase severely time, the ability of power system process accident;Tested power system is passed through in proof procedure the plant stand analogue system of standard interface adaptation layer access dispatching automated system simulation layer, and the simulation of plant stand analogue system generates the snowslide data of multiple plant stands;Electric network information includes remote signalling displacement information, sequence of events recording SOE information and telemetry intelligence (TELINT);
Plant stand analogue system provides real time mass data, simulation plant-station accesses number no less than 1000, need the normal of power system simulation amount, quantity of state, the varied number of sequence of events recording SOE, period of change, variation pattern, quality of data flag bit and remote terminal control system RTU and abnormal operation are emulated according to test simultaneously, support remote control, remote regulating, channel operation, multi-source data craft and switching at runtime;
When the information change amount set, whether checking power system processes normally, and whether the process including remote measurement and remote signalling real time data is normal;Whether sequence of events recording SOE transmits in time;Whether remote regulating and guidance command process correct, utilize network test subsystem that verification experimental verification layer provides and computing power test analysis subsystem to monitor whether system performance index meets the requirements simultaneously.
CN201410838561.9A 2014-12-29 2014-12-29 A kind of power dispatching automation main station system test platform and its test method Active CN105807749B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410838561.9A CN105807749B (en) 2014-12-29 2014-12-29 A kind of power dispatching automation main station system test platform and its test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410838561.9A CN105807749B (en) 2014-12-29 2014-12-29 A kind of power dispatching automation main station system test platform and its test method

Publications (2)

Publication Number Publication Date
CN105807749A true CN105807749A (en) 2016-07-27
CN105807749B CN105807749B (en) 2018-11-16

Family

ID=56980734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410838561.9A Active CN105807749B (en) 2014-12-29 2014-12-29 A kind of power dispatching automation main station system test platform and its test method

Country Status (1)

Country Link
CN (1) CN105807749B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107634878A (en) * 2017-09-14 2018-01-26 郑州云海信息技术有限公司 A kind of performance test management platform
CN108539800A (en) * 2018-03-19 2018-09-14 南方电网科学研究院有限责任公司 A kind of AGC closed loop test methods and device
CN108958216A (en) * 2018-06-06 2018-12-07 南京国电南自电网自动化有限公司 The automatic checkout system and method for new energy AGC or AVC control system
CN109067956A (en) * 2018-08-01 2018-12-21 北京奇安信科技有限公司 Method and device that terminal for police system is detected, police system
CN109342848A (en) * 2018-09-29 2019-02-15 国网河北省电力有限公司电力科学研究院 Avalanche test method, system and terminal device for dispatching automation main website
CN110018392A (en) * 2019-04-12 2019-07-16 许继集团有限公司 A kind of test macro of electrical power distribution automatization system main website
CN110765616A (en) * 2019-10-24 2020-02-07 南方电网科学研究院有限责任公司 Simulation closed loop test system and method for power plant computer monitoring system
CN110908296A (en) * 2019-11-25 2020-03-24 深圳供电局有限公司 Method and system for automatically testing virtual power plant regulation and control system
CN110932401A (en) * 2019-12-05 2020-03-27 国网辽宁省电力有限公司锦州供电公司 Method for improving safety of remote control high-voltage switch
CN111600760A (en) * 2020-05-25 2020-08-28 广东电科院能源技术有限责任公司 Quality detection system, method and equipment of power grid operation monitoring system
CN114143101A (en) * 2021-12-03 2022-03-04 中国南方电网有限责任公司 Network attack simulation platform system of power grid

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011145209A (en) * 2010-01-15 2011-07-28 Chugoku Electric Power Co Inc:The Device and method for testing of ground fault relay
CN102209074A (en) * 2011-05-30 2011-10-05 中国电力科学研究院 All-digital dynamic simulation system of power system
CN103123758A (en) * 2012-11-28 2013-05-29 大同电力高级技工学校 Dispatching automation digital physical hybrid simulation training system
CN103544555A (en) * 2013-08-22 2014-01-29 国家电网公司 Uniform resource management platform for automatic power grid dispatch system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011145209A (en) * 2010-01-15 2011-07-28 Chugoku Electric Power Co Inc:The Device and method for testing of ground fault relay
CN102209074A (en) * 2011-05-30 2011-10-05 中国电力科学研究院 All-digital dynamic simulation system of power system
CN103123758A (en) * 2012-11-28 2013-05-29 大同电力高级技工学校 Dispatching automation digital physical hybrid simulation training system
CN103544555A (en) * 2013-08-22 2014-01-29 国家电网公司 Uniform resource management platform for automatic power grid dispatch system

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107634878A (en) * 2017-09-14 2018-01-26 郑州云海信息技术有限公司 A kind of performance test management platform
CN108539800A (en) * 2018-03-19 2018-09-14 南方电网科学研究院有限责任公司 A kind of AGC closed loop test methods and device
CN108958216A (en) * 2018-06-06 2018-12-07 南京国电南自电网自动化有限公司 The automatic checkout system and method for new energy AGC or AVC control system
CN109067956B (en) * 2018-08-01 2021-04-27 奇安信科技集团股份有限公司 Method and device for detecting terminal for police system and police system
CN109067956A (en) * 2018-08-01 2018-12-21 北京奇安信科技有限公司 Method and device that terminal for police system is detected, police system
CN109342848A (en) * 2018-09-29 2019-02-15 国网河北省电力有限公司电力科学研究院 Avalanche test method, system and terminal device for dispatching automation main website
CN109342848B (en) * 2018-09-29 2022-01-25 国网河北省电力有限公司电力科学研究院 Avalanche testing method and system for dispatching automation master station and terminal equipment
CN110018392A (en) * 2019-04-12 2019-07-16 许继集团有限公司 A kind of test macro of electrical power distribution automatization system main website
CN110018392B (en) * 2019-04-12 2021-11-19 许继集团有限公司 Test system of distribution automation system main station
CN110765616A (en) * 2019-10-24 2020-02-07 南方电网科学研究院有限责任公司 Simulation closed loop test system and method for power plant computer monitoring system
CN110908296A (en) * 2019-11-25 2020-03-24 深圳供电局有限公司 Method and system for automatically testing virtual power plant regulation and control system
CN110932401A (en) * 2019-12-05 2020-03-27 国网辽宁省电力有限公司锦州供电公司 Method for improving safety of remote control high-voltage switch
CN111600760A (en) * 2020-05-25 2020-08-28 广东电科院能源技术有限责任公司 Quality detection system, method and equipment of power grid operation monitoring system
CN114143101A (en) * 2021-12-03 2022-03-04 中国南方电网有限责任公司 Network attack simulation platform system of power grid

Also Published As

Publication number Publication date
CN105807749B (en) 2018-11-16

Similar Documents

Publication Publication Date Title
CN105807749A (en) Test platform and test method for power dispatching automatic master station system
CN103488835B (en) The emulation platform of a kind of dispatch automated system and emulation mode thereof
CN103199521B (en) Power network planning construction method based on network reconstruction and optimized load-flow simulating calculation
Rohjans et al. mosaik-A modular platform for the evaluation of agent-based Smart Grid control
CN102222982B (en) Method and device for realizing programmed operation of transformer station based on SVG (Scalable Vector Graphics) technology
CN103454928B (en) Based on reactive voltage control simulation system and the method thereof of power grid regulation one pattern
CN112260331B (en) Extra-high voltage alternating current-direct current power grid simulation platform and construction method
CN202735445U (en) Test system for intelligent transformer station secondary equipment scene
CN103995932A (en) Unified modeling method employing generalized measuring transverse correlation mode
CN207883176U (en) Power network schedule automation integration training system
CN104007978A (en) Intelligent substation secondary equipment logic emulation system
CN101727106A (en) Simulation test platform of process layer of digitalization transformer substation
CN105808880A (en) Relay protection setting method and system based on graphical power distribution network
CN102567800A (en) Decision-making modeling method for relay protection on-line condition based maintenance of power system
CN107133870B (en) Electric power spot transaction security check method based on 30-second period static analysis
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN105242134A (en) Distributed test method suitable for system-grade test of intelligent high-voltage equipment
CN107093151B (en) Intelligent section management and online safety check system for electric power system
CN103309312B (en) A kind of voltage security early warning based on multiple information sources and anti-Ore-controlling Role
CN202121376U (en) Scheduling automation analogue simulation device
CN204129734U (en) A kind of digital dynamic realtime emulation system
CN104376614A (en) One-key ticket outlet method for substation operation tickets
CN103760775A (en) Merging unit simulator
Ping et al. The reaserch of users-transformer relationship verification method based on data-driven
CN102185380A (en) Analogue simulator with automated dispatching

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant