CN110908296A - A method and system for automatic testing of a virtual power plant control system - Google Patents

A method and system for automatic testing of a virtual power plant control system Download PDF

Info

Publication number
CN110908296A
CN110908296A CN201911168755.1A CN201911168755A CN110908296A CN 110908296 A CN110908296 A CN 110908296A CN 201911168755 A CN201911168755 A CN 201911168755A CN 110908296 A CN110908296 A CN 110908296A
Authority
CN
China
Prior art keywords
test
control
power plant
data
virtual power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911168755.1A
Other languages
Chinese (zh)
Other versions
CN110908296B (en
Inventor
焦丰顺
鲍重廷
周浩
张植华
邓永生
向乾亮
岳程燕
程濛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Power Supply Bureau Co Ltd
Original Assignee
Shenzhen Power Supply Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Power Supply Bureau Co Ltd filed Critical Shenzhen Power Supply Bureau Co Ltd
Priority to CN201911168755.1A priority Critical patent/CN110908296B/en
Publication of CN110908296A publication Critical patent/CN110908296A/en
Application granted granted Critical
Publication of CN110908296B publication Critical patent/CN110908296B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B17/00Systems involving the use of models or simulators of said systems
    • G05B17/02Systems involving the use of models or simulators of said systems electric
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/36Prevention of errors by analysis, debugging or testing of software
    • G06F11/3668Testing of software
    • G06F11/3672Test management
    • G06F11/3684Test management for test design, e.g. generating new test cases
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/36Prevention of errors by analysis, debugging or testing of software
    • G06F11/3668Testing of software
    • G06F11/3672Test management
    • G06F11/3688Test management for test execution, e.g. scheduling of test suites

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Quality & Reliability (AREA)
  • General Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Testing And Monitoring For Control Systems (AREA)

Abstract

本发明涉及一种对虚拟电厂调控系统进行自动测试的方法,包括步骤:步骤S1、测试配置模块读取配置的调控对象模型与参数,生成系统测试脚本,测试用例以及测试仿真数据;步骤S2、仿真数据模块接收所述测试仿真数据文件,并生成测试用途的实时数据;步骤S3,优化运行模块对实时测试数据进行优化运行计算;步骤S4、测试验证模块读取本次测试用例的期望结果与优化运行计算结果进行对比,判断虚拟电厂调控系统运行是否异常。本发明还提供了相应的系统。实施本发明,可以全面测试虚拟电厂调控系统存在的问题,提高了测试效率,减少了测试时间。

Figure 201911168755

The invention relates to a method for automatically testing a control system of a virtual power plant, comprising the steps of: step S1, a test configuration module reads a configured control object model and parameters, and generates a system test script, test cases and test simulation data; step S2, The simulation data module receives the test simulation data file, and generates real-time data for testing purposes; step S3, the optimization operation module performs an optimization operation calculation on the real-time test data; step S4, the test verification module reads the expected result and the test case of this test case. The calculation results of the optimized operation are compared to determine whether the operation of the control system of the virtual power plant is abnormal. The present invention also provides a corresponding system. By implementing the invention, the problems existing in the control system of the virtual power plant can be fully tested, the test efficiency is improved, and the test time is reduced.

Figure 201911168755

Description

Method and system for automatically testing virtual power plant regulation and control system
Technical Field
The invention relates to a test method and a test system of a virtual power plant, in particular to a method and a system for automatically testing a regulation and control system of a virtual power plant.
Background
The virtual power plant is used as an energy aggregation form, and distributed adjustable and controllable resources such as large-scale distributed generator sets, controllable loads, distributed energy storage and the like are integrated into a virtual power plant regulation and control system; the system test of the resource widely distributed in the region is very difficult, the test work is heavy, the test efficiency is low, and the accuracy and the completeness of the test are difficult to ensure.
In order to solve the above problems, a method and a system for automatically testing a virtual power plant regulation and control system are needed.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a method and a system for automatically testing a virtual power plant regulation and control system, which can quickly verify whether the virtual power plant regulation and control system operates correctly, can simulate the test workload of the power plant regulation and control system, and improve the test efficiency and the test accuracy.
In order to solve the technical problem, in an aspect of the present invention, a method for automatically testing a virtual power plant regulation and control system is provided, where the virtual power plant regulation and control system includes a regulation and control master station and a plurality of regulation and control terminals, and the method includes the following steps:
step S1, a test configuration module arranged in the control master station automatically reads a control object model and parameters configured by the control master station, automatically generates a system test script, a test case and test simulation data, and sends the system test script, the test case and the test simulation data to the control terminal;
step S2, a simulation data module arranged in the regulation terminal receives the test simulation data file, generates real-time data of test use and sends the real-time data to the regulation master station;
step S3, the optimization operation module arranged in the regulation and control main station performs optimization operation calculation on the real-time test data received by the regulation and control main station from each regulation and control terminal, and stores the optimization result;
and S4, reading the expected result of the test case and the optimized operation calculation result of the test data by a test verification module arranged in the regulation and control main station, comparing the expected result with the optimized operation calculation result of the test data, and judging whether the operation of the virtual power plant regulation and control system is abnormal or not according to the comparison result.
Preferably, the simulation data format generated by the test configuration module is a general format for transient data exchange of the power system; the simulation data generated by the test configuration module includes current, voltage values, and power.
Preferably, the test configuration module sends the test simulation data to a signal generator connected to the control terminal, and generates simulation test data by receiving data of the signal generator.
Preferably, the system test script generated by the test configuration module includes all test cases and test simulation data corresponding to the test cases, and when the test system executes the script, each test case is automatically executed in sequence until the script is finished.
Preferably, the step S4 further includes:
if the test data optimization operation calculation result is the same as the expected result of the test case or within the error range specified by the expected result, judging that the virtual power plant regulation and control system operates correctly; otherwise, judging that the virtual power plant regulation and control system is abnormal in operation.
In another aspect of the present invention, a system for automatically testing a virtual power plant regulation and control system is further provided, where the virtual power plant regulation and control system includes a regulation and control master station and a plurality of regulation and control terminals, and the system for automatically testing the virtual power plant regulation and control system includes:
the test configuration module is arranged in the regulation and control main station and used for automatically reading a regulation and control object model and parameters configured by the regulation and control main station, automatically generating a system test script, a test case and test simulation data and sending the system test script, the test case and the test simulation data to the regulation and control terminal;
the simulation data module is arranged in the regulation and control terminal and used for receiving the test simulation data file, generating real-time data for test purposes and sending the real-time data to the regulation and control master station;
the optimization operation module is arranged in the regulation and control main station and used for performing optimization operation calculation on the real-time test data received by the regulation and control main station from each regulation and control terminal and storing an optimization result;
and the test verification module is arranged in the regulation and control main station and used for reading the expected result of the test case and comparing the result with the optimized operation calculation result of the test data obtained by the optimized operation module, and judging whether the operation of the virtual power plant regulation and control system is abnormal or not according to the comparison result.
Preferably, the simulation data format generated by the test configuration module is a general format for transient data exchange of the power system; the simulation data generated by the test configuration module includes current, voltage values, and power.
Preferably, further comprising:
and the signal generator is connected with the regulation and control terminal and used for receiving the test simulation data from the test configuration module and generating simulation test data.
Preferably, the system test script generated by the test configuration module includes all test cases and test simulation data corresponding to the test cases, and when the test system executes the script, each test case is automatically executed in sequence until the script is finished.
Preferably, the test verification module further comprises:
the comparison unit is used for reading the expected result of the test case and comparing the expected result with the optimized operation calculation result of the test data obtained by the optimized operation module;
the operation state judging unit is used for judging that the virtual power plant regulation and control system operates correctly when the comparison result of the comparison unit is that the optimal operation calculation result is the same as the expected result of the test case or is within the error range specified by the expected result; otherwise, judging that the virtual power plant regulation and control system is abnormal in operation.
By implementing the embodiment of the invention, the invention has the following beneficial effects:
in the method and the system for automatically testing the virtual power plant regulation and control system, the virtual power plant test configuration module reads the configuration and data of the regulation and control master station of the virtual power plant, automatically generates the test script, automatically tests the virtual power plant regulation and control system, and verifies the test result, thereby realizing the complete automatic test of the whole virtual power plant regulation and control system. The application of the method reduces the test workload of the virtual power plant regulation and control system, improves the test efficiency and the test accuracy, and is effective in the correct and stable operation of the virtual power plant regulation and control system.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
Fig. 1 is a schematic main flow chart of a method for automatically testing a virtual power plant regulation and control system according to the present invention;
FIG. 2 is a schematic structural diagram of an embodiment of a system for automatically testing a regulation system of a virtual power plant according to the present invention;
fig. 3 is a schematic structural diagram of the test verification module in fig. 2.
Detailed Description
In order to make the aforementioned objects, features and advantages of the present invention comprehensible, embodiments accompanied with figures are described in detail below. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention. This invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein, but rather should be construed as broadly as the present invention is capable of modification in various respects, all without departing from the spirit and scope of the present invention.
Referring to fig. 1, a main flow diagram of a method for automatically testing a virtual power plant regulation and control system provided by the present invention is shown. In this embodiment, the virtual power plant regulation and control system includes a regulation and control master station and a plurality of regulation and control terminals, and the method includes the following steps:
step S1, a test configuration module arranged in the control master station automatically reads a control object model and parameters configured by the control master station, automatically generates a system test script, a test case and test simulation data, and sends the system test script, the test case and the test simulation data to the control terminal;
specifically, in a practical example, the simulation data format generated by the test configuration module is a common format for transient data exchange of the power system; the simulation data generated by the test configuration module includes current, voltage values, and power. For example, in one example, the test simulation data is stored in a common format of transient data exchange of the power system, that is, a COMTRADE format file, and a COMTRADE format test simulation data file is created for all the regulation and control terminals participating in the test in the virtual power plant, and the virtual power plant master station establishes a communication link with each regulation and control terminal of the virtual power plant and correctly transmits the corresponding COMTRADE file to each regulation and control terminal in the virtual power plant.
Step S2, a simulation data module arranged in the regulation terminal receives the test simulation data file, generates real-time data of test use and sends the real-time data to the regulation master station; specifically, a simulation data module deployed at a virtual power plant regulation and control terminal interprets a received test simulation data file, the data file specifies that a data source is the module (such as the regulation and control terminal), and the simulation data module generates real-time test data according to the simulation data file and transmits the real-time test data to a virtual power plant master station;
specifically, in another practical example, the test configuration module sends the test simulation data to a signal generator connected to the regulation and control terminal, and generates simulation test data by receiving data from the signal generator. For example, a simulation data module deployed at a virtual power plant regulation and control terminal interprets a received test simulation data file, the data file specifies that a data source is an external signal generator, the virtual power plant simulation data module sends the simulation data file to the external signal generator, the external signal generator sends output simulation data to the regulation and control terminal, and the simulation data module reads data of the signal generator, generates real-time test data, and sends the real-time test data to a virtual power plant master station.
Step S3, the optimization operation module arranged in the regulation and control main station performs optimization operation calculation on the real-time test data received by the regulation and control main station from each regulation and control terminal, and stores the optimization result;
in one example, the virtual power plant master station receives real-time test data sent by all the regulation and control terminals, and the real-time test data are sent to an optimization operation module for optimization operation calculation, wherein the module is a basic module of the virtual power plant master station and does not belong to the invention content of the invention, and after the optimization operation of the virtual power plant is finished, an optimization result is stored;
and S4, reading the expected result of the test case and the optimized operation calculation result of the test data by a test verification module arranged in the regulation and control main station, comparing the expected result with the optimized operation calculation result of the test data, and judging whether the operation of the virtual power plant regulation and control system is abnormal or not according to the comparison result.
In a practical example, the step S4 further includes:
if the test data optimization operation calculation result is the same as the expected result of the test case or within the error range specified by the expected result, judging that the virtual power plant regulation and control system operates correctly; otherwise, judging that the virtual power plant regulation and control system is abnormal in operation.
Specifically, in an actual example, the system test script generated by the test configuration module includes all test cases and test simulation data corresponding to the test cases, and when the test system executes the script, the test cases are automatically executed in sequence until the script is finished running.
As shown in fig. 2, which is a schematic structural diagram illustrating a system for automatically testing a virtual power plant regulation and control system provided by the present invention, and is shown in fig. 3, in this embodiment, the virtual power plant regulation and control system includes a regulation and control master station 1 and a plurality of regulation and control terminals 2, and the system for automatically testing a virtual power plant regulation and control system includes:
the test configuration module 11 is arranged in the regulation and control master station 1 and used for automatically reading a regulation and control object model and parameters configured by the regulation and control master station, automatically generating a system test script, a test case and test simulation data and sending the system test script, the test case and the test simulation data to the regulation and control terminal;
the simulation data module 21 is arranged in the regulation and control terminal 2 and used for receiving the test simulation data file, generating real-time data for test purposes and sending the real-time data to the regulation and control master station;
the optimized operation module 12 is arranged in the regulation and control main station 1 and is used for performing optimized operation calculation on the real-time test data received by the regulation and control main station from each regulation and control terminal and storing an optimized result;
and the test verification module 12 is arranged in the regulation and control main station 1 and is used for reading the expected result of the test case and comparing the result with the optimized operation calculation result of the test data obtained by the optimized operation module, and judging whether the operation of the virtual power plant regulation and control system is abnormal or not according to the comparison result.
The test system further comprises a signal generator 4 connected with the regulation and control terminal 2 and used for receiving the test simulation data from the test configuration module 11 and generating simulation test data.
Specifically, in a practical example, the simulation data format generated by the test configuration module 11 is a common format for power system transient data exchange; the simulation data generated by the test configuration module 11 includes current, voltage values and power.
Specifically, in an actual example, the system test script generated by the test configuration module 11 includes all test cases and test simulation data corresponding to the test cases, and when the test system executes the script, the test cases are automatically executed in sequence until the script is finished running.
The test validation module 12 further comprises:
a comparing unit 120, configured to read an expected result of the test case of this time and compare the expected result with an optimized operation calculation result of the test data obtained by the optimized operation module;
the operation state judging unit 121 is configured to judge that the virtual power plant regulation and control system operates correctly when the comparison result of the comparing unit 120 is that the optimal operation calculation result is the same as the expected result of the test case, or is within an error range specified by the expected result; otherwise, judging that the virtual power plant regulation and control system is abnormal in operation.
For more details, reference may be made to the preceding description of fig. 1, which is not detailed here.
By implementing the embodiment of the invention, the invention has the following beneficial effects:
in the method and the system for automatically testing the virtual power plant regulation and control system, the virtual power plant test configuration module reads the configuration and data of the regulation and control master station of the virtual power plant, automatically generates the test script, automatically tests the virtual power plant regulation and control system, and verifies the test result, thereby realizing the complete automatic test of the whole virtual power plant regulation and control system. The application of the method reduces the test workload of the virtual power plant regulation and control system, improves the test efficiency and the test accuracy, and is effective in the correct and stable operation of the virtual power plant regulation and control system.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (10)

1.一种对虚拟电厂调控系统进行自动测试的方法,所述虚拟电厂调控系统包括调控主站以及多个调控终端,其特征在于,所述方法包括如下步骤:1. a method for carrying out automatic testing to a virtual power plant control system, the virtual power plant control system comprising a control master station and a plurality of control terminals, is characterized in that, the method comprises the steps: 步骤S1、设置于调控主站中的测试配置模块自动读取调控主站配置的调控对象模型与参数,自动生成系统测试脚本,测试用例以及测试仿真数据,并发送给调控终端;Step S1, the test configuration module arranged in the control master station automatically reads the control object model and parameters configured by the control master station, automatically generates system test scripts, test cases and test simulation data, and sends them to the control terminal; 步骤S2、设置于调控终端中的仿真数据模块接收所述测试仿真数据文件,并生成测试用途的实时数据,并发送给调控主站;Step S2, the simulation data module arranged in the control terminal receives the test simulation data file, and generates real-time data for testing purposes, and sends it to the control master station; 步骤S3,设置于调控主站中的优化运行模块对调控主站所接收的来自各调控终端的实时测试数据进行优化运行计算,并保存优化结果;Step S3, the optimization operation module arranged in the control master station performs optimization operation calculation on the real-time test data received by the control master station from each control terminal, and saves the optimization results; 步骤S4、设置于调控主站中的测试验证模块读取本次测试用例的期望结果与测试数据的优化运行计算结果进行对比,根据对比结果判断虚拟电厂调控系统运行是否异常。Step S4, the test verification module disposed in the control master station reads the expected result of the test case and compares the result of the optimized operation calculation of the test data, and judges whether the operation of the control system of the virtual power plant is abnormal according to the comparison result. 2.根据权利要求1的方法,其特征在于,所述测试配置模块生成的仿真数据格式为电力系统瞬态数据交换的通用格式;所述测试配置模块所生成的仿真数据包含电流、电压值以及功率。2. The method according to claim 1, wherein the simulation data format generated by the test configuration module is a general format for power system transient data exchange; the simulation data generated by the test configuration module comprises current, voltage value and power. 3.根据权利要求2所述的方法,其特征在于,所述测试配置模块将的测试仿真数据发送至与调控终端相连的信号发生器,通过所述接收信号发生器数据生成仿真测试数据。3. The method according to claim 2, wherein the test simulation data sent by the test configuration module is sent to a signal generator connected to the control terminal, and the simulation test data is generated by the received signal generator data. 4.根据权利要求3所述的方法,其特征在于,所述测试配置模块生成的系统测试脚本中包括所有的测试用例与测试用例对应的测试仿真数据,测试系统执行脚本时,自动按顺序执行各个测试用例,直到脚本运行结束。4. The method according to claim 3, wherein the system test script generated by the test configuration module includes all test cases and the test simulation data corresponding to the test cases, and when the test system executes the script, it automatically executes in sequence. individual test cases until the end of the script run. 5.如权利要求4所述的方法,其特征在于,所述步骤S4进一步包括:5. The method of claim 4, wherein the step S4 further comprises: 如果测试数据优化运行计算结果与测试用例的期望结果相同,或者在期望结果规定的误差范围内,则判断虚拟电厂调控系统运行正确;否则,判断虚拟电厂调控系统运行异常。If the calculation result of the optimization operation of the test data is the same as the expected result of the test case, or within the error range specified by the expected result, it is judged that the virtual power plant control system is running correctly; otherwise, it is judged that the virtual power plant control system is abnormal. 6.一种对虚拟电厂调控系统进行自动测试的系统,所述虚拟电厂调控系统包括调控主站以及多个调控终端,其特征在于,所述虚拟电厂调控系统进行自动测试的系统包括:6. A system for automatic testing of a virtual power plant control system, the virtual power plant control system comprising a control master station and a plurality of control terminals, characterized in that the virtual power plant control system for an automatic test system comprises: 测试配置模块,其设置于调控主站中,用于自动读取调控主站配置的调控对象模型与参数,自动生成系统测试脚本,测试用例以及测试仿真数据,并发送给调控终端;The test configuration module, which is set in the control master station, is used to automatically read the control object model and parameters configured by the control master station, automatically generate system test scripts, test cases and test simulation data, and send them to the control terminal; 仿真数据模块,其设置于调控终端中,用于接收所述测试仿真数据文件,并生成测试用途的实时数据,并发送给调控主站;A simulation data module, which is arranged in the control terminal, is used for receiving the test simulation data file, generates real-time data for testing purposes, and sends it to the control master station; 优化运行模块,其设置于调控主站中,用于对调控主站所接收的来自各调控终端的实时测试数据进行优化运行计算,并保存优化结果;an optimization operation module, which is arranged in the control master station, and is used to perform optimization operation calculation on the real-time test data received from each control terminal by the control master station, and save the optimization results; 测试验证模块,其设置于调控主站中,用于读取本次测试用例的期望结果与优化运行模块获得的测试数据的优化运行计算结果进行对比,根据对比结果判断虚拟电厂调控系统运行是否异常。The test verification module, which is set in the control master station, is used to read the expected results of this test case and compare the optimization operation calculation results of the test data obtained by the optimization operation module, and judge whether the operation of the control system of the virtual power plant is abnormal according to the comparison results. . 7.根据权利要求6的系统,其特征在于,所述测试配置模块生成的仿真数据格式为电力系统瞬态数据交换的通用格式;所述测试配置模块所生成的仿真数据包含电流、电压值以及功率。7. The system according to claim 6, wherein the simulation data format generated by the test configuration module is a general format for power system transient data exchange; the simulation data generated by the test configuration module comprises current, voltage value and power. 8.根据权利要求7所述的系统,其特征在于,进一步包括:8. The system of claim 7, further comprising: 信号发生器,与调控终端相连接,用于接收来自测试配置模块的测试仿真数据,并生成仿真测试数据。The signal generator, connected with the control terminal, is used for receiving the test simulation data from the test configuration module and generating the simulation test data. 9.根据权利要求8所述的系统,其特征在于,所述测试配置模块生成的系统测试脚本中包括所有的测试用例与测试用例对应的测试仿真数据,测试系统执行脚本时,自动按顺序执行各个测试用例,直到脚本运行结束。9. The system according to claim 8, wherein the system test script generated by the test configuration module includes all test cases and the test simulation data corresponding to the test cases, and when the test system executes the script, it automatically executes in sequence individual test cases until the end of the script run. 10.如权利要求9所述的系统,其特征在于,所述测试验证模块进一步包括:10. The system of claim 9, wherein the test verification module further comprises: 比较单元,用于读取本次测试用例的期望结果与优化运行模块获得的测试数据的优化运行计算结果进行对比;The comparison unit is used to read the expected result of this test case and compare it with the optimization operation calculation result of the test data obtained by the optimization operation module; 运行状态判断单元,用于在比较单元的对比结果为优化运行计算结果与测试用例的期望结果相同,或者在期望结果规定的误差范围内时,判断虚拟电厂调控系统运行正确;否则,判断虚拟电厂调控系统运行异常。The operation state judgment unit is used to judge that the virtual power plant control system is running correctly when the comparison result of the comparison unit is that the optimal operation calculation result is the same as the expected result of the test case, or is within the error range specified by the expected result; otherwise, the virtual power plant is judged The control system is operating abnormally.
CN201911168755.1A 2019-11-25 2019-11-25 Method and system for automatically testing virtual power plant regulation and control system Active CN110908296B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911168755.1A CN110908296B (en) 2019-11-25 2019-11-25 Method and system for automatically testing virtual power plant regulation and control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911168755.1A CN110908296B (en) 2019-11-25 2019-11-25 Method and system for automatically testing virtual power plant regulation and control system

Publications (2)

Publication Number Publication Date
CN110908296A true CN110908296A (en) 2020-03-24
CN110908296B CN110908296B (en) 2023-07-11

Family

ID=69819398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911168755.1A Active CN110908296B (en) 2019-11-25 2019-11-25 Method and system for automatically testing virtual power plant regulation and control system

Country Status (1)

Country Link
CN (1) CN110908296B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114154660A (en) * 2021-12-07 2022-03-08 国网辽宁省电力有限公司电力科学研究院 Traction station operation and maintenance management system based on intelligent simulation
CN114610631A (en) * 2022-03-18 2022-06-10 广东电网有限责任公司 Data processing method and device, electronic equipment and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105528290A (en) * 2015-12-04 2016-04-27 中国航空综合技术研究所 Construction method of script-based embedded software simulation and test integrated platform
CN105807749A (en) * 2014-12-29 2016-07-27 国家电网公司 Test platform and test method for power dispatching automatic master station system
CN106340968A (en) * 2016-10-21 2017-01-18 国网山东省电力公司电力科学研究院 An integrated support system and method for distribution network management and control
CN108873735A (en) * 2018-06-29 2018-11-23 许继集团有限公司 A kind of distribution main station system component simulation testing device and method
CN109193616A (en) * 2018-07-24 2019-01-11 珠海市通电力科技有限公司 A kind of substation's telecontrol information distribution acceptance method and system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105807749A (en) * 2014-12-29 2016-07-27 国家电网公司 Test platform and test method for power dispatching automatic master station system
CN105528290A (en) * 2015-12-04 2016-04-27 中国航空综合技术研究所 Construction method of script-based embedded software simulation and test integrated platform
CN106340968A (en) * 2016-10-21 2017-01-18 国网山东省电力公司电力科学研究院 An integrated support system and method for distribution network management and control
CN108873735A (en) * 2018-06-29 2018-11-23 许继集团有限公司 A kind of distribution main station system component simulation testing device and method
CN109193616A (en) * 2018-07-24 2019-01-11 珠海市通电力科技有限公司 A kind of substation's telecontrol information distribution acceptance method and system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114154660A (en) * 2021-12-07 2022-03-08 国网辽宁省电力有限公司电力科学研究院 Traction station operation and maintenance management system based on intelligent simulation
CN114610631A (en) * 2022-03-18 2022-06-10 广东电网有限责任公司 Data processing method and device, electronic equipment and storage medium

Also Published As

Publication number Publication date
CN110908296B (en) 2023-07-11

Similar Documents

Publication Publication Date Title
CN103792448B (en) A kind of digital protection device automatic test control system and control method thereof
CN111708284B (en) Simulation test method, device, equipment and storage medium for fuel cell system
CN106707065B (en) Battery management system standard DBC interfaces automatization test system and method
CN109597733B (en) Multifunctional efficient dynamic chip verification simulation method and equipment
WO2014153764A1 (en) Method and device for automatic test of relay protection function of intelligent substation
CN114124767B (en) Automatic test method and device for gateway network management strategy
CN110850354B (en) Metering fault recognition module detection method, device, system and storage medium
CN108845269A (en) Battery testing method and battery test system
CN110569158A (en) method and device for testing abnormal power failure in SSD random scene and computer equipment
CN110908296A (en) A method and system for automatic testing of a virtual power plant control system
CN104635722A (en) Abnormal power failure simulation test device
CN111597083B (en) Testing system of intelligent terminal
CN113051179A (en) Automatic testing method, system and storage medium
CN110334385B (en) Test method, device and equipment for central controller of comprehensive energy system
KR102494709B1 (en) System for Testing Function of Distributed Resources and Method using thereof
CN112487588A (en) Wind power plant reactive voltage regulation function test method, terminal equipment and storage medium
CN116360294A (en) Simulation method and device based on active distribution network
CN117991017A (en) Charging process testing method, device, system and charging controller
CN111901155A (en) Internet of things debugging method, device and system and storage medium
CN110535162A (en) A kind of local load starting control method and energy storage inverter of energy storage inverter
CN115499348A (en) A local communication micro-application detection system and method
CN111541589B (en) Method, device and equipment for testing expansion module interface of intelligent terminal
CN113609703A (en) A method and system for remote simulation verification of safety and stability control device faults
CN108390374B (en) Big data analysis-based transfer path selection method and system
CN111478728A (en) Automatic debugging method, device, equipment and storage medium for optical power of optical module

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant