CN105804445A - Skid-mounted mobile control room - Google Patents

Skid-mounted mobile control room Download PDF

Info

Publication number
CN105804445A
CN105804445A CN201610299294.1A CN201610299294A CN105804445A CN 105804445 A CN105804445 A CN 105804445A CN 201610299294 A CN201610299294 A CN 201610299294A CN 105804445 A CN105804445 A CN 105804445A
Authority
CN
China
Prior art keywords
control room
room
skidization
operation control
instrument rack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610299294.1A
Other languages
Chinese (zh)
Inventor
张悦崑
王威
张柳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Huanqiu Contracting and Engineering Corp
China Huanqiu Engineering Co Ltd
Original Assignee
China Huanqiu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Huanqiu Engineering Co Ltd filed Critical China Huanqiu Engineering Co Ltd
Priority to CN201610299294.1A priority Critical patent/CN105804445A/en
Publication of CN105804445A publication Critical patent/CN105804445A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/04Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate against air-raid or other war-like actions
    • E04H9/10Independent shelters; Arrangement of independent splinter-proof walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a skid-mounted mobile control room which comprises an operation control room and an instrument cabinet chamber which can be connected in a detachable and combined mode. The operation control room and the instrument cabinet chamber are of a full-welding steel frame antiknock structure. The top is provided with a lifting lug plate. The Incoming cables enter the operation control room and the instrument cabinet chamber through a multi-cable penetrating module and are all in sealed design.

Description

The removable control room of a kind of skidization
Technical field
The present invention relates to engineering field, in particular to the removable control room of a kind of skidization.
Background technology
In recent years, domestic and international project becomes increasingly complex.Existing country variant follows the multiformity of different designs specification, there is also the diversity of same country disparity items designing requirement.Control room is the important component part of a process units, is also ensure the core that whole safe and stable arrangement is run, and its design is directly connected to convenience and the safety of device production management.When meeting firebreak and requirement of explosion proof, the position of control room will close to explained hereafter device.Therefore, in, enlarging newly-built at some or reconstruction project, it is considered to each device is distant and the feature do not concentrated, and a project needs to build a lot of control room and on-the-spot rack room, brings bigger workload to on-the-spot civil engineering.
Summary of the invention
The present invention provides a kind of skidization removable control room, in order to overcome at least one problem existed in prior art.
For reaching above-mentioned purpose, the invention provides the removable control room of a kind of skidization, including: detachably, combine the operation control room and instrument rack room that connect, described operation control room and described instrument rack room all adopt full welding parameters calculated explosion resistant structure, top is provided with hanger plate, the long cable section of ingoing line of described operation control room and described instrument rack room is entered by multiway cable threading module, and all long cable section of ingoing line all adopt Seal Design.
Further, operate control room described in cable incoming-outgoing and described instrument rack room both passes through bottom or sidewall, and adopt MCT material to seal.
Further, described operation control room and described instrument rack room all adopt anti-static movable floor.
Further, the cable laying of interiorly or exteriorly equipment is realized inside described operation control room and described instrument rack room each through cable tray.
Further, the assembling center of gravity of described operation control room and described instrument rack room and physics center of gravity are in same level.
Further, the outside of described operation control room and described instrument rack room at least arranges two earth plates at diagonal angle, and is connected with factory owner's grounded screen.
Further, steel column below movable floor of described operation control room and described instrument rack room or steel construction are provided with ground connection confluence copper bar, and are connected to factory owner's grounded screen.
Further, described operation control room and described instrument rack room are provided with fireproof heat-insulation system.
Further, the mode of bottom each strong point employing prepared screw-bolt hole of described operation control room and described instrument rack room, it is fixing that entirety is connected realization with the foundation bolt preset after slinging.
Further, 1 described operation control room and 1 described instrument rack room forming basic antiknock modular structure, multiple described basic antiknock modules are extended on vertical or horizontal.
Considering the factor such as duration, cost, adopt the removable control room of skidization will to become the inevitable choice of most of project, beneficial effects of the present invention is embodied in:
1) civilwork engineering quantity is few
Construction is a more complicated comprehensive production task.The construction of construction, particularly heavy construction, it is necessary to multiple units, the cooperating of multiple work post, mutually coordinated, carries out cooperation, just can be accomplished.Which increase the complexity of construction, especially bring more unsafe factor to safety in production, add the difficulty in safety management.Adopting the removable control room of skidization, the most direct advantage is just that of avoiding substantial amounts of on-the-spot civil engineering, decreases the support to job site (especially external on-the-spot) construction team.
2) can the reduction of erection time.
Improving product quality, reducing cost and provide this series of problems key of good service is exactly the time.Undertaken design and construction process integrating and just can substantially reduce the duration, improve design and the flexibility of construction.Comparing with the totle drilling cost of whole project, the cost of design process seems insignificant, but the enforcement smoothly of project construction process and the quality of final building products are had a significant impact by it.The integration of design and construction can be greatly shortened the project cycle, reduces project cost, better meets the needs of client, it is provided that personalized designs simultaneously.Work progress often runs into some precognitions and the unknown resource limit, and including the restriction of human resources and goods and materials, on-the-spot especially abroad, some rainy seasons are frequent, somebody's power high cost etc..The design standardization of control room, the integration standardization of control room can be saved undoubtedly the substantial amounts of time and save cost.
3) install convenient
The design of control room skid, each strong point of bottom can adopt the mode of prepared screw-bolt hole.Entirety can be connected fixing with default foundation bolt after slinging.
4) can maker integrated, optimize design and construction integration, save cost.
Produce at maker, form the maker of specialty, design and construction are integrated comprehensively, can so that designer can exchange in time with workmen, by adopting total quality control, batch production to eliminate all wastes, aspire after perfection, with minimizing of the maximization generated profit and cost.Traditional construction, owing to being carry out according to the principle of " first designing, afterwards construction ", exchanges very few, causes substantial amounts of design alteration between designer with workmen.Although the cost of product design only accounts for the small part of whole cost, but the cost of 70%-80% is by design impact.The integration of design and construction so that exchange fully between designer with workmen, completes product jointly.Due to be on-demand enter material, it is to avoid overstocking of unnecessary material.Traditional construction exists fluke mind, waits until just to go time problem is very serious to solve;And in this integration process, encountering problems just can solve at once, which offers a saving the cost much caused because of " doing over again " increases.
The integration of design and construction.Contribute to designer and more easily complete the work of oneself, contribute to construction unit's design of arranged rational product more, production, additionally aid unit in charge of construction can the reduction of erection time, reduce cause because of change do over again.Therefore, the integration of design and construction is built upon on " multi-win " basis, final Sharing Interests achievement.
Use task management, workflow management and value control, while satisfactory TK project, it is ensured that minimize waste and maximize value simultaneously.Finally can form the maker of specialty, perfect management system, save cost and reduce support to external world.
5) removable, and reusable.
Standardized removable control room can reuse to a certain extent.When certain device is not coming into operation, if having employed removable control room, just can reuse.Existing control room is transformed, just can be reused, saved the investment of project to a certain extent.Such as, the exploitation of oil gas field, often some well head stops production (shut-in well), the control room just repeatable utilization got off of partly leaving unused.
6) safety
Due to the situation relative complex that engineering project especially project program abroad faces, as political situation situation, natural conditions etc. are all likely to differ greatly from state internal memory.The removable control room of skidization can be integrated in factory, can reduce the risk of project produced on-site at home and abroad to a certain extent.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, the accompanying drawing used required in embodiment or description of the prior art will be briefly described below, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skill in the art, under the premise not paying creative work, it is also possible to obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is the removable control room schematic diagram of skidization of one embodiment of the invention.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is only a part of embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, the every other embodiment that those of ordinary skill in the art obtain under not paying creative work premise, broadly fall into the scope of protection of the invention.
Fig. 1 is the removable control room schematic diagram of skidization of one embodiment of the invention.As shown in the figure, the removable control room of skidization includes: detachably, combine the operation control room 10 and instrument rack room 20 that connect, described operation control room and described instrument rack room all adopt full welding parameters calculated explosion resistant structure, top is provided with hanger plate, the long cable section of ingoing line of described operation control room and described instrument rack room is entered by multiway cable threading module 30, and all long cable section of ingoing line all adopt Seal Design.
The present embodiment skid control room will be divided into two rooms.One is designed as control room, and another is as instrument rack room.Control room is for placement operation platform, operator station and printer etc., and rack room is for placing the rack of all control equipment.
Additionally, aforesaid operations control room and instrument rack room also can be respectively arranged with multiple.When implementing, operated control room by 1 and 1 instrument rack room forms basic antiknock modular structure (such as its size can be the wide 3M* long 8M of height 3.6M*), can by 2 or 3 basic antiknock modular structure longitudinal combinations (such as it be of a size of wide 6M or wide 9M etc.), also can by 2 or 3 basic antiknocks modular structure transverse combination (such as it is of a size of long 16M or 24M etc.), can infinite expanding in principle.
Control room will be arranged at non-hazardous area's upwind, it is therefore intended that allows control room be arranged on the minimum risk region of process unit.The impact of people and building is protected by building of control room by surface water, the entrance of external humidification and the accumulation of internal moisture.This control room is overall protection type and manufactures in factory and assemble completely.Relate to safety, all of material and for the operational procedure of production process according to applicable standard.
The penetration pipe of the threading such as instrument cable tray box and gas detector, alarm and manual pull station.
Control room leads to outdoor door top and is provided with exterior lighting lamp (light sensation controls, degree of protection IP65) and has the sustainable power supply reserve battery of 30 minutes.
This skidization control room design is two parts.The two part can assemble easily/connect and transport.
The inlet wire of all control room cables to enter control room from bottom or sidewall by multiway cable threading module (MCTs).The inlet wire of all cables is what seal.The positions and dimensions of threading module makes threading be easier.
But box house to leave enough cable trays for cable laying.
The design of control room to make assembling center of gravity align with physics center of gravity.It addition, the position of suspension ring to make lifting maintenance level or consider that lifting sling is for keeping center of gravity when lifting.
Control room adopts modularity welding parameters calculated version, in the design except considering to bear construction, install and in normal course of operation except the conventional load of generation, also carries out the designs such as anti-explosion design, design of transportation, hoisting Design.
Building frame and bearing bear alone load in particular cases, and including the load that sea-freight produces with lifting and explosion time, body beam power meets the requirement of AISC/BS5950.
Steel frame primary structural member (beam, post and floor etc.) adopts American Standard ASTMA36 or domestic Q345B level steel, and all the other structural elements such as stair cat ladder and handrail etc. can adopt ASTMA36 or domestic Q235B level steel.
Structural design provides the hanger plate being suitable for and other hanging device to carry out the whole control room of loading and unloading.Time in hoisting Design as adopted single-point lifting, it is necessary to install strut on control room additional, during hanger design, consider double lifting load.
The design of control room considers and the installation harmony on lower concrete basis, installs the steel bracket of location for control room and concrete foundation.
The metope of steel building adopts compression moulded steel plates compound insulation system with roof, single-layer metal profiled sheet facing is adopted outside exterior wall antiknock plate, metal sheet outer surface all sprays the self-cleaning paint of Kynoar to meet anticorrosion, antifouling requirement, composite heat-preservation steel board body of wall is adopted inside antiknock plate, heat insulation layer adopts rock wool (non-combustible material), inner plating inner face spraying polyester, factory sprays, and securing member connects.
Roofing adopts compression moulded steel plates composite thermal-insulating water-proof system (type hidden by purlin) just plate face thickness >=0.6mm, heat-insulation layer adopts extra-fine glass-wool felt or rock wool (for non-combustible material), waterproof ventilative layer adopts 0.5 thick spunbond polyethylene and polypropylene screen, vapor barrier layer adopts 0.2mm paper substrate to add reinforced aluminium foil veneer, top plate fixed form is that 180 ° of undercuts connect, bottom plate adopts thickness to be not less than 0.5mm galvanized steel plain sheet and fixes with roofing antiknock plate, surface is polyester coatings, Roof Design is avoided because of maintenance with building consideration, the activity of installation and the destruction brought, the roof drainage gradient >=2%, double, two slopes are arranged.
Control room ground adopts finished product antistatic raised floor, being generally used for computer equipment ground, movable floor meets maximum capacity every piece 45Kg, and movable floor surface meets anlistatig requirement, convenient construction, meeting the requirement of cable laying position, movable floor height is 300mm.
Floor adopts galvanizing mild steel flase floor, is continuously welded on bottom frame sets a roof beam in place, outsourcing 4 millimeters thick antistatic and anti-skidding vinyl tile cover layer.
Exterior wall meets antiknock requirement, and interior wall adopts the profiled sheet metope of complex heat-preservation.
Ceiling material meets phase code requirement and adopts anti-flammability construction material, and reaches the fire endurance of phase according to national standard.Building ceiling adopts the galvanized steel plain sheet insulation material being lined with PVC film.
The opening on all metopes and floor will have seal approach, and the place of sealing to be mechanically fixed.
Air conditioning system includes considering standby air-cooled integral air conditioner unit, humidity sensor, temperature controller, and ON/OFF controls and permutator.
Owing to control room considers hexahedro anti-explosion design, new wind entrance and wind exhausting outlet in air conditioning system pass through explosion resistant structure place and are provided with the anti-explosive valve of equal drag, and ventilation airduct all adopts galvanized steel plain sheet to make.
In control room, all power loads are powered from the distribution box being arranged in control room.Illumination and power are powered from different distribution boxs respectively.
All distribution boxs are industrial, and degree of protection is NEMAType1 or equal IEC standard grade, on-wall type.Main bus-bar is the copper conductor of high conductivity, and short circuit and rated current can be born in its cross section.All distribution boxs are internal is equipped with neutral conductor busbar and ground connection busbar.All distribution boxs are equipped with inlet wire master switch, and its size is mated with main bus-bar rated current.Master switch is breaker of plastic casing, and outlet switch can be selected for breaker of plastic casing or miniature circuit breaker.Outlet switch is not less than 10A.Receptacle loop is equipped with earth leakage protective device.Computer, instrument rack or other electronic equipment adopt dedicated circuit.Distribution box considers 20% back-up circuit.Distribution box centre-height is positioned at 1.4 meters, more than flooring.
Control room inner cable is specified 0.6/1kV, and copper conductor is crosslinked polyetylene insulated, pvc sheath, non-armouring, meets IEC60501-1, and by the combustion testing of IEC60332-3.Conductor is rope-lay strand and meets ASTMB8 grade B or C, or ASTMB496, or IEC60228 grade 2.
Control room inner cable lays on furred ceiling, under movable floor or along wall.Cable run can not have transition joint.When cable is likely to be subject to damage, with crane span structure or hot-galvanized steel protection of pipe.Crane span structure cover plate.
Steel pipe two ends seal.The safe distance of spaced apart necessity of electrical power cable and instrument signal cable is to prevent electromagnetic interference.
Cable incoming-outgoing control room wears bottom or sidewall, and adopts MCT material to seal.MCT material allows the spare space of 20%.
Cable, crane span structure, steel pipe are each through steel structure support.The support interval of crane span structure and steel pipe is not more than 3 meters, and bare cable horizontal support spacing is not more than 2 meters, and vertical support spacing is not more than 0.5 meter.Steel pipe is increasing support apart from its terminal less than 1 meter of.
Flexible water-proof metal flexible pipe may be used for being likely to the equipment of vibrations or movement or the situation of other necessity.But hose length is less than 1.8 meters.
All cables mark its numbering at two ends, and mark is permanent, clear.At binding post place, power cable is identified by color or letter A, B, C, N etc., controls cable and is identified by color or numeral.It is proposed with plastics sheath shrinkable sleeve.
Control room has enough illuminations, and when ensureing normal operation between main operation, illuminance of ground is not less than 300lx.In escape way and exit, the light fixture of 20%, as anxious illumination, provides 30 minutes accumulator for oneself.Anxious illumination at ordinary times is powered by normal power source, and when normal power source lost efficacy, the accumulator provided for oneself can light anxious illumination automatically.
At each exit port, one light-operated water proof and dust proof lighting is set.Light control device has hands automatic change-over.
Light fixture, for quickly to start high efficiency fluorescent lamp, carries ballast and capacitance compensation, and power factor is not less than 0.92.Light fixture can fit the single-phase voltage of 120-230V, suitable 50/60Hz frequency.Light source is cool white, band colour correction.
Two earth plates are at least set at diagonal angle outside control room, in order to be connected with factory owner's grounded screen by control room.Earth plate and steel column or steel construction form electric path, and connect reliable.Earth plate material is identical with building main structure material.
Steel column below control room immanent action floor or install prefabricated ground connection confluence copper bar on steel construction, and it is connected to factory owner's grounded screen by 2.
Instrumentation has safety ground and system earth.Safety ground can with electrical equipment shared grounding copper bar, but system earth according to instrument specialty and system manufacturer requirement use Special grounding copper bar.Ups system neutral-point solid ground.
Earth lead is yellowish green phase insulation copper cash.Connecting the earth lead of grounding copper bar and factory owner's grounded screen minimum for 70mm2 (2/0AWG), the earth lead connecting equipment and grounding copper bar is minimum for 16mm2 (6AWG).
Earth lead suitably supports and fixes.When being likely subject to damage, adopt pvc pipe protective grounding line.
Considering the factor such as duration, cost, adopt the removable control room of skidization will to become the inevitable choice of most of project, beneficial effects of the present invention is embodied in:
1) civilwork engineering quantity is few
Construction is a more complicated comprehensive production task.The construction of construction, particularly heavy construction, it is necessary to multiple units, the cooperating of multiple work post, mutually coordinated, carries out cooperation, just can be accomplished.Which increase the complexity of construction, especially bring more unsafe factor to safety in production, add the difficulty in safety management.Adopting the removable control room of skidization, the most direct advantage is just that of avoiding substantial amounts of on-the-spot civil engineering, decreases the support to job site (especially external on-the-spot) construction team.
2) can the reduction of erection time.
Improving product quality, reducing cost and provide this series of problems key of good service is exactly the time.Undertaken design and construction process integrating and just can substantially reduce the duration, improve design and the flexibility of construction.Comparing with the totle drilling cost of whole project, the cost of design process seems insignificant, but the enforcement smoothly of project construction process and the quality of final building products are had a significant impact by it.The integration of design and construction can be greatly shortened the project cycle, reduces project cost, better meets the needs of client, it is provided that personalized designs simultaneously.Work progress often runs into some precognitions and the unknown resource limit, and including the restriction of human resources and goods and materials, on-the-spot especially abroad, some rainy seasons are frequent, somebody's power high cost etc..The design standardization of control room, the integration standardization of control room can be saved undoubtedly the substantial amounts of time and save cost.
3) install convenient
The design of control room skid, each strong point of bottom can adopt the mode of prepared screw-bolt hole.Entirety can be connected fixing with default foundation bolt after slinging.
4) can maker integrated, optimize design and construction integration, save cost.
Produce at maker, form the maker of specialty, design and construction are integrated comprehensively, can so that designer can exchange in time with workmen, by adopting total quality control, batch production to eliminate all wastes, aspire after perfection, with minimizing of the maximization generated profit and cost.Traditional construction, owing to being carry out according to the principle of " first designing, afterwards construction ", exchanges very few, causes substantial amounts of design alteration between designer with workmen.Although the cost of product design only accounts for the small part of whole cost, but the cost of 70%-80% is by design impact.The integration of design and construction so that exchange fully between designer with workmen, completes product jointly.Due to be on-demand enter material, it is to avoid overstocking of unnecessary material.Traditional construction exists fluke mind, waits until just to go time problem is very serious to solve;And in this integration process, encountering problems just can solve at once, which offers a saving the cost much caused because of " doing over again " increases.
The integration of design and construction.Contribute to designer and more easily complete the work of oneself, contribute to construction unit's design of arranged rational product more, production, additionally aid unit in charge of construction can the reduction of erection time, reduce cause because of change do over again.Therefore, the integration of design and construction is built upon on " multi-win " basis, final Sharing Interests achievement.
Use task management, workflow management and value control, while satisfactory TK project, it is ensured that minimize waste and maximize value simultaneously.Finally can form the maker of specialty, perfect management system, save cost and reduce support to external world.
5) removable, and reusable.
Standardized removable control room can reuse to a certain extent.When certain device is not coming into operation, if having employed removable control room, just can reuse.Existing control room is transformed, just can be reused, saved the investment of project to a certain extent.Such as, the exploitation of oil gas field, often some well head stops production (shut-in well), the control room just repeatable utilization got off of partly leaving unused.
6) safety
Due to the situation relative complex that engineering project especially project program abroad faces, as political situation situation, natural conditions etc. are all likely to differ greatly from state internal memory.The removable control room of skidization can be integrated in factory, can reduce the risk of project produced on-site at home and abroad to a certain extent.
One of ordinary skill in the art will appreciate that: accompanying drawing is the schematic diagram of an embodiment, module or flow process in accompanying drawing are not necessarily implemented necessary to the present invention.
One of ordinary skill in the art will appreciate that: the module in device in embodiment can describe in the device being distributed in embodiment according to embodiment, it is also possible to carries out respective change and is disposed other than in one or more devices of the present embodiment.The module of above-described embodiment can merge into a module, it is also possible to is further split into multiple submodule.
Finally illustrate: above example only in order to technical scheme to be described, is not intended to limit;Although the present invention being described in detail with reference to previous embodiment, those of ordinary skill in the art is when understanding: the technical scheme described in previous embodiment still can be modified by it, or wherein portion of techniques feature carries out equivalent replacement;And these amendments or replacement, do not make the essence of phase technical scheme depart from the spirit and scope of embodiment of the present invention technical scheme.

Claims (10)

1. the removable control room of skidization, it is characterized in that, including: detachably, combine the operation control room and instrument rack room that connect, described operation control room and described instrument rack room all adopt full welding parameters calculated explosion resistant structure, top is provided with hanger plate, the long cable section of ingoing line of described operation control room and described instrument rack room is entered by multiway cable threading module, and all long cable section of ingoing line all adopt Seal Design.
2. the removable control room of skidization according to claim 1, it is characterised in that operate control room described in cable incoming-outgoing and described instrument rack room both passes through bottom or sidewall, and adopt MCT material to seal.
3. the removable control room of skidization according to claim 1, it is characterised in that described operation control room and described instrument rack room all adopt anti-static movable floor.
4. the removable control room of skidization according to claim 1, it is characterised in that described operation control room and realize the cable laying of interiorly or exteriorly equipment inside described instrument rack room each through cable tray.
5. the removable control room of skidization according to claim 1, it is characterised in that the assembling center of gravity of described operation control room and described instrument rack room and physics center of gravity are in same level.
6. the removable control room of skidization according to claim 1, it is characterised in that the outside of described operation control room and described instrument rack room at least arranges two earth plates at diagonal angle, and is connected with factory owner's grounded screen.
7. the removable control room of skidization according to claim 1, it is characterised in that be provided with ground connection confluence copper bar on steel column below movable floor of described operation control room and described instrument rack room or steel construction, and be connected to factory owner's grounded screen.
8. the removable control room of skidization according to claim 1, it is characterised in that described operation control room and described instrument rack room are provided with fireproof heat-insulation system.
9. the removable control room of skidization according to claim 1, it is characterised in that it is fixing that each strong point of bottom of described operation control room and described instrument rack room adopts the mode of prepared screw-bolt hole, entirety to be connected realization with the foundation bolt preset after slinging.
10. the removable control room of skidization according to claim 1, it is characterised in that being formed basic antiknock modular structure by 1 described operation control room and 1 described instrument rack room, multiple described basic antiknock modules are extended on vertical or horizontal.
CN201610299294.1A 2016-05-06 2016-05-06 Skid-mounted mobile control room Pending CN105804445A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610299294.1A CN105804445A (en) 2016-05-06 2016-05-06 Skid-mounted mobile control room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610299294.1A CN105804445A (en) 2016-05-06 2016-05-06 Skid-mounted mobile control room

Publications (1)

Publication Number Publication Date
CN105804445A true CN105804445A (en) 2016-07-27

Family

ID=56456434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610299294.1A Pending CN105804445A (en) 2016-05-06 2016-05-06 Skid-mounted mobile control room

Country Status (1)

Country Link
CN (1) CN105804445A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110571655A (en) * 2019-09-12 2019-12-13 四川杰瑞恒日天然气工程有限公司 cable threading pipe hidden laying method for skid-mounted equipment

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1059010A (en) * 1990-08-17 1992-02-26 北京市西城区新开通用试验厂 Container-type standardized central control room
JPH05130724A (en) * 1991-10-31 1993-05-25 Sukemasa Nakamoto Wiring line construction for wall, floor and ceiling
CN1874095A (en) * 2006-06-26 2006-12-06 吕迎智 Composite type cabinet type transformer substation
CN200953442Y (en) * 2006-06-26 2007-09-26 吕迎智 Assembling box type transformer substation
CN201802090U (en) * 2010-08-31 2011-04-20 中国石油集团工程设计有限责任公司 Electric control equipment skid-mounted room of natural gas engineering station
CN202299527U (en) * 2011-11-11 2012-07-04 中联重科股份有限公司 Movable container type central control chamber
CN103774869A (en) * 2014-01-24 2014-05-07 李光宇 Container type control room
CN204326608U (en) * 2014-12-06 2015-05-13 内蒙古兴泰建设集团有限公司 A kind of radiation proof noise reduction machine room
CN204967088U (en) * 2015-08-14 2016-01-13 江苏润圣电气有限公司 Modular assembly formula transformer substation
CN205976631U (en) * 2016-05-06 2017-02-22 中国寰球工程有限公司 But sled dressization mobility control room

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1059010A (en) * 1990-08-17 1992-02-26 北京市西城区新开通用试验厂 Container-type standardized central control room
JPH05130724A (en) * 1991-10-31 1993-05-25 Sukemasa Nakamoto Wiring line construction for wall, floor and ceiling
CN1874095A (en) * 2006-06-26 2006-12-06 吕迎智 Composite type cabinet type transformer substation
CN200953442Y (en) * 2006-06-26 2007-09-26 吕迎智 Assembling box type transformer substation
CN201802090U (en) * 2010-08-31 2011-04-20 中国石油集团工程设计有限责任公司 Electric control equipment skid-mounted room of natural gas engineering station
CN202299527U (en) * 2011-11-11 2012-07-04 中联重科股份有限公司 Movable container type central control chamber
CN103774869A (en) * 2014-01-24 2014-05-07 李光宇 Container type control room
CN204326608U (en) * 2014-12-06 2015-05-13 内蒙古兴泰建设集团有限公司 A kind of radiation proof noise reduction machine room
CN204967088U (en) * 2015-08-14 2016-01-13 江苏润圣电气有限公司 Modular assembly formula transformer substation
CN205976631U (en) * 2016-05-06 2017-02-22 中国寰球工程有限公司 But sled dressization mobility control room

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
中国电力建设企业协会: "《电力建设质量管理小组成功选编》", 31 March 2015, 中国电力出版社 *
刘家明: "《炼油厂设计与工程》", 31 January 2014, 中国石化出版社 *
包红旗等: "《大型车载移动变电站》", 31 May 2013, 中国水利水电出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110571655A (en) * 2019-09-12 2019-12-13 四川杰瑞恒日天然气工程有限公司 cable threading pipe hidden laying method for skid-mounted equipment
CN110571655B (en) * 2019-09-12 2021-04-02 四川杰瑞恒日天然气工程有限公司 Cable threading pipe hidden laying method for skid-mounted equipment

Similar Documents

Publication Publication Date Title
CN204627053U (en) A kind of multiple field steel work ITS
EP2917430A1 (en) Modular structural system for solar panel installation
CN202127186U (en) Semi-embedding prefabricated type substation
CN108824648A (en) Space module house
CN104143774A (en) Prefabricated cabin structure of intelligent substation secondary equipment
CN101654928B (en) Structure of multi-layer combined type house and assembly method thereof
WO2016055067A1 (en) Wind turbine generator assemblies
CN204753823U (en) Have enough to meet need double -decker that room constitutes by standard
CN106759481A (en) Guan Suicanggou formulas communication station
CN103628710A (en) Portable and detachable box-type medium-voltage frequency conversion chamber
CN205976631U (en) But sled dressization mobility control room
CN105804445A (en) Skid-mounted mobile control room
CN105649208B (en) A kind of method and structure being combined into big room by standard relocation housing
CN104124913A (en) New solar roof integration power generation system
CN204492262U (en) Electric control system for drilling machine modularization skid room
CN202139871U (en) Electric automobile charging room with detachable roof and wiring bin
CN110259207A (en) A kind of modularization hierarchical structure digital transformer substation
CN202081666U (en) Mounting working pergola for cable accessory
CN104362733A (en) Prefabricated uninterruptible power supply system
CN201276756Y (en) Multi-layer combined house
CN102296842A (en) Operation shed frame for mounting cable accessory
CN204290470U (en) A kind of prefabricated uninterruptible power system
CN210738179U (en) Digital transformer substation with modular hierarchical structure
CN210685523U (en) Prefabricated cabin of modulization transformer substation
CN203850627U (en) Overall framework type modularization secondary device applied to substation construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160727