CN105804115B - Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method - Google Patents

Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method Download PDF

Info

Publication number
CN105804115B
CN105804115B CN201610112478.2A CN201610112478A CN105804115B CN 105804115 B CN105804115 B CN 105804115B CN 201610112478 A CN201610112478 A CN 201610112478A CN 105804115 B CN105804115 B CN 105804115B
Authority
CN
China
Prior art keywords
assembled
wall
construction
ground
prefabricated pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610112478.2A
Other languages
Chinese (zh)
Other versions
CN105804115A (en
Inventor
王国富
商金华
路林海
卢庆亮
曹正龙
谢松彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Heavy Tunnel Construction Equipment Co Ltd
Jinan Rail Transit Group Co Ltd
Original Assignee
Jinan Heavy Tunnel Construction Equipment Co Ltd
Jinan Rail Transit Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Heavy Tunnel Construction Equipment Co Ltd, Jinan Rail Transit Group Co Ltd filed Critical Jinan Heavy Tunnel Construction Equipment Co Ltd
Priority to CN201610112478.2A priority Critical patent/CN105804115B/en
Publication of CN105804115A publication Critical patent/CN105804115A/en
Application granted granted Critical
Publication of CN105804115B publication Critical patent/CN105804115B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The invention discloses assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction methods, the constructing device includes the gantry crane equipped with lifting machine, gantry crane includes lateral gantry hanging beam and is used to support two supporting racks of lateral gantry hanging beam, two supporting racks are respectively arranged on the both sides of estimated excavation pit, it is equipped at least one sliding rail in the bottom of lateral gantry hanging beam, grab claw is fixed on a wherein sliding rail, fixes a slotter the inside of two supporting racks is each.The beneficial effects of the invention are as follows:Slotter, grab claw and lifting machine are combined together by gantry crane, facilitate the movement to these machines, meanwhile, that has saved these machines goes out entry time, and the construction period is greatly saved;The method of the present invention can be improved speed of application, shorten the construction period, and environmental pollution is small, it can be achieved that the advantages that industrialization production.

Description

Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and Construction method
Technical field
The present invention relates to underground structrue engineering fields more particularly to assembled ground-connecting-wall or prefabricated pile with assembled to get off It stands integrative construction device and construction method.
Background technology
Traditional underground station is built to carry out frequently with cut and cover method, cap excavation method or shield method, these underground station construction sides Method has some limitations, and can only be directed to a certain special geology or environmental condition can be applicable in.As underground engineering is applied The progress of work technology and new material manufacture craft occurs using prefabricated components modularizations, My Perspective On The Co-building underground station New method, this method have the characteristics that environmental pollution is small, speed of application is fast, efficient, have vast potential for future development.
Chinese patent CN104762990A provides a kind of modularly debarkation stop method of construction, first ties station before construction Every ring of structure is all divided into combinable bottom plate prefabricated components, top plate prefabricated components and side wall prefabricated components;It is advanced when construction Row substrate cushion construction;Then reaction frame is set;First boxing is connected on steel plate after the assembled first ring of reaction frame, cyclization later On reaction frame, assembled other rings successively later, and to prefabricated components upper tenon groove mortar depositing construction while each ring assembly.The party Method increases working procedure, reduces construction efficiency.
Chinese patent CN104674846A discloses a kind of construction method for digging underground station using precast construction lid, adopts With the prefabricated respective members of outer batch production on construction ground, then utilize pile press machine by prefabricated fender post, column on construction ground The position of stake indentation design requirement, carries out excavation of foundation pit, pours the collar tie beam that bears down on one, horizontally-supported, be laid with prefabricated superimposed sheet, pour knot Then structure top plate backfills top cubic metre of earth, continues downward earth excavation later, pour negative one layer bottom plate, pour sole plate and build Object abutment wall is built, underground station construction is completed.This method takes step-by-step construction, considerably increases working procedure, extends construction week Phase.
Invention content
The object of the present invention is to provide with formula ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and Construction method.It relates to a kind of pattern foundation pit supporting structure, excavation and station assembly integrated construction, improves construction efficiency, reduces environment Pollution reduces project cost, contributes to the process for further pushing underground engineering industrialization.
In order to achieve the above objectives, the present invention adopts the following technical scheme that:
Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device, include the dragon equipped with lifting machine Gantry crane, gantry crane include lateral gantry hanging beam and are used to support two supporting racks of lateral gantry hanging beam, two supporting rack difference Set on the both sides of estimated excavation pit, it is equipped at least one sliding rail in the bottom of lateral gantry hanging beam, wherein solid on a sliding rail Determine grab claw, fixes a slotter the inside of two supporting racks is each;By the way that lifting machine, grab claw and slotter are respectively provided with In on a gantry crane, gantry crane moves, while driving the movement of all devices, saves going out entry time for device, machine It can simultaneously or individually operate, the construction period is greatly saved.
Further, idler wheel, idler wheel and the long rails for being set to foundation pit both sides are respectively equipped in the bottom of two supporting racks Cooperation;The movement of gantry crane drives each machine movement on gantry crane;For machine one by one, facilitate Movement to these machines, while saving working hour.
Further, further include control device, the control system difference of control device and lifting machine, grab claw and slotter Individually connection is uniformly controlled these machines by control device is unified, saves manpower.
Further, further include remote controler, remote controler with the control device by wirelessly or non-wirelessly connecting, by being remotely controlled Device realizes remote control, ensures construction safety.
Using the construction method of the assembled ground-connecting-wall or prefabricated pile and assembled underground station of above-mentioned constructing device, specifically Steps are as follows:
1) constructing device is placed in the initial position of underground station boundary of works area;
2) control slotter in initial position as the mobile stage excavation groove of gantry crane is to set depth;
3) after grooving, control lifting machine does assembled ground-connecting-wall;Or control lifting machine is arranged simultaneously with individual piling machine It is pressed into prefabricated pile;
4) control grab claw is from one end stage excavation of foundation pit to bottom of foundation ditch, and successively setting welded steel beam supports both sides Ground-connecting-wall or prefabricated pile;
5) component of underground station is carried out from down to up assembled;
6) underground station internal structure is poured, after the completion, underground station construction is completed in earthing backfill.
Further, in step 3) in real time use testing apparatus for verticality detection assembled ground-connecting-wall or prefabricated pile hang down Straight degree.
Further, the component of underground station includes middle part bottom plate, two pieces of L-shaped bottom side plates, sets in step 5) Framed side wallboard and at least two blocks of crown plates in subway station both sides.
Further, the middle part bottom plate, bottom side plate, framed side wallboard and crown plate are prefabricated by armored concrete.
Further, when doing ground-connecting-wall or prefabricated pile in the step 3), it is necessary first to pacify in the groove excavated Fill ground-connecting-wall or prefabricated pile locating rack.
Further, in assembled framed side wallboard, the verticality and flatness of side wall need to be detected in real time.
The present invention operation principle be:According to the integral layout of underground station, agent structure each section is divided into can be pre- Assembling members processed, are mainly composed of precast member for reinforcing bar concrete.Assembly segment structure is made of prefabricated components, including:In Portion's bottom plate, two pieces of L-shaped bottom side plates, framed side wallboard and at least two blocks of crown plates set on subway station both sides.Station main body Component circumferential direction contact surface for double-layer double-span formula station, underground station connects for tongue-and-groove, setting positioning shear-pin, tongue-and-groove in tongue-and-groove The lubricants such as butter are filled there are gap and inside it, in favor of the connection between prefabricated components;Floor is adopted in underground station With cast-in-place structural, straight thread connector and floor bar are buried in component using being mechanically connected;Assembled ground-connecting-wall is by perpendicular type and Z Type prefabricated components form, and play the role of pattern foundation pit supporting structure;Construction machinery is combination gantry crane, mainly by slotter, hydraulic grab machine It is formed with lifting machine, grooving, excavation of foundation pit and lifting institutional operation can be carried out.Sequence of construction first with slotter grooving, Be pressed into assembled ground-connecting-wall or prefabricated pile, then utilize hydraulic grab stage excavation, according still further to sequence of construction from lower to upper into Driving station is assembled, last cast-in-place station internal structure, and station construction is completed in earthing backfill.
The beneficial effects of the invention are as follows:
1) slotter, grab claw and lifting machine are combined together by gantry crane, facilitate the movement to these machines, Meanwhile that has saved these machines goes out entry time, and the construction period is greatly saved.
2) action of each mechanism is controlled by control device or remote controller collaborative, it is easy to control, simple, meanwhile, it avoids Each machine at work, the case where being provided with one or more staff, saves manpower.
3) speed of application can be improved in method of the invention, shortens the construction period, and environmental pollution is small, it can be achieved that industrialization production The advantages that.
Description of the drawings
Fig. 1 assembled station structure sectional views;
Fig. 2 assembled station construction layouts;
Fig. 3 (a)~3 (h) is assembled metro station construction block diagram.
Wherein:1. lifting machine, 2. grab claws, 3. slotters, the component of 4. ground-connecting-walls (prefabricated pile), 5. underground station.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Whole description.
As shown in Fig. 2, assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device, including be equipped with The gantry crane of lifting machine 1, gantry crane include lateral gantry hanging beam and are used to support two supporting racks of lateral gantry hanging beam, two Supporting rack is respectively arranged on the both sides of estimated excavation pit, at least one sliding rail is equipped in the bottom of lateral gantry hanging beam, wherein one Grab claw 2 is fixed on sliding rail, fixes a slotter 3 the inside of two supporting racks is each;By by lifting machine 1, grab claw 2 It may be contained on a gantry crane with slotter 3, gantry crane movement, while driving the movement of all devices, save device Go out entry time, machine simultaneously or can be operated individually, and the construction period is greatly saved.
It is respectively equipped with idler wheel in the bottom of two supporting racks, idler wheel coordinates with the long rails set on foundation pit both sides;Gantry The movement hung drives each machine movement on gantry crane;For machine one by one, facilitate to these machines Movement, while saving working hour.
The constructing device further includes control device and remote controler, control device and lifting machine 1, grab claw 2 and slotter 3 Control system individually connects, and is uniformly controlled to these machines by control device is unified, saves manpower;Remote controler and institute The control device stated realizes remote control by wirelessly or non-wirelessly connecting, by remote controler, ensures construction safety.
As shown in Figure 1, the component of underground station includes middle part I, two piece of L-shaped bottom side plate II of bottom plate, is set to subway The framed side wallboard III of station both sides and at least two blocks of crown plates IV, V, the middle part bottom plate I, bottom side plate II, framed side wallboard III and top Arch bar IV, V is prefabricated by armored concrete.
As shown in Fig. 3 (a)~3 (h), using assembled ground-connecting-wall or prefabricated pile and the assembled underground of above-mentioned constructing device The construction method at station, is as follows:
1) combination gantry crane construction machinery is set up, using 3 grooving of slotter, and places assembled ground-connecting-wall on groove (prefabricated pile) locating rack, locating rack are made by scene and prefabricated components (prefabricated pile) size, place and fix, and recycle lifting Machine 1 is pressed into along locating rack in groove, then utilizes 2 stage excavation of grab claw to foundation pit bottom;And successively setting welded steel beam supports The ground-connecting-wall or prefabricated pile of both sides, welded steel beam are horizontally disposed;
2) the middle part bottom plate I of first ring underground station component 5 is accurately positioned, determines component assembly axial location;
3) according to position in step 2), station bottom plate assembled first, bottom plate is by one piece of middle part I, two piece of bottom side plate of bottom plate II component forms, and using lifting machine 1 and human assistance, first spells middle part bottom plate I and spells bottom side plate II again, carried out to axis after having spelled Correction;
4) assembled side wall, side wall are made of two pieces of framed side wallboards III, are checked the upper elevation of III piece of framed side wallboard before the mounting and are put down Whole degree, it is ensured that the verticality and flatness of side wall;
5) assembled crown, crown are made of IV, V liang of module component of crown plate, are completed with gantry crane and trolley;
6) cast-in-place station internal structure, including floor and column, then earthing backfill, complete station construction.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (6)

1. assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device, which is characterized in that including being equipped with The gantry crane of lifting machine, gantry crane include lateral gantry hanging beam and are used to support two supporting racks of lateral gantry hanging beam, two Supporting rack is respectively arranged on the both sides of estimated excavation pit, at least one sliding rail is equipped in the bottom of lateral gantry hanging beam, wherein one Grab claw is fixed on sliding rail, fixes a slotter the inside of two supporting racks is each;Further include control device, control device It is individually connect with the control system of lifting machine, grab claw and slotter.
2. constructing device as described in claim 1, which is characterized in that be respectively equipped with idler wheel in the bottom of two supporting racks, roll Wheel coordinates with the long rails set on foundation pit both sides.
3. constructing device as described in claim 1, which is characterized in that further include remote controler, remote controler is filled with the control It sets by wirelessly or non-wirelessly connecting.
4. using the assembled ground-connecting-wall or prefabricated pile of the constructing device described in any one of claim 1-3 and assembled underground The construction method at station, which is characterized in that be as follows:
1)Combination gantry crane construction machinery is set up, using slotter grooving, when doing ground-connecting-wall or prefabricated pile, it is necessary first to excavate Installation ground-connecting-wall or prefabricated pile locating rack in good groove, locating rack are made by scene and ground-connecting-wall or prefabricated pile size, are placed And fix, recycle lifting machine, by ground-connecting-wall or prefabricated pile indentation groove, then to be opened using grab claw layering along locating rack It digs to foundation pit bottom;And successively setting welded steel beam supports the ground-connecting-wall or prefabricated pile of both sides, welded steel beam horizontally disposed;
2)The middle part bottom plate I of first ring underground station component is accurately positioned, determines component assembly axial location;
3)According to step 2)Middle position, station bottom plate assembled first, bottom plate is by one piece of middle part I, two piece of II structure of bottom side plate of bottom plate Part forms, and using lifting machine and human assistance, first spells middle part bottom plate I and spells bottom side plate II again, corrected to axis after having spelled;
4)Assembled side wall, side wall are made of two pieces of framed side wallboards III, check elevation and flatness on framed side wallboard III before the mounting, really Protect the verticality and flatness of side wall;
5)Assembled crown, crown are made of IV, V liang of module component of crown plate, are completed with gantry crane and trolley;
6)Cast-in-place station internal structure, including floor and column, then earthing backfill, complete station construction.
5. construction method as claimed in claim 4, which is characterized in that in step 4)In in real time use testing apparatus for verticality examine Survey the verticality of side wall.
6. construction method as claimed in claim 4, which is characterized in that the middle part bottom plate I, bottom side plate II, framed side wallboard III It is prefabricated by armored concrete with crown plate IV, V.
CN201610112478.2A 2016-02-29 2016-02-29 Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method Active CN105804115B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610112478.2A CN105804115B (en) 2016-02-29 2016-02-29 Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610112478.2A CN105804115B (en) 2016-02-29 2016-02-29 Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method

Publications (2)

Publication Number Publication Date
CN105804115A CN105804115A (en) 2016-07-27
CN105804115B true CN105804115B (en) 2018-08-31

Family

ID=56465890

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610112478.2A Active CN105804115B (en) 2016-02-29 2016-02-29 Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method

Country Status (1)

Country Link
CN (1) CN105804115B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756090B (en) * 2016-02-29 2018-02-06 济南轨道交通集团有限公司 Cast-in-situ bored pile and assembled metro station construction integral method
CN105672354B (en) * 2016-02-29 2018-05-11 济南轨道交通集团有限公司 Cast-in-place ground-connecting-wall and cast-in-place metro station construction integral method
CN108396778A (en) * 2018-01-25 2018-08-14 成都城投建筑科技投资管理集团有限公司 A kind of construction method in precast assembly tunnel
CN110080294A (en) * 2019-04-23 2019-08-02 中铁第四勘察设计院集团有限公司 A kind of lid of assembled vault greatly across no column underground structure digs half reversed construction method

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2845060B2 (en) * 1992-11-17 1999-01-13 株式会社大林組 Construction method of underground construction by fully automatic building construction system
CN102505706A (en) * 2011-09-30 2012-06-20 北京市政建设集团有限责任公司 Method for building subway station
CN103967050B (en) * 2014-01-29 2015-05-20 广州机施建设集团有限公司 Construction system of subway station
CN103912010B (en) * 2014-04-04 2015-08-12 北京城建设计发展集团股份有限公司 The prefabricated assembled Underground Construction method of open cut
CN104060629B (en) * 2014-07-02 2015-08-05 中铁十二局集团第七工程有限公司 The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN104153389A (en) * 2014-08-11 2014-11-19 中铁建大桥工程局集团第六工程有限公司 Construction method for prefabricated assembly type subway station
CN204959762U (en) * 2015-09-10 2016-01-13 沈阳铁道勘察设计院有限公司 Barricade formula portal crane track girder construction

Also Published As

Publication number Publication date
CN105804115A (en) 2016-07-27

Similar Documents

Publication Publication Date Title
CN105804115B (en) Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method
CN107558494B (en) Underground station structure for rail transit and construction method thereof
CN107218046A (en) Mechanical assistance sealing Station structure and construction method in a kind of pilot tunnel
CN104131565B (en) A kind of against making the construction method that the earthwork is just made to excavate
CN102127974A (en) Design and construction method of additional cellar under existing building
CN105672353B (en) A kind of cast-in-place diaphram wall and assembled metro station construction integral method
CN205875209U (en) Temporary road surface system supports with concrete and closes subway station half range bedding structure of establishing
CN103912134B (en) Existing building underground space structure and construction method in situ
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN210086295U (en) Compound assembled underground structure
CN201972155U (en) Topdown-construction-method foundation pit supporting structure of steel plate pile
CN102031785A (en) Foundation pit supporting technique for replacing temporary enclosing purlin by using plate belt of permanent structure
CN104234082A (en) Jump-layer reversed construction method for deep foundation pit
CN101793023A (en) Foundation pit construction method
CN105714851B (en) Assembled ground-connecting-wall or prefabricated pile are with cast-in-place underground station integrative construction device and using its construction method
CN204715366U (en) A kind of large-area deep foundation pit subregion is along the support system under inverse operating mode
CN101824825B (en) Deep foundation pit open cutting construction method
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN110144936A (en) One kind adjoining the unilateral formwork of support pile outer wall of basement and construction method
CN103215965A (en) Laminate type high-rise platform pile tower crane foundation and construction method
CN201567523U (en) Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level
CN103132465A (en) Underground box culvert constructing method closely attached to pile foundation bearing platform
CN204040042U (en) A kind of super large ultra-deep support with manually dug piles structure
CN105625184A (en) Subway station building method using bridge and station combined building mode
CN104594367B (en) A kind of combined type cofferdam structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant