CN201567523U - Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level - Google Patents
Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level Download PDFInfo
- Publication number
- CN201567523U CN201567523U CN2009202151335U CN200920215133U CN201567523U CN 201567523 U CN201567523 U CN 201567523U CN 2009202151335 U CN2009202151335 U CN 2009202151335U CN 200920215133 U CN200920215133 U CN 200920215133U CN 201567523 U CN201567523 U CN 201567523U
- Authority
- CN
- China
- Prior art keywords
- existing railway
- bridge
- suspension bridge
- temporary
- railway
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 12
- 238000005553 drilling Methods 0.000 claims abstract description 6
- 239000000725 suspension Substances 0.000 claims description 23
- 238000010276 construction Methods 0.000 claims description 19
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 18
- 241000272165 Charadriidae Species 0.000 claims description 9
- 229910052742 iron Inorganic materials 0.000 claims description 9
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 230000015572 biosynthetic process Effects 0.000 claims description 2
- 230000001681 protective effect Effects 0.000 abstract 1
- 238000000034 method Methods 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 239000002689 soil Substances 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 230000008093 supporting effect Effects 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000011218 segmentation Effects 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
- Foundations (AREA)
Abstract
The utility model relates to a temporary bridge for erecting an existing railway overhead in sections with soft foundation or high water level. The existing railway is erected overhead by utilizing simple buttresses and temporary beams at the two sides of the existing railway to form a temporary bridge erected for the first time, and the existing railway is erected overhead again by utilizing columniform piers, rectangular bridge abutments and temporary beams below the existing railway to form a temporary bridge erected for the second time. After the temporary bridge is erected for the first time, a plurality of vertical sheet piles are connected below the temporary beams, protective walls are connected with the outer sides of the sheet piles, a space for the operation of drilling mechanical equipment is formed between every two adjacent sheet piles, the top of the space is provided with I-beam as a top support, and the bottom of the space is provided with a bottom support formed by concrete pouring to form a working channel for constructing a pile foundation. The pile foundation is formed by drilling downwards in the working channel and pouring, and the upper part of the pile foundation is manufactured into a rectangular bridge abutment bearing platform, a platform body and a pier capping beam. By adopting the temporary bridge for erecting the railway overhead in sections with soft foundation or high water level, land levy and remove are reduced, land can be little occupied, the engineering is ensured to be smoothly actualized, and the safe operation of the existing railway can be effectively ensured at the same time.
Description
Technical field
The utility model relates to the construction technology of setting up suspension bridge on the existing railway of high water level, geological conditions difference and circuit difficulty, specifically is a kind of suspension bridge that is used for soft base, the built on stilts existing railway in high water level location.
Background technology
Construction along with railway, highway, urban road, newly-built road, railway and existing railway disturb also more and more, basically adopt usual friendship, on stride and under the mode of wearing solve, wherein usual friendship is big to railway, road safety hidden danger, basically do not consider usual friendship now, on to stride mode less to existing railway operation influence, but the mode of wearing down is very big to existing railway operation influence.
Under in the city, wear existing railway, because constructing just, line takes up an area of many, the place is limited, be difficult to carry out mostly, the general employing maked somebody a mere figurehead the construction of existing railway method, problems such as but suspension bridge pier difficulty of construction is very big under high water level, geological conditions extreme difference situation, and job practices existed potential safety hazard big in the past, and the construction period is long.At under wear existing railway, construction railroad suspension bridge how under the condition of guaranteeing railway operation, high water level, geological conditions extreme difference, the construction of suspension bridge pier and safeguard procedures are engineering key of success.
Summary of the invention
The purpose of this utility model provides a kind of suspension bridge that is used for soft base, the built on stilts existing railway in high water level location, can effectively solve the problem that above-mentioned prior art exists.
This suspension bridge that is used for soft base, the built on stilts existing railway in high water level location of the present utility model, comprise just beam, columnar pier, rectangle abutment and pile foundation, it is characterized in that: utilize to be positioned at the simple and easy buttress of existing railway both sides and the just empty existing railway of roof beam structure, form the suspension bridge that sets up the first time; Utilization is positioned at columnar pier under the existing railway, rectangle abutment and the just empty existing railway of roof beam structure, forms the suspension bridge that sets up for the second time; After for the first time setting up suspension bridge, just the beam below is connected with several vertical sheet piles, the sheet pile outside is connected with retaining wall, between two adjacent sheet piles, form the space that to satisfy the operation of drilling machine equipment, the top in this space has i iron to do to shore, and the service aisle of the bottom bracing of concreting for the construction stake basis arranged at the bottom; Hole downwards in service aisle and build the formation pile foundation, rectangle abutment cushion cap, abutment body and bridge pier bent cap are made in this pile foundation top.
Aforesaid i iron is shored and is adopted angle steel laterally to connect.
Be equipped with i iron in the aforesaid concrete bottom bracing.
Wide * the height of aforesaid service aisle is 5m * 6m.
The utlity model has following advantage:
(a) adopt the suspension bridge overhead wire in locations such as high water level, soft bases, both reduced expropriation of land and removed, take ground less, can make the engineering smooth implementation again, can ensure the safe operation of existing railway simultaneously again effectively.
(b) utilize and set up just beam twice, the temporary bridge for construction pier can carry out accelerating construction progress synchronously one by one.
(c) save engineering cost, economical rationality, technological innovation.
More have superiority on the existing railway of many railway operations such as the utility model job practices is applicable under the newly-built road wears existing railway, interior at the train station.
Description of drawings
The suspension bridge structural representation of Fig. 1~5 for illustrating and form according to the suspension bridge construction process that the utility model proposes.
The specific embodiment
Construction graphical analysis procedure below in conjunction with the suspension bridge pier is described in further detail the utility model:
Among Fig. 1, do simple and easy buttress 3 earlier, utilize just beam 1 built on stilts existing railway 2 in the existing railway both sides.
Among Fig. 2, merogenesis construction retaining wall 8 utilizes retaining wall 8 supportings, the job-hopping hand excavation soil body 5, construction sheet pile 7.Add i iron 6 at 7 tops of two sheet piles and do to shore, adopt angle steel laterally to connect between i iron.The excavation soil body 5 is to sheet pile bottom design absolute altitude and build sheet pile.
Among Fig. 3, excavate the soil body 5 between two sheet piles, the supporting while excavating is excavated to and can satisfies till the space that drilling machine equipment operates, and builds steel concrete in this bottom, space and makes bottom bracing 9, to form the service aisle of suspension bridge pier pile foundation 10 constructions.Can in concrete, add i iron during construction bottom bracing 9.
Among Fig. 4, set up drilling machine equipment, temporary bridge for construction pier pile foundation 10 is holed to design elevation, and the segmentation descending reinforcing cage is built pile foundation.Construct then abutment cushion cap, abutment body and the bridge pier bent cap 11 on top.
Among Fig. 5, vertically move and set up just beam 1, the excavation railway is the beam cubic metre of earth 5 road grooves to newly-built road 4 down just, and remove influential part retaining wall 8.Newly-built road 4 road surfaces and ancillary facility thereof on the groove of construction road.
Claims (4)
1. suspension bridge that is used for the built on stilts existing railway of soft base, high water level location, comprise just beam, columnar pier, rectangle abutment and pile foundation, it is characterized in that: utilize to be positioned at the simple and easy buttress of existing railway both sides and the just empty existing railway of roof beam structure, form the suspension bridge that sets up the first time; Utilization is positioned at columnar pier under the existing railway, rectangle abutment and the just empty existing railway of roof beam structure, forms the suspension bridge that sets up for the second time; After for the first time setting up suspension bridge, just the beam below is connected with several vertical sheet piles, the sheet pile outside is connected with retaining wall, between two adjacent sheet piles, form the space that to satisfy the operation of drilling machine equipment, the top in this space has i iron to do to shore, and the service aisle of the bottom bracing of concreting for the construction stake basis arranged at the bottom; Hole downwards in service aisle and build the formation pile foundation, rectangle abutment cushion cap, abutment body and bridge pier bent cap are made in this pile foundation top.
2. the suspension bridge of built on stilts existing railway as claimed in claim 1 is characterized in that: i iron is shored and is adopted angle steel laterally to connect.
3. the suspension bridge of built on stilts existing railway as claimed in claim 1 is characterized in that: be equipped with i iron in the concrete bottom bracing.
4. the suspension bridge of built on stilts existing railway as claimed in claim 1 is characterized in that: the wide * high 5m * 6m of being of service aisle.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009202151335U CN201567523U (en) | 2009-12-31 | 2009-12-31 | Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009202151335U CN201567523U (en) | 2009-12-31 | 2009-12-31 | Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN201567523U true CN201567523U (en) | 2010-09-01 |
Family
ID=42659806
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2009202151335U Expired - Fee Related CN201567523U (en) | 2009-12-31 | 2009-12-31 | Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN201567523U (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108385531A (en) * | 2018-03-01 | 2018-08-10 | 成都佰人佰思科技有限公司 | A kind of road and bridge combined type construction method |
| CN111305031A (en) * | 2020-03-27 | 2020-06-19 | 中铁二院昆明勘察设计研究院有限责任公司 | Reverse construction of bridge structure and construction method under existing road |
| CN112323627A (en) * | 2020-09-11 | 2021-02-05 | 中铁二院昆明勘察设计研究院有限责任公司 | Frame type construction system and construction method in existing railway temporary bridge construction |
| CN114606804A (en) * | 2022-03-02 | 2022-06-10 | 中铁二院昆明勘察设计研究院有限责任公司 | Method for constructing large-scale frame by repeatedly overhead existing railway on soft foundation |
| CN115110393A (en) * | 2022-04-18 | 2022-09-27 | 浙江中桓建设有限公司 | Stable section steel bridge and construction method of steel bridge |
| CN115852765A (en) * | 2023-01-17 | 2023-03-28 | 中建八局轨道交通建设有限公司 | Method for reconstructing and expanding road under existing operating railway bridge |
-
2009
- 2009-12-31 CN CN2009202151335U patent/CN201567523U/en not_active Expired - Fee Related
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108385531A (en) * | 2018-03-01 | 2018-08-10 | 成都佰人佰思科技有限公司 | A kind of road and bridge combined type construction method |
| CN111305031A (en) * | 2020-03-27 | 2020-06-19 | 中铁二院昆明勘察设计研究院有限责任公司 | Reverse construction of bridge structure and construction method under existing road |
| CN112323627A (en) * | 2020-09-11 | 2021-02-05 | 中铁二院昆明勘察设计研究院有限责任公司 | Frame type construction system and construction method in existing railway temporary bridge construction |
| CN114606804A (en) * | 2022-03-02 | 2022-06-10 | 中铁二院昆明勘察设计研究院有限责任公司 | Method for constructing large-scale frame by repeatedly overhead existing railway on soft foundation |
| CN115110393A (en) * | 2022-04-18 | 2022-09-27 | 浙江中桓建设有限公司 | Stable section steel bridge and construction method of steel bridge |
| CN115852765A (en) * | 2023-01-17 | 2023-03-28 | 中建八局轨道交通建设有限公司 | Method for reconstructing and expanding road under existing operating railway bridge |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101768924B (en) | Overhead method for existing railway in area with soft foundation and high water level | |
| CN107558494B (en) | A rail transit underground station structure and construction method thereof | |
| CN107119711B (en) | Connecting structure for large-range adjacent existing transfer station and construction method | |
| CN105862930B (en) | A kind of protection structure to creating existing tunnel below underground engineering | |
| CN201567523U (en) | Temporary bridge for erecting existing railway overhead in sections with soft foundation or high water level | |
| CN101761068A (en) | Box-raft pressure-bearing type foundation underpinning and construction reinforcing method for tunnel across pile foundation of bridge above river | |
| CN105064397A (en) | Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation | |
| CN105089670B (en) | Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel | |
| CN105804119A (en) | Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure | |
| CN112983493B (en) | Reinforcing structure for shield to closely penetrate large-section bridge and culvert downwards and construction method | |
| CN111270615B (en) | Bridge-tunnel connection part tunnel widening structure | |
| CN103103988A (en) | Foundation ditch construction method of horizontal bracing structure of central island floor slaps | |
| CN113293665B (en) | Roadbed reinforcing method for long side of railway bridge and culvert connection | |
| CN104631489A (en) | Bridge cushion cap force underpinning technology in underneath pass open trench tunnel construction | |
| CN111236241B (en) | Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method | |
| CN217299022U (en) | Open cut tunnel is striden existing subway cross section protection system | |
| CN114718104A (en) | Open-cut tunnel combined bridge underpinning integrated construction method | |
| CN104652444A (en) | Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation | |
| CN106013173A (en) | Subway station construction body envelop enclosing structure | |
| CN114232602A (en) | Underground continuous pile construction process | |
| CN105350589A (en) | Underpinning construction method for pile foundation crossing existing protective building structure | |
| CN113235639A (en) | Existing line lower row pile enclosure structure and construction method thereof | |
| CN216765941U (en) | Tunnel decompression load shedding structure under bias voltage state | |
| CN110439000A (en) | Internal transportation system and construction method of underground structure based on slab chute | |
| CN110939139B (en) | Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C17 | Cessation of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100901 Termination date: 20131231 |