CN105780828B - The model test apparatus and operating method that open-cut foundation ditch influences on adjacent building basis - Google Patents
The model test apparatus and operating method that open-cut foundation ditch influences on adjacent building basis Download PDFInfo
- Publication number
- CN105780828B CN105780828B CN201610276119.0A CN201610276119A CN105780828B CN 105780828 B CN105780828 B CN 105780828B CN 201610276119 A CN201610276119 A CN 201610276119A CN 105780828 B CN105780828 B CN 105780828B
- Authority
- CN
- China
- Prior art keywords
- soil
- simulation
- tank
- rock
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D33/00—Testing foundations or foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
Abstract
Description
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610276119.0A CN105780828B (en) | 2016-04-29 | 2016-04-29 | The model test apparatus and operating method that open-cut foundation ditch influences on adjacent building basis |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610276119.0A CN105780828B (en) | 2016-04-29 | 2016-04-29 | The model test apparatus and operating method that open-cut foundation ditch influences on adjacent building basis |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105780828A CN105780828A (en) | 2016-07-20 |
CN105780828B true CN105780828B (en) | 2018-01-23 |
Family
ID=56400039
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610276119.0A Active CN105780828B (en) | 2016-04-29 | 2016-04-29 | The model test apparatus and operating method that open-cut foundation ditch influences on adjacent building basis |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105780828B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110631560B (en) * | 2019-08-13 | 2021-11-26 | 中铁上海工程局集团有限公司 | Underground excavation interval monitoring and measuring method for subway station in dense building area |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4378244B2 (en) * | 2004-08-23 | 2009-12-02 | 株式会社竹中工務店 | Loading test method for piled raft foundation |
CN201843152U (en) * | 2010-10-19 | 2011-05-25 | 同济大学 | Simulation tester for construction and monitoring of deep foundation pit engineering |
CN102914632A (en) * | 2012-10-16 | 2013-02-06 | 武汉理工大学 | Multifunctional geotechnical model test chamber |
CN103454400A (en) * | 2013-07-11 | 2013-12-18 | 北京工业大学 | Model box applied to large stereoscopic synthesis simulation test bench in geotechnical engineering |
CN204590103U (en) * | 2015-02-04 | 2015-08-26 | 山东大学 | Base Pit Excavation Simulation device under hypergravity condition |
CN205712226U (en) * | 2016-04-29 | 2016-11-23 | 石家庄铁道大学 | The model test apparatus that adjacent building basis is affected by open-cut foundation ditch |
-
2016
- 2016-04-29 CN CN201610276119.0A patent/CN105780828B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4378244B2 (en) * | 2004-08-23 | 2009-12-02 | 株式会社竹中工務店 | Loading test method for piled raft foundation |
CN201843152U (en) * | 2010-10-19 | 2011-05-25 | 同济大学 | Simulation tester for construction and monitoring of deep foundation pit engineering |
CN102914632A (en) * | 2012-10-16 | 2013-02-06 | 武汉理工大学 | Multifunctional geotechnical model test chamber |
CN103454400A (en) * | 2013-07-11 | 2013-12-18 | 北京工业大学 | Model box applied to large stereoscopic synthesis simulation test bench in geotechnical engineering |
CN204590103U (en) * | 2015-02-04 | 2015-08-26 | 山东大学 | Base Pit Excavation Simulation device under hypergravity condition |
CN205712226U (en) * | 2016-04-29 | 2016-11-23 | 石家庄铁道大学 | The model test apparatus that adjacent building basis is affected by open-cut foundation ditch |
Also Published As
Publication number | Publication date |
---|---|
CN105780828A (en) | 2016-07-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106013052B (en) | The construction method of steel sheet pile and open caisson Combined type underground garage parking | |
CN106950070B (en) | Experimental rig for rectangular top pipe jacking construction Whole Process Simulation | |
CN106596268B (en) | Multi-immersion working condition simulation test model box and test method | |
CN106013053B (en) | A kind of steel sheet pile construction method for supporting for being used to build underground garage open caisson | |
CN103837360B (en) | Tunnel pipe shed construction method simulated excavation device and implementation method thereof | |
CN105672356B (en) | A kind of municipal pipeline group's Underground Construction method of spanning over subway tunnel | |
CN105888703A (en) | Method for constructing super-shallow-burial subway station under transverse canopy erected inside micro pilot tunnel | |
KR101733144B1 (en) | Tunnelling equipment using the trap-door and model test equipment using the same | |
CN103806464B (en) | Large-scale high ferro station and subway cross top-down construction method up and down | |
CN106153358B (en) | Topographic change and restructural comprehensive test device and test method | |
CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
CN105672314A (en) | Method for constructing steel pipe upright pile through semi-reversed-construction method | |
CN112881166B (en) | Device and method for testing stability of foundation in mining overall process and mining subsidence area | |
CN112229981A (en) | Device for simulating comprehensive influence of foundation pit excavation and multi-gradient precipitation on tunnel | |
CN107237350A (en) | The pushing tow correction support replacement system and method for prefabricated assembled underpass structure | |
CN112240025A (en) | Station foundation pit engineering cover-excavation construction method | |
CN210263062U (en) | Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom | |
CN105780828B (en) | The model test apparatus and operating method that open-cut foundation ditch influences on adjacent building basis | |
CN105804115B (en) | Assembled ground-connecting-wall or prefabricated pile and assembled underground station integrative construction device and construction method | |
CN207609374U (en) | Lift self-travel type full-sleeve full-rotation drill | |
CN105714851B (en) | Assembled ground-connecting-wall or prefabricated pile are with cast-in-place underground station integrative construction device and using its construction method | |
CN105840216B (en) | A kind of tunneling construction method of underground space development | |
CN110700299B (en) | Deep foundation pit structural beam reinforcement framework modularization rapid construction method | |
CN205712226U (en) | The model test apparatus that adjacent building basis is affected by open-cut foundation ditch | |
CN210037042U (en) | Frictional resistance testing device during jacking of rectangular jacking pipe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Zhang Jian Inventor after: Du Yanliang Inventor after: Zhao Weigang Inventor after: Wang Jingchun Inventor after: Gao Yang Inventor after: Li Jianzhi Inventor before: Du Yanliang Inventor before: Zhang Jian Inventor before: Zhao Weigang Inventor before: Wang Jingchun Inventor before: Gao Yang Inventor before: Li Jianzhi |
|
GR01 | Patent grant | ||
GR01 | Patent grant |