CN105735140B - An aerial work platform device on the side of a bridge - Google Patents

An aerial work platform device on the side of a bridge Download PDF

Info

Publication number
CN105735140B
CN105735140B CN201610233289.0A CN201610233289A CN105735140B CN 105735140 B CN105735140 B CN 105735140B CN 201610233289 A CN201610233289 A CN 201610233289A CN 105735140 B CN105735140 B CN 105735140B
Authority
CN
China
Prior art keywords
walking
hanging basket
guide rail
work platform
shaped guide
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610233289.0A
Other languages
Chinese (zh)
Other versions
CN105735140A (en
Inventor
唐丽
姜友荣
李丽
刘云辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201710585517.5A priority Critical patent/CN107178035B/en
Priority to CN201610233289.0A priority patent/CN105735140B/en
Publication of CN105735140A publication Critical patent/CN105735140A/en
Application granted granted Critical
Publication of CN105735140B publication Critical patent/CN105735140B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00—Structural or constructional details of bridges
    • E01D19/10—Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/106—Movable inspection or maintenance platforms, e.g. travelling scaffolding or vehicles specially designed to provide access to the undersides of bridges
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a bridge side aerial work platform device which comprises an I-shaped guide rail, moving suspension beams, a hanging basket assembly and a platform walking control device, wherein a strip-shaped groove is formed in a vertical plate of the I-shaped guide rail, one end of each of the two moving suspension beams is arranged in the strip-shaped groove, track wheels are arranged on the moving suspension beams on two sides of the vertical plate, and the track wheels drive the moving suspension beams to move along the tracks on two sides of the I-shaped guide rail; the other ends of the two movable suspension beams are connected with the hanging basket component in a suspension manner; the platform walking control device drives the movable suspension beam to suspend the hanging basket component to walk on the I-shaped guide rail. The I-shaped guide rail is used as a moving rail of the aerial work platform, the moving suspension beam is horizontally limited in a sliding groove of the I-shaped guide rail through the two sets of rail wheels, the two sets of rail wheels not only ensure the horizontal limitation of the moving suspension beam, but also enable the work platform device to move along the I-shaped guide rail through the two sets of rail wheels.

Description

一种桥梁侧方高空作业平台装置An aerial work platform device on the side of a bridge

技术领域technical field

本发明涉及一种高空作业平台装置领域,具体涉及一种桥梁侧方高空作业平台装置。The invention relates to the field of aerial work platform devices, in particular to a bridge side aerial work platform device.

背景技术Background technique

随着交通量的日益增大,在桥梁建设或养护中,往往需要对桥梁的侧面进行作业施工,比如检修、走线、安装装饰材料等。现有的桥梁侧方高空作业平台装置一般都是大型专业工具,使用成本高,需要多人协同操作,另外,也有采用悬挑脚手架钢梁为部分悬挑的结构提供施工平台的方法来解决工程问题,或者采用需底部进行支撑的平台进行施工。它们的不足之处是:拆卸不方便、占用空间大,当桥梁较高时,搭建也不方便,还无法移动。With the increasing traffic volume, in bridge construction or maintenance, it is often necessary to carry out work on the side of the bridge, such as maintenance, routing, installation of decorative materials, etc. The existing aerial work platform devices on the side of the bridge are generally large-scale professional tools, which are expensive to use and require the cooperation of multiple people. In addition, there are also methods of using cantilevered scaffolding steel beams to provide construction platforms for partially cantilevered structures to solve engineering problems. problem, or use a platform that needs to be supported by the bottom for construction. Their disadvantages are: it is inconvenient to disassemble and takes up a lot of space. When the bridge is high, it is also inconvenient to build and cannot be moved.

发明内容Contents of the invention

本发明的目的即在于克服现有技术的不足,提供一种桥梁侧方高空作业平台装置,解决桥梁侧方高空作业缺少简易操作平台,导致施工麻烦,施工成本大的问题。The purpose of the present invention is to overcome the deficiencies of the prior art, provide a bridge side aerial work platform device, and solve the problem of lack of a simple operation platform for bridge side aerial work, resulting in troublesome construction and high construction costs.

本发明的通过下述技术方案实现:一种桥梁侧方高空作业平台装置,包括工字型导轨、移动悬挂梁、吊篮组件和平台行走操控装置,所述工字型导轨的立板上设置有条形槽,两根所述移动悬挂梁一端设置在条形槽内,位于所述立板两侧的移动悬挂梁上均设置有轨道轮,所述的轨道轮沿工字型导轨两侧轨道内带动移动悬挂梁移动;两根所述移动悬挂梁另一端与吊篮组件悬挂连接;所述的平台行走操控装置带动移动悬挂梁悬挂着吊篮组件在工字型导轨上行走。The present invention is realized through the following technical solutions: a bridge side aerial work platform device, including an I-shaped guide rail, a mobile suspension beam, a hanging basket assembly and a platform walking control device, and the vertical plate of the I-shaped guide rail is set There is a strip groove, and one end of the two mobile suspension beams is arranged in the strip groove, and track wheels are arranged on the mobile suspension beams on both sides of the vertical plate, and the track wheels are arranged along the two sides of the I-shaped guide rail. The mobile suspension beam is driven to move; the other ends of the two mobile suspension beams are suspended and connected to the hanging basket assembly; the platform walking control device drives the mobile suspension beam to hang the hanging basket assembly to walk on the I-shaped guide rail.

进一步的,所述的平台行走操控装置包括行走横轴、行走立轴和手轮组件,所述的行走横轴平行设置在两根移动悬挂梁之间,所述行走横轴一端设置有在桥面移动的行走轮,所述行走横轴另一端部与吊篮组件连接并在端头上设置有横轴伞齿,所述的行走立轴与行走横轴垂直设置在吊篮组件,所述的行走立轴两端均设有上伞齿和下伞齿,其中行走立轴上端设置的上伞齿与行走横轴上的横轴伞齿相互啮合,所述的手轮组件与行走立轴垂直设置在吊篮组件上,所述手轮组件上也设置有与行走立轴下伞齿相互啮合的手轮伞齿。Further, the platform walking control device includes a walking horizontal axis, a walking vertical axis and a handwheel assembly, the walking horizontal axis is arranged in parallel between two mobile suspension beams, and one end of the walking horizontal axis is arranged on the bridge deck. The moving wheel, the other end of the horizontal walking axis is connected to the hanging basket assembly and the end is provided with a horizontal axis bevel tooth, the vertical walking axis and the horizontal walking axis are vertically arranged on the hanging basket assembly, and the walking Both ends of the vertical shaft are provided with upper bevel teeth and lower bevel teeth, wherein the upper bevel teeth set on the upper end of the walking vertical shaft mesh with the horizontal axis bevel teeth on the walking horizontal axis, and the hand wheel assembly is vertically arranged on the hanging basket with the walking vertical shaft On the assembly, the hand wheel assembly is also provided with hand wheel bevel teeth that mesh with the lower bevel teeth of the walking vertical shaft.

进一步的,所述吊篮组件上设置有罩在行走立轴、上伞齿和下伞齿的防护罩。Further, the hanging basket assembly is provided with a protective cover covering the walking vertical shaft, the upper bevel teeth and the lower bevel teeth.

进一步的,所述的平台行走操控装置包括行走横轴、电机及带动电机的锂电池,所述的行走横轴平行设置在两根移动悬挂梁之间,所述行走横轴一端设置有在桥面移动的行走轮,所述行走横轴另一端与电机传动连接,所述的锂电池设置在吊篮组件上通过导线与电机连接。Further, the platform walking control device includes a walking axis, a motor and a lithium battery for driving the motor, the walking axis is arranged in parallel between two mobile suspension beams, and one end of the walking axis is provided with a bridge The other end of the horizontal axis of travel is connected to the motor drive, and the lithium battery is set on the hanging basket assembly and connected to the motor through wires.

进一步的,所述的吊篮组件包括竖直吊臂、斜吊臂和作业平台,两根所述的竖直吊臂上端分别与两根移动悬挂梁端头固定连接,两根所述的竖直吊臂下端分别与作业平台端部连接,两根所述的斜吊臂上端分别与移动悬挂梁连接,两根所述的斜吊臂下端分别与作业平台两侧连接。Further, the hanging basket assembly includes a vertical boom, an inclined boom and a work platform, the upper ends of the two vertical booms are respectively fixedly connected with the ends of the two mobile suspension beams, and the two vertical booms The lower ends of the straight booms are respectively connected to the ends of the work platform, the upper ends of the two inclined booms are respectively connected to the mobile suspension beam, and the lower ends of the two inclined booms are respectively connected to both sides of the work platform.

进一步的,所述的吊篮组件上还设置有爬梯,所述的爬梯与竖直吊臂平行设置。方便施工人员进入吊篮,方便安全。Further, the hanging basket assembly is also provided with a ladder, and the ladder is arranged parallel to the vertical boom. It is convenient for construction workers to enter the hanging basket, which is convenient and safe.

进一步的,所述的作业平台上设置有两根水平支腿,所述的水平支腿上设置有在桥梁体立面横向移动的支撑滑轮。通过支撑滑轮可以有效增加正移动悬挂梁在工字型导轨内的平衡度,减少了轨道轮在工字型导轨内的摩擦力,便于移动悬挂梁悬挂着吊篮组件在工字型导轨上行走。Further, the working platform is provided with two horizontal outriggers, and the horizontal outriggers are provided with support pulleys which move laterally on the bridge body elevation. The support pulley can effectively increase the balance of the moving suspension beam in the I-shaped guide rail, reduce the friction of the track wheel in the I-shaped guide rail, and facilitate the movement of the suspension beam hanging on the I-shaped guide rail. .

本发明与现有技术相比,具有如下的优点和有益效果:Compared with the prior art, the present invention has the following advantages and beneficial effects:

1、通过设置的工字型导轨作为高空作业平台移动轨道,移动悬挂梁通过两套轨道轮被水平限位在工字型导轨的滑槽内,两套轨道轮不但保证对移动悬挂梁的水平限位,还可以通过两套轨道轮使作业平台装置沿工字型导轨移动;1. The I-shaped guide rail is used as the moving track of the aerial work platform, and the mobile suspension beam is horizontally limited in the chute of the I-shaped guide rail by two sets of track wheels. The two sets of track wheels not only ensure the level of the mobile suspension beam The limit position can also move the working platform device along the I-shaped guide rail through two sets of track wheels;

2、通过设置手动控制的平台行走操控装置,可以实现作业人员自己转动手轮控制吊篮组件沿桥梁移动,这种操控装置结构简单,依靠人工没有动力使用限制,不受施工场地的限制,便于实施;2. By setting up a manually controlled platform walking control device, the operator can turn the hand wheel to control the movement of the hanging basket assembly along the bridge. This control device has a simple structure, and there is no power usage limit depending on manual work. It is not limited by the construction site and is convenient. implementation;

3、通过设置电动控制的平台行走操控装置,可以实现电能控制吊篮组件沿桥梁移动,这种操控装置结构也简单,不需要人工提供动力移动,可以减少工人劳动强度,缺点就是需要对移动锂电池充电,受施工场地的限制;3. By setting the electric control platform walking control device, the electric energy can control the movement of the hanging basket assembly along the bridge. The structure of this control device is also simple, and it does not need manual power to move, which can reduce the labor intensity of workers. The disadvantage is that it needs to move lithium Battery charging is limited by the construction site;

4、在吊篮组件上设置爬梯,方便施工人员进入吊篮,方便安全;4. Set up a ladder on the hanging basket assembly to facilitate the construction personnel to enter the hanging basket, which is convenient and safe;

5、在作业平台上设置有两根水平支腿,水平支腿上设置有在桥梁体立面横向移动的支撑滑轮,通过支撑滑轮可以有效增加正移动悬挂梁在工字型导轨内的平衡度,减少了轨道轮在工字型导轨内的摩擦力,便于移动悬挂梁悬挂着吊篮组件在工字型导轨上行走。5. There are two horizontal outriggers on the work platform, and the horizontal outriggers are equipped with supporting pulleys that move laterally on the bridge body elevation. The supporting pulleys can effectively increase the balance of the positively moving suspension beam in the I-shaped guide rail , reducing the friction of the track wheels in the I-shaped guide rail, which is convenient for moving the suspension beam and hanging the basket assembly to walk on the I-shaped guide rail.

附图说明Description of drawings

此处所说明的附图用来提供对本发明实施例的进一步理解,构成本申请的一部分,并不构成对本发明实施例的限定。在附图中:The drawings described here are used to provide a further understanding of the embodiments of the present invention, constitute a part of the application, and do not limit the embodiments of the present invention. In the attached picture:

图1为本发明一种桥梁侧方高空作业平台装置手动移动的结构示意图;Fig. 1 is a structural schematic diagram of the manual movement of a bridge side aerial work platform device according to the present invention;

图2为本发明一种桥梁侧方高空作业平台装置手动移动立体的结构示意图;Fig. 2 is a schematic structural diagram of a bridge side aerial work platform device manually moving in the present invention;

图3为本发明一种桥梁侧方高空作业平台装置电动移动的结构示意图;Fig. 3 is a structural schematic diagram of the electric movement of a bridge side aerial work platform device according to the present invention;

图4为本发明一种桥梁侧方高空作业平台装置电动移动立体的结构示意图;Fig. 4 is a structural schematic diagram of the electric mobile three-dimensional structure of a bridge side aerial work platform device according to the present invention;

附图中标记及相应的零部件名称:Marks and corresponding component names in the attached drawings:

1-工字型导轨,2-移动悬挂梁,3-吊篮组件,4-平台行走操控装置,5-条形槽,6-轨道轮,7-行走横轴,8-行走立轴,9-手轮组件,10-行走轮,11-横轴伞齿,12-上伞齿,13-下伞齿,14-手轮伞齿,15-防护罩,16-电机,17-锂电池,18-竖直吊臂19-斜吊臂,20-作业平台,21-爬梯,22-水平支腿,23-支撑滑轮。1-I-shaped guide rail, 2-Moving suspension beam, 3-Basket assembly, 4-Platform walking control device, 5-Strip groove, 6-Track wheel, 7-Traveling horizontal axis, 8-Traveling vertical shaft, 9- Hand wheel assembly, 10-walking wheel, 11-horizontal shaft bevel gear, 12-upper bevel gear, 13-lower bevel gear, 14-hand wheel bevel gear, 15-protective cover, 16-motor, 17-lithium battery, 18 -vertical boom 19-slanted boom, 20-operating platform, 21-climbing ladder, 22-horizontal support leg, 23-support pulley.

具体实施方式detailed description

为使本发明的目的、技术方案和优点更加清楚明白,下面结合实施例和附图,对本发明作进一步的详细说明,本发明的示意性实施方式及其说明仅用于解释本发明,并不作为对本发明的限定。In order to make the purpose, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the examples and accompanying drawings. As a limitation of the present invention.

实施例1Example 1

如图1-4所示,本发明一种桥梁侧方高空作业平台装置,包括工字型导轨1、移动悬挂梁2、吊篮组件3和平台行走操控装置4,移动悬挂梁2采用外径为50的圆钢制成,工字型导轨1的立板上设置有条形槽5,两根移动悬挂梁2一端设置在条形槽5内,在位于立板两侧的移动悬挂梁2上均设置有轨道轮6,轨道轮6沿工字型导轨1两侧轨道内带动移动悬挂梁2移动;两根移动悬挂梁2另一端与吊篮组件3悬挂连接;平台行走操控装置4带动移动悬挂梁2悬挂着吊篮组件3在工字型导轨1上行走。通过设置的工字型导轨1作为高空作业平台移动轨道,移动悬挂梁2通过两套轨道轮6被水平限位在工字型导轨1的滑槽内,两套轨道轮6不但保证对移动悬挂梁2的水平限位,还可以通过两套轨道轮6使作业平台装置沿工字型导轨1移动。As shown in Figures 1-4, a bridge side aerial work platform device according to the present invention includes an I-shaped guide rail 1, a mobile suspension beam 2, a hanging basket assembly 3 and a platform walking control device 4, and the mobile suspension beam 2 adopts an outer diameter It is made of 50 round steel, and the vertical plate of the I-shaped guide rail 1 is provided with a strip groove 5, and one end of two mobile suspension beams 2 is arranged in the strip groove 5, and the mobile suspension beams 2 on both sides of the vertical plate There are track wheels 6 on both sides, and the track wheels 6 drive the mobile suspension beam 2 to move along the tracks on both sides of the I-shaped guide rail 1; the other ends of the two mobile suspension beams 2 are suspended and connected with the hanging basket assembly 3; The mobile suspension beam 2 hangs the hanging basket assembly 3 and walks on the I-shaped guide rail 1. The I-shaped guide rail 1 is used as the moving track of the aerial work platform, and the mobile suspension beam 2 is horizontally limited in the chute of the I-shaped guide rail 1 by two sets of track wheels 6. The horizontal limit of the beam 2 can also make the work platform device move along the I-shaped guide rail 1 by two sets of track wheels 6 .

吊篮组件3包括竖直吊臂18、斜吊臂19和作业平台20,两根竖直吊臂18上端分别与两根移动悬挂梁2端头固定连接,两根竖直吊臂18下端分别与作业平台20端部连接,两根斜吊臂19上端分别与移动悬挂梁2连接,两根斜吊臂19下端分别与作业平台20两侧连接,竖直吊臂18、斜吊臂19以及作业平台20的框架采用外径20的圆钢制成,作业平台20的板面采用4mm厚的花纹钢板。The hanging basket assembly 3 comprises a vertical boom 18, an inclined boom 19 and a working platform 20, the upper ends of the two vertical booms 18 are fixedly connected with the ends of the two mobile suspension beams 2 respectively, and the lower ends of the two vertical booms 18 are respectively Connect with the end of the work platform 20, the upper ends of the two inclined booms 19 are connected with the mobile suspension beam 2 respectively, the lower ends of the two inclined booms 19 are respectively connected with the two sides of the work platform 20, the vertical boom 18, the inclined boom 19 and the The frame of the work platform 20 is made of round steel with an outer diameter of 20, and the plate surface of the work platform 20 is made of a 4mm thick checkered steel plate.

吊篮组件3上还设置有爬梯21,爬梯21与竖直吊臂18平行设置,在吊篮组件上设置爬梯21,方便施工人员进入吊篮,方便安全。作业平台20上设置有两根水平支腿22,水平支腿22上设置有在桥梁体立面横向移动的支撑滑轮23。在作业平台上设置有两根水平支腿22,水平支腿22上设置有在桥梁体立面横向移动的支撑滑轮23,通过支撑滑轮23可以有效增加正移动悬挂梁2在工字型导轨1内的平衡度,减少了轨道轮6在工字型导轨1内的摩擦力,便于移动悬挂梁2悬挂着吊篮组件3在工字型导轨1上行走。Hanging basket assembly 3 is also provided with climbing ladder 21, and climbing ladder 21 is arranged in parallel with vertical boom 18, and climbing ladder 21 is set on hanging basket assembly, convenient construction personnel enters hanging basket, convenient and safe. The work platform 20 is provided with two horizontal outriggers 22, and the horizontal outriggers 22 are provided with a supporting pulley 23 which moves laterally on the bridge body elevation. Two horizontal outriggers 22 are arranged on the working platform, and the supporting pulley 23 which moves laterally on the bridge body elevation is arranged on the horizontal outrigger 22. The support pulley 23 can effectively increase the positive movement of the suspension beam 2 on the I-shaped guide rail 1. The inner balance degree reduces the frictional force of track wheel 6 in the I-shaped guide rail 1, and is convenient to move the suspension beam 2 to hang the hanging basket assembly 3 and walk on the I-shaped guide rail 1.

使用时,现将工字型导轨1固定在桥面上,由于移动悬挂梁2和吊篮组件3为焊接一体结构,现场将移动悬挂梁2和轨道轮6安装在工字型导轨1内,检验安装牢固性后,作业人员通过爬梯21进入吊篮工作,需要移动作业平台装置时,作业人员通过平台行走操控装置4控制作业平台装置前后移动,当一个工字型导轨1对应的桥体侧方工作面完成施工后,移动工字型导轨1到下一个工作面施工。When in use, the I-shaped guide rail 1 is now fixed on the bridge deck. Since the mobile suspension beam 2 and the hanging basket assembly 3 are welded in one structure, the mobile suspension beam 2 and the track wheels 6 are installed in the I-shaped guide rail 1 on site. After checking the firmness of the installation, the operator enters the hanging basket to work through the ladder 21. When the operation platform device needs to be moved, the operator controls the operation platform device to move forward and backward through the platform walking control device 4. When the side of the bridge body corresponding to an I-shaped guide rail 1 After the construction of the square working face is completed, move the I-shaped guide rail 1 to the next working face for construction.

实施例2Example 2

如图1-2所示,本发明一种桥梁侧方高空作业平台装置,平台行走操控装置4包括行走横轴7、行走立轴8和手轮组件9,行走横轴7平行设置在两根移动悬挂梁2之间,行走横轴7一端设置有在桥面移动的行走轮10,行走横轴7另一端部与吊篮组件3连接并在端头上设置有横轴伞齿11,行走立轴8与行走横轴7垂直设置在吊篮组件3,行走立轴8两端均设有上伞齿12和下伞齿13,其中行走立轴8上端设置的上伞齿12与行走横轴7上的横轴伞齿11相互啮合,手轮组件9与行走立轴8垂直设置在吊篮组件3上,手轮组件9上也设置有与行走立轴8下伞齿13相互啮合的手轮伞齿14。通过设置手动控制的平台行走操控装置4,可以实现作业人员自己转动手轮控制吊篮组件3沿桥梁移动,这种操控装置结构简单,依靠人工没有动力使用限制,不受施工场地的限制,便于实施;吊篮组件3上设置有罩在行走立轴8、上伞齿12和下伞齿13的防护罩15。As shown in Figure 1-2, the present invention is an aerial work platform device on the side of a bridge. The platform walking control device 4 includes a walking horizontal axis 7, a walking vertical axis 8 and a handwheel assembly 9. The walking horizontal axis 7 is arranged in parallel on two moving Between the suspension beams 2, one end of the traveling horizontal shaft 7 is provided with a traveling wheel 10 that moves on the bridge deck, the other end of the traveling horizontal shaft 7 is connected to the hanging basket assembly 3 and the end is provided with a horizontal shaft bevel tooth 11, and the traveling vertical shaft 8 is vertically arranged on the hanging basket assembly 3 with the walking horizontal axis 7, and both ends of the walking vertical shaft 8 are provided with an upper bevel tooth 12 and a lower bevel tooth 13, wherein the upper bevel tooth 12 arranged at the upper end of the walking vertical shaft 8 is connected to the upper bevel tooth 12 on the walking vertical axis 7. The horizontal axis bevel teeth 11 mesh with each other, the hand wheel assembly 9 is vertically arranged on the hanging basket assembly 3 with the walking vertical shaft 8 , and the hand wheel assembly 9 is also provided with a hand wheel bevel tooth 14 which meshes with the lower bevel teeth 13 of the walking vertical shaft 8 . By setting the manually controlled platform walking control device 4, the operator can turn the hand wheel to control the movement of the hanging basket assembly 3 along the bridge. The structure of this control device is simple, and there is no power usage limit by manual work, and it is not limited by the construction site, so it is convenient Implementation; the hanging basket assembly 3 is provided with a protective cover 15 covering the walking vertical shaft 8 , the upper bevel teeth 12 and the lower bevel teeth 13 .

实施例3Example 3

如图3-4所示,本发明一种桥梁侧方高空作业平台装置,平台行走操控装置4包括行走横轴7、电机16及带动电机16的锂电池17,行走横轴7平行设置在两根移动悬挂梁2之间,所述行走横轴7一端设置有在桥面移动的行走轮10,所述行走横轴7另一端与电机16传动连接,所述的锂电池17设置在吊篮组件3上通过导线与电机16连接。通过设置电动控制的平台行走操控装置4,可以实现电能控制吊篮组件3沿桥梁移动,这种操控装置结构也简单,不需要人工提供动力移动,可以减少工人劳动强度,缺点就是需要对移动锂电池充电,受施工场地的限制。As shown in Fig. 3-4, the present invention is a bridge side aerial work platform device, the platform walking control device 4 includes a walking horizontal axis 7, a motor 16 and a lithium battery 17 driving the motor 16, and the walking horizontal axis 7 is arranged on two sides in parallel. Between the two moving suspension beams 2, one end of the traveling horizontal shaft 7 is provided with a traveling wheel 10 that moves on the bridge deck, the other end of the traveling horizontal shaft 7 is connected to a motor 16 through transmission, and the lithium battery 17 is arranged in the hanging basket The assembly 3 is connected with the motor 16 through wires. By setting the electric control platform walking control device 4, it is possible to control the movement of the hanging basket assembly 3 along the bridge by electric energy. Battery charging is limited by the construction site.

以上所述的具体实施方式,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施方式而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The specific embodiments described above have further described the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above descriptions are only specific embodiments of the present invention and are not intended to limit the scope of the present invention. Protection scope, within the spirit and principles of the present invention, any modification, equivalent replacement, improvement, etc., shall be included in the protection scope of the present invention.

Claims (4)

1.一种桥梁侧方高空作业平台装置,包括工字型导轨(1)、移动悬挂梁(2)、吊篮组件(3)和平台行走操控装置(4),其特征在于:所述工字型导轨(1)的立板上设置有条形槽(5),两根所述移动悬挂梁(2)一端设置在条形槽(5)内,在位于所述立板两侧的移动悬挂梁(2)上均设置有轨道轮(6),所述的轨道轮(6)沿工字型导轨(1)两侧轨道内带动移动悬挂梁(2)移动;两根所述移动悬挂梁(2)另一端与吊篮组件悬挂(3)连接;所述的平台行走操控装置(4)带动移动悬挂梁(2)悬挂着吊篮组件(3)在工字型导轨(1)上行走;1. A bridge side aerial work platform device, comprising an I-shaped guide rail (1), a mobile suspension beam (2), a hanging basket assembly (3) and a platform walking control device (4), it is characterized in that: the work The vertical plate of the font guide rail (1) is provided with a strip groove (5), and one end of the two mobile suspension beams (2) is arranged in the strip groove (5). The suspension beams (2) are all provided with track wheels (6), and the track wheels (6) drive the mobile suspension beams (2) to move along the tracks on both sides of the I-shaped guide rail (1); The other end of the beam (2) is connected to the hanging basket assembly (3); the platform walking control device (4) drives the mobile suspension beam (2) to hang the hanging basket assembly (3) on the I-shaped guide rail (1) walk; 所述的平台行走操控装置(4)包括行走横轴(7)、行走立轴(8)和手轮组件(9),所述的行走横轴(7)平行设置在两根移动悬挂梁(2)之间,所述行走横轴(7)一端设置有在桥面移动的行走轮(10),所述行走横轴(7)另一端部与吊篮组件(4)连接并在端头上设置有横轴伞齿(11),所述的行走立轴(8)与行走横轴(7)垂直设置在吊篮组件(3),所述的行走立轴(8)两端均设有上伞齿(12)和下伞齿(13),其中行走立轴(8)上端设置的上伞齿(12)与行走横轴(7)上的横轴伞齿(11)相互啮合,所述的手轮组件(9)与行走立轴(8)垂直设置在吊篮组件(3)上,所述手轮组件(9)上也设置有与行走立轴(8)下伞齿(13)相互啮合的手轮伞齿(14);The platform walking control device (4) includes a walking horizontal axis (7), a walking vertical axis (8) and a hand wheel assembly (9), and the walking horizontal axis (7) is arranged in parallel on two mobile suspension beams (2 ), one end of the walking horizontal axis (7) is provided with a walking wheel (10) that moves on the bridge deck, and the other end of the walking horizontal axis (7) is connected with the hanging basket assembly (4) and on the end The horizontal shaft bevel gear (11) is provided, the walking vertical shaft (8) and the walking horizontal shaft (7) are vertically arranged on the hanging basket assembly (3), and both ends of the walking vertical shaft (8) are provided with upper umbrellas Teeth (12) and lower bevel teeth (13), wherein the upper bevel teeth (12) provided at the upper end of the walking vertical shaft (8) mesh with the horizontal axis bevel teeth (11) on the walking horizontal axis (7), and the hand The wheel assembly (9) and the walking vertical shaft (8) are vertically arranged on the hanging basket assembly (3), and the hand wheel assembly (9) is also provided with a hand wheel that meshes with the lower bevel teeth (13) of the walking vertical shaft (8). Bevel gear (14); 所述的吊篮组件(3)包括竖直吊臂(18)、斜吊臂(19)和作业平台(20),两根所述的竖直吊臂(18)上端分别与两根移动悬挂梁(2)端头固定连接,两根所述的竖直吊臂(18)下端分别与作业平台(20)端部连接,两根所述的斜吊臂(19)上端分别与移动悬挂梁(2)连接,两根所述的斜吊臂(19)下端分别与作业平台(20)两侧连接。The hanging basket assembly (3) includes a vertical boom (18), an inclined boom (19) and a work platform (20), and the upper ends of the two vertical booms (18) are respectively connected to two movable suspensions. The ends of the beam (2) are fixedly connected, the lower ends of the two vertical booms (18) are respectively connected to the ends of the work platform (20), and the upper ends of the two inclined booms (19) are connected to the mobile suspension beam respectively. (2) connection, two described inclined booms (19) lower ends are respectively connected with the work platform (20) both sides. 2.根据权利要求1所述的一种桥梁侧方高空作业平台装置,其特征在于:所述吊篮组件(3)上设置有罩在行走立轴(8)、上伞齿(12)和下伞齿(13)的防护罩(15)。2. A bridge side aerial work platform device according to claim 1, characterized in that: the hanging basket assembly (3) is provided with a cover covering the walking vertical shaft (8), the upper bevel gear (12) and the lower The protective cover (15) of bevel tooth (13). 3.根据权利要求1所述的一种桥梁侧方高空作业平台装置,其特征在于:所述的吊篮组件(3)上还设置有爬梯(21),所述的爬梯(21)与竖直吊臂(18)平行设置。3. A bridge side aerial work platform device according to claim 1, characterized in that: said hanging basket assembly (3) is also provided with a ladder (21), said ladder (21) and vertical Straight boom (18) is arranged in parallel. 4.根据权利要求1或3所述的一种桥梁侧方高空作业平台装置,其特征在于:所述的作业平台(20)上设置有两根水平支腿(22),所述的水平支腿(22)上设置有在桥梁体立面横向移动的支撑滑轮(23)。4. A bridge side aerial work platform device according to claim 1 or 3, characterized in that: said work platform (20) is provided with two horizontal legs (22), said horizontal legs The legs (22) are provided with support pulleys (23) that move laterally on the bridge body facade.
CN201610233289.0A 2016-04-15 2016-04-15 An aerial work platform device on the side of a bridge Active CN105735140B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201710585517.5A CN107178035B (en) 2016-04-15 2016-04-15 Bridge side high altitude operation Electronic control stage apparatus
CN201610233289.0A CN105735140B (en) 2016-04-15 2016-04-15 An aerial work platform device on the side of a bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610233289.0A CN105735140B (en) 2016-04-15 2016-04-15 An aerial work platform device on the side of a bridge

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201710585517.5A Division CN107178035B (en) 2016-04-15 2016-04-15 Bridge side high altitude operation Electronic control stage apparatus

Publications (2)

Publication Number Publication Date
CN105735140A CN105735140A (en) 2016-07-06
CN105735140B true CN105735140B (en) 2017-10-24

Family

ID=56254378

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201710585517.5A Active CN107178035B (en) 2016-04-15 2016-04-15 Bridge side high altitude operation Electronic control stage apparatus
CN201610233289.0A Active CN105735140B (en) 2016-04-15 2016-04-15 An aerial work platform device on the side of a bridge

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201710585517.5A Active CN107178035B (en) 2016-04-15 2016-04-15 Bridge side high altitude operation Electronic control stage apparatus

Country Status (1)

Country Link
CN (2) CN107178035B (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758806A (en) * 2017-01-11 2017-05-31 刘少伟 A kind of portable bridge inspection vehicle
CN107724235B (en) * 2017-11-07 2018-09-18 内蒙古路桥集团有限责任公司 A kind of bridge-collision-avoidance wall Safety operation platform
US10287150B1 (en) 2018-01-06 2019-05-14 Ford Miller Holding Company, LLC Mobile platform carrying system
CN108130861A (en) * 2018-01-29 2018-06-08 中国有色金属工业第十四冶金建设公司 A kind of steel box-girder movable type Hanging Basket
CN108457203A (en) * 2018-02-09 2018-08-28 安徽兰兮工程技术开发有限公司 A kind of motor pattern switching mechanism
CN108411788B (en) * 2018-04-23 2019-07-02 广州市市政工程监理有限公司 A kind of base angle structure that bridge construction test truss auxiliary is built
CN109083008A (en) * 2018-06-09 2018-12-25 中交航局第工程有限公司 A kind of walking Coping Construction job platform and its packaging technology
CN108678358A (en) * 2018-08-03 2018-10-19 中建八局第建设有限公司 A kind of hanging basket suspension platform
CN108708546B (en) * 2018-09-13 2018-12-07 上海建工集团股份有限公司 It is attached to the construction elevator wall-attached frame mounting platform and method of steel platform mould bases
CN112065023A (en) * 2020-08-07 2020-12-11 中国核工业华兴建设有限公司 Hanging basket traveling crane for nuclear reactor-based high-altitude outer wall operation
CN112127611A (en) * 2020-09-23 2020-12-25 中国五冶集团有限公司 An assembled high-altitude corbel construction operation platform device
CN114420331A (en) * 2021-12-13 2022-04-29 中广核工程有限公司 High-altitude operation hanging basket for containment vessel of nuclear power plant and wind resisting method thereof
CN116971295B (en) * 2023-08-16 2026-02-27 中国十七冶集团有限公司 A high-altitude work platform for the cantilever section of a long-span viaduct and its operation method
CN117488653A (en) * 2023-09-28 2024-02-02 中国一冶集团有限公司 A box beam modification and tension grouting operation platform device and its installation and use method
CN117141653A (en) * 2023-10-18 2023-12-01 湖南联诚轨道装备有限公司 A passageway for covered bridges
CN117340604A (en) * 2023-11-09 2024-01-05 海洋石油工程(青岛)有限公司 A wave-type firewall high-altitude welding and cutting protection device

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205501842U (en) * 2016-04-15 2016-08-24 中国五冶集团有限公司 Bridge side aerial working platform device

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4992156B2 (en) * 2008-03-26 2012-08-08 株式会社ピーエス三菱 Formwork support device for PC bridge construction
KR101024412B1 (en) * 2010-10-06 2011-03-23 김옥형 Safety device for bridge inspection passage
CN102296548B (en) * 2011-06-14 2013-06-26 乔国华 Hydraulic truss type moving hanging basket for bridge maintenance and construction method thereof
CN102817320A (en) * 2012-04-27 2012-12-12 中铁大桥局集团第五工程有限公司 Concrete wall guard template construction trolley
CN203834369U (en) * 2014-05-13 2014-09-17 中交第三公路工程局有限公司 Device capable of being rotated by 360 degrees and vertically lifted for bridge
CN203923926U (en) * 2014-07-09 2014-11-05 陈爽 A kind of bridge triangular hanging basket
CN204125842U (en) * 2014-09-09 2015-01-28 中交第一公路工程局有限公司总承包经营分公司 The jointing of case beam breast board is constructed removable Hanging Basket Mobile workbench
CN204418013U (en) * 2014-12-31 2015-06-24 中铁二十一局集团第三工程有限公司 Bridge flange plate is constructed self-propelled cantilever hanging basket
CN204919354U (en) * 2015-08-17 2015-12-30 北京奇力建通工程技术有限公司 A construction equipment that is arranged in construction of taking one's place of cable -stay bridge cable wire
CN105239515B (en) * 2015-09-02 2017-04-19 中铁大桥局武汉桥梁特种技术有限公司 Device and method for bracket installation of railway protective scaffolding in combined highway and railway bridge

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205501842U (en) * 2016-04-15 2016-08-24 中国五冶集团有限公司 Bridge side aerial working platform device

Also Published As

Publication number Publication date
CN105735140A (en) 2016-07-06
CN107178035A (en) 2017-09-19
CN107178035B (en) 2018-11-23

Similar Documents

Publication Publication Date Title
CN107178035B (en) Bridge side high altitude operation Electronic control stage apparatus
CN105000482B (en) Tower crane with traveling mechanism
CN103352559B (en) Storage tank keeps in repair special hanging movable job platform
CN102587277A (en) Mobile equipment special for construction and maintenance of bridge barriers
CN106012824A (en) Movable bridge anti-collision guardrail construction operation trolley
CN114408819A (en) High-altitude edge-facing multifunctional operation platform
CN104291222B (en) The inner hard protection of a kind of high-rise building Core Walls Structure hangs integrated system with row
CN204980946U (en) Take running gear's tower crane
CN202379620U (en) Lifting and operating platform comprehensive equipment
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN206108841U (en) Elevating gear for building small -size
CN213416063U (en) Overhead hanging basket for steel reinforcement framework
CN209653350U (en) A kind of climbing frame to be climbed by gear structure
CN205501842U (en) Bridge side aerial working platform device
CN210713752U (en) High-altitude operation construction hanging basket capable of moving in three-dimensional space
CN203531352U (en) Hanging type movable working platform for storage tank maintenance
CN202729645U (en) Tower crane with elevator
CN211949524U (en) 3D Curtain Wall Construction System
CN210313209U (en) Novel multifunctional crane cab
CN218150028U (en) Novel building outrigger packway structure
CN207434895U (en) A kind of harbour container loop wheel machine
CN216889750U (en) Detachable movable portal frame for improving hoisting operation safety
CN205295947U (en) Portable bridge anticollision wall construction equipment
CN210885045U (en) Tower crane with vertical ladder anti-falling device
CN210594980U (en) Quick detachable hoisting accessory based on building major structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant