CN105715068A - 既有砖混结构隔震支座托换加固结构及其施工方法 - Google Patents
既有砖混结构隔震支座托换加固结构及其施工方法 Download PDFInfo
- Publication number
- CN105715068A CN105715068A CN201610138037.XA CN201610138037A CN105715068A CN 105715068 A CN105715068 A CN 105715068A CN 201610138037 A CN201610138037 A CN 201610138037A CN 105715068 A CN105715068 A CN 105715068A
- Authority
- CN
- China
- Prior art keywords
- isolation cushion
- embedded board
- underpinning
- double bracket
- basis
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0229—Increasing or restoring the load-bearing capacity of building construction elements of foundations or foundation walls
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明公开了一种既有砖混结构隔震支座托换加固结构,包括:形成在原基础上的增大基础、设置在增大基础上部的下支墩、设置在下支墩上部的隔震垫下预埋板、设置在隔震垫下预埋板上部的隔震垫、设置在隔震垫上部的隔震垫上预埋板、设置在隔震垫上预埋板上部的双托梁和设置在双托梁上部的隔震板,所述双托梁内部还设有销键,所述双托梁、销键和隔震板为一体式浇筑成型结构;本发明还提供了上述既有砖混结构隔震支座托换加固结构的施工方法。通过上述方式,本发明结构稳定,安全性高,有较好的抗震性能,另外安装施工比较方便,效率高。
Description
技术领域
本发明涉及建筑结构抗震改造技术领域,特别是涉及一种既有砖混结构隔震支座托换加固结构及其施工方法。
背景技术
既有砖混结构建筑抗震性能不符合现行规范需要加固时,常常用两种方法进行处理:
a、通过对上部结构进行抗震加固,提高结构的抗震性能。
这种方法对上部结构进行抗震加固涉及施工范围广,一般整幢建筑均应加固,施工周期长,并且需破坏原有装饰面加固后重新装修,费用高,构件加固往往增大截面,使建筑使用面积减小。
b、在建筑底部(一般在地圈梁以下)增设隔震层,减小地震作用。
这种方法采用隔震技术仅在房屋底部施工,施工周期短,对上部结构几乎没有影响,不需要破坏原装饰面,节省费用,不影响建筑使用面积。
但目前这种方法的施工技术还不成熟,都是先将隔震垫上下支墩浇筑完成,隔震垫再安放在上下支墩之间,这种施工方法的缺点是:
1、上下支墩施工完成后,隔震垫安装不便;
2、隔震垫与混凝土支墩之间连接不紧密,使结构受力不均,影响结构安全;
3、双托梁与隔震板无法一次浇筑完成,影响浇筑质量且浪费人工。
本申请就是针对目前的建筑底部隔震层增设技术提出的一种改进。
发明内容
本发明主要解决的技术问题是提供一种既有砖混结构隔震支座托换加固结构及其施工方法,结构稳定,安全性高,有较好的抗震性能,另外安装施工比较方便,效率高。
为解决上述技术问题,本发明采用的一个技术方案是:提供一种既有砖混结构隔震支座托换加固结构,包括:形成在原基础上的增大基础、设置在增大基础上部的下支墩、设置在下支墩上部的隔震垫下预埋板、设置在隔震垫下预埋板上部的隔震垫、设置在隔震垫上部的隔震垫上预埋板、设置在隔震垫上预埋板上部的双托梁和设置在双托梁上部的隔震板,所述双托梁内部还设有销键,所述双托梁、销键和隔震板为一体式浇筑成型结构。
在本发明一个较佳实施例中,所述隔震垫下预埋板与下支墩之间通过浇筑下支墩的混凝土固结为一个整体。
在本发明一个较佳实施例中,所述隔震垫上预埋板与双托梁之间通过浇筑双托梁的混凝土固结为一个整体。
在本发明一个较佳实施例中,所述销键的断面高度为双托梁与隔震板总高度的一半,所述销键的底面与双托梁的底面齐平。
本发明还提供了上述既有砖混结构隔震支座托换加固结构的施工方法,包括以下具体步骤:
a、开挖砖混结构的基础并对基础进行加固改造,在原基础上形成增大基础,并对构造柱进行加腋处理,形成构造柱加腋部;
b、用千斤顶和钢管配合支撑,千斤顶上端支撑在地圈梁上,钢管的下端支撑在增大基础上;
c、拆除地圈梁以下构造柱;
d、在增大基础上部绑扎下支墩钢筋;
e、在下支墩钢筋上部放置隔震垫下预埋板;
f、浇筑下支墩,隔震垫下预埋板与下支墩固结为一体;
g、在隔震垫下预埋板上部安放隔震垫;
h、在隔震垫上部放置隔震垫上预埋板;
i、在隔震垫上预埋板上部绑扎双托梁钢筋;
g、一次性浇筑双托梁、销键和隔震板;
k、待全部混凝土强度达到设计强度后,拆除千斤顶支撑;
l、拆除地圈梁以下墙体。
在本发明一个较佳实施例中,施工过程中全程对砖混结构的变形和位移进行实时监控,保证施工安全。
本发明具有以下有益效果:
1、本发明的施工工序,自下而上顺序施工,隔震垫安装方便,提高整体施工效率;
2、隔震垫与混凝土支墩直接无缝连接,使得整体结构受力均匀,安全性高;
3、双托梁与隔震板一次浇筑成型,浇筑质量高,结构稳固,隔震板与双托梁互相连接,在建筑底部形成整体托盘,增加建筑的整体性,提高其抗震性能;
4、全程位移监测,保证结构安全。
附图说明
为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图,其中:
图1是本发明既有砖混结构隔震支座托换加固结构的施工示意图;
图2是图1的A-A向剖视图;
图3是本发明的施工流程图。
附图中各部件的标记如下:1、原基础,2、增大基础,3、下支墩,4、隔震垫下预埋板,5、隔震垫,6、隔震垫上预埋板,7、双托梁,8、隔震板,9、销键,10、构造柱,11、构造柱加腋部,12、千斤顶,13、钢管,14、地圈梁,15、加宽垫层。
具体实施方式
下面将对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。
请参阅图1至图3,本发明实施例包括:
一种既有砖混结构隔震支座托换加固结构,包括:形成在原基础1上的增大基础2,基础增大截面后承载力加大,基础整体性增强。
还包括设置在增大基础2上部的下支墩3、设置在下支墩3上部的隔震垫下预埋板4、设置在隔震垫下预埋板4上部的隔震垫5、设置在隔震垫5上部的隔震垫上预埋板6,隔震垫下预埋板4、隔震垫5和隔震垫上预埋板6之间能够很好的相连接,隔震垫是在加固完成后把上部结构的竖向力传递至基础的构件,有地震作用时可随地震力摆动,消耗地震能量,从而隔离地震力对上部结构的作用。
另外,所述隔震垫下预埋板与下支墩之间通过浇筑下支墩的混凝土固结为一个整体,连接紧密;所述隔震垫上预埋板与双托梁之间通过浇筑双托梁的混凝土固结为一个整体,连接紧密,从而保证隔震垫有最佳的受力工作状态,安全性高。
还包括设置在隔震垫上预埋板6上部的双托梁7和设置在双托梁7上部的隔震板8,所述双托梁内部还设有销键9,所述双托梁7、销键9和隔震板8为一体式浇筑成型结构,双托梁是把墙体线荷载转化成集中荷载传递至隔震垫的构件,隔震板与双托梁互相连接,在建筑底部形成整体托盘,增加建筑的整体性,提高其抗震性能。
优选的,所述销键9的断面高度为双托梁与隔震板总高度的一半,所述销键的底面与双托梁的底面齐平,所述销键的断面呈长方形,有助于整体加固结构的稳定性。
本发明还提供了上述既有砖混结构隔震支座托换加固结构的施工方法,包括以下具体步骤:
a、开挖砖混结构的基础并对基础进行加固改造,在原基础上形成增大基础,并对构造柱10进行加腋处理,形成构造柱加腋部11;
b、用千斤顶12和钢管13配合支撑,千斤顶上端支撑在地圈梁上,钢管的下端支撑在增大基础上;
c、拆除地圈梁以下构造柱;
d、在增大基础上部绑扎下支墩钢筋;
e、在下支墩钢筋上部放置隔震垫下预埋板;
f、浇筑下支墩,隔震垫下预埋板与下支墩固结为一体;
g、在隔震垫下预埋板上部安放隔震垫;
h、在隔震垫上部放置隔震垫上预埋板;
i、在隔震垫上预埋板上部绑扎双托梁钢筋;
g、一次性浇筑双托梁、销键和隔震板;
k、待全部混凝土强度达到设计强度后,拆除千斤顶支撑;
l、拆除地圈梁以下墙体。
上述施工过程中全程对砖混结构的变形和位移进行实时监控,保证砖混结构和施工人员的安全。
本发明具有以下有益效果:
1、本发明的施工工序,自下而上顺序施工,隔震垫安装方便,提高整体施工效率;
2、隔震垫与混凝土支墩直接无缝连接,使得整体结构受力均匀,安全性高;
3、双托梁与隔震板一次浇筑成型,浇筑质量高,结构稳固,隔震板与双托梁互相连接,在建筑底部形成整体托盘,增加建筑的整体性,提高其抗震性能;
4、全程位移监测,保证结构安全。
以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书内容所作的等效结构或等效流程变换,或直接或间接运用在其它相关的技术领域,均同理包括在本发明的专利保护范围内。
Claims (6)
1.一种既有砖混结构隔震支座托换加固结构,其特征在于,包括:形成在原基础上的增大基础、设置在增大基础上部的下支墩、设置在下支墩上部的隔震垫下预埋板、设置在隔震垫下预埋板上部的隔震垫、设置在隔震垫上部的隔震垫上预埋板、设置在隔震垫上预埋板上部的双托梁和设置在双托梁上部的隔震板,所述双托梁内部还设有销键,所述双托梁、销键和隔震板为一体式浇筑成型结构。
2.根据权利要求1所述的既有砖混结构隔震支座托换加固结构,其特征在于,所述隔震垫下预埋板与下支墩之间通过浇筑下支墩的混凝土固结为一个整体。
3.根据权利要求1所述的既有砖混结构隔震支座托换加固结构,其特征在于,所述隔震垫上预埋板与双托梁之间通过浇筑双托梁的混凝土固结为一个整体。
4.根据权利要求1所述的既有砖混结构隔震支座托换加固结构,其特征在于,所述销键的断面高度为双托梁与隔震板总高度的一半,所述销键的底面与双托梁的底面齐平。
5.一种如权利要求1~4任一项所述的既有砖混结构隔震支座托换加固结构的施工方法,其特征在于,包括以下具体步骤:
a、开挖砖混结构的基础并对基础进行加固改造,在原基础上形成增大基础,并对构造柱进行加腋处理,形成构造柱加腋部;
b、用千斤顶和钢管配合支撑,千斤顶上端支撑在地圈梁上,钢管的下端支撑在增大基础上;
c、拆除地圈梁以下构造柱;
d、在增大基础上部绑扎下支墩钢筋;
e、在下支墩钢筋上部放置隔震垫下预埋板;
f、浇筑下支墩,隔震垫下预埋板与下支墩固结为一体;
g、在隔震垫下预埋板上部安放隔震垫;
h、在隔震垫上部放置隔震垫上预埋板;
i、在隔震垫上预埋板上部绑扎双托梁钢筋;
g、一次性浇筑双托梁、销键和隔震板;
k、待全部混凝土强度达到设计强度后,拆除千斤顶支撑;
l、拆除地圈梁以下墙体。
6.根据权利要求5所述的既有砖混结构隔震支座托换加固结构的施工方法,其特征在于,施工过程中全程对砖混结构的变形和位移进行实时监控,保证施工安全。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610138037.XA CN105715068B (zh) | 2016-03-11 | 2016-03-11 | 既有砖混结构隔震支座托换加固结构及其施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610138037.XA CN105715068B (zh) | 2016-03-11 | 2016-03-11 | 既有砖混结构隔震支座托换加固结构及其施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105715068A true CN105715068A (zh) | 2016-06-29 |
CN105715068B CN105715068B (zh) | 2018-08-28 |
Family
ID=56157615
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610138037.XA Active CN105715068B (zh) | 2016-03-11 | 2016-03-11 | 既有砖混结构隔震支座托换加固结构及其施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105715068B (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106760851A (zh) * | 2016-12-30 | 2017-05-31 | 河北华研卓筑加固工程集团有限公司 | 既有砖混结构新增隔震层的施工方法 |
CN107724559A (zh) * | 2017-10-23 | 2018-02-23 | 南京百西思建筑科技有限公司 | 既有建筑隔震加固施工流程 |
CN107795144A (zh) * | 2017-10-23 | 2018-03-13 | 南京百西思建筑科技有限公司 | 既有建筑隔震加固的托换结构与托换施工方法 |
CN108518079A (zh) * | 2016-11-10 | 2018-09-11 | 叶香菲 | 大高度砖混房屋加固方法 |
CN109667295A (zh) * | 2018-11-23 | 2019-04-23 | 河海大学 | 一种既有建筑物基底下部暗挖拼装式托换结构及其施工方法 |
CN109914847A (zh) * | 2019-03-26 | 2019-06-21 | 西安理工大学 | 一种砖石古塔地基托换减震装置及其实施方法 |
CN110512665A (zh) * | 2019-07-18 | 2019-11-29 | 上海建工一建集团有限公司 | 既有下沉老建筑同步抬升及纠偏结构及其施工方法 |
CN110512666A (zh) * | 2019-07-18 | 2019-11-29 | 上海建工一建集团有限公司 | 既有下沉老建筑同步抬升及隔震结构及其施工方法 |
CN110805141A (zh) * | 2019-11-14 | 2020-02-18 | 山东建筑大学 | 一种建筑物顶升后钢管柱与隔震支座的连接装置及方法 |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111441400B (zh) * | 2020-04-08 | 2021-05-28 | 四川省建筑科学研究院有限公司 | 一种既有建筑基础隔震加固方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001311314A (ja) * | 2000-04-27 | 2001-11-09 | Kajima Corp | 既存建物の免震構造化方法 |
CN102605965A (zh) * | 2011-12-31 | 2012-07-25 | 北京筑福建设工程有限责任公司 | 砖混结构隔震支座的安装托换方法 |
CN104018434A (zh) * | 2014-06-20 | 2014-09-03 | 丰泽工程橡胶科技开发股份有限公司 | 建筑隔震橡胶支座的更换方法 |
-
2016
- 2016-03-11 CN CN201610138037.XA patent/CN105715068B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001311314A (ja) * | 2000-04-27 | 2001-11-09 | Kajima Corp | 既存建物の免震構造化方法 |
CN102605965A (zh) * | 2011-12-31 | 2012-07-25 | 北京筑福建设工程有限责任公司 | 砖混结构隔震支座的安装托换方法 |
CN104018434A (zh) * | 2014-06-20 | 2014-09-03 | 丰泽工程橡胶科技开发股份有限公司 | 建筑隔震橡胶支座的更换方法 |
Non-Patent Citations (2)
Title |
---|
陈文海等: ""既有砖混结构校舍隔震加固技术及其工程应用"", 《建筑技术》 * |
陈淑娟等: ""某中学砖混结构教学楼隔震加固设计与施工"", 《工程抗震与加固改造》 * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108518079A (zh) * | 2016-11-10 | 2018-09-11 | 叶香菲 | 大高度砖混房屋加固方法 |
CN106760851A (zh) * | 2016-12-30 | 2017-05-31 | 河北华研卓筑加固工程集团有限公司 | 既有砖混结构新增隔震层的施工方法 |
CN107724559A (zh) * | 2017-10-23 | 2018-02-23 | 南京百西思建筑科技有限公司 | 既有建筑隔震加固施工流程 |
CN107795144A (zh) * | 2017-10-23 | 2018-03-13 | 南京百西思建筑科技有限公司 | 既有建筑隔震加固的托换结构与托换施工方法 |
CN107724559B (zh) * | 2017-10-23 | 2019-07-05 | 南京百西思建筑科技有限公司 | 既有建筑隔震加固施工流程 |
CN109667295A (zh) * | 2018-11-23 | 2019-04-23 | 河海大学 | 一种既有建筑物基底下部暗挖拼装式托换结构及其施工方法 |
CN109667295B (zh) * | 2018-11-23 | 2020-11-10 | 河海大学 | 一种既有建筑物基底下部暗挖拼装式托换结构及其施工方法 |
CN109914847A (zh) * | 2019-03-26 | 2019-06-21 | 西安理工大学 | 一种砖石古塔地基托换减震装置及其实施方法 |
CN110512665A (zh) * | 2019-07-18 | 2019-11-29 | 上海建工一建集团有限公司 | 既有下沉老建筑同步抬升及纠偏结构及其施工方法 |
CN110512666A (zh) * | 2019-07-18 | 2019-11-29 | 上海建工一建集团有限公司 | 既有下沉老建筑同步抬升及隔震结构及其施工方法 |
CN110805141A (zh) * | 2019-11-14 | 2020-02-18 | 山东建筑大学 | 一种建筑物顶升后钢管柱与隔震支座的连接装置及方法 |
CN110805141B (zh) * | 2019-11-14 | 2021-08-24 | 山东建筑大学 | 一种建筑物顶升后钢管柱与隔震支座的连接装置及方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105715068B (zh) | 2018-08-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105715068A (zh) | 既有砖混结构隔震支座托换加固结构及其施工方法 | |
CN104746422B (zh) | 一种桥梁预制空心墩柱后浇连接结构及施工方法 | |
CN102677784B (zh) | 一种预制混凝土管柱钢筋混凝土梁节点结构及其施工方法 | |
CN103935911B (zh) | 塔吊附墙支撑结构及其施工方法 | |
CN103669866B (zh) | 地下室钢筋混凝土柱节点连接结构的施工方法 | |
CN108005401A (zh) | 一种既有框架结构隔震加固的柱的托换方法 | |
CN105040594A (zh) | 一种变截面箱梁桥合龙段施工方法 | |
KR20200032316A (ko) | 트러스형 지지체를 이용한 탑다운 방식의 지하 구조물 형성 방법 | |
CN111335611B (zh) | 一种大跨度悬挑构件施工系统及其施工方法 | |
CN110374349A (zh) | 一种受损钢筋混凝土柱体的托换处理装置及其使用方法 | |
KR102286225B1 (ko) | 무지주 탑다운 지하구조물 pc복합화 시공공법 | |
CN107100322B (zh) | 后张法竖向预应力现浇混凝土柱结构及施工方法 | |
CN103758347B (zh) | 大跨度钢筋混凝土梁板结构后浇带支撑托换施工方法 | |
CN206769199U (zh) | 后穿式后张法竖向预应力现浇混凝土柱结构 | |
CN102936953B (zh) | “大”字型劲钢结构模板施工方法 | |
KR101072958B1 (ko) | 마이크로파일 및 트러스를 이용한 기초구조, 및 주위구조물과 인접한 곳에서 이의 시공방법 | |
KR20060096706A (ko) | 데크 현수식 지하 구조물 역타설공법 | |
CN109184741B (zh) | 一种高承载力盾构隧道管片接头结构 | |
CN109610338B (zh) | 一种悬索桥塔柱底口防漏浆施工方法 | |
CN109267578B (zh) | 一种斜面素混凝土结构及其施工方法 | |
CN108277817B (zh) | 高桩承台塔吊基础加固结构的施工方法 | |
KR100390369B1 (ko) | 개착(開鑿)식으로 시공되는 지하철 및 공동구의 아치형 구조 시공 방법 | |
CN203603176U (zh) | 一种古建筑基础整体托盘隔震加固结构 | |
CN210622366U (zh) | 一种受损钢筋混凝土柱体的托换处理装置 | |
KR100500143B1 (ko) | 통수단면 확보를 위한 교각의 중공 단면확대 시공방법 및그 구조 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 213015 Jiangsu province Changzhou City Zhonglou District Mushu Road No. 10 Co-patentee after: CHANGZHOU ARCHITECTUAL RESEARCH INSTITUTE GROUP Co.,Ltd. Patentee after: JIANGSU DINGDA HIGH-TECH CONSTRUCTION Co.,Ltd. Address before: 213015 Jiangsu province Changzhou City Zhonglou District Mushu Road No. 10 Co-patentee before: CHANGZHOU ARCHITECTURAL RESEARCH INSTITUTE Co.,Ltd. Patentee before: JIANGSU DINGDA HIGH-TECH CONSTRUCTION Co.,Ltd. |
|
CP01 | Change in the name or title of a patent holder |