CN105696801B - Prefabricated part hanging accurate positioning device - Google Patents

Prefabricated part hanging accurate positioning device Download PDF

Info

Publication number
CN105696801B
CN105696801B CN201610071824.7A CN201610071824A CN105696801B CN 105696801 B CN105696801 B CN 105696801B CN 201610071824 A CN201610071824 A CN 201610071824A CN 105696801 B CN105696801 B CN 105696801B
Authority
CN
China
Prior art keywords
positioning
floor
hole
shaped riser
prefabricated panel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610071824.7A
Other languages
Chinese (zh)
Other versions
CN105696801A (en
Inventor
范玉
范佳琦
黄继战
董素玲
王凤清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Institute of Architectural Technology
Original Assignee
Jiangsu Institute of Architectural Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Institute of Architectural Technology filed Critical Jiangsu Institute of Architectural Technology
Priority to CN201610071824.7A priority Critical patent/CN105696801B/en
Publication of CN105696801A publication Critical patent/CN105696801A/en
Application granted granted Critical
Publication of CN105696801B publication Critical patent/CN105696801B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements

Abstract

The present invention announces a kind of prefabricated part hanging accurate positioning device for being mainly used in prefabricated panel installation, belongs to technical field of building construction.Including the U-shaped riser being placed on lower floor's floor, there is oblique angle on the inner edge of U-shaped riser upper end;U-shaped riser is provided with the alignment pin for being used for being fixed on U-shaped riser on lower floor's floor, and U-shaped riser bottom is fixed with horizontal positioning plate;The positioning hole I coordinated with the embedded bar of lower floor floor is provided with positioning plate;Prefabricated part hanging accurate positioning device also includes being located on positioning plate and being enclosed on the spacing positioning sleeve on embedded bar;In use, embedded bar is inserted into branch sleeve pre-buried in prefabricated panel, spacing positioning sleeve is against branch sleeve lower surface.Simple in construction, accurate positioning of the invention, it is easy for installation, the installation effectiveness of prefabricated panel is substantially increased, new slip casting structure also ensures the bonding strength between prefabricated panel and lower floor's floor after construction, reliable construction quality.

Description

Prefabricated part hanging accurate positioning device
Technical field
The present invention relates to technical field of building construction, specifically a kind of prefabricated components for being mainly used in prefabricated panel installation are hung Fill accurate positioning device.
Background technology
Fabricated construction prefabricated reinforced concrete wall panel is in hoisting process, and prefabricated reinforced concrete wall panel is by under in place Lower floor's embedded bar on layer concrete floor is inserted into the branch sleeve being reserved in prefabricated reinforced concrete wall panel, then By being in the milk, branch sleeve is attached.In actually lifting operating process, because branch sleeve is located at prefabricated reinforced concrete Recess in wallboard bottom, it is impossible to observe directly the relative position relation of reinforced bar sleeve and lower floor's embedded bar, operating personnel need Bend to go for the relative position of lower floor's embedded bar and reinforcing steel bar connecting sleeve tube, then could complete lifting operation, therefore cause Prefabricated reinforced concrete wall panel lifts process slow shortcoming in place.
The content of the invention
In order to solve the above technical problems, the present invention provides a kind of prefabricated part hanging accurate positioning device.
The present invention is achieved through the following technical solutions:A kind of prefabricated part hanging accurate positioning device, including be placed on down There is oblique angle on U-shaped riser on floor plate, the inner edge of U-shaped riser upper end;Described U-shaped riser, which is provided with, to be used to stand U-shaped Plate is fixed on the alignment pin on lower floor's floor, and U-shaped riser bottom is fixed with horizontal positioning plate;Opened on described positioning plate There is the positioning hole I that the embedded bar with lower floor floor coordinates;Described prefabricated part hanging accurate positioning device also includes being located at On positioning plate and it is enclosed on the spacing positioning sleeve on embedded bar;In use, described embedded bar is inserted into prefabricated panel In pre-buried branch sleeve, described spacing positioning sleeve is against branch sleeve lower surface.
It is further:Described prefabricated panel upper end is provided with the through hole of connection branch sleeve;Described prefabricated panel leads to Hole inwall is provided with vertical slip casting groove, prefabricated panel through hole and is provided with connection reinforcing bar.
Described slip casting groove has four, is in crossing distribution along through-hole wall.
Vertical installation through-hole is provided with described U-shaped riser;Described positioning plate is elongated plates, positioning plate with One end of U-shaped riser connection is provided with positioning hole II;Described alignment pin is inserted into U-shaped riser installation through-hole and positioning plate positioning Hole II is interior and is fixed on lower floor's floor.
During construction, first placement positioning bottom plate, the positioning hole I of positioning plate one end passes through the embedded bar of lower floor's floor;
Spacing positioning sleeve is enclosed on embedded bar;
Place U-shaped riser, by alignment pin, U-shaped riser installation through-hole, positioning plate positioning hole II by U-shaped riser, positioning Bottom plate is fixedly connected with lower floor floor;
Prefabricated part hanging accurate positioning device is arranged symmetrically two, respectively positioned at the two ends of prefabricated panel;
Hoisting prefabricated wallboard, by the oblique angle of U-shaped riser upper end, correct position is slipped into by prefabricated panel;
From in prefabricated panel through hole slip casting groove carry out slip casting, the concrete poured full of branch sleeve, spacing positioning sleeve with And the gap between lower floor's floor and prefabricated panel.
Simple in construction, accurate positioning of the invention, it is easy for installation, the installation effectiveness of prefabricated panel is substantially increased, it is new Slip casting structure also ensures the bonding strength between prefabricated panel and lower floor's floor after construction, reliable construction quality.
Brief description of the drawings
Fig. 1 is inventive structure schematic diagram;
Fig. 2 is top view in Fig. 1;
Fig. 3 is a construction mounting structure schematic diagram of the invention.
In figure:1st, lower floor's floor;2nd, U-shaped riser;3rd, alignment pin;4th, prefabricated panel;4-1, slip casting groove;5th, reinforcing bar is connected; 6th, branch sleeve;7th, positioning plate;8th, spacing positioning sleeve;9th, embedded bar.
Embodiment
The following is the specific embodiment of the present invention, in conjunction with accompanying drawing, the invention will be further described.
As shown in Figure 1 to Figure 3, a kind of prefabricated part hanging accurate positioning device, including the U being placed on lower floor's floor 1 Shape riser 2, U-shaped riser 2 is formed by connecting by three straight panels, has oblique angle on the inner edge of its upper end.The bottom of U-shaped riser 2 is fixed There is horizontal positioning plate 7, positioning plate 7 is attached on lower floor's floor 1, its quantity and the quantity of embedded bar 9 on lower floor's floor 1 Unanimously.Positioning plate 7 is elongated plates, and the one end of positioning plate 7 is provided with the positioning hole coordinated with the embedded bar 9 of lower floor floor 1 I, the other end is provided with positioning hole II.Spacing positioning sleeve 8 is enclosed on embedded bar 9 and is attached to the upper surface of positioning plate 7.U-shaped riser 2 On be provided with vertical installation through-hole, alignment pin 3 is inserted into the installation through-hole of U-shaped riser 2 and the positioning hole II of positioning plate 7 and solid It is scheduled on lower floor's floor 1.The upper end of prefabricated panel 4 is provided with the through hole of connection branch sleeve 6;The through-hole wall of prefabricated panel 4 is provided with perpendicular To slip casting groove 4-1, connection reinforcing bar 5 is installed in the through hole of prefabricated panel 4.Slip casting groove has four, is in cross along through-hole wall Shape is distributed.
During construction, first placement positioning bottom plate, the positioning hole I of positioning plate one end passes through the embedded bar of lower floor's floor;
Spacing positioning sleeve is enclosed on embedded bar;
Place U-shaped riser, by alignment pin, U-shaped riser installation through-hole, positioning plate positioning hole II by U-shaped riser, positioning Bottom plate is fixedly connected with lower floor floor;
Prefabricated part hanging accurate positioning device is arranged symmetrically two, respectively positioned at the two ends of prefabricated panel;
Hoisting prefabricated wallboard, by the oblique angle of U-shaped riser upper end, correct position is slipped into by prefabricated panel;Spacing positioning sleeve 8 So that leaving certain interval between lower floor's floor and prefabricated panel;
From in prefabricated panel through hole slip casting groove carry out slip casting, the concrete poured full of branch sleeve, spacing positioning sleeve with And the gap between lower floor's floor and prefabricated panel.

Claims (1)

1. a kind of prefabricated panel localization method of use prefabricated part hanging accurate positioning device,
It is characterized in that:
Described prefabricated part hanging accurate positioning device includes being placed on lower floor's floor(1)On U-shaped riser(2), U-shaped riser (2)There is oblique angle on the inner edge of upper end;Described U-shaped riser(2)Being provided with is used for U-shaped riser(2)It is fixed on lower floor's floor (1)On alignment pin(3), U-shaped riser(2)Bottom is fixed with horizontal positioning plate(7);Described positioning plate(7)On open Have and lower floor's floor(1)Embedded bar(9)The positioning hole I of cooperation;Described prefabricated part hanging accurate positioning device is also wrapped Include positioned at positioning plate(7)Go up and be enclosed on embedded bar(9)On spacing positioning sleeve(8);In use, described embedded bar (9)It is inserted into prefabricated panel(4)Interior pre-buried branch sleeve(6)Interior, described spacing positioning sleeve(8)It is against branch sleeve(6) Lower surface;
Described U-shaped riser(2)On be provided with vertical installation through-hole;Described positioning plate(7)It is elongated plates, positioning plate (7)With U-shaped riser(2)One end of connection is provided with positioning hole II;Described alignment pin(3)It is inserted into U-shaped riser(2)Installation through-hole And positioning plate(7)Positioning hole II is interior and is fixed on lower floor's floor(1)On;
Described prefabricated panel(4)Upper end is provided with connection branch sleeve(6)Through hole;Described prefabricated panel(4)Through-hole wall It is provided with vertical slip casting groove(4-1), prefabricated panel(4)Connection reinforcing bar is installed in through hole(5);
Described prefabricated panel localization method comprises the following steps:
1. first placement positioning bottom plate(7), positioning plate(7)The positioning hole I of one end passes through lower floor's floor(1)Embedded bar(9);
2. by spacing positioning sleeve(8)It is enclosed on embedded bar(9)On;
3. U-shaped riser is placed(2), pass through alignment pin(3), U-shaped riser(2)Installation through-hole, positioning plate(7)Positioning hole II is by U Shape riser(2), positioning plate(7)With lower floor's floor(1)It is fixedly connected;
4. prefabricated part hanging accurate positioning device is arranged symmetrically two, respectively positioned at prefabricated panel(4)Two ends;
5. hoisting prefabricated wallboard(4), pass through U-shaped riser(2)The oblique angle of upper end, by prefabricated panel(4)Slip into correct position;It is spacing Positioning sleeve(8)So that lower floor's floor(1)And prefabricated panel(4)Between leave certain interval;
6. from prefabricated panel(4)Slip casting groove carries out slip casting in through hole, and the concrete poured is full of branch sleeve(6), spacing positioning Set(8)And lower floor's floor(1)And prefabricated panel(4)Between gap.
CN201610071824.7A 2016-02-02 2016-02-02 Prefabricated part hanging accurate positioning device Active CN105696801B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610071824.7A CN105696801B (en) 2016-02-02 2016-02-02 Prefabricated part hanging accurate positioning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610071824.7A CN105696801B (en) 2016-02-02 2016-02-02 Prefabricated part hanging accurate positioning device

Publications (2)

Publication Number Publication Date
CN105696801A CN105696801A (en) 2016-06-22
CN105696801B true CN105696801B (en) 2017-10-13

Family

ID=56230078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610071824.7A Active CN105696801B (en) 2016-02-02 2016-02-02 Prefabricated part hanging accurate positioning device

Country Status (1)

Country Link
CN (1) CN105696801B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109113349A (en) * 2017-06-24 2019-01-01 李聪 A kind of positioning device and its localization method of precast floor slab
CN107476586B (en) * 2017-08-09 2020-04-10 东莞市建安住宅工业有限公司 Installation device and method for house PC prefabricated part
CN107620477B (en) * 2017-10-20 2022-12-06 浙江萧云建设有限公司 Mounting and positioning device and method for prefabricated wall panel
CN110387821A (en) * 2018-04-23 2019-10-29 东宏建设股份有限公司 Bridge beam slab lifts spacer bar accurate placement technology
CN108643347B (en) * 2018-04-27 2020-11-24 长江大学 Steel reinforced concrete frame-reinforced concrete wallboard mixed structure system
CN109296061A (en) * 2018-11-30 2019-02-01 中国冶集团有限公司 The simple aligning device of vestibule supporting leg and installation method
CN109914823B (en) * 2019-04-15 2021-03-02 锦汇建设集团有限公司 Method for installing prefabricated wall board of prefabricated building
CN109914822B (en) * 2019-04-15 2021-01-15 南通建诚混凝土有限公司 Sliding chute structure of device is built towards assembled building wallboard
CN110541495B (en) * 2019-08-19 2020-09-18 惠州市鸿泰建筑工程有限公司 Prefabricated wall body of prefabricated building
CN112411741B (en) * 2020-11-28 2022-03-08 中实翊(福建)建设工程有限公司 Fabricated building structure and construction method
CN112814146A (en) * 2020-12-31 2021-05-18 湖北创威建筑装饰工程有限公司 BIM technology-based wall green construction method
CN113802861B (en) * 2021-10-29 2022-11-25 广州城市职业学院 Steel structure assembly type wallboard movable suspension hoisting construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4787619B2 (en) * 2006-01-13 2011-10-05 カヤバ システム マシナリー株式会社 Built-in adjustment device
CN102392540B (en) * 2011-10-24 2013-10-16 上海城建市政工程(集团)有限公司 High-precision method and structure for positioning high-precision precast beam
CN105040989B (en) * 2015-06-26 2017-06-09 南京长江都市建筑设计股份有限公司 Anchor and its construction method for anchoring prefabricated superimposed sheet and prefabricated components
CN204826680U (en) * 2015-07-28 2015-12-02 湖南省三新建筑工业股份有限公司 Prefabricated component spacing guider of installation and prefabricated component mounting structure
CN204983701U (en) * 2015-08-07 2016-01-20 中国建筑第八工程局有限公司 A guiding device for prefabricating wall body is assembled

Also Published As

Publication number Publication date
CN105696801A (en) 2016-06-22

Similar Documents

Publication Publication Date Title
CN105696801B (en) Prefabricated part hanging accurate positioning device
CN207177102U (en) Prefabricated conversion layer reserves sleeve joint bar accurate-location device
CN206233596U (en) Building block exterior wall constructional column concrete casting device
CN105507470B (en) A kind of periphery overlapping overall assembled floor and its construction method
CN206625428U (en) Floor closed system is poured after a kind of pipe well
CN102733608B (en) Construction method for spray head layer of granulation tower
CN206127746U (en) Isolation bearing handles accurate location structure of pre -buried steel sheet in back
CN204983593U (en) Modular elevartor shaft construction operation platform
CN105347142B (en) A kind of building hoist is mounted on the threading installation method on basement roof
CN105332511B (en) A kind of huge steel core concrete column filling core, which pours, smashes device and method
CN207499451U (en) Outer wall of basement single-face support mold apparatus
CN107419667B (en) A kind of self-anchored suspension bridge installing Cable-clamp method
CN205617732U (en) Job site pipeline formula floor rubbish clearance system
CN209129163U (en) A kind of steel board easy for construction and vertically pull muscle bridging arrangement
CN106284978A (en) A kind of movement joint both sides shear wall synchronous construction technique and canalization template
CN202401026U (en) Construction equipment for installing flue elbow pipe through pulley lifting
CN207376661U (en) A kind of plugging structure of poured band of outer wall of basement
CN207295768U (en) Device for piping lane top plate of constructing
CN104404923A (en) Arch dam bracket template device and construction method based on arch dam bracket template device
CN206245557U (en) prefabricated reinforced concrete floor
CN106013568B (en) Based on detachable positioning controller cast-in-situ floorslab structure and construction method
CN209620636U (en) Prefabricated assembled concrete structure outer hanging plate elevation of bottom regulating device
CN210597742U (en) Shear wall
CN209277547U (en) It is a kind of that having enough to meet the need for hole to be provided closure is assisted to hang hole mold
CN210263910U (en) Cast-in-place slab of superimposed sheet takes die block board

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20181206

Address after: 233010 Pioneering Building 316, Huineng Small and Micro Enterprises Pioneering Center, 1750 Shengli West Road, Yuhui District, Bengbu City, Anhui Province

Patentee after: Bengbu Dingrong Science and Technology Information Consulting Co., Ltd.

Address before: No. 26, Xue Yuan Road, Quanshan District, Xuzhou, Jiangsu

Patentee before: Jiangsu Institute of Architectural Technology

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20181229

Address after: No. 26, Xue Yuan Road, Quanshan District, Xuzhou, Jiangsu

Patentee after: Jiangsu Institute of Architectural Technology

Address before: 233010 Pioneering Building 316, Huineng Small and Micro Enterprises Pioneering Center, 1750 Shengli West Road, Yuhui District, Bengbu City, Anhui Province

Patentee before: Bengbu Dingrong Science and Technology Information Consulting Co., Ltd.