CN105696543A - Dam front drainage method for sub-dam building in red mud stacking area - Google Patents
Dam front drainage method for sub-dam building in red mud stacking area Download PDFInfo
- Publication number
- CN105696543A CN105696543A CN201410684171.0A CN201410684171A CN105696543A CN 105696543 A CN105696543 A CN 105696543A CN 201410684171 A CN201410684171 A CN 201410684171A CN 105696543 A CN105696543 A CN 105696543A
- Authority
- CN
- China
- Prior art keywords
- dam
- sub
- red mud
- soakaway trench
- row
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
The invention discloses a dam front drainage method for sub-dam building in red mud stacking area. The method includes the following steps: a composite soil engineering drainage network is arranged on an inner slope surface of a sub-dam; a gravel drainage layer is arranged on a dam toe of an inner slope; the bottom base of the gravel drainage layer is reinforced through soil and stone materials; area internal drainage pipes are arranged on the inner bottom of the gravel drainage layer; red mud seepage water in the front of a dam enters the area internal drainage pipes via the composite soil engineering drainage network and the gravel drainage layer; the seepage water flows to a drainage ditch on a dam toe of an outer slope of the sub-dam through the area internal drainage pipes, the seepage water flows to stacking area drainage pipes through the drainage ditch, and the seepage water is finally drained to a downstream return pipe along an outer slope surface of a primary dam through the stacking area drainage pipes. According to the method, the red mud seepage water in a front zone of the sub-dam can be drained out as soon as possible, the drying speed of red mud in the front zone of the dam can be increased, and the safety of the dam can be ensured.
Description
Technical field
The present invention relates to a kind of method that when red mud dump constructs sub-dam, front row, dam is oozed, belong to front row, red mud dump dam and ooze technical field。
Background technology
Red mud is to extract the solid residue after aluminium oxide from bauxite with alkali, is be likely to one of principal element to environment in aluminum oxide production process。Due to the difference of the grade of ore and production method, produce the red mud amount of 1t aluminium oxide generation at about 0.8~1.5t。
Red mud Main Components is Si0
2
、CaO、Fe
2
0
3
、A1
2
0
3
、Na
2
0、TiO
2
、K
2
O etc.。Red mud Main Ingredients and Appearance does not belong to the material that environment has harm especially, and the hazard factor of environment is mainly it containing Na by red mud
2
The attached liquid of 0。Attached liquid is containing alkali 2~3g/L, and pH value is up to 13~14。Wastewater from red mud Main Ingredients and Appearance is K
+
、Na
+
、Ca
2+
、Mg
2+
、A1
3+
、OH
-
、F
-
、C1
-
、S0
4
2-
Deng, red mud to the pollution of environment based on alkali pollution。
When red mud can't utilize in a large number and must store up, red mud dump need to be built and make red mud concentrate stacking。Red mud generally has wet method to store up, semidry method is stored up, dry method stores up three kinds of techniques in process both at home and abroad。Blowing before stockyard periphery or dam is generally adopted, owing to tapping point and blowing amount are uneven, it is easy to causing hydrops before dam, before dam, the red mud drying time is long, is unfavorable for safety of dam body, it is also difficult to ensure the requirement of dry beach, stockyard length when red mud wet method is stored up, semidry method is stored up。
Summary of the invention
It is an object of the invention to, it is provided that a kind of method that when red mud dump constructs sub-dam, front row, dam is oozed, can discharge smoothly by hydrops before dam, shorten the red mud drying time, extend dry beach, stockyard length, to guarantee safety of dam body。
Technical scheme:
A kind of method that when red mud dump constructs sub-dam, front row, dam is oozed, the method is to construct Zi Ba at the initial dam top stacking red mud, and bottom sub-dam, wide top is narrow, and before constructing sub-dam, the row first carried out bottom sub-dam is oozed, and row oozes construction according to the following steps:
Step one, before sub-dam is constructed in dam crest portion in the early stage, first some building stones of throwing in the red mud of position at the bottom of domatic dam, Zi Ba upstream, then with vibrating roller by building stones compaction by rolling to >=0.93, arrange the basis bottom infiltration layer as sandstone;
Step 2, in one layer of upper berth, basis geotextiles, in geotextiles, then put soakaway trench, soakaway trench arrival end one layer of geotextiles of parcel, the soakaway trench port of export is connected with the gutter of initial dam end face, and soakaway trench is placed with a soakaway trench along sub-dam length direction at interval of 30-50 rice;
Step 3, lays sandstone row's infiltration layer on soakaway trench, is pressed on the limit of composite earthwork drainage network bottom sandstone row's infiltration layer when laying sandstone row's infiltration layer, arranges infiltration layer top at sandstone and repave one layer of geotextiles;
Step 4, construct Zi Ba between the geotextiles at dam and sandstone row infiltration layer top in the early stage, when group height of dam degree reaches 90%, composite earthwork drainage network is layered on Zi Ba upstream domatic, another limit of composite earthwork drainage network is embedded in sub-dam, then sub-dam is filled to design height;
Step 5, digs a gutter at sub-Ba Bajiaochu along dam body length direction, and bottom of trench is provided with drain pipe, and drain pipe backwater ditch with initial dam base of dam domatic along initial dam downstream is connected。
In preceding method, described basis, slightly above initial dam end face, makes the soakaway trench being laid between basis and initial dam end face low inside and high outside to guarantee that in storehouse, infiltration can be discharged in time。
In preceding method, described soakaway trench is positioned at the tube wall of field part and is provided with water seepage hole, and soakaway trench is wrapped with geotextiles。
Compared with prior art, the backwater ditch that the hydrops in red mud dump is drained into initial dam base of dam by soakaway trench by the present invention makes the red mud infiltration of Zi Ba dam forefoot area to discharge as early as possible, and then accelerates the rate of drying of dam forefoot area red mud, is conducive to safety of dam body。
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention。
Being labeled as in figure: 1-dam, 2-composite earthwork drainage network, 3-sandstone row's infiltration layer, 4-basis, 5-soakaway trench, 6-gutter, 7-drain pipe, 8-backwater ditch, 9-geotextiles, 10-red mud, 11-initial dam。
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is described in further detail, but not as any limitation of the invention。
Embodiment
A kind of method that when red mud dump constructs sub-dam, front row, dam is oozed, the method is to construct sub-dam 1 at initial dam 11 top stacking red mud 10, and bottom sub-dam 1, wide top is narrow, and before constructing sub-dam 1, the row first carried out bottom sub-dam 1 is oozed, and row oozes construction according to the following steps:
Step one, before sub-dam 1 is constructed at top, dam 11 in the early stage, first some building stones of throwing in the red mud 10 of position at the bottom of domatic dam, upstream, sub-dam 1, again with vibrating roller by building stones compaction by rolling to >=0.93(namely with vibrating roller by building stones compaction by rolling to compactness >=0.93), arrange the basis 4 bottom infiltration layer 3 as sandstone;
Step 2, in the one layer of geotextiles 9 in basic 4 upper berth, in geotextiles 9, then put soakaway trench 5, soakaway trench 5 arrival end one layer of geotextiles 9 of parcel, soakaway trench 5 port of export is connected with the gutter 6 of initial dam 11 end face, and soakaway trench 5 is placed with a soakaway trench 5 along sub-dam 1 length direction at interval of 30-50 rice;
Step 3, lays sandstone row's infiltration layer 3 on soakaway trench 5, is pressed on the limit of composite earthwork drainage network 2 bottom sandstone row's infiltration layer 3 when laying sandstone row's infiltration layer 3, arranges infiltration layer 3 top at sandstone and repave one layer of geotextiles 9;
Step 4, construct sub-dam 1 between the geotextiles 9 at dam 11 and sandstone row infiltration layer 3 top in the early stage, when group dam 1 highly reaches 90%, composite earthwork drainage network 2 is layered on upstream, sub-dam 1 domatic, another limit of composite earthwork drainage network 2 is embedded in sub-dam 1, then sub-dam 1 is built to design height;
Step 5, the end face on dam 11 digs a gutter along dam body length direction in the early stage, and bottom of trench is provided with drain pipe 7, and along initial dam 11 downstream, the domatic backwater ditch 8 with initial dam 11 base of dam is connected drain pipe 7。
When being embodied as, basis 4, slightly above initial dam 11 end face, makes the soakaway trench 5 being laid between basis 4 and initial dam 11 end face low inside and high outside to guarantee that in storehouse, infiltration can be discharged in time。Soakaway trench 5 is positioned at the tube wall of field part and is provided with water seepage hole, and soakaway trench 5 is wrapped with geotextiles。
Claims (3)
1. the method that when a red mud dump constructs sub-dam, front row, dam is oozed, it is characterized in that: the method is to construct Zi Ba at the initial dam top stacking red mud, bottom sub-dam, wide top is narrow, and before constructing sub-dam, the row first carried out bottom sub-dam is oozed, and row oozes construction according to the following steps:
Step one, before sub-dam is constructed in dam crest portion in the early stage, first some building stones of throwing in the red mud of position at the bottom of domatic dam, Zi Ba upstream, then with vibrating roller by building stones compaction by rolling to >=0.93, arrange the basis bottom infiltration layer as sandstone;
Step 2, in one layer of upper berth, basis geotextiles, in geotextiles, then put soakaway trench, soakaway trench arrival end one layer of geotextiles of parcel, the soakaway trench port of export is connected with the gutter of initial dam end face, and soakaway trench is placed with a soakaway trench along sub-dam length direction at interval of 30-50 rice;
Step 3, lays sandstone row's infiltration layer on soakaway trench, is pressed on the limit of composite earthwork drainage network bottom sandstone row's infiltration layer when laying sandstone row's infiltration layer, arranges infiltration layer top at sandstone and repave one layer of geotextiles;
Step 4, construct Zi Ba between the geotextiles at dam and sandstone row infiltration layer top in the early stage, when group height of dam degree reaches 90%, composite earthwork drainage network is layered on Zi Ba upstream domatic, another limit of composite earthwork drainage network is embedded in sub-dam, then sub-dam is filled to design height;
Step 5, digs a gutter at sub-Ba Bajiaochu along dam body length direction, and bottom of trench is provided with drain pipe, and drain pipe backwater ditch with initial dam base of dam domatic along initial dam downstream is connected。
2. the method that when red mud dump constructs sub-dam according to claim 1, front row, dam is oozed, it is characterised in that: described basis, slightly above initial dam end face, makes the soakaway trench being laid between basis and initial dam end face low inside and high outside to guarantee that in storehouse, infiltration can be discharged in time。
3. the method that when red mud dump constructs sub-dam according to claim 2, front row, dam is oozed, it is characterised in that: described soakaway trench is positioned at the tube wall of field part and is provided with water seepage hole, and soakaway trench is wrapped with geotextiles。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410684171.0A CN105696543B (en) | 2014-11-25 | 2014-11-25 | A kind of method that dam front row is seeped when red mud dump constructs sub- dam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410684171.0A CN105696543B (en) | 2014-11-25 | 2014-11-25 | A kind of method that dam front row is seeped when red mud dump constructs sub- dam |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105696543A true CN105696543A (en) | 2016-06-22 |
CN105696543B CN105696543B (en) | 2019-12-03 |
Family
ID=56941402
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410684171.0A Active CN105696543B (en) | 2014-11-25 | 2014-11-25 | A kind of method that dam front row is seeped when red mud dump constructs sub- dam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105696543B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106087953A (en) * | 2016-06-29 | 2016-11-09 | 上海朗兆公路铁路养护工程技术有限公司 | A kind of drainage and construction method preventing and treating large-scale spoil ground, mountain area mud-rock flow |
CN106759388A (en) * | 2017-02-14 | 2017-05-31 | 贵阳铝镁设计研究院有限公司 | A kind of slurry dry method red mud storage yard constructs the method and its structure of fill dam |
CN111593742A (en) * | 2020-05-27 | 2020-08-28 | 四川会东大梁矿业有限公司 | Construction method for rectifying and improving tailing pond based on rubble silt squeezing method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1837108A (en) * | 2005-03-23 | 2006-09-27 | 贵阳铝镁设计研究院 | Process for dry treatment of red mud and clinker in alumina plant |
CN1843923A (en) * | 2006-04-03 | 2006-10-11 | 贵阳铝镁设计研究院 | House-sealing method for dry-process piling yard of red mud |
CN201560429U (en) * | 2009-12-16 | 2010-08-25 | 贵阳铝镁设计研究院 | Heap dam structure using red mud generated by alumina produced by gibbsite as material |
CN201695404U (en) * | 2010-06-23 | 2011-01-05 | 贵阳铝镁设计研究院 | Dry-method capacity increasing structure of valley-type wet-method red mud disposal site |
CN103572747A (en) * | 2013-11-15 | 2014-02-12 | 付文堂 | Method for burying drainage-seepage body of reverse filtering pipe in tailing dam |
KR101459703B1 (en) * | 2014-01-29 | 2014-11-12 | 주식회사 항도엔지니어링 | Method for draining and reinfrocing dredged reclaimed land |
-
2014
- 2014-11-25 CN CN201410684171.0A patent/CN105696543B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1837108A (en) * | 2005-03-23 | 2006-09-27 | 贵阳铝镁设计研究院 | Process for dry treatment of red mud and clinker in alumina plant |
CN1843923A (en) * | 2006-04-03 | 2006-10-11 | 贵阳铝镁设计研究院 | House-sealing method for dry-process piling yard of red mud |
CN201560429U (en) * | 2009-12-16 | 2010-08-25 | 贵阳铝镁设计研究院 | Heap dam structure using red mud generated by alumina produced by gibbsite as material |
CN201695404U (en) * | 2010-06-23 | 2011-01-05 | 贵阳铝镁设计研究院 | Dry-method capacity increasing structure of valley-type wet-method red mud disposal site |
CN103572747A (en) * | 2013-11-15 | 2014-02-12 | 付文堂 | Method for burying drainage-seepage body of reverse filtering pipe in tailing dam |
KR101459703B1 (en) * | 2014-01-29 | 2014-11-12 | 주식회사 항도엔지니어링 | Method for draining and reinfrocing dredged reclaimed land |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106087953A (en) * | 2016-06-29 | 2016-11-09 | 上海朗兆公路铁路养护工程技术有限公司 | A kind of drainage and construction method preventing and treating large-scale spoil ground, mountain area mud-rock flow |
CN106087953B (en) * | 2016-06-29 | 2019-01-18 | 上海朗兆公路铁路养护工程技术有限公司 | A kind of drainage and construction method for preventing and treating mountain area large size spoil ground mud-rock flow |
CN106759388A (en) * | 2017-02-14 | 2017-05-31 | 贵阳铝镁设计研究院有限公司 | A kind of slurry dry method red mud storage yard constructs the method and its structure of fill dam |
CN111593742A (en) * | 2020-05-27 | 2020-08-28 | 四川会东大梁矿业有限公司 | Construction method for rectifying and improving tailing pond based on rubble silt squeezing method |
CN111593742B (en) * | 2020-05-27 | 2022-05-24 | 四川会东大梁矿业有限公司 | Construction method for rectifying and improving tailing pond based on rubble silt squeezing method |
Also Published As
Publication number | Publication date |
---|---|
CN105696543B (en) | 2019-12-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203947484U (en) | A kind of drainage of foundation pit and circulating water utilization system | |
CN103806437B (en) | Double-layer vacuum preloading and hydraulic reclamation soft foundation processing method | |
CN206530363U (en) | One kind can the outer drainage system of maintenance type railway tunnel bottom structure | |
CN104929224B (en) | Pavement system for percolate guide blind pipe | |
CN105696543A (en) | Dam front drainage method for sub-dam building in red mud stacking area | |
CN203925527U (en) | A kind of construction joint of tunnel percolating water punishment system | |
CN105201024B (en) | Refuse landfill HDPE film rain dirt separation panel water channel | |
CN205035768U (en) | Enrockment concrete permeable dike | |
CN204898465U (en) | Ecological drainage facility of permafrost region dish | |
CN204402513U (en) | A kind of device solving the infiltration of underground chamber lining cutting surface and leak | |
CN207672616U (en) | A kind of outdoor cable penetration pipe is passed by one's way laying structure | |
CN202000365U (en) | Seepage-proof structure for underground continuous wall | |
CN102261082B (en) | Method for controlling seepage by laying membrane for slag field in high water level area, membrane laying slag field and use method thereof | |
CN205378514U (en) | Saline and alkaline land environmental protection salt system of arranging | |
CN204266191U (en) | The structure that when a kind of red mud dump constructs sub-dam, front row, dam is oozed | |
CN103999592A (en) | Method for avoiding vegetation degradation of acid mine waste rock yard | |
CN103270903B (en) | Ecological planting device | |
CN202325677U (en) | Drainage structure at position of tunnel deformation seam | |
CN206467765U (en) | A kind of casta region stepped ramp type basement drain structure | |
CN202055256U (en) | Concentrated water diversion and drainage device for large-area water seepage slope surface | |
CN206561028U (en) | refuse landfill | |
CN206052924U (en) | Buried filter pipe gully | |
CN203302051U (en) | Ecological planting device | |
CN201649110U (en) | Drainage structure for wall at hydropower station shore-type plant upstream | |
CN206094506U (en) | Air conditioner stage body water guide structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |