CN105672690B - Load bearing wall reinforcing method - Google Patents
Load bearing wall reinforcing method Download PDFInfo
- Publication number
- CN105672690B CN105672690B CN201610181708.0A CN201610181708A CN105672690B CN 105672690 B CN105672690 B CN 105672690B CN 201610181708 A CN201610181708 A CN 201610181708A CN 105672690 B CN105672690 B CN 105672690B
- Authority
- CN
- China
- Prior art keywords
- arched girder
- presstressed reinforcing
- reinforcing steel
- brick wall
- load bearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 20
- 238000000034 method Methods 0.000 title claims abstract description 16
- 239000011449 brick Substances 0.000 claims abstract description 84
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims abstract description 80
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 24
- 239000010959 steel Substances 0.000 claims abstract description 24
- 238000005728 strengthening Methods 0.000 claims abstract description 19
- 210000002435 tendon Anatomy 0.000 claims abstract description 14
- 239000004570 mortar (masonry) Substances 0.000 claims description 3
- 210000003205 muscle Anatomy 0.000 description 6
- 240000002853 Nelumbo nucifera Species 0.000 description 4
- 235000006508 Nelumbo nucifera Nutrition 0.000 description 4
- 235000006510 Nelumbo pentapetala Nutrition 0.000 description 4
- 238000010276 construction Methods 0.000 description 4
- 238000005520 cutting process Methods 0.000 description 4
- 238000005266 casting Methods 0.000 description 2
- 239000004744 fabric Substances 0.000 description 2
- 238000003359 percent control normalization Methods 0.000 description 2
- 238000003825 pressing Methods 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000001788 irregular Effects 0.000 description 1
- 238000005086 pumping Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0222—Replacing or adding wall ties
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
- E04G23/0244—Increasing or restoring the load-bearing capacity of building construction elements of beams at places of holes, e.g. drilled in them
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0274—Temporary shoring of wall opening
Abstract
The invention discloses a kind of load bearing wall reinforcing method, it is characterized in that arched girder is set in load bearing wall hole top, arched girder both ends set arched girder buttress, arched girder bottom sets arched girder presstressed reinforcing steel, arched girder presstressed reinforcing steel passes through arched girder buttress one through to constructional column, constructional column is fixed on by anchorage after arched girder presstressed reinforcing steel prestressed stretch-draw, arched girder top sets arched girder non-prestressing tendon, and arched girder non-prestressing tendon stretches into arched girder buttress;Arched girder buttress position brick wall both sides set strengthening steel slab, and strengthening steel slab is fixed by split bolt;Load bearing wall presstressed reinforcing steel is set above arched girder, and brick wall presstressed reinforcing steel forms broken line after prestressed stretch-draw;Brick wall presstressed reinforcing steel is divided into several tensioned units, and tensioned unit both ends are welded brace rod, fixed after brick wall tension of prestressed tendon with lacing wire.
Description
Technical field
The present invention relates to a kind of load bearing wall reinforcing method, suitable for building field.
Background technology
Load bearing wall punch can cause it is unbalance in stress, on the one hand because the load above hole needs to carry, if
Unreasonable structure weight can then cause brick wall to cave in, and gently then occur crack around hole.Conventionally employed Horizontal concrete lintel shape
Formula usually occurs hole edge in engineering practice and splayed crack or Vertical Cracks occurs.On the other hand can be divided again due to stress
There is the region of high stress in brick wall of the cloth above load-bearing wall opening, if the brick wall above no technical measures load-bearing wall opening can go out
Existing irregular cracks.In addition, partial pressing occurs in the brick wall of load-bearing wall opening edge, if not causing the attention of height can make
Into security incident.
The content of the invention
The present invention is to provide a kind of load bearing wall reinforcing method, solves that traditional reinforcement means security performance is bad to ask
Topic.
Due to arch girder construction in stress it is more reasonable, the load above arched girder can rationally be transmitted, thus this
Invention sets arched girder in load bearing wall hole top, and arch depth of beam is 350~600mm, arch beam width and brick wall width phase
Together, arched girder both ends set arched girder buttress, and arched girder buttress is highly 350~600mm, and arched girder bottom sets arched girder pre-
Stress rib, a diameter of 18~25mm of arched girder presstressed reinforcing steel, arched girder presstressed reinforcing steel pass through arched girder buttress one through to construction
Post, constructional column is fixed on by anchorage after arched girder presstressed reinforcing steel prestressed stretch-draw, arched girder top set arched girder it is non-it is pre- should
Power muscle, a diameter of 18~25mm of arched girder non-prestressing tendon, arched girder non-prestressing tendon stretch into arched girder buttress.Arched girder buttress
Position brick wall both sides set strengthening steel slab, and strengthening steel slab thickness is 12~15mm, and strengthening steel slab is to local below arched girder buttress
Brick wall is reinforced, and strengthening steel slab reinforcing scope extends to 0.5~0.7m below hole, and strengthening steel slab is carried out by split bolt
Fixed, a diameter of 16~18mm of split bolt, it is 350~450mm that split bolt, which sets spacing,.The setting of strengthening steel slab is effectively kept away
The partial pressing for having exempted from arched girder buttress position destroys.
Because the brick wall formation stress concentration above arched girder is easily cracking, it is necessary to which the brick wall above arched girder enters
Row is reinforced.According to simulation analysis of computer, arc area of stress concentration can be formed above arched girder, according to stress distribution feature, arch
Load bearing wall presstressed reinforcing steel, a diameter of 12~16mm of load bearing wall presstressed reinforcing steel, when brick wall presstressed reinforcing steel is just arranged are set above ellbeam
For level, vertical spacing of the brick wall presstressed reinforcing steel in level is 200~250mm, position of the brick wall presstressed reinforcing steel in level
Brick wall mortar joint position is arranged on as much as possible, and brick wall presstressed reinforcing steel forms broken line after prestressed stretch-draw.According to stress characteristic cloth
Put six row's brick wall presstressed reinforcing steels or four row's brick wall presstressed reinforcing steels, first row brick wall presstressed reinforcing steel and second row brick wall presstressed reinforcing steel
Flush, the 3rd row's brick wall presstressed reinforcing steel and the 4th row's brick wall presstressed reinforcing steel are retracted relative to second row brick wall presstressed reinforcing steel, retraction
Length is 40~60mm, and the 5th row's brick wall presstressed reinforcing steel and the 6th row's brick wall presstressed reinforcing steel are relative to the 4th row's brick wall presstressed reinforcing steel
Retraction, retraction length is 40~60mm;It is 50~70mm with a distance from first row brick wall presstressed reinforcing steel is vertical from arched girder.Brick wall is pre-
Stress rib both ends setting porthole, porthole width, length, highly identical with load bearing wall width, the interior placement billet of porthole, brick wall are pre-
Stress rib is welded with billet, and intensity is clogged in porthole as C30 or the concrete of the above.Brick wall presstressed reinforcing steel divides
For several tensioned units, each tensioned unit length is 1.5~2m, and brace rod, brick wall prestressing force are welded in tensioned unit both ends
Fixed after muscle tensioning with lacing wire.
Construction procedure includes:
(1) form bracing is set, load bearing wall load is laid down.
(2) load-bearing wall opening is opened up with cutting machine, load bearing wall sets groove arched girder presstressed reinforcing steel is passed to through groove
Constructional column, colligation arch beam steel install arch beam forms and arched girder buttress template, and arch side template sets concrete to pour
Hole, a diameter of 80~120mm of concrete pouring hole are built, it is 2~3m that concrete pouring hole, which sets spacing,.
(3) porthole at brick wall presstressed reinforcing steel both ends is opened up with cutting machine, billet is placed in porthole, by brick wall presstressed reinforcing steel
It is welded on billet, casting concrete after brick wall presstressed reinforcing steel is fixed.
(4) brace rod is welded on by brick wall presstressed reinforcing steel according to tensioned unit.
(5) arched girder concrete and arched girder buttress use pumped commercial concrete, and slump is 8~10mm, pump business
Product concrete is entered and poured by concrete pouring hole.
(6) tensioning of arched girder presstressed reinforcing steel is carried out, tensioning process is using as follows:By arched girder presstressed reinforcing steel initial tensioning
10% control tension stress is pulled to, lotus 3min is held and establishes primary stress, then is stretched to control tension stress, holds lotus 5min foundation
Prestressing force.Arched girder presstressed reinforcing steel is fixed on constructional column by anchorage after tensioning.
(7) brick wall prestressing force is carried out after the porthole concrete at brick wall presstressed reinforcing steel both ends reaches design strength more than 90%
Muscle tensioning, brick wall tension of prestressed tendon use vertical tension, are welded and fixed after vertical tension with lacing wire.
Mechanical property of the present invention is good, and safe operation is reliable.
Brief description of the drawings
Fig. 1 is load bearing wall reinforcing structural representation.
Reference:1st, arched girder, 2, arched girder presstressed reinforcing steel, 3, arched girder non-prestressing tendon, 4, arched girder buttress, 5,
Anchorage, 6, strengthening steel slab, 7, split bolt, 8, constructional column, 9, brick wall presstressed reinforcing steel, 10, billet, 11 concrete, 12, support
Muscle, 13, lacing wire.
Embodiment
The present embodiment is described in detail below in conjunction with accompanying drawing.
The present embodiment sets arched girder 1 in load bearing wall hole top, and the height of arched girder 1 be 400mm, the width of arched girder 1 and
Brick wall width is identical, and the both ends of arched girder 1 set arched girder buttress 4, and the height of arched girder buttress 4 is 400mm, and the bottom of arched girder 1 is set
Arched girder presstressed reinforcing steel 2,2 a diameter of 22mm of arched girder presstressed reinforcing steel are put, arched girder presstressed reinforcing steel 2 passes through arched girder buttress 4 one
Through to constructional column 8, constructional column 8 is fixed on by anchorage 5 after the prestressed stretch-draw of arched girder presstressed reinforcing steel 2, the top of arched girder 1 is set
Arched girder non-prestressing tendon 3,3 a diameter of 22mm of arched girder non-prestressing tendon are put, arched girder non-prestressing tendon 3 stretches into arched girder branch
Pier 4.The position brick wall both sides of arched girder buttress 4 set strengthening steel slab 6, and the thickness of strengthening steel slab 6 is 14mm, and strengthening steel slab 6 is to arch
Beam buttress 4 below reinforced by local brick wall, and the reinforcing scope of strengthening steel slab 6 extends to 0.6m below hole, and strengthening steel slab 6 passes through
Split bolt 7 is fixed, 7 a diameter of 16mm of split bolt, and it is 400mm that split bolt 7, which sets spacing,.
The top of arched girder 1 sets load bearing wall presstressed reinforcing steel, a diameter of 12~16mm of load bearing wall presstressed reinforcing steel, brick wall prestressing force
It is level when muscle 9 is just arranged, vertical spacing of the brick wall presstressed reinforcing steel 9 in level is 240mm, and brick wall presstressed reinforcing steel 9 is in level
When position be arranged on brick wall mortar joint position as much as possible, brick wall presstressed reinforcing steel 9 forms broken line after prestressed stretch-draw.According to should
Power feature arranges six row's brick wall presstressed reinforcing steels 9, and first row brick wall presstressed reinforcing steel 9 and second row brick wall presstressed reinforcing steel 9 flush, the 3rd
Row's brick wall presstressed reinforcing steel 9 and the 4th row's brick wall presstressed reinforcing steel 9 are retracted relative to second row brick wall presstressed reinforcing steel 9, and retraction length is
50mm, the 5th row's brick wall presstressed reinforcing steel 9 and the 6th row's brick wall presstressed reinforcing steel 9 are retracted relative to the 4th row's brick wall presstressed reinforcing steel 9, contracting
It is 50mm to enter length;It is 60mm with a distance from first row brick wall presstressed reinforcing steel 9 is vertical from arched girder 1.The both ends of brick wall presstressed reinforcing steel 9 are set
Porthole, porthole width, length, highly identical with load bearing wall width, placement billet 10, brick wall presstressed reinforcing steel 9 and steel in porthole
Backing plate 10 is welded, and intensity is clogged in porthole as C30 or the concrete 11 of the above.If brick wall presstressed reinforcing steel 9 is divided into
Dry tensioned unit, each tensioned unit length are 1.8m, and brace rod 12 is welded at tensioned unit both ends, and brick wall presstressed reinforcing steel 9 is opened
Fixed after drawing with lacing wire 13.
Construction procedure includes:
(1) form bracing is set, load bearing wall load is laid down.
(2) load-bearing wall opening is opened up with cutting machine, load bearing wall sets groove arched girder presstressed reinforcing steel 2 is passed to through groove
Constructional column 8, the reinforcing bar of colligation arched girder 1 install the template of arched girder 1 and the template of arched girder buttress 4, and the side template of arched girder 1 sets mixed
Native pouring hole, a diameter of 100mm of concrete pouring hole are coagulated, it is 2.5m that concrete pouring hole, which sets spacing,.
(3) porthole at the both ends of brick wall presstressed reinforcing steel 9 is opened up with cutting machine, billet 10 is placed in porthole, brick wall in advance should
Power muscle 9 is welded on billet 10, casting concrete 11 after brick wall presstressed reinforcing steel 9 is fixed.
(4) brace rod 12 is welded on by brick wall presstressed reinforcing steel 9 according to tensioned unit.
(5) concrete of arched girder 1 and arched girder buttress 4 use pumped commercial concrete, and slump is 8~10mm, pumping
Commerical ready-mixed concrete is entered and poured by concrete pouring hole.
(6) tensioning of arched girder presstressed reinforcing steel 2 is carried out, tensioning process is using as follows:By the initial tensioning of arched girder presstressed reinforcing steel 2
10% control tension stress is stretched to, lotus 3min is held and establishes primary stress, then is stretched to control tension stress, lotus 5min is held and builds
Vertical prestressing force.Arched girder presstressed reinforcing steel 2 is fixed on constructional column 8 by anchorage 5 after tensioning.
(7) it is pre- that brick wall is carried out after the porthole concrete 11 at the both ends of brick wall presstressed reinforcing steel 9 reaches design strength more than 90%
The tensioning of stress rib 9, the tensioning of brick wall presstressed reinforcing steel 9 use vertical tension, are welded and fixed after vertical tension with lacing wire 13.
Claims (7)
1. a kind of load bearing wall reinforcing method, it is characterized in that setting arched girder in load bearing wall hole top, arched girder both ends are set
Arched girder buttress is put, arched girder bottom sets arched girder presstressed reinforcing steel, and arched girder presstressed reinforcing steel is led directly to through arched girder buttress one
To constructional column, constructional column is fixed on by anchorage after arched girder presstressed reinforcing steel prestressed stretch-draw, arched girder top sets arched girder
Non-prestressing tendon, arched girder non-prestressing tendon stretch into arched girder buttress;Arched girder buttress position brick wall both sides set strengthening steel slab,
Strengthening steel slab is reinforced to local brick wall below arched girder buttress, and strengthening steel slab reinforcing scope extends to 0.5 below hole~
0.7m, strengthening steel slab are fixed by split bolt;
Brick wall presstressed reinforcing steel, brick wall presstressed reinforcing steel a diameter of 12~16mm are set above arched girder, and brick wall presstressed reinforcing steel is just arranged
When for level, vertical spacing of the brick wall presstressed reinforcing steel in level be 200~250mm, position of the brick wall presstressed reinforcing steel in level
Put and be arranged on brick wall mortar joint position as much as possible, brick wall presstressed reinforcing steel forms broken line after prestressed stretch-draw;Brick wall presstressed reinforcing steel
Both ends set porthole, porthole width, length, highly identical with load bearing wall width, placement billet, brick wall presstressed reinforcing steel in porthole
Welded with billet, intensity is clogged in porthole as C30 or the concrete of the above;Brick wall presstressed reinforcing steel is divided into some
Individual tensioned unit, each tensioned unit length are 1.5~2m, and brace rod, brick wall tension of prestressed tendon are welded in tensioned unit both ends
After fixed with lacing wire.
2. load bearing wall reinforcing method according to claim 1, it is characterized in that arch depth of beam is 350~600mm, arch
Ellbeam width is identical with brick wall width.
3. load bearing wall reinforcing method according to claim 1, it is characterized in that arched girder buttress highly for 350~
600mm。
4. load bearing wall reinforcing method according to claim 1, it is characterized in that arched girder presstressed reinforcing steel a diameter of 18~
25mm。
5. load bearing wall reinforcing method according to claim 1, it is characterized in that arched girder non-prestressing tendon a diameter of 18
~25mm.
6. load bearing wall reinforcing method according to claim 1, it is characterized in that strengthening steel slab thickness is 12~15mm.
7. load bearing wall reinforcing method according to claim 1, it is characterized in that, a diameter of 16~18mm of split bolt,
It is 350~450mm that split bolt, which sets spacing,.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610181708.0A CN105672690B (en) | 2016-03-02 | 2016-03-02 | Load bearing wall reinforcing method |
CN201710707381.0A CN107299773B (en) | 2016-03-02 | 2016-03-02 | Load bearing wall reinforcing construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610181708.0A CN105672690B (en) | 2016-03-02 | 2016-03-02 | Load bearing wall reinforcing method |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710707381.0A Division CN107299773B (en) | 2016-03-02 | 2016-03-02 | Load bearing wall reinforcing construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105672690A CN105672690A (en) | 2016-06-15 |
CN105672690B true CN105672690B (en) | 2017-11-28 |
Family
ID=56224368
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710707381.0A Expired - Fee Related CN107299773B (en) | 2016-03-02 | 2016-03-02 | Load bearing wall reinforcing construction method |
CN201610181708.0A Expired - Fee Related CN105672690B (en) | 2016-03-02 | 2016-03-02 | Load bearing wall reinforcing method |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710707381.0A Expired - Fee Related CN107299773B (en) | 2016-03-02 | 2016-03-02 | Load bearing wall reinforcing construction method |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN107299773B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108867931B (en) * | 2018-07-02 | 2019-12-13 | 中国建筑第八工程局有限公司 | Shear wall building door opening structure |
CN108999422A (en) * | 2018-08-15 | 2018-12-14 | 庐江荣睿建设工程有限公司 | A kind of method that bearing wall opens up door-window opening |
CN109653533A (en) * | 2019-02-13 | 2019-04-19 | 程勇俊 | A kind of concrete floor reinforced construction method |
CN110331795B (en) * | 2019-07-25 | 2022-04-29 | 石家庄市住宅开发建设公司 | Reverse construction method for arch coupon structure |
CN115653346B (en) * | 2022-12-26 | 2023-03-10 | 上海建工一建集团有限公司 | Existing house wall beam replacement structure and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100693137B1 (en) * | 2004-06-15 | 2007-03-13 | 김상남 | Structure for reinforcing a building using prestress |
CN102434008A (en) * | 2010-09-29 | 2012-05-02 | 贵阳铝镁设计研究院有限公司 | Opening reinforcing method implemented after punching hole on cast-in-place concrete plate |
CN102877656A (en) * | 2012-08-10 | 2013-01-16 | 南京工业大学 | Method for reinforcing masonry wall through steel structure |
CN103741842A (en) * | 2014-01-22 | 2014-04-23 | 天津大学建筑设计研究院 | Lightweight fabricated shear wall structure |
CN204212447U (en) * | 2014-10-17 | 2015-03-18 | 中国十七冶集团有限公司 | Door and window concrete arch lintel strengthening construction device |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6505450B1 (en) * | 1997-10-29 | 2003-01-14 | Reginald A. J. Locke | Masonry reinforcement system |
CN201206337Y (en) * | 2008-03-14 | 2009-03-11 | 中建三局建设工程股份有限公司 | Prestressed concrete structure |
CN101446138A (en) * | 2008-12-19 | 2009-06-03 | 上海市第五建筑有限公司 | Reconstructed project wall external decoration material anti-seepage construction method |
CN201531124U (en) * | 2009-09-24 | 2010-07-21 | 马人乐 | Graded external pre-stress strengthening masonry structure |
CN202509790U (en) * | 2012-01-12 | 2012-10-31 | 中国水电顾问集团华东勘测设计研究院 | Reinforcing structure of structure pool |
CN103352581B (en) * | 2013-07-09 | 2015-12-09 | 北京筑福国际工程技术有限责任公司 | Adopt the method for inner prestressed reinforcement bolt anchorage sintered clay brick masonry structure |
-
2016
- 2016-03-02 CN CN201710707381.0A patent/CN107299773B/en not_active Expired - Fee Related
- 2016-03-02 CN CN201610181708.0A patent/CN105672690B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100693137B1 (en) * | 2004-06-15 | 2007-03-13 | 김상남 | Structure for reinforcing a building using prestress |
CN102434008A (en) * | 2010-09-29 | 2012-05-02 | 贵阳铝镁设计研究院有限公司 | Opening reinforcing method implemented after punching hole on cast-in-place concrete plate |
CN102877656A (en) * | 2012-08-10 | 2013-01-16 | 南京工业大学 | Method for reinforcing masonry wall through steel structure |
CN103741842A (en) * | 2014-01-22 | 2014-04-23 | 天津大学建筑设计研究院 | Lightweight fabricated shear wall structure |
CN204212447U (en) * | 2014-10-17 | 2015-03-18 | 中国十七冶集团有限公司 | Door and window concrete arch lintel strengthening construction device |
Also Published As
Publication number | Publication date |
---|---|
CN105672690A (en) | 2016-06-15 |
CN107299773B (en) | 2019-08-30 |
CN107299773A (en) | 2017-10-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105672690B (en) | Load bearing wall reinforcing method | |
CN103615053B (en) | Monolithic reinforced concrete structure post empiricism engineering method | |
CN101886466B (en) | Construction method for support structure of coal tower template for tamping type coke oven | |
CN101748681B (en) | Pretensioning method construction technology of 50m broken line reinforced concrete T-shaped beam | |
CN108005387B (en) | Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall | |
CN105040970A (en) | Comprehensive gymnasium high formwork support system and construction method of comprehensive gymnasium high formwork support system | |
CN104278841B (en) | The method of casting concrete in steel pipe column | |
CN104863063B (en) | Cofferdam method for rapidly reinforcing is exempted from based on the bridge submerged structure of PVC composite shuttering | |
CN103806659B (en) | Super thick prestressing force change-over panel individual layer comprehensively supports and splits temperature control construction technology with control | |
CN110939051A (en) | Subway hidden cover beam construction method | |
CN108330902B (en) | Construction method for cast-in-situ lower cross beam of high-pile wharf | |
CN103938871B (en) | A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint | |
CN205976167U (en) | Based on cast -in -place floor structures of detachable positioning control spare | |
CN108086674A (en) | A kind of roof boarding hangs the construction method of mould and roof boarding | |
CN108104284B (en) | Wallboard connecting structure of shear wall steel arm embedded floor slab and assembly method | |
CN111074950B (en) | Pre-closed advanced water stop post-cast strip for basement outer wall and construction method | |
CN205804745U (en) | A kind of precast concrete shear wall component | |
CN102605988B (en) | Synchronous construction method for chimney lining external concrete | |
CN105370027B (en) | The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure | |
CN108130889B (en) | Manufacturing method of stepped construction joint between main bottom plate of pump brake and side wall of runner layer | |
CN105926657A (en) | Concrete foundation prefabricated slab and construction method thereof | |
CN203320810U (en) | Steel tube concrete structure | |
CN207110174U (en) | It is a kind of that support UHPC poured light rib floors are exempted from based on steel bar girder main rib prefabricated component | |
CN108951643B (en) | Super high-rise deep foundation pit basement core tube large-span large-area support changing construction method | |
CN208072974U (en) | A kind of self-supporting hoistable platform jacking hole steel beam structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20190814 Address after: 330000 No. 69 Gaoxin Road, Nanchang High-tech Zone, Jiangxi Province Patentee after: Jiangxi High Energy Construction Engineering Co.,Ltd. Address before: 325000 Room 302, 11 Building of Jingshan Group, Wenzhou City, Zhejiang Province Patentee before: Ye Xiangzhu |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171128 |