CN107299773A - Load bearing wall reinforcing construction method - Google Patents

Load bearing wall reinforcing construction method Download PDF

Info

Publication number
CN107299773A
CN107299773A CN201710707381.0A CN201710707381A CN107299773A CN 107299773 A CN107299773 A CN 107299773A CN 201710707381 A CN201710707381 A CN 201710707381A CN 107299773 A CN107299773 A CN 107299773A
Authority
CN
China
Prior art keywords
reinforcing steel
presstressed reinforcing
brick wall
arched girder
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710707381.0A
Other languages
Chinese (zh)
Other versions
CN107299773B (en
Inventor
叶香竹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Zhonglin Engineering Construction Co ltd
Qiaozhi Construction Co ltd
Fuzhou University
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201710707381.0A priority Critical patent/CN107299773B/en
Publication of CN107299773A publication Critical patent/CN107299773A/en
Application granted granted Critical
Publication of CN107299773B publication Critical patent/CN107299773B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0222Replacing or adding wall ties
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0244Increasing or restoring the load-bearing capacity of building construction elements of beams at places of holes, e.g. drilled in them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0274Temporary shoring of wall opening

Abstract

The invention discloses a kind of load bearing wall reinforcing construction method, it is characterized in that construction procedure includes:(1) form bracing is set, load bearing wall load is laid down;(2) load bearing wall sets groove arched girder presstressed reinforcing steel is passed to constructional column through groove, and colligation arch beam steel installs arch beam forms and arched girder buttress template, and arch side template sets concreting hole;(3) brick wall presstressed reinforcing steel is fixed and finishes after-pouring concrete;(4) brace rod is welded on by brick wall presstressed reinforcing steel according to tensioned unit;(5) pumped commercial concrete is entered and poured by concreting hole;(6) tensioning of arched girder presstressed reinforcing steel is carried out;Arched girder presstressed reinforcing steel by anchorage is fixed on constructional column by tensioning after finishing;(7) brick wall tension of prestressed tendon uses vertical tension, vertical tension to be welded and fixed after finishing with lacing wire.

Description

Load bearing wall reinforcing construction method
Technical field
The present invention relates to a kind of load bearing wall reinforcing construction method, it is adaptable to building field.
Background technology
Load bearing wall punch to cause unbalance in stress, on the one hand because the load above hole needs carrying, if Unreasonable structure weight can then cause brick wall to cave in, and gently then occur crack around hole.Conventionally employed Horizontal concrete lintel shape Formula usually occurs hole edge in engineering practice and splayed crack or Vertical Cracks occurs.On the other hand can again it be divided due to stress There is the region of high stress in brick wall of the cloth above load-bearing wall opening, if can go out without the brick wall above technical measures load-bearing wall opening Existing irregular cracks.In addition, partial pressing occurs in the brick wall of load-bearing wall opening edge, it can be made if not causing the attention of height Into security incident.
The content of the invention
The present invention is to provide a kind of load bearing wall reinforcing construction method, solves traditional reinforcement means security performance bad Problem.
Due to arch girder construction in stress it is more reasonable, the load above arched girder can rationally be transmitted, thus this Invention sets arched girder in load bearing wall hole top, and arch depth of beam is 350~600mm, arch beam width and brick wall width phase Together, arched girder two ends set arched girder buttress, and arched girder buttress is highly 350~600mm, and arched girder bottom sets arched girder pre- Stress rib, a diameter of 18~25mm of arched girder presstressed reinforcing steel, arched girder presstressed reinforcing steel passes through arched girder buttress one through to construction Constructional column is fixed on by anchorage after post, arched girder presstressed reinforcing steel prestressed stretch-draw, arched girder top set arched girder it is non-it is pre- should Power muscle, a diameter of 18~25mm of arched girder non-prestressing tendon, arched girder non-prestressing tendon stretches into arched girder buttress.Arched girder buttress Position brick wall both sides set strengthening steel slab, and strengthening steel slab thickness is 12~15mm, and strengthening steel slab is to local below arched girder buttress Brick wall is reinforced, and strengthening steel slab reinforcing scope extends to 0.5~0.7m below hole, and strengthening steel slab is carried out by split bolt Fixed, a diameter of 16~18mm of split bolt, split bolt sets spacing to be 350~450mm.The setting of strengthening steel slab is effectively kept away Partial pressing's destruction at arched girder buttress position is exempted from.
Because the brick wall formation stress concentration above arched girder is easily cracking, it is necessary to which the brick wall above arched girder is entered Row is reinforced.According to simulation analysis of computer, arc area of stress concentration can be formed above arched girder, according to stress distribution feature, arch When being arranged at the beginning of load bearing wall presstressed reinforcing steel, a diameter of 12~16mm of load bearing wall presstressed reinforcing steel, brick wall presstressed reinforcing steel are set above ellbeam For level, vertical spacing of the brick wall presstressed reinforcing steel in level is 200~250mm, position of the brick wall presstressed reinforcing steel in level Brick wall mortar joint position is arranged on as much as possible, and brick wall presstressed reinforcing steel forms broken line after prestressed stretch-draw.According to stress characteristic cloth Put six row's brick wall presstressed reinforcing steels or four row's brick wall presstressed reinforcing steels, first row brick wall presstressed reinforcing steel and second row brick wall presstressed reinforcing steel Flush, the 3rd row's brick wall presstressed reinforcing steel and the 4th row's brick wall presstressed reinforcing steel are retracted relative to second row brick wall presstressed reinforcing steel, retraction Length is 40~60mm, and the 5th row's brick wall presstressed reinforcing steel and the 6th row's brick wall presstressed reinforcing steel are relative to the 4th row's brick wall presstressed reinforcing steel Retraction, retraction length is 40~60mm;It is 50~70mm with a distance from first row brick wall presstressed reinforcing steel is vertical from arched girder.Brick wall in advance should Power muscle two ends set porthole, porthole width, length, highly identical with load bearing wall width, billet are placed in porthole, brick wall in advance should Power muscle is welded with billet, and it is C30 or the concrete of the above that intensity is clogged in porthole.Brick wall presstressed reinforcing steel is divided into Several tensioned units, each tensioned unit length is 1.5~2m, tensioned unit two ends welding brace rod, brick wall presstressed reinforcing steel Tensioning is fixed after finishing with lacing wire.
Construction procedure includes:
(1) form bracing is set, load bearing wall load is laid down.
(2) load-bearing wall opening is opened up with cutting machine, load bearing wall sets groove arched girder presstressed reinforcing steel is passed to through groove Constructional column, colligation arch beam steel installs arch beam forms and arched girder buttress template, and arch side template sets concrete to pour Hole is built, concreting bore dia is 80~120mm, and concreting hole sets spacing to be 2~3m.
(3) opened up with cutting machine and billet is placed in the porthole at brick wall presstressed reinforcing steel two ends, porthole, by brick wall presstressed reinforcing steel Billet is welded on, brick wall presstressed reinforcing steel is fixed and finishes after-pouring concrete.
(4) brace rod is welded on by brick wall presstressed reinforcing steel according to tensioned unit.
(5) arched girder concrete and arched girder buttress concrete use pumped commercial concrete, and slump is 8~10mm, Pumped commercial concrete is entered and poured by concreting hole.
(6) tensioning of arched girder presstressed reinforcing steel is carried out, tensioning process is as follows:By arched girder presstressed reinforcing steel initial tensioning to 10% Control tension stress, hold lotus 3min and set up primary stress, then be stretched to control tension stress, hold lotus 5min and set up prestressing force. Arched girder presstressed reinforcing steel by anchorage is fixed on constructional column by tensioning after finishing.
(7) brick wall prestressing force is carried out after the porthole concrete at brick wall presstressed reinforcing steel two ends reaches design strength more than 90% Muscle tensioning, brick wall tension of prestressed tendon uses vertical tension, vertical tension to be welded and fixed after finishing with lacing wire.
Mechanical property of the present invention is good, and safe operation is reliable.
Brief description of the drawings
Fig. 1 is load bearing wall reinforcing structural representation.
Reference:1st, arched girder, 2, arched girder presstressed reinforcing steel, 3, arched girder non-prestressing tendon, 4, arched girder buttress, 5, Anchorage, 6, strengthening steel slab, 7, split bolt, 8, constructional column, 9, brick wall presstressed reinforcing steel, 10, billet, 11 concrete, 12, support Muscle, 13, lacing wire.
Embodiment
The present embodiment is described in detail below in conjunction with accompanying drawing.
The present embodiment load bearing wall hole top set arched girder 1, the height of arched girder 1 be 400mm, the width of arched girder 1 with Brick wall width is identical, and the two ends of arched girder 1 set arched girder buttress 4, and the height of arched girder buttress 4 is 400mm, and the bottom of arched girder 1 is set Arched girder presstressed reinforcing steel 2 is put, a diameter of 22mm of arched girder presstressed reinforcing steel 2, arched girder presstressed reinforcing steel 2 passes through arched girder buttress 4 one Through to constructional column 8, constructional column 8 is fixed on by anchorage 5 after the prestressed stretch-draw of arched girder presstressed reinforcing steel 2, the top of arched girder 1 is set Arched girder non-prestressing tendon 3 is put, a diameter of 22mm of arched girder non-prestressing tendon 3, arched girder non-prestressing tendon 3 stretches into arched girder branch Pier 4.The position brick wall both sides of arched girder buttress 4 set strengthening steel slab 6, and the thickness of strengthening steel slab 6 is 14mm, and strengthening steel slab 6 is to arch Beam buttress 4 below reinforced by local brick wall, and the reinforcing scope of strengthening steel slab 6 extends to 0.6m below hole, and strengthening steel slab 6 passes through Split bolt 7 is fixed, a diameter of 16mm of split bolt 7, and split bolt 7 sets spacing to be 400mm.
The top of arched girder 1 sets load bearing wall presstressed reinforcing steel, a diameter of 12~16mm of load bearing wall presstressed reinforcing steel, brick wall prestressing force It is level when muscle 9 is just arranged, vertical spacing of the brick wall presstressed reinforcing steel 9 in level is 240mm, and brick wall presstressed reinforcing steel 9 is in level When position be arranged on brick wall mortar joint position as much as possible, brick wall presstressed reinforcing steel 9 forms broken line after prestressed stretch-draw.According to should Power feature arranges six row's brick wall presstressed reinforcing steels 9, and first row brick wall presstressed reinforcing steel 9 and second row brick wall presstressed reinforcing steel 9 are flushed, the 3rd Row's brick wall presstressed reinforcing steel 9 and the 4th row's brick wall presstressed reinforcing steel 9 are retracted relative to second row brick wall presstressed reinforcing steel 9, and retraction length is 50mm, the 5th row's brick wall presstressed reinforcing steel 9 and the 6th row's brick wall presstressed reinforcing steel 9 are retracted relative to the 4th row's brick wall presstressed reinforcing steel 9, contracting Enter length for 50mm;It is 60mm with a distance from first row brick wall presstressed reinforcing steel 9 is vertical from arched girder 1.The two ends of brick wall presstressed reinforcing steel 9 are set Porthole, porthole width, length, highly identical with load bearing wall width, placement billet 10, brick wall presstressed reinforcing steel 9 and steel in porthole Backing plate 10 is welded, and it is C30 or the concrete 11 of the above that intensity is clogged in porthole.If brick wall presstressed reinforcing steel 9 is divided into Dry tensioned unit, each tensioned unit length is 1.8m, tensioned unit two ends welding brace rod 12, brick wall presstressed reinforcing steel 9 Pull and fixed after finishing with lacing wire 13.
Construction procedure includes:
(1) form bracing is set, load bearing wall load is laid down.
(2) load-bearing wall opening is opened up with cutting machine, load bearing wall sets groove arched girder presstressed reinforcing steel 2 is passed to through groove Constructional column 8, the reinforcing bar of colligation arched girder 1 installs the template of arched girder 1 and the template of arched girder buttress 4, and the side template of arched girder 1 sets mixed Solidifying soil pouring hole, concreting bore dia is 100mm, and concreting hole sets spacing to be 2.5m.
(3) opened up with cutting machine and billet 10 is placed in the porthole at the two ends of brick wall presstressed reinforcing steel 9, porthole, brick wall in advance should Power muscle 9 is welded on billet 10, and brick wall presstressed reinforcing steel 9 is fixed and finishes after-pouring concrete 11.
(4) brace rod 12 is welded on by brick wall presstressed reinforcing steel 9 according to tensioned unit.
(5) concrete of arched girder 1 and the concrete of arched girder buttress 4 use pumped commercial concrete, and slump is 8~ 10mm, pumped commercial concrete is entered and poured by concreting hole.
(6) tensioning of arched girder presstressed reinforcing steel 2 is carried out, tensioning process is as follows:By the initial tensioning of arched girder presstressed reinforcing steel 2 extremely 10% control tension stress, holds lotus 3min and sets up primary stress, then is stretched to control tension stress, holds lotus 5min and sets up and in advance should Power.Arched girder presstressed reinforcing steel 2 by anchorage 5 is fixed on constructional column 8 by tensioning after finishing.
(7) brick wall is carried out after the porthole concrete 11 at the two ends of brick wall presstressed reinforcing steel 9 reaches design strength more than 90% pre- The tensioning of stress rib 9, the tensioning of brick wall presstressed reinforcing steel 9 uses vertical tension, vertical tension to be welded and fixed after finishing with lacing wire 13.

Claims (2)

1. a kind of load bearing wall reinforcing construction method, it is characterized in that construction procedure includes:
(1) form bracing is set, load bearing wall load is laid down;
(2) load-bearing wall opening is opened up with cutting machine, load bearing wall sets groove arched girder presstressed reinforcing steel is passed to construction through groove Post, colligation arch beam steel installs arch beam forms and arched girder buttress template, and arch side template sets concreting Hole, concreting bore dia is 80~120mm, and concreting hole sets spacing to be 2~3m;
(3) opened up with cutting machine and billet is placed in the porthole at brick wall presstressed reinforcing steel two ends, porthole, brick wall presstressed reinforcing steel is welded In billet, brick wall presstressed reinforcing steel is fixed and finishes after-pouring concrete;
(4) brace rod is welded on by brick wall presstressed reinforcing steel according to tensioned unit;
(5) arched girder concrete and arched girder buttress concrete use pumped commercial concrete, and slump is 8~10mm, pumping Commerical ready-mixed concrete is entered and poured by concreting hole;
(6) tensioning of arched girder presstressed reinforcing steel is carried out, tensioning process is as follows:By the control of arched girder presstressed reinforcing steel initial tensioning to 10% Tension stress processed, holds lotus 3min and sets up primary stress, then is stretched to control tension stress, holds lotus 5min and sets up prestressing force;Tensioning Arched girder presstressed reinforcing steel is fixed on constructional column by anchorage after finishing;
(7) brick wall presstressed reinforcing steel is carried out after the porthole concrete at brick wall presstressed reinforcing steel two ends reaches design strength more than 90% Draw, brick wall tension of prestressed tendon uses vertical tension, vertical tension to be welded and fixed after finishing with lacing wire.
2. load bearing wall reinforcing construction method according to claim 1, it is characterized in that arranging six rows according to stress characteristic Brick wall presstressed reinforcing steel or four row's brick wall presstressed reinforcing steels, first row brick wall presstressed reinforcing steel and second row brick wall presstressed reinforcing steel are flushed, 3rd row's brick wall presstressed reinforcing steel and the 4th row's brick wall presstressed reinforcing steel are retracted relative to second row brick wall presstressed reinforcing steel, and retraction length is 40~60mm, the 5th row's brick wall presstressed reinforcing steel and the 6th row's brick wall presstressed reinforcing steel are retracted relative to the 4th row's brick wall presstressed reinforcing steel, Retraction length is 40~60mm;It is 50~70mm with a distance from first row brick wall presstressed reinforcing steel is vertical from arched girder.
CN201710707381.0A 2016-03-02 2016-03-02 Load bearing wall reinforcing construction method Expired - Fee Related CN107299773B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710707381.0A CN107299773B (en) 2016-03-02 2016-03-02 Load bearing wall reinforcing construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710707381.0A CN107299773B (en) 2016-03-02 2016-03-02 Load bearing wall reinforcing construction method
CN201610181708.0A CN105672690B (en) 2016-03-02 2016-03-02 Load bearing wall reinforcing method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610181708.0A Division CN105672690B (en) 2016-03-02 2016-03-02 Load bearing wall reinforcing method

Publications (2)

Publication Number Publication Date
CN107299773A true CN107299773A (en) 2017-10-27
CN107299773B CN107299773B (en) 2019-08-30

Family

ID=56224368

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610181708.0A Expired - Fee Related CN105672690B (en) 2016-03-02 2016-03-02 Load bearing wall reinforcing method
CN201710707381.0A Expired - Fee Related CN107299773B (en) 2016-03-02 2016-03-02 Load bearing wall reinforcing construction method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201610181708.0A Expired - Fee Related CN105672690B (en) 2016-03-02 2016-03-02 Load bearing wall reinforcing method

Country Status (1)

Country Link
CN (2) CN105672690B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999422A (en) * 2018-08-15 2018-12-14 庐江荣睿建设工程有限公司 A kind of method that bearing wall opens up door-window opening
CN110331795A (en) * 2019-07-25 2019-10-15 石家庄市住宅开发建设公司 Arch construction top-down construction method

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867931B (en) * 2018-07-02 2019-12-13 中国建筑第八工程局有限公司 Shear wall building door opening structure
CN109653533A (en) * 2019-02-13 2019-04-19 程勇俊 A kind of concrete floor reinforced construction method
CN115653346B (en) * 2022-12-26 2023-03-10 上海建工一建集团有限公司 Existing house wall beam replacement structure and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6505450B1 (en) * 1997-10-29 2003-01-14 Reginald A. J. Locke Masonry reinforcement system
CN201206337Y (en) * 2008-03-14 2009-03-11 中建三局建设工程股份有限公司 Prestressed concrete structure
CN101446138A (en) * 2008-12-19 2009-06-03 上海市第五建筑有限公司 Reconstructed project wall external decoration material anti-seepage construction method
CN201531124U (en) * 2009-09-24 2010-07-21 马人乐 Graded external pre-stress strengthening masonry structure
CN202509790U (en) * 2012-01-12 2012-10-31 中国水电顾问集团华东勘测设计研究院 Reinforcing structure of structure pool
CN103352581A (en) * 2013-07-09 2013-10-16 北京筑福国际工程技术有限责任公司 Method for strengthening sintering clay brick masonry structure through internal prestressed steel anchor rods

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100693137B1 (en) * 2004-06-15 2007-03-13 김상남 Structure for reinforcing a building using prestress
CN102434008B (en) * 2010-09-29 2015-02-25 贵阳铝镁设计研究院有限公司 Opening reinforcing method implemented after punching hole on cast-in-place concrete plate
CN102877656B (en) * 2012-08-10 2016-08-03 南京工业大学 The method of steel structure reinforcing masonry wall
CN103741842A (en) * 2014-01-22 2014-04-23 天津大学建筑设计研究院 Lightweight fabricated shear wall structure
CN204212447U (en) * 2014-10-17 2015-03-18 中国十七冶集团有限公司 Door and window concrete arch lintel strengthening construction device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6505450B1 (en) * 1997-10-29 2003-01-14 Reginald A. J. Locke Masonry reinforcement system
CN201206337Y (en) * 2008-03-14 2009-03-11 中建三局建设工程股份有限公司 Prestressed concrete structure
CN101446138A (en) * 2008-12-19 2009-06-03 上海市第五建筑有限公司 Reconstructed project wall external decoration material anti-seepage construction method
CN201531124U (en) * 2009-09-24 2010-07-21 马人乐 Graded external pre-stress strengthening masonry structure
CN202509790U (en) * 2012-01-12 2012-10-31 中国水电顾问集团华东勘测设计研究院 Reinforcing structure of structure pool
CN103352581A (en) * 2013-07-09 2013-10-16 北京筑福国际工程技术有限责任公司 Method for strengthening sintering clay brick masonry structure through internal prestressed steel anchor rods

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108999422A (en) * 2018-08-15 2018-12-14 庐江荣睿建设工程有限公司 A kind of method that bearing wall opens up door-window opening
CN110331795A (en) * 2019-07-25 2019-10-15 石家庄市住宅开发建设公司 Arch construction top-down construction method

Also Published As

Publication number Publication date
CN107299773B (en) 2019-08-30
CN105672690B (en) 2017-11-28
CN105672690A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN105672690B (en) Load bearing wall reinforcing method
CN101886466B (en) Construction method for support structure of coal tower template for tamping type coke oven
CN103615053B (en) Monolithic reinforced concrete structure post empiricism engineering method
CN101748681B (en) Pretensioning method construction technology of 50m broken line reinforced concrete T-shaped beam
CN107030874A (en) Precast lattice beam for slope reinforcement and preparation method thereof and construction method
CN108005387B (en) Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall
CN105040970A (en) Comprehensive gymnasium high formwork support system and construction method of comprehensive gymnasium high formwork support system
CN110259184A (en) Column construction method is pulled out based on Removing Columns combined support jack-up system
CN108915725A (en) A kind of small template lining construction method in double -side approach tunnel
CN103603359A (en) Deep foundation pit diagonal bracing support structure demolition method
CN104863063A (en) Bridge underwater structure cofferdam-free fast reinforcing method based on PVC composite formwork
CN104060760B (en) High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN110939051A (en) Subway hidden cover beam construction method
CN107268634A (en) Deep basal pit waist rail construction typified form system
CN103806659B (en) Super thick prestressing force change-over panel individual layer comprehensively supports and splits temperature control construction technology with control
CN108330902B (en) Construction method for cast-in-situ lower cross beam of high-pile wharf
CN111042569B (en) Construction method for additionally building linear accelerator machine room in limited space of hospital basement
CN205976167U (en) Based on cast -in -place floor structures of detachable positioning control spare
CN205348761U (en) Basement does not have reinforced structure of no basic lift of installation on back board
CN108104284B (en) Wallboard connecting structure of shear wall steel arm embedded floor slab and assembly method
CN103938871A (en) Method for constructing concrete-filled steel tube column and bonded prestressed frame beam structure adopting reinforced concrete ring beam joints
CN111074950B (en) Pre-closed advanced water stop post-cast strip for basement outer wall and construction method
CN209837009U (en) Steel reinforcement cage supporting member for cast-in-place pile of overhead transmission line
CN105370027B (en) The construction method of steel supporting platform structure is integrally lifted in high-rise hanging structure
CN105926657A (en) Concrete foundation prefabricated slab and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210107

Address after: 251800 Liangwang village, Yanghu Township, Yangxin County, Binzhou City, Shandong Province

Patentee after: Yangxin Longfeng metal products Co.,Ltd.

Address before: Room 302, building 11, Jingshan group, Wenzhou City, Zhejiang Province 325000

Patentee before: Ye Xiangzhu

TR01 Transfer of patent right

Effective date of registration: 20210602

Address after: No. 58, Yingbin Avenue, Xiadu community, Pingnan County, Guigang City, Guangxi Zhuang Autonomous Region, 537300

Patentee after: Li Weizhi

Address before: 251800 Liangwang village, Yanghu Township, Yangxin County, Binzhou City, Shandong Province

Patentee before: Yangxin Longfeng metal products Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221019

Address after: 353500 No. 275, Gongnong East Road, Songyuan street, Songxi County, Nanping City, Fujian Province

Patentee after: Fujian Zhonglin Engineering Construction Co.,Ltd.

Patentee after: Qiaozhi Construction Co.,Ltd.

Patentee after: FUZHOU University

Address before: No. 58, Yingbin Avenue, Xiadu community, Pingnan County, Guigang City, Guangxi Zhuang Autonomous Region, 537300

Patentee before: Li Weizhi

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190830

CF01 Termination of patent right due to non-payment of annual fee