CN105672486A - Method for embedding anchor bars in concrete - Google Patents

Method for embedding anchor bars in concrete Download PDF

Info

Publication number
CN105672486A
CN105672486A CN201610014172.3A CN201610014172A CN105672486A CN 105672486 A CN105672486 A CN 105672486A CN 201610014172 A CN201610014172 A CN 201610014172A CN 105672486 A CN105672486 A CN 105672486A
Authority
CN
China
Prior art keywords
phase
concrete
dowel
sleeve
anchor bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610014172.3A
Other languages
Chinese (zh)
Inventor
朱少华
邓渊
李军
蔡建国
张志鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201610014172.3A priority Critical patent/CN105672486A/en
Publication of CN105672486A publication Critical patent/CN105672486A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • E04B1/4157Longitudinally-externally threaded elements extending from the concrete or masonry, e.g. anchoring bolt with embedded head
    • E04B1/4164Longitudinally-externally threaded elements extending from the concrete or masonry, e.g. anchoring bolt with embedded head with an adjustment sleeve

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention relates to a novel method for embedding anchor bars in concrete. By the adoption of the method, holes do not need to be dug in a formwork, so that template consumption is reduced, working efficiency is improved and construction cost is reduced. According to the technical scheme, the method is characterized by comprising the steps of 1, conducting threaded connection of first-phase anchor bars and a straight thread sleeve, wherein the other end of the sleeve is attached to a formwork, and the sleeve is filled with cotton fabric; 2, embedding the first-phase anchor bars connected with the straight thread sleeve in first-phase concrete; 3, taking the cotton fabric in the straight thread sleeve out after first-phase concrete pouring is finished and the formwork is removed; 4, conducting threaded connection of second-phase anchor bars. The method is suitable for anchor bar embedding during concrete pouring of hydraulic and hydroelectric engineering, constructional engineering and other similar engineering.

Description

A kind of method of pre-buried dowel in concrete
Technical field
The present invention relates to a kind of method of pre-buried dowel in concrete. It is mainly used in pre-buried dowel when Hydraulic and Hydro-Power Engineering, architectural engineering and other similar engineering concreting.
Background technology
In Hydraulic and Hydro-Power Engineering, architectural engineering, often refer to pre-buried dowel in concrete, a dowel part is embedded in fist stage concrete together builds with fist stage concrete, another part stretches out fist stage concrete, later stage builds into second stage concrete or is connected with other structures, and dowel plays a part to connect power transmission. The mode that traditional pre-buried dowel construction is typically employed in template perforate, namely needing to bury underground cutting hole in the template position that dowel position is corresponding, stretches out dowel. Dowel bury underground quantity more time, this kind of mode efficiency of construction is low, and template waste is big, especially at present in Construction for Hydroelectric Project, in order to improve concrete pouring quality and efficiency, widely used large-scale customized steel form, the template loss that template perforate causes will be greatly increased construction cost.
Summary of the invention
The technical problem to be solved in the present invention is: for the problems referred to above, it is provided that a kind of brand-new method of pre-buried dowel in concrete, and the method need not dig hole in template, thus template loss can be reduced, improves work efficiency, reduces construction cost.
The technical solution adopted in the present invention is: a kind of method of pre-buried dowel in concrete, it is characterised in that comprise the following steps:
1. being threadeded with straight screw sleeve by a phase dowel, the other end of this sleeve is adjacent to template, and sleeve inner adopts bafta to fill;
2. the phase dowel being connected with straight screw sleeve is buried underground in fist stage concrete;
3. built after form removal until fist stage concrete, taken out the bafta being filled in straight screw sleeve;
4. threaded second phase dowel.
The invention has the beneficial effects as follows: 1), compensate for the deficiency of now widely used pre-buried dowel construction method, it is to avoid template perforate, decrease the loss of template, reduce construction cost; 2), owing to avoiding template perforate, and then avoid tapping spillage during concreting, while improve concrete pouring quality, ensure that concrete good looking appearance; 3), for needing the building of a large amount of pre-buried dowel, this form of construction work has simple in construction, good reliability, the construction interference advantage such as little, is greatly improved efficiency of construction.
Accompanying drawing explanation
Fig. 1 is the structural representation of the pre-buried phase dowel of the present invention.
Fig. 2 is the structural representation that the present invention connects second phase dowel.
Detailed description of the invention
The present embodiment is the method for pre-buried dowel in concrete, specifically includes following steps:
1. as shown in Figure 1, during pre-buried dowel, dowel is disconnected, divided for two phases carried out, first a phase dowel 2 is threadeded with straight screw sleeve 3, the other end of this sleeve is adjacent to template 4, sleeve inner (does not coordinate dowel part) and adopts bafta (gauze or cotton or both) to fill, it is prevented that during concreting, serosity enters in sleeve;
2. the phase dowel 2 being connected with straight screw sleeve 3 is buried underground in fist stage concrete 1;
3. built after form removal 4 until fist stage concrete 1, taken out the bafta being filled in straight screw sleeve 3;
4. threaded second phase dowel 5, as in figure 2 it is shown, at this moment second phase dowel 5 is connected with a phase dowel 2 and is anchored in fist stage concrete 1, possesses and connects power transmission condition, builds for the later stage and gets ready into second stage concrete or be connected with other structures.
It is a kind of steel concrete supporting mode of allowing of relevant Regulations that the straight screw sleeve adopted in the present invention connects, and has that technique is simple, an advantage of dependable performance and economical rationality, and the thread making of dowel and sleeve are installed and should be met corresponding Regulations requirement.

Claims (1)

1. the method for pre-buried dowel in concrete, it is characterised in that comprise the following steps:
1.1, being threadeded with straight screw sleeve (3) by a phase dowel (2), the other end of this sleeve is adjacent to template (4), and sleeve inner adopts bafta to fill;
1.2, the phase dowel (2) that will be connected with straight screw sleeve (3) is buried underground in fist stage concrete (1);
1.3, built after form removal (4) until fist stage concrete (1), taken out the bafta being filled in straight screw sleeve (3);
1.4, threaded second phase dowel (5).
CN201610014172.3A 2016-01-07 2016-01-07 Method for embedding anchor bars in concrete Pending CN105672486A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610014172.3A CN105672486A (en) 2016-01-07 2016-01-07 Method for embedding anchor bars in concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610014172.3A CN105672486A (en) 2016-01-07 2016-01-07 Method for embedding anchor bars in concrete

Publications (1)

Publication Number Publication Date
CN105672486A true CN105672486A (en) 2016-06-15

Family

ID=56299924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610014172.3A Pending CN105672486A (en) 2016-01-07 2016-01-07 Method for embedding anchor bars in concrete

Country Status (1)

Country Link
CN (1) CN105672486A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351259A (en) * 2016-11-30 2017-01-25 二十二冶集团天津建设有限公司 Pipe gallery assembly type bridge frame installing method
CN107013040A (en) * 2017-06-02 2017-08-04 杭州宥盛建筑科技有限公司 The construction method of floor is poured after a kind of sleeve built-in type
CN107740497A (en) * 2017-11-07 2018-02-27 中国水利水电第十四工程局有限公司 A kind of construction method of hydraulic structure flow-passing surface pre-embedded anchoring bolts
CN108894336A (en) * 2018-09-17 2018-11-27 重庆宜喆塑胶厂 A kind of concrete embedded external member and construction method
CN110158452A (en) * 2019-06-28 2019-08-23 中国电力工程顾问集团西北电力设计院有限公司 A kind of built-in fitting and its construction method for the laying of cable bridge
CN110295711A (en) * 2019-06-28 2019-10-01 中国一冶集团有限公司 The construction method of pre-buried connector
CN110905185A (en) * 2019-12-13 2020-03-24 中冶建工集团有限公司 Overhanging I-shaped steel fixing method
CN112695897A (en) * 2020-12-30 2021-04-23 中交路桥华南工程有限公司 Embedded part embedding method and embedded part

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103953121A (en) * 2014-05-14 2014-07-30 中建七局第二建筑有限公司 Pre-buried sleeve for wall tie bar, and positioning method thereof
CN104452978A (en) * 2014-12-02 2015-03-25 中建三局集团有限公司 Beam bar anchoring sleeve pre-embedded in thin wall and construction method thereof
DE102014001514A1 (en) * 2014-02-07 2015-08-13 Josef Harrer Anchor insulation rod
CN204608996U (en) * 2015-05-08 2015-09-02 中天西北建设投资集团有限公司 The temporary fixed component of prefabricated panel
CN204919996U (en) * 2015-07-23 2015-12-30 中国新兴保信建设总公司 Pre -buried connection structure of secondary structure reinforcing bar sleeve

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102014001514A1 (en) * 2014-02-07 2015-08-13 Josef Harrer Anchor insulation rod
CN103953121A (en) * 2014-05-14 2014-07-30 中建七局第二建筑有限公司 Pre-buried sleeve for wall tie bar, and positioning method thereof
CN104452978A (en) * 2014-12-02 2015-03-25 中建三局集团有限公司 Beam bar anchoring sleeve pre-embedded in thin wall and construction method thereof
CN204608996U (en) * 2015-05-08 2015-09-02 中天西北建设投资集团有限公司 The temporary fixed component of prefabricated panel
CN204919996U (en) * 2015-07-23 2015-12-30 中国新兴保信建设总公司 Pre -buried connection structure of secondary structure reinforcing bar sleeve

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106351259A (en) * 2016-11-30 2017-01-25 二十二冶集团天津建设有限公司 Pipe gallery assembly type bridge frame installing method
CN107013040A (en) * 2017-06-02 2017-08-04 杭州宥盛建筑科技有限公司 The construction method of floor is poured after a kind of sleeve built-in type
CN107740497A (en) * 2017-11-07 2018-02-27 中国水利水电第十四工程局有限公司 A kind of construction method of hydraulic structure flow-passing surface pre-embedded anchoring bolts
CN107740497B (en) * 2017-11-07 2024-01-02 中国水利水电第十四工程局有限公司 Construction method for embedding foundation bolts on overflow surface of hydraulic building
CN108894336A (en) * 2018-09-17 2018-11-27 重庆宜喆塑胶厂 A kind of concrete embedded external member and construction method
CN110158452A (en) * 2019-06-28 2019-08-23 中国电力工程顾问集团西北电力设计院有限公司 A kind of built-in fitting and its construction method for the laying of cable bridge
CN110295711A (en) * 2019-06-28 2019-10-01 中国一冶集团有限公司 The construction method of pre-buried connector
CN110905185A (en) * 2019-12-13 2020-03-24 中冶建工集团有限公司 Overhanging I-shaped steel fixing method
CN112695897A (en) * 2020-12-30 2021-04-23 中交路桥华南工程有限公司 Embedded part embedding method and embedded part

Similar Documents

Publication Publication Date Title
CN105672486A (en) Method for embedding anchor bars in concrete
CN204112604U (en) The slip casting rebar connector of band cone tail
CN104032856B (en) A kind of precast shear wall horizontal connecting node
CN204118627U (en) A kind of pre-buried wiring electricity box being exclusively used in xoncrete structure
CN108797579A (en) The attachment device of prefabricated tubular pile and connection method
CN101914915A (en) Construction method for anti-floating anchor rod and special long auger
CN107546635A (en) The construction method of pre-buried electrical power wiring box on a kind of shear wall
CN102312427A (en) Half soil squeezing screw expansion pile forming method
CN106759269A (en) The construction method of diaphram wall in macrorelief scar stratum
CN106930278A (en) A kind of method that compromise joint pipe is used for support pile occlusion
CN106149874A (en) Prefabricated assembled concrete structure reinforcing bars Novel connecting method
CN104929129A (en) Concrete cover-weight consolidation grouting method for non-cover-weight combination of different holes through guide pipes
CN106480880B (en) Recoverable soil nailing and the construction method for using recoverable soil nail
CN209703838U (en) Steel bar connecting structure between reinforcing bar connector and precast concrete
CN208219638U (en) A kind of deep foundation pit precast stake
CN201339189Y (en) Pile hanging bracket
CN101270578A (en) Follow type anchor wire secondary slip casting construction method
CN101649746B (en) Method for arranging drain plug peripheral water stopping sheet of tunnel plug
CN109667388A (en) Steel bar connecting structure between reinforcing bar connector and precast concrete
CN211395748U (en) Superposed beam-slab structure for construction of reversed beam and consequent slab in foundation pit engineering
CN209261490U (en) A kind of infiltration starter
CN103306293A (en) Reinforcement structure and construction method for water-rich landslide
CN210500792U (en) Double-tube type steel bar connecting structure between precast concrete components
CN201747261U (en) Long twist drill for construction of anti-floating anchor rod
CN206542144U (en) A kind of prefabricated integrated line box building element

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160615