CN105672444A - Combined pipe network based rainwater partition treatment system - Google Patents
Combined pipe network based rainwater partition treatment system Download PDFInfo
- Publication number
- CN105672444A CN105672444A CN201610086648.4A CN201610086648A CN105672444A CN 105672444 A CN105672444 A CN 105672444A CN 201610086648 A CN201610086648 A CN 201610086648A CN 105672444 A CN105672444 A CN 105672444A
- Authority
- CN
- China
- Prior art keywords
- rainwater
- wall
- water inlet
- pipe
- storage pond
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F1/00—Methods, systems, or installations for draining-off sewage or storm water
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F1/00—Methods, systems, or installations for draining-off sewage or storm water
- E03F1/001—Methods, systems, or installations for draining-off sewage or storm water into a body of water
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/10—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/10—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
- E03F5/101—Dedicated additional structures, interposed or parallel to the sewer system
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F5/00—Sewerage structures
- E03F5/10—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
- E03F5/102—Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins using already existing parts of the sewer system for runoff-regulation
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F2201/00—Details, devices or methods not otherwise provided for
- E03F2201/10—Dividing the first rain flush out of the stormwater flow
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
Abstract
The invention relates to the technical field of rainwater pretreatment, in particular to a combined pipe network based rainwater partition treatment system. A pipe network region comprises a branch rainwater pipe, a branch wastewater pipe and a main wastewater pipe; the whole pipe network region is divided into rainwater treatment sub-regions with the areas of 0.2-4 square kilometers according to meshes; each rainwater treatment sub-region comprises a branch rainwater pipe, a branch wastewater pipe and a rainwater partition treatment unit; the rainwater partition treatment unit is provided with a water inlet, a wastewater outlet and a purified water outlet; the water outlets of the branch rainwater pipe and the branch wastewater pipe in the rainwater treatment sub-region are both communicated with the water inlet of the rainwater partition treatment unit in the rainwater treatment sub-region; the wastewater outlet of the rainwater partition treatment unit is communicated with the main wastewater pipe; and the purified water outlet of the rainwater partition treatment unit is connected with a natural water body. With the adoption of a fragmental treatment method, a plurality of small-sized rainwater partition treatment units are established along the pipe network, so that the problem that first rain contains later rainwater due to a flow concentration time difference of a far point and a near point of the pipe network is avoided and the rainwater treatment effect is good.
Description
Technical field
The present invention relates to rainwater preconditioning technique field, be specifically related to a kind of based on combined system pipe networkRainwater division treatment system.
Background technology
Current social, Development of Urbanization is more and more rapider, and the area in city is increasing, cityStorm Sewer Network structure becomes increasingly complex, and the processing pressure of urban rainwater treatment system is increasing.At present, Urban Rainwater Pipe Networks is divided into three kinds: separate system, combined system and mixed flow system.
As shown in Figure 1, it adopts a large rain to traditional combined system pipe network rain processing systemWater treatment system is responsible for the watershed that a slice is very large, because watershed is excessive, not fullyConsider and the time delay of rainwater on pipeline or rainwash cause early-stage rainwater and later stageRainwater mixes in a large number. For example, certain city has been built in the area near urban sewage treatment systemStorage pond, supposes that M area is apart from this storage pond 1Km, and the urban rainwater in M area passes throughPipe network is directly discharged into storage pond, and the city early-stage rainwater in M area is fully discharged into storage pondTime is T1. For the distance storage pond area far away that exceeds this region, suppose N areaBe 10km apart from the air line distance of storage pond, the city early-stage rainwater in N area is fully discharged intoThe time of storage pond is T2, and from time length, T2 obviously will be far longer than T1. And work asStorage pond is collected has expired after early-stage rainwater, and the rainwater exceeding just starts automatic-discharging to natural waterIn, storage pond from start to collect rainwater to the time starting to natural water discharge be T3. RealWhen border is moved, iff the storm-water drainage situation of taking M area into account, the i.e. initial stage in M areaRainwater can enter into the clean rainwater of sewage disposal system intermediary and later stages by storage pond and can arrangeBe put in natural water, need T3 to be greater than T1, once exceed T3, storage pond is immediately to natureWater body discharge, and the rainwater that now N area flows to storage pond still pollutes very serious initial stage rainWater, T3 is less than T2, can cause undoubtedly very serious pollution to natural water discharge.
Iff the storm-water drainage situation of considering N area, T3 is greater than T2, that N groundThe early-stage rainwater in district can enter into urban sewage treatment system by storage pond, obtains fineProcessing. But for M area, M area has a large amount of later stage clean rainwaters also to existIn the time of the early-stage rainwater in storage pond discharge N area, be discharged into urban sewage treatment systemIn, such emission behaviour can cause very large processing pressure to urban sewage system. In addition,When actual motion, the pipe network in M area and N area is generally connection situation, due to distance notWith, the delay effect on road, the early-stage rainwater in N area may severe contamination M areaLater stage clean rainwater, also can cause the unreasonable of storm-water drainage situation.
Because first rain mixes in a large number with later stage rainwater, if realization is to this region early-stage rainwaterRegulate and store completely, need to build a bulky large-scale storage pond 8, cause high cost,Its effect of regulating and storing also reduces greatly due to the mixing of first rain and later stage rainwater.
Some place also arranges multiple storage ponds rainwater is processed, but the quantity of storage pond existsWhile setting, do not consider poor problem of concentration time between aforementioned far point and near point, therefore its first rainStill have a large amount of phenomenons of mixing with later stage rainwater, rainwater treatment effect and economic benefit are stillUndesirable.
Summary of the invention
For solving the problems of the technologies described above, the invention provides the better base of a kind of rainwater treatment effectIn the rainwater division of combined system pipe network treatment system.
Technical scheme of the present invention is: a kind of rainwater division treatment system based on combined system pipe network,Pipe network region comprises rainwater arm, branch sewer and common sewer, and grid is pressed in whole pipe network regionBe divided into the rainwater of area between 0.2~4 square kilometre and process subregion, each described rainwater placeReason subregion comprises a rainwater arm, a branch sewer and a rainwater division processing unit,Described rainwater division processing unit has water inlet, outlet of sewer and pure water inlet, each rainwaterProcessing the delivery port of the interior rainwater arm of subregion and branch sewer all processes in subregion with this rainwaterRainwater division processing unit water inlet is communicated with, the outlet of sewer of described rainwater division processing unit withCommon sewer is communicated with, and pure water inlet is connected with natural water.
Further, described rainwater division processing unit is in abandoned stream well, storage pond, Vatch basinAny one.
Further, at least two described rainwater are processed the rainwater division processing unit knot in subregionStructure difference.
Further, also comprise end storage pond and sewage treatment plant, described end storage pond entersThe mouth of a river is communicated with common sewer end, and delivery port is communicated with sewage treatment plant.
Further, described rainwater division processing unit comprises abandoned stream well, the well of described abandoned stream wellBody comprises mud chamber, the separate chamber in buoyancy tank chamber and three of float chambers, and described mud chamber connectsConnect abandoned stream well water inlet pipe, described buoyancy tank chamber, float chamber connect abandoned stream well outlet pipe jointly, described inFloat chamber connects abandoned stream well abandoned stream pipe, the abandoned stream pipe mouth of pipe of described abandoned stream well respectively lower than water inlet pipe,The outlet pipe mouth of pipe, has the first overfall between described mud chamber and buoyancy tank chamber, described mud chamberAnd between float chamber, have the second overfall, the area of described the first overfall is less than the second overflowThe area of mouth, described the first overfall, the second overfall are all higher than the abandoned stream pipe mouth of pipe, described floatingThe indoor buoyancy tank that is provided with of case, in described float chamber, be provided be communicated to abandoned stream pipe abandoned stream passage and can be byThe ball float that abandoned stream passway covers, the weight of described buoyancy tank is greater than the weight of ball float, described buoyancy tankAnd be connected by transmission device between ball float.
Further, in the well body of described abandoned stream well, first of orthogonal vertical layout is setBarricade the second barricade, surrounds mud chamber, described first between described the first barricade and well body inwallBetween a part, the second barricade and the well body inwall of barricade, surround buoyancy tank chamber, described the first barricadeAnother part, the second barricade and well body inwall between surround float chamber, described the first overfallOpen in a part for the first barricade, described the second overfall is opened the another part at the first barricadeOn.
Further, described rainwater division processing unit comprises the Buffer Pool being communicated with common sewer,The drain outlet end of described Buffer Pool is provided with flow control valve, and described Buffer Pool is other to be provided withThe first rain storage pond that is communicated with it, process storage pond and urgent flood discharge passage online; Described just rainOn the shared sidewall body of wall of storage pond and described Buffer Pool, be provided with just rain storage pond water inlet; InstituteState on the shared sidewall body of wall of online processing storage pond and described Buffer Pool and be provided with online processingStorage pond water inlet; On the shared sidewall body of wall of described urgent flood discharge passage and described Buffer Pool, establishBe equipped with urgent flood discharge passage water inlet; Described just rain storage pond water inlet and described urgent flood discharge are logicalOn road water inlet, be provided with weir gate or hydraulic gate; Described online processing storage pond water inletWater inlet lowest water level line A be more than or equal to the water inlet of described just rain storage pond water inletMaximum water level B; The water inlet maximum water level C of described online processing storage pond water inlet is littleIn or equal the water inlet lowest water level line D of described urgent flood discharge passage water inlet.
Further, described just rain storage pond is by the sidewall body of wall perpendicular to described Buffer PoolThe 4th body of wall, the second body of wall and be parallel to described Buffer Pool sidewall body of wall the 3rd body of wall andThe sidewall body of wall of described Buffer Pool surrounds, and described online processing storage pond is by described Buffer PoolSidewall body of wall, the first body of wall, the 3rd body of wall and the 4th body of wall surround; On described the 4th body of wall, establishBe equipped with gate.
Further, in described online processing storage pond, be provided with waterpower particle separator, waterDistrict and sewage gallery; Described sewage gallery is positioned at the one end near the sidewall body of wall of described Buffer Pool;The pond bottom face of described sewage gallery is lower than the pond bottom face of described online processing storage pond; DescribedAt the bottom of online pond of processing storage pond and described sewage gallery, all there is the gradient; Described water district passes throughThe first body of wall, the 3rd body of wall, the 4th body of wall and the 7th body of wall surround; The height of described the 7th body of wallDegree is less than or equal to the height of described the 3rd body of wall; Flap type punching is installed on described the 7th body of wallWash door.
Further, the sidewall body of wall of described urgent flood discharge passage by described Buffer Pool, described inJust the second body of wall, the 3rd body of wall, first body of wall of rain storage pond and be parallel to described Buffer PoolThe 3rd body of wall the 5th body of wall and be parallel to the 6th body of wall of the second body of wall of described Buffer PoolBecome; At the bottom of the pond of described urgent flood discharge passage, be provided with the gradient; The draining of described urgent flood discharge passageThe port of export is communicated with natural water.
Beneficial effect of the present invention: pipe network is divided into area at the rainwater place of 0.2-4 square kilometreReason subregion, each rainwater is processed subregion and is set up independent rainwater division processing unit, each rainwaterThe rainwater that subregion processing unit is processed in subregion each rainwater is processed. Due to rainwater processingDivision area is less, the rainwater of distance rainwater division processing unit far point and near point in each subregionConflux less to the time difference of rainwater division processing unit water inlet, first rain and later stage rainwater mixedRight reduction greatly, the obvious processing effect of rainwater improves. In addition, each rainwater is processed subregionBy rainwater division processing unit separately, the rainwater in subregion is processed different subregion rainThe processing procedure of water can be carried out simultaneously, has improved greatly the efficiency of rainwater processing. Compared toIn whole region, build total large-scale rainwater regulating pondage system, section of the present invention absolute constructionVolume is less, and first rain collection purity is higher, has saved a large amount of man power and materials, has realized warpJi maximizing the benefits.
Brief description of the drawings
Fig. 1 is the rain processing system structural representation of existing combined system pipe network;
Fig. 2 is structural representation of the present invention;
Fig. 3 is a kind of abandoned stream well construction schematic diagram wherein;
Fig. 4 is the top view of Fig. 3;
Fig. 5 is the wherein structural representation of a kind of embodiment of rainwater division of the present invention processing unit;
Fig. 6 is Fig. 5 Buffer Pool structural representation;
Fig. 7 is urgent flood discharge passage X-X sectional schematic diagram;
Fig. 8 is first rain storage pond Y-Y sectional schematic diagram;
Fig. 9 is the online storage pond Z-Z sectional schematic diagram of processing;
Wherein: 1.1. far point rainwater is processed all the other rainwater of subregion 1.2. and processed subregion 2. rainwater arms3. branch sewer 4. abandoned stream well 5. common sewer 6. sewage treatment plant's 7. natural waters 8. are large-scaleStorage pond 9. end storage pond 10. well body 11. water inlet pipe 12. outlet pipe 13. mud chambers 14.Buoyancy tank chamber 15. float chamber's 16. ball float 17. first buoyancy tank 18. abandoned stream pipe 19. first overfalls20. second overfall 21. spilled water hole 22. assembly pulley 23. first barricade 24. second barricades 25.Abandoned stream passage sewage overflow mouth in 26. dry season 27. buoyancy tank limited block 28. collecting pipe 29. Buffer PoolsThe 30. flow control valves 31. just urgent flood discharge of rain storage pond 32. online processing storage pond 33. are logicalThe first rain storage pond water inlet 35. in road 34. surges and rotates the water inlet of the online processing storage pond of weir gate 36.Mouth 37. urgent flood discharge passage water inlet 38. Hydro-automatic gate 39. self-cleaning horizontal grates40. gate 41. intelligent wash device 42. collecting-tank 43. waterpower particle separators, 44. flap typesRinse door 45. water district 46. sewage gallery 47. first bodies of wall; 48. second bodies of wall 49. the 3rdBody of wall 50. the 4th body of wall 51. the 5th body of wall 52. the 6th body of wall 53. the 7th body of wall 54. rotating shafts55. second buoyancy tank 56. weir gate plates.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, to the technical side in the embodiment of the present inventionCase is clearly and completely described, and obviously, described embodiment is only one of the present inventionDivide embodiment, instead of whole embodiment. Based on the embodiment in the present invention, this area is generalLogical technical staff is not making all other embodiment of obtaining under creative work prerequisiteBelong to the scope of protection of the invention.
Be illustrated in figure 2 the structural representation of the rainwater division treatment system based on combined system pipe network,This system comprise rainwater arm 2 in pipe network region, branch sewer 3 and with sewage treatment plant 6The common sewer 5 being communicated with. Multiple rainwater processing subregions that grid is divided are pressed in whole pipe network region,Rainwater is processed subregion and is comprised far point rainwater processing subregion 1.1 Hes farthest apart from sewage treatment plant 6All the other rainwater are processed subregion 1.2, and all the other rainwater are processed in subregion 1.2 and are provided with collecting pipe 28. OftenIndividual rainwater is processed the area of subregion between 0.2~4 square kilometre, and each rainwater is processed in subregionInclude a rainwater arm 2, branch sewer 3 and a rainwater division processing unit 4.Rainwater division processing unit 4 can be any one in abandoned stream well, Vatch basin, storage pond.Have at least two rainwater to process the rainwater division processing unit 4 structure differences in subregion.
Describe taking rainwater division processing unit 4 as abandoned stream well, the structure of abandoned stream well has multiple,The all abandoned streams well that can realize function of the present invention all should drop in protection domain of the present invention, as figure3-4 is depicted as the wherein structural representation of a kind of embodiment of abandoned stream well. Abandoned stream Jing Bao of the present inventionDraw together well body 10, interior mud chamber 13, buoyancy tank chamber 14 and the float chamber 15 of arranging of described well body 10Three separate chambers, described precipitation Room 13 connect water inlet pipe 11, described buoyancy tank chamber 14,The common outlet pipe 12 that connects in float chamber 15, described float chamber 15 connects abandoned stream pipe 18, described inAbandoned stream pipe 18 mouths of pipe are respectively lower than water inlet pipe 11, outlet pipe 12 mouths of pipe, described mud chamber 13And between buoyancy tank chamber 14, have the first overfall 19, described mud chamber 13 and float chamber 15 itBetween have the second overfall 20, the area of described the first overfall 19 is less than the second overfall 20Area, described the first overfall 19, the second overfall 20 be all higher than abandoned stream pipe 18 mouths of pipe,In described buoyancy tank chamber 14, be provided with the first buoyancy tank 17, in described float chamber 15, be provided with to be communicated to and abandonThe abandoned stream passage 25 of stream pipe 18 and the ball float 16 that logical abandoned stream 25 road junctions can be covered, described theThe weight of one buoyancy tank 17 is greater than the weight of ball float 16, described the first buoyancy tank 17 and ball float 16Between connect by transmission device.
In technique scheme, interior first of the orthogonal vertical layout that arranges of described well body 10Barricade 23 and the second barricade 24, it is heavy between described the first barricade 23 and well body 10 inwalls, to surroundChamber, shallow lake 13, the part of described the first barricade 23, the second barricade 24 and well body 10 inwalls itBetween surround buoyancy tank chamber 14, another part of described the first barricade 23, the second barricade 24 and wellBetween body 10 inwalls, surround float chamber 15. Described the first overfall 19 is opened at the first barricade 23A part on, described the second overfall 20 is opened on another part of the first barricade 23.
In technique scheme, described the second overfall 20 bottoms have sewage overflow mouth in dry season26, described dry season, sewage overflow mouth 26 was offered lower than the second overfall 20. Drought stream when fine daySewage enters accurate abandoned stream well by water inlet pipe 11, after mud chamber's 13 precipitations, flows by droughtSewage overflow mouth 26 enters float chamber 15, then discharges by abandoned stream pipe 18. Because drought stream is dirtyWater overfall 26 height are lower than the second overfall 20 and the first overfall 19, and dry flow sewage is notCan enter buoyancy tank chamber 14, can avoid buoyancy tank chamber 14 spilled water holes 21 to stop up.
In technique scheme, described jockey comprises connection cord, described connection cord one end withThe first buoyancy tank 17 is fixing, and the other end is fixing with ball float 16 through assembly pulley 103.
In technique scheme, between described buoyancy tank chamber 14 and float chamber 15, bottom has sluicingHole 21, the aperture of described spilled water hole 21 is less than the area of outlet pipe 12 and abandoned stream pipe 18 mouths of pipe.
In technique scheme, described buoyancy tank chamber 14 inner bottom parts are provided with buoyancy tank limited block 27.
Rainwater of the present invention enters accurate abandoned stream well by water inlet pipe 11, after mud chamber's 13 precipitations,Enter respectively buoyancy tank chamber 14 and float chamber 15 by the first overfall 19, the second overfall 20.The first buoyancy tank 17 is connected by assembly pulley 103 with ball float 16. Because the weight of buoyancy tank 14 is largeIn the weight of ball float, under original state the first buoyancy tank 17 in extreme lower position, and ball float 16 placesIn extreme higher position (being opening), if begin to rain, just rain can be abandoned by abandoned stream pipe 18Stream. In the time that rainfall increases gradually, the water level in buoyancy tank chamber 14 raises gradually, reaches and stops abandoningFlowing water position, now the first buoyancy tank 17 is issued to extreme higher position in buoyancy, and ball float 16 reachesTo extreme lower position (being closed condition). Because ball float 16 is blocked abandoned stream passage 25, now rainWater can be in the interior gathering in float chamber 15, in the time that the interior water level in float chamber 15 is increased to outlet pipe 13 place,Rainwater is discharged from outlet pipe 13, and now rainwater has become comparatively clean, has reached pretreatedEffect. This device needs periodic maintenance, the mud in cleaning mud chamber. Wherein, the first overflowMouthfuls 19, the openings of sizes ratio of the second overfall 20 and stop abandoned stream water level, can be according to differenceThe volume settings of the first rainfall of situation.
Rainwater division processing unit 4 can also be another kind of rain water treatment structure, and this structure comprisesThe Buffer Pool 29 being connected with common sewer 5; The drain outlet end of Buffer Pool 29 is provided with flowBy-pass valve control 30, is provided with 1% gradient at the bottom of the pond of Buffer Pool 29, flow rate control gate 30 byFlow sensor and electric gate valve composition, flow rate control gate is set a constant flow at ordinary times,The sewage that ensures 5 li of common sewers enters sewage treatment plant with a constant flow; Buffer Pool29 other be provided with the first rain storage pond 31 that is communicated with it, process storage pond 32 and promptly let out onlineFlood passage 33; Just rain storage pond 31 connects by first rain storage pond water inlet 34 and Buffer Pool 29Logical; Just on rain storage pond water inlet 34, be provided with the rotation weir gate 35 that surges; Online processing regulated and storedPond 32 is communicated with Buffer Pool 29 by online processing storage pond water inlet 36; Urgent flood discharge is logicalRoad 33 is communicated with Buffer Pool 29 by urgent flood discharge passage water inlet 37; Urgent flood discharge passageOn water inlet 37, be provided with Hydro-automatic gate 38; Online processing storage pond water inlet 36Water inlet lowest water level line A equals the just water inlet maximum water level of rain storage pond water inlet 34B; It is logical that the online water inlet maximum water level C that processes storage pond water inlet 36 equals urgent flood dischargeThe water inlet lowest water level line D of road water inlet 37. Wherein, first rain storage pond water inlet 34 HesThe weir gate or the hydraulic gate that on described urgent flood discharge passage water inlet 37, arrange are not necessarilyConcrete structure in the present embodiment, as long as but this weir gate or hydraulic gate can be according to describedThe water level of the interior just rain amount of rainfall of Buffer Pool 29 is realized and being opened and closed automatically.
Wherein, Buffer Pool structural representation is as shown in Figure 6 known, the water inlet of Buffer Pool 29End is communicated with the sewage effluent end of combined system pipeline 1, and the water outlet end of Buffer Pool 29 is communicated withSewage treatment plant, the water outlet end of Buffer Pool 29 is provided with to ensure sewerage discharging flowFlow control valve, on the sidewall of Buffer Pool 29, be provided be communicated with first rain storage pond 31 at the beginning ofRain storage pond water inlet 34, these first rain storage pond water inlet 34 places are provided with self-cleaning HORIZONTAL PLAIDGrid 39 and the rotation weir gate 35 that surges, the rotation weir gate 35 that surges comprises that being fixedly installed just rain regulates and storesThe oil cylinder of pond water inlet 34 1 sides, hydraulic oil cylinder driving end and door-plate one side end face are hinged; Door-plate is anotherOne side end face is hinged on just rain storage pond water inlet 34 opposite sides by rotating shaft, passes through oil cylinderDrive, door-plate can swing centered by rotating shaft, thereby makes just rain storage pond water inlet34 open or close, and the oil cylinder of the present embodiment can also be equipped with automatic control system, automatically controlWhether system processed can control oil cylinder work automatically according to the height of water level, and then reaches automatic controlSystem just rain storage pond water inlet 34 is opened or is closed, and reaches full automatic object. BufferingOn the sidewall in pond 29, be also provided with the online processing storage pond being communicated with online processing storage pond 32Water inlet 36, processes online storage pond water inlet 36 places self-cleaning horizontal grate 39 is installed;On the sidewall of Buffer Pool 29, be also provided with the urgent flood discharge passage being communicated with urgent flood discharge passage 33Water inlet 37, urgent flood discharge passage water inlet 37 places are provided with Hydro-automatic gate 38. WhereinGrille strip, oil cylinder that comprise self-cleaning horizontal grate 39 framework, level are fixed on framework prop upFrame, the second hydraulic jack and rake teeth, cylinder bracket comprises stiff end and movable end, stiff end is perpendicularBetween being directly fixed on framework below, totally four of movable ends, are vertically arranged on framework activityUpper and lower side and the framework of end are slidably connected, and between four movable ends, connect by connecting rod. The second liquidCompressing cylinder horizontal symmetrical is arranged at stiff end both sides, and the cylinder base of oil cylinder is fixed on stiff end,Piston rod is fixed on movable end, and along with the work of the second hydraulic jack, piston rod substitutes activityEnd is along framework horizontal slip. Rake teeth is longitudinally uniformly distributed on movable end, corresponding with grille strip.
From the urgent flood discharge passage X-X sectional schematic diagram shown in Fig. 5 and Fig. 7, promptly let outFlood passage 33 is by the of the sidewall body of wall of described Buffer Pool 29, described just rain storage pond 31Two bodies of wall 48, the 3rd body of wall 49, the first body of wall 47 and be parallel to the 3rd of Buffer Pool 29The 5th body of wall 51 of body of wall 49 and be parallel to the 6th body of wall 52 of the second body of wall 48 of Buffer PoolSurround; At the bottom of the pond of urgent flood discharge passage 33, be provided with the gradient; The draining of urgent flood discharge passage 33The port of export is communicated with natural water. Urgent flood discharge passage water inlet 37 places of urgent flood discharge passage 33Be provided with Hydro-automatic gate 38, Hydro-automatic gate 38 comprises the rotating shaft being arranged in water channel54, the second buoyancy tank 55 and weir gate plate 56, described buoyancy tank 55 is fixed by buoyancy tank support armIn one end of rotating shaft 54, described weir gate plate 56 is fixed on rotation by weir gate plate support armOn axle 54, buoyancy tank 55 and weir gate plate 56 are positioned at the homonymy of rotating shaft 54. Its operation principle is:The buoyancy tank chamber water inlet height of buoyancy tank chamber is by calculating, and the water level indoor when buoyancy tank is highWhen degree reaches the height of buoyancy tank chamber water inlet, the suffered buoyancy of buoyancy tank 55 just in time overcomes its gravity,Buoyancy tank 55 can float. In the time raining in torrents, the water level in the water channel of rain drainage pipe startsRise, when the height of accumulating gradually when the water before weir gate covers the height of buoyancy tank chamber water inlet, needTo carry out flood discharge to rainwater. Now the rainwater moment in water channel is poured into buoyancy tank chamber, and moment withThe height of buoyancy tank chamber water inlet is concordant. Now its gravity of the buoyancy overcoming of buoyancy tank, buoyancy tank is to floatingRise. Because buoyancy tank 55 and weir gate plate 56 are all fixed on rotating shaft, and rotating shaft canBetween two water channel side walls, rotate, again because weir gate plate 56 and buoyancy tank 55 are positioned at the same of rotating shaftSide, so weir gate plate 56 moves upward under the drive of rotating shaft, weir gate reaches moment unlatching.Due to orientation draining under being adopting, floating thing is all tackled by weir gate plate, has prevented the dirt of water bodyDye. In the time that the water level of water channel declines gradually, the indoor water that no longer includes of buoyancy tank enters, and buoyancy tank is indoorWater is discharged slowly by the small-bore buoyancy tank chamber delivery port on the sidewall of buoyancy tank chamber, and buoyancy tank is indoorLiquid level slowly declines, and buoyancy reduces gradually, and buoyancy tank 55 slowly sinks, and weir gate plate 56 is in rotationUnder the drive of axle, slowly close, slower owing to closing, can prevent the damage of weir gate plate.Close rear weir gate plate and weir gate sealing ring close contact, realized good sealing. Flow into urgentThe early-stage rainwater of flood discharge passage 33 is directly discharged into natural water.
From the first rain storage pond Y-Y sectional schematic diagram shown in Fig. 5 and Fig. 8, first rain is regulated and storedPond 31 is by the 4th body of wall 50, second wall of the sidewall body of wall perpendicular to described Buffer Pool 29Body 48 and be parallel to the 3rd body of wall 49 of sidewall body of wall of described Buffer Pool 29 and described slowThe sidewall body of wall that rushes pond 29 surrounds. Just in rain storage pond 31, be also provided with intelligent wash device41; Intelligent wash device 41 comprises automation control system, liquid level sensor, flusherAnd submersible sewage pump; Flusher comprises water pump, outlet pipe assembly and motor; Water pump and outlet pipe are totalBetween one-tenth, connect by the swivel joint that can rotate along horizontal plane; Outlet pipe assembly and machine shaftConnect; The pivot of machine shaft and swivel joint is positioned on same vertical curve; Level sensingDevice, motor, submersible sewage pump and water pump are all electrically connected with automation control system. Automation control systemSystem is controlled submersible sewage pump the water of first rain storage pond is outwards extracted out, and first rain storage pond water level starts to declineTime control that flusher stirs at the bottom of to first rain storage pond and fixed-direction rinses, rain is adjusted originallyHold pool inner water position while dropping to preset height, automation control system control flusher is to first rainStorage pond is rotated flushing. When just rain storage pond water is emptying, automation control system control punchingCleaning device is rotated flushing to first rain storage pond; After spin rinse finishes, automation control systemSystem is controlled flusher first rain storage pond is carried out to the flushing of stain fixed point; Described flusher at the beginning ofAfter rain storage pond is rotated and rinses and finish, just rain storage pond bottom field of camera collection, andThis picture signal is passed to automation control system, and automation control system is to first rain storage pondAt the bottom of pond, carry out the division of intelligent net region, if just rain storage pond bottom exists stain, basisThe coordinate relation of stain position and flusher, controls water pump water outlet lift and flusher requiredThe anglec of rotation, carries out point-to-point cleaning to stain position. Just in rain storage pond 31, be provided with collectionPond 42; At the bottom of the pond of the pond bottom face of described collecting-tank 42 lower than described just rain storage pond 31End face. Just at the bottom of the pond of rain storage pond 31 and described collecting-tank 42, all there is the gradient.
From the online processing storage pond Z-Z sectional schematic diagram shown in Fig. 5 and Fig. 9, onlineProcess sidewall body of wall by described Buffer Pool 29 of storage pond 32, the first body of wall 47, the 3rdBody of wall 49 and the 4th body of wall 50 surround; On the 4th body of wall 50, be provided with gate 40. Online placeIn reason storage pond 32, be provided with waterpower particle separator 43, flap type rinses door 44, water district45 and sewage gallery 46; Water district 45 is by the first body of wall 47, the 3rd body of wall 49, the 4thBody of wall 50 and the 7th body of wall 53 surround; The height of the 7th body of wall 53 is less than or equal to the 3rd wallThe height of body 49; Flap type is installed on the 7th body of wall 53 and rinses door 44; Online processing adjustedAt the bottom of holding the pond of pond 32 and sewage gallery 46, all there is the gradient; And waterpower particle separator 43 wrapsDraw together support and water fender; Water fender is parallel to each other and is connected on described support; Water fender and levelThere is inclination angle in direction; The top of water fender is connected with the described tank of crossing. Just rain storage pond 31 HesDescribed online processing storage pond 32 is communicated with by gate 40. The online storage pond 32 of processing filtersAfter rainwater by cross tank overflow to natural water.
Whole pipe network region is divided into multiple little rainwater division processing unit 4 by grid, realizesTo the burst processing of rainwater. This processing mode, because pipe network route is short, has shortened rain greatlyThe acquisition time of moisture district processing unit 4 far points and near point rainwater is poor, has prevented first rain and later stageThe mixing of rainwater, thus make the treatment effect of rainwater more good. And each rainwater division placeReason unit 4 can be processed rainwater simultaneously, and rainwater treatment effeciency improves greatly.
The above, be only the specific embodiment of the present invention, it should be pointed out that any basis of being familiar withThe technical staff in field in the disclosed technical scope of the present invention, the variation that can expect easily orReplace, within all should being encompassed in protection scope of the present invention.
Claims (10)
1. the rainwater division treatment system based on combined system pipe network, pipe network region comprises rainwaterArm (2), branch sewer (3) and common sewer (5), it is characterized in that: whole pipe networkRegion is divided into the rainwater of area between 0.2~4 square kilometre by grid and processes subregion, eachDescribed rainwater is processed subregion and is comprised a rainwater arm (2), a branch sewer (3) andIndividual rainwater division processing unit (4), described rainwater division processing unit (4) has water inlet,Outlet of sewer and pure water inlet, each rainwater is processed the interior rainwater arm (2) of subregion and sewage props upThe delivery port of pipe (3) all enters with the rainwater division processing unit (4) that this rainwater is processed in subregionThe mouth of a river is communicated with, the outlet of sewer of described rainwater division processing unit (4) and common sewer (5)Be communicated with, pure water inlet is connected with natural water (7).
2. the rainwater division treatment system based on combined system pipe network as claimed in claim 1, itsBe characterised in that: described rainwater division processing unit (4) is abandoned stream well, storage pond, Vatch basinIn any one.
3. the rainwater division treatment system based on combined system pipe network as claimed in claim 1, itsBe characterised in that: at least two described rainwater are processed the rainwater division processing unit (4) in subregionStructure difference.
4. the rainwater division treatment system based on combined system pipe network as claimed in claim 1, itsBe characterised in that: also comprise end storage pond (9) and sewage treatment plant (6), described end is adjustedHold pond (9) water inlet and be communicated with common sewer (5) end, delivery port and sewage treatment plant (6)Be communicated with.
5. the rainwater division treatment system based on combined system pipe network as claimed in claim 2, itsBe characterised in that: described rainwater division processing unit (8) comprises abandoned stream well, described abandoned stream wellWell body (10) comprises mud chamber (13), buoyancy tank chamber (14) and (15) three of float chambers phaseChamber independently mutually, described mud chamber (13) connect abandoned stream well (4) water inlet pipe, described floatingCase chamber (14), float chamber (15) connect abandoned stream well outlet pipe (12), described float chamber jointly(15) connect abandoned stream well abandoned stream pipe (18), abandoned stream pipe (18) pipe of described abandoned stream well (4)Mouthful respectively lower than water inlet pipe (11), outlet pipe (12) mouth of pipe, described mud chamber (13) withBetween buoyancy tank chamber (14), have the first overfall (19), described mud chamber (13) and ball floatBetween chamber (15), have the second overfall (20), the area of described the first overfall (19)Be less than the area of the second overfall (20), described the first overfall (19), the second overfall(20) all higher than abandoned stream pipe (18) mouth of pipe, in described buoyancy tank chamber (14), be provided with buoyancy tank (17),In described float chamber (15), be provided be communicated to abandoned stream pipe (18) abandoned stream passage (25) and canThe ball float (16) that abandoned stream passway is covered, the weight of described buoyancy tank (17) is greater than ball float (16)Weight, between described buoyancy tank (17) and ball float (16), be connected by transmission device.
6. the rainwater division treatment system based on combined system pipe network as claimed in claim 5, itsBe characterised in that: in the well body (10) of described abandoned stream well (4), orthogonal vertical cloth is setThe first barricade (23) of putting and the second barricade (24), described the first barricade (23) and well body(10) between inwall, surround mud chamber (13), the part of described the first barricade (23),Between the second barricade (24) and well body (10) inwall, surround buoyancy tank chamber (14), described firstBetween another part, the second barricade (24) and well body (10) inwall of barricade (23), surroundFloat chamber (15), described the first overfall (19) is opened the part in the first barricade (23)Upper, described the second overfall (20) is opened on another part of the first barricade (23).
7. the rainwater division treatment system based on combined system pipe network as claimed in claim 2, itsBe characterised in that: described rainwater division processing unit (4) comprises and being communicated with common sewer (5)Buffer Pool (29), the drain outlet end of described Buffer Pool (29) is provided with flow control valve(3), described Buffer Pool (29) other be provided with the first rain storage pond (31) that is communicated with it,Line is processed storage pond (32) and urgent flood discharge passage (33); Described just rain storage pond (31)With on the shared sidewall body of wall of described Buffer Pool (29), be provided with just rain storage pond water inlet (34);On the shared sidewall body of wall of described online processing storage pond (32) and described Buffer Pool (29), establishBe equipped with online processing storage pond water inlet (36); Described urgent flood discharge passage (33) with described inOn the shared sidewall body of wall of Buffer Pool (29), be provided with urgent flood discharge passage water inlet (37);Described just rain storage pond water inlet (34) and described urgent flood discharge passage water inlet (37) are all upperBe provided with weir gate or hydraulic gate; The water inlet of described online processing storage pond water inlet (36)Mouth lowest water level line (A) is more than or equal to the described just water inlet of rain storage pond water inlet (34)Mouth maximum water level (B); The water inlet of described online processing storage pond water inlet (36)High-water line (C) is less than or equal to the water inlet of described urgent flood discharge passage water inlet (37)Lowest water level line (D).
8. the rainwater division treatment system based on combined system pipe network as claimed in claim 7, itsBe characterised in that: described just rain storage pond (31) is by the side perpendicular to described Buffer Pool (29)The 4th body of wall (50), second body of wall (48) of wall body of wall and be parallel to described Buffer Pool (29)The 3rd body of wall (49) of sidewall body of wall and the sidewall body of wall of described Buffer Pool (29) surround,Described online processing storage pond (32) is by the sidewall body of wall, first of described Buffer Pool (29)Body of wall (47), the 3rd body of wall (49) and the 4th body of wall (50) surround; Described the 4th body of wall(50) on, be provided with gate (40).
9. the rainwater division treatment system based on combined system pipe network as claimed in claim 8, itsBe characterised in that: in described online processing storage pond (32), be provided with waterpower particle separator (43),Water district (45) and sewage gallery (46); Described sewage gallery (46) be positioned near described inOne end of the sidewall body of wall of Buffer Pool (29); The pond bottom face of described sewage gallery (46) is lowIn the pond bottom face of described online processing storage pond (32); Described online processing storage pond (32)With at the bottom of the pond of described sewage gallery (46), all there is the gradient; Described water district (45) is by theOne body of wall (47), the 3rd body of wall (49), the 4th body of wall (50) and the 7th body of wall (53) encloseBecome; The height of described the 7th body of wall (53) is less than or equal to the height of described the 3rd body of wall (49)Degree; Flap type is installed on described the 7th body of wall (53) and rinses door (44).
10. the rainwater division treatment system based on combined system pipe network as claimed in claim 9,It is characterized in that: described urgent flood discharge passage (33) is by the sidewall of described Buffer Pool (29)Second body of wall (48) of body of wall, described just rain storage pond (31), the 3rd body of wall (49), theOne body of wall (47) and be parallel to described Buffer Pool (29) the 3rd body of wall (49) the 5thBody of wall (51) and be parallel to the 6th body of wall (52) of second body of wall (48) of described Buffer PoolSurround; At the bottom of the pond of described urgent flood discharge passage (33), be provided with the gradient; Described urgent flood discharge is logicalThe drain outlet end in road (33) is communicated with natural water.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610086648.4A CN105672444B (en) | 2016-02-15 | 2016-02-15 | Rainwater division processing system based on combined system pipe network |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610086648.4A CN105672444B (en) | 2016-02-15 | 2016-02-15 | Rainwater division processing system based on combined system pipe network |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105672444A true CN105672444A (en) | 2016-06-15 |
CN105672444B CN105672444B (en) | 2018-03-02 |
Family
ID=56304460
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610086648.4A Active CN105672444B (en) | 2016-02-15 | 2016-02-15 | Rainwater division processing system based on combined system pipe network |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105672444B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105888031A (en) * | 2016-04-26 | 2016-08-24 | 武汉圣禹排水系统有限公司 | Rainwater partition split-flow system based on combined system pipe network |
CN106545069A (en) * | 2016-12-09 | 2017-03-29 | 南京工业大学 | Method for treating urban black and odorous water by serially connecting sewage interception and collection pipes |
CN106638889A (en) * | 2016-12-30 | 2017-05-10 | 武汉圣禹排水系统有限公司 | Un-obvious initial rain characteristic online fragment treatment discharge system under combined system or mixed system and control method of discharge system |
CN110847518A (en) * | 2019-11-21 | 2020-02-28 | 江苏环保产业技术研究院股份公司 | Industrial factory building initial rainwater collecting and processing system and collecting and processing method thereof |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005256433A (en) * | 2004-03-11 | 2005-09-22 | Jfe Engineering Kk | Treated sewage and rainwater sending and draining system |
DE202009010367U1 (en) * | 2009-07-31 | 2009-11-26 | Medam, Jürgen | Device for separating rainwater from chemically, biologically and / or toxic polluted wastewater |
CN102776949A (en) * | 2012-08-14 | 2012-11-14 | 上海市城市建设设计研究总院 | Separately-built type rainwater storage system |
JP2013159925A (en) * | 2012-02-02 | 2013-08-19 | Toshiba Corp | Sewage treatment system |
CN104763038A (en) * | 2015-04-10 | 2015-07-08 | 浙江省水利水电勘测设计院 | Initial rainwater discarding system and discarding method thereof |
CN205475586U (en) * | 2016-02-15 | 2016-08-17 | 武汉圣禹排水系统有限公司 | Rainwater subregion processing system based on confluence tubulation net |
-
2016
- 2016-02-15 CN CN201610086648.4A patent/CN105672444B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005256433A (en) * | 2004-03-11 | 2005-09-22 | Jfe Engineering Kk | Treated sewage and rainwater sending and draining system |
DE202009010367U1 (en) * | 2009-07-31 | 2009-11-26 | Medam, Jürgen | Device for separating rainwater from chemically, biologically and / or toxic polluted wastewater |
JP2013159925A (en) * | 2012-02-02 | 2013-08-19 | Toshiba Corp | Sewage treatment system |
CN102776949A (en) * | 2012-08-14 | 2012-11-14 | 上海市城市建设设计研究总院 | Separately-built type rainwater storage system |
CN104763038A (en) * | 2015-04-10 | 2015-07-08 | 浙江省水利水电勘测设计院 | Initial rainwater discarding system and discarding method thereof |
CN205475586U (en) * | 2016-02-15 | 2016-08-17 | 武汉圣禹排水系统有限公司 | Rainwater subregion processing system based on confluence tubulation net |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105888031A (en) * | 2016-04-26 | 2016-08-24 | 武汉圣禹排水系统有限公司 | Rainwater partition split-flow system based on combined system pipe network |
CN106545069A (en) * | 2016-12-09 | 2017-03-29 | 南京工业大学 | Method for treating urban black and odorous water by serially connecting sewage interception and collection pipes |
CN106638889A (en) * | 2016-12-30 | 2017-05-10 | 武汉圣禹排水系统有限公司 | Un-obvious initial rain characteristic online fragment treatment discharge system under combined system or mixed system and control method of discharge system |
CN110847518A (en) * | 2019-11-21 | 2020-02-28 | 江苏环保产业技术研究院股份公司 | Industrial factory building initial rainwater collecting and processing system and collecting and processing method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN105672444B (en) | 2018-03-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105625545B (en) | A kind of region fragment rain processing system based on separate system pipe network | |
CN105544698B (en) | A kind of region fragment rain water drainage processing system based on separate system pipe network | |
CN105544697B (en) | Region burst rainwater based on combined system pipe network shunts, regulated and stored and processing system | |
CN207469397U (en) | Rain sewage is regulated and stored processing system | |
CN105155615A (en) | Initial rainwater collection and treatment system having self-cleaning function | |
CN204781084U (en) | Processing system is collected from cleaning function's first rain in area | |
CN105714913B (en) | A kind of region fragment rainwater shunting processing system based on separate system pipe network | |
CN205475657U (en) | Confluence system is rain regulation processing system just | |
CN105625555B (en) | A kind of rainwater shunting of combined system, regulate and store and processing system | |
CN110984351A (en) | Automatic diverging device of initial stage rainwater | |
CN105863021A (en) | Fragmentation closure regulation and storage discharging system | |
CN103590484B (en) | Automatic hydraulic control leaping weir initial rainwater catch basin and flow closure method | |
CN205475586U (en) | Rainwater subregion processing system based on confluence tubulation net | |
CN105672444A (en) | Combined pipe network based rainwater partition treatment system | |
CN107587595A (en) | A kind of system comprising storage pond and online processing pond | |
CN207959470U (en) | A kind of system including storage pond and online processing pond | |
CN105569163B (en) | Region burst rain processing system based on mixed flow tubulation net | |
CN205475588U (en) | Regional burst rainwater processing system based on reposition of redundant personnel tubulation net | |
CN105804200A (en) | Sectioned intercepting and online treatment and discharging system | |
CN205637026U (en) | Regional burst rainwater processing system based on mixed flow tubulation net | |
CN205475587U (en) | Regional burst rainwater reposition of redundant personnel processing system based on reposition of redundant personnel tubulation net | |
CN205636892U (en) | Reposition of redundant personnel of regional burst rainwater, regulation and processing system based on mixed flow tubulation net | |
CN205637032U (en) | Burst regulation discharge system that dams | |
CN104975649A (en) | Separate system type initial rainwater regulation and storage pool | |
CN208363234U (en) | Overflow well with float flashboards for controlling flow of closure pipeline |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: No. 509 Weihu Road, Shamao Street, Hannan District, Wuhan City, Hubei Province, 430090 Patentee after: Wuhan Shengyu Smart Ecological Environmental Protection Co.,Ltd. Address before: 430056 zhuanyang science and Technology Industrial Park, Wuhan Economic and Technological Development Zone, Wuhan City, Hubei Province Patentee before: WUHAN SHENGYU DRAINAGE SYSTEM Co.,Ltd. |