A kind of construction method and structure of pin-connected panel standard relocation housing Download PDFInfo
- Publication number
- CN105649207B CN105649207B CN201510113456.3A CN201510113456A CN105649207B CN 105649207 B CN105649207 B CN 105649207B CN 201510113456 A CN201510113456 A CN 201510113456A CN 105649207 B CN105649207 B CN 105649207B
- Authority
- CN
- China
- Prior art keywords
- plug connector
- column
- framework
- standard relocation
- relocation housing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
Landscapes
- Building Environments (AREA)
Abstract
The invention discloses a kind of construction methods and structure of pin-connected panel standard relocation housing, and this method is using standardization production method, and during assembly in addition to frame is connected by screw bolts, all clampings of rest part or inserting mode, entire assembly process is without welding.Frame all bends forming using the Q235 hot-dip galvanizing sheet steels of 3mm thickness, and intensity height is not easy to get rusty, to improve turnover rate.The dimensional accuracy of each component of the present invention is high, and interchangeability is good when assembled, and assembled process is connected only with galvanized bolt, and assembly and disassembly are easy, quick, short construction period.Combination is flexible, arbitrarily assembling combination can go out different area, the office of different purposes, temporary meeting room, dormitory, dining room, bathroom, toilet, mark and support room, power distribution room, pump house etc..Institute's live wire is used in whole disposable pre-buried wallboards, is not necessarily to field wiring in factory process.The present invention also has the characteristics that sturdy and durable, moisture-proof, windproof, fire prevention, anti-corrosion, heat-insulated, sound insulation, heat preservation.
Description
Technical field
The present invention relates to a kind of construction methods and structure of pin-connected panel standard relocation housing, belong to architectural engineering production and living and face
When facility technology field.
Background technology
The most significant feature of building enterprise is exactly that mobility is big, after the completion of a project, receives new projects' entirety again
It is transferred to another building site.In order to facilitate transfer, production, office and the living facilities of most building enterprise's building-site are interim
Structure.
Traditional way is new everywhere construction site, begins with waste and scrap and sets up some temporary offices
With makeshift house as place of handling official business and live, handled as building waste after just discarding does not have to or removes when finally withdrawing.Tradition
Way can not only cause the waste of material, can also leave many building wastes.Energy-saving and environment-friendly theory is not met, it is national thus
It promulgates《Architectural engineering civilized construction standard》, to civilization, more stringent requirements are proposed with safety in production, therefore traditional way
Requirement is cannot be satisfied.
In order to adapt to the needs of civilized construction, some assembled type moveable plank houses have been gradually appeared in building trade.These are lived
The appearance in movable plate room plays civilized construction certain facilitation, but there are problems that.Such as the mark of movable plank house
Quasi-ization degree is low, and interchangeability and using flexible are poor, and assembly is got up cumbersome.Height is required to terrace when construction, needs to be laid with
10cm rubbles will also be laid with 5cm pea gravel concretens face layer as base in base.The existing movable plank house strength of materials is poor, weight
Multiple utilization rate is low.The performances such as some material fire retardant anticorrosion, sound-insulatings are bad, and construction site office and dormitory condition are poor.It tears open
It is more to move rear building waste, is unfavorable for environmental protection.
Invention content
The object of the present invention is to provide a kind of construction methods and structure of pin-connected panel standard relocation housing, pass through specialization
The mode of production improves the standardization of components of prefabricated house, simplifies assembly process and improves assembled speed, does not have substantially after dismounting
Building waste, to improve the level of carrying out production strictly in line with rules and regulations of construction, to overcome the deficiencies in the prior art.
The technical proposal of the invention is realized in this way:
A kind of construction method of pin-connected panel standard relocation housing of the present invention is that this method is constructed according to the following steps:
Step 1: all professional factory is transferred to be processed by standardisation requirements in designed drawing;
Step 2: constructing standard relocation housing basis at the construction field (site) according to design drawing;
Step 3: component needed for all standard relocation housings that professional factory processes is transported to construction site;
Step 4: on the basis of two root long beams are placed in standard relocation housing with lifting equipment, then two short beams are inserted in length
On the horizontal plug connector of beam-ends head, galvanized bolt is used in combination to fix short beam and plug connector, constitutes bottom framework;
Step 5: installing terrestrial components on bottom framework;
Step 6: four columns are inserted on the vertical plug connector of long beam-ends head, it is used in combination galvanized bolt by column and grafting
Part is fixed;
Step 7: wall assemblies are mounted between two columns;
Step 8: two short beams are inserted on the horizontal plug connector of long beam-ends head on ground, it is used in combination galvanized bolt by short beam
It is fixed with plug connector, constitutes top frame;
Step 9: completing the assembling of roof assembly and top frame on ground;
Step 10: the four vertical plug connectors that will be equipped with the top frame bottom of roof assembly with lifting equipment and four are vertical
Top end grafting, is used in combination galvanized bolt to fix top frame and column;Completion standard relocation housing is assembled.
In preceding method, standard relocation housing basis is to be embedded in the prefabricated reinforced concrete item of ground grading to constitute
The top surface of rectangle frame corresponding with bottom framework size, rectangle frame is concordant with ground and is in horizontality.
In preceding method, the long beam, short beam, column and plug connector are that be converted into section with Q235 hot-dip galvanizing sheet steels be L
Steel column of the type both ends with flange;The sectional dimension of wherein plug connector is slightly less than the sectional dimension of short beam and column, short to be inserted into
Beam and column.
A kind of pin-connected panel standard relocation housing structure of the present invention constituted as stated above is that the standard relocation housing is case
Formula structure includes by long beam, short beam and the assembled cuboid framework of column;Each apex angle of cuboid framework, which is equipped with, to be added
Strong plate, hole for hoist when reinforcing plate is equipped with lifting for bundling steel wire rope;The both ends Chang Liang be respectively welded horizontal plug connector and
Vertical plug connector;Horizontal plug connector fixes composition bottom framework and top frame with short beam grafting and through galvanized bolt;Vertical plug connector
It fixes with column grafting and through galvanized bolt and constitutes cuboid framework;The bottom surface of cuboid framework is equipped with terrestrial components, rectangular
The top surface of body frame is equipped with roof assembly;Cuboid framework surrounding is equipped with wall assemblies.
In aforementioned structure, the wall assemblies include mounted on the side wall of cuboid framework two sides and mounted on cuboid
The headwall of frame both ends of the surface;Headwall is equipped with door component and/or window assembly, and wall assemblies are equipped with power outlet, power switch
And/or distribution box;The junction of terrestrial components and wall assemblies is equipped with skirting board;Roof assembly.With the junction of wall assemblies
And the corner of wall assemblies is equipped with ornamental strip everywhere.
In aforementioned structure, the side wall and headwall are made of one group of wallboard, and wallboard is chromatic steel sandwich plate, chromatic steel sandwich plate
It is interior to be filled with rock wool;A side of wallboard is equipped with tenon, and another side of wallboard is equipped with groove;Wallboard is assembled into side wall through tongue-and-groove
Or headwall.
In aforementioned structure, the chromatic steel sandwich plate medial surface is equipped with power outlet, control switch and/or distribution box, color steel
It is equipped with PVC spools in battenboard, power cord is equipped in PVC spools, power cord both ends are equipped with connector.
In aforementioned structure, the terrestrial components include cement pressure plate, and anti-skidding PVC floor is equipped on cement pressure plate.
In aforementioned structure, the roof assembly includes ceiling board, and rock wool fireproof heat-insulation plate, furred ceiling are equipped with above ceiling board
Board bottom face is equipped with LED energy-saving lamps.
In aforementioned structure, the terrestrial components are stuck in the card slot formed between the L-type both ends flange of bottom framework;Roof group
Part is stuck in the card slot formed between the L-type both ends flange of top frame;Roof assembly top surface is equipped with waterproof layer.
By adopting the above-described technical solution, compared with prior art, the present invention the most important feature of the present invention is standard
For all components of relocation housing by professional factory standardized production, the dimensional accuracy for substantially increasing each component is high, mutual when assembled
Transsexual good, assembled process is all connected using galvanized bolt without welding.Assembly and disassembly are easy, quick, short construction period.Of the present invention group
It closes flexibly, assembling combination can go out different area, the office of different purposes, temporary meeting room, dormitory, dining room, bath as needed
Room, toilet, mark support room, power distribution room, pump house etc..Electrical equipment and electric wire in the present invention are all installed in factory process
In place, the trouble of field wiring can be omitted by only connecting respective wire by number when assembling.The present invention, which also has, to be fabricated to
The characteristics of this is low, sturdy and durable, moisture-proof, windproof, fire prevention, anti-corrosion, heat-insulated, sound insulation, heat preservation.
By taking 5 two layers lower of 10 dormitories on assembled one 5 as an example, the set-up time in traditional activity room needs 5 days, of the invention
3 days only are needed, is shortened the construction period 2 days.The present invention can also assemble standard relocation housing in factory, after transporting to building site, directly hang
It can be used after dress.Two days only are needed according to the integral hoisting present invention, can be shortened the construction period 3 days.The present invention when shifting building site,
It can not have to remove the office accommodation and equipment in standard relocation housing, Integral lifting entrucking transhipment.Service life of the invention is up to 15 years
As long as, it is repeatable to be used in turn 6 times, lose small in circular flow, the building waste of generation almost can be ignored.
It is the comparative analysis that the present invention makes use cost with traditional activity room below.Construction site is in Shanghai, processing factory
In Suzhou.It is provided according to related current specifications, the usage time summation of traditional color steel battenboard prefabricated house must not exceed 5
Year, the number of turnover must not exceed 3 times.
The unit price in existing traditional activity room is 310 yuan/m2(Including installation fee), transport, installation fee Shanghai to Suzhou consider
66 yuan/m2, 25 yuan/m of temporary electricity installation fee consideration2, traditional activity premises level ground need to individually construct, and be configured to 10cm crushed rock base courses
5cm pea gravel concretens face layer, unit price is added to consider 21.75 yuan/m2, in addition consider that the wind loading rating in traditional activity room is insufficient, typhoon
Season need to increase safeguard procedures expense by the 7.5 yuan of considerations of every square meter, and traditional activity room is considered 3 times using the number of turnover, is installed, is taken
If expense considers 2 times, the size of every traditional activity board house is 6000 × 3640=21.84m2, every prefabricated house consideration burglary-resisting window
70 yuan/door frame of fee of material and installation fee, every 2 door frames are 70 × 2 × 21.84=6.41 yuan/m per square meter expense2, then traditional activity room
It is per amortization charge of square meter:(310+66×2+25×3+21.75×3+7.5×3+6.41×3)3=207.99 yuan/m of ÷2。
Prefabricated house assembles and disassembles loss and considers 25% every time, then traditional activity room once amortizes actual cost and is:207.99+207.99×25%=
259.99 member/m2。
The standard relocation housing area of the present invention is 6158 × 3000, then the area of a standard room is 18.474m2.Unit price
It it is 16800 yuan, transport installation fee considers that Shanghai to Suzhou is 63 yuan/m2, 8 yuan/m of temporary electricity installation fee consideration2, the number of turnover
Consider 6 times.It is per square meter assembled prefabricated house unit price then:16800 18.474=909.38 yuan/m of ÷2, it is used in turn 6 times, then
One time amortization charge is:(909+63×6+8×6)× 6=222.50 yuan/m2.The assembly and disassembly loss of fabricated construction temporary facility is examined by 5%
Consider, then a practical amortization charge is:22.50+222.50 × 5%=233.63 yuan/m2, therefore set temporarily using fabricated construction
Expense can be saved compared to per square meter by granting traditional prefabricated house:259.99-233.63=26.36(Member).
The expense of relocation housing of the present invention is between totally 10 under 5 in assembling 15:18.474×233.63×10=43160.81
(Member).
The expense in totally 10 traditional activity rooms is under assembling 5 on 15:21.84×259.99×10=56781.82(Member).
Then assemble on 15 under 5 between totally 10 relocation housing of the present invention under setting up 5 on 15 compared with totally 10 traditional activity rooms
56781.82-43160.81=13621.01 can be saved(Member).Not only one, one building site, at least need several it is even more,
Economic benefit is considerable.
Description of the drawings
Fig. 1 is the assembling flow path schematic diagram of standard relocation housing;
Fig. 2 is the structural schematic diagram one of standard relocation housing;
Fig. 3 is the structural schematic diagram two of standard relocation housing;
Fig. 4 is the attachment structure schematic diagram of long beam and short beam and column;
Fig. 5 is terrestrial components and the connection diagram of bottom framework;
Fig. 6 is the connection diagram of roof component and top frame;
Fig. 7 is the connection diagram of wall assemblies and column.
Label in attached drawing be:1- long beams, 2- short beams, 3- columns, 4- reinforcing plates, 5- holes for hoist, the horizontal plug connectors of 6-, 7-
Vertical plug connector, 8- galvanized bolts, 9- terrestrial components, 10- roof assemblies, 11- side walls, 12- headwalls, 13- power outlets, 14-
Power switch, 15- door components, 16- window assemblies, 17- skirting boards, 18- cement pressure plates, the anti-skidding PVC floors of 19-, 20- furred ceilings
Plate, 21- rock wool fireproof heat-insulation plates, 22-LED energy-saving lamps, 23- waterproof layers, 24- distribution boxs, 25- ornamental strips, 26- coloured silk steel clamp cores
Plate, 27- rock wools, 28- tenons, 29- grooves, 30- standards relocation housing basis.
Specific implementation mode
The present invention is described in further detail with reference to the accompanying drawings and examples, but not as to any of the present invention
Limitation.
A kind of construction method of pin-connected panel standard relocation housing of the present invention, shown in Fig. 1, this method is constructed according to the following steps:
Step 1: all professional factory is transferred to be processed by standardisation requirements in designed drawing;
Step 2: constructing standard relocation housing basis at the construction field (site) according to design drawing;Standard relocation housing basis 30 such as Fig. 1
In 1. shown in, be that prefabricated reinforced concrete item is buried on smooth ground, prefabricated reinforced concrete item is constituted and bottom frame
The top surface of the corresponding rectangle frame of frame size, rectangle frame is concordant with ground and is in horizontality.
Step 3: component needed for all standard relocation housings that professional factory processes is transported to construction site;
Step 4: as 2. shown in Fig. 1, two root long beams 1 are placed on installation foundation 30 with lifting equipment, are schemed for another example
It is 3. shown in 1, two short beams 2 are inserted on the horizontal plug connector 6 of 1 end of long beam, are used in combination galvanized bolt 8 by short beam 2 and water
Plug flat fitting 6 is fixed, and bottom framework is constituted;
Step 5: as 4. shown in Fig. 1, terrestrial components 9 are installed on bottom framework;
Step 6: as 5. shown in Fig. 1, four columns 3 be inserted on the vertical plug connector 7 of 1 end of long beam, plating is used in combination
Zinc bolt 8 fixes column 3 and vertical plug connector 7;
Step 7: as 6. shown in Fig. 1, wall assemblies are mounted between two columns 3;
Step 8: as 7. shown in Fig. 1, two short beams 2 are inserted on the horizontal plug connector 6 of 1 end of long beam on ground,
It is used in combination galvanized bolt 8 to fix short beam 2 and horizontal plug connector 6, constitutes top frame;
Step 9: the assembling of roof assembly 10 and top frame is completed on ground, while can also be by LED energy-saving lamps 22 1
And it installs;
Step 10: as 8. shown in Fig. 1, four of the top frame bottom of roof assembly 10 will be installed with lifting equipment
Vertical plug connector 7 and 3 top grafting of four columns, are used in combination galvanized bolt 8 to fix top frame and column 3;Completion standard is had enough to meet the need
Room is assembled.
The long beam 1, short beam 2, column 3 and plug connector are that be converted into section with Q235 hot-dip galvanizing sheet steels be L as shown in Figure 4
Steel column of the type both ends with flange;Wherein plug connector(Including horizontal plug connector 6 and vertical plug connector 7)Cross sectional shape it is identical, but
It is dimensioned slightly smaller than the sectional dimension of short beam 2 and column 3, to be inserted into short beam 2 and column 3.
The pin-connected panel standard relocation housing structure constituted as stated above, as shown in Figures 2 and 3, the standard relocation housing is
Case structure includes equal by long beam 1, short beam 2 and the assembled cuboid framework of column 3, each apex angle of cuboid framework
Equipped with reinforcing plate 4, the hole for hoist 5 when reinforcing plate 4 is equipped with lifting for bundling steel wire rope.Long beam 1 and short beam 2 and column 3
Connection structure as shown in figure 4,1 both ends of long beam are respectively welded horizontal plug connector 6 and vertical plug connector 7, horizontal plug connector 6 with it is short
Beam 2 presses direction grafting shown in horizontal arrow in Fig. 4 and fixes composition bottom framework and top frame through galvanized bolt 8;Vertical plug connector 7
By direction grafting shown in vertical arrow in Fig. 4 and composition cuboid framework is fixed with column 3 through galvanized bolt 8;Cuboid framework
Bottom surface terrestrial components 9 are installed, the top surface of cuboid framework is equipped with roof assembly 10;Cuboid framework surrounding is equipped with wall
Body component.As shown in Figures 2 and 3, wall assemblies include mounted on the side wall 11 of cuboid framework two sides and mounted on rectangular
The headwall 12 of body frame both ends of the surface;Headwall 12 is equipped with door component 15 and/or window assembly 16, and wall assemblies are equipped with power outlet
13, power switch 14 and/or distribution box 24;Terrestrial components 9 and the junction of wall assemblies are equipped with skirting board 17;Roof assembly
10.It is equipped with ornamental strip 25 everywhere with the junction of wall assemblies and the corner of wall assemblies.Side wall 11 and headwall 12 are by one
Group wallboard is constituted, and wallboard is illustrated in figure 7 chromatic steel sandwich plate 26, and rock wool 27 is filled in chromatic steel sandwich plate;A side of wallboard
Equipped with tenon 28, another side of wallboard is equipped with groove 29;Wallboard is assembled into side wall 11 or headwall 12 through tongue-and-groove.Such as Fig. 2 and Fig. 3
Shown, chromatic steel sandwich plate medial surface is equipped with power outlet 23, control switch 24 and/or distribution box 25.It is equipped in chromatic steel sandwich plate
PVC spools(It is not drawn into figure), PVC spools are interior to be equipped with power cord, and power cord both ends are equipped with connector.Such as Fig. 5 institutes of terrestrial components 9
Show, including cement pressure plate 18, anti-skidding PVC floor 19 is equipped on cement pressure plate 18.Roof assembly 10 includes as shown in Figure 6
Ceiling board 20,20 top of ceiling board are equipped with rock wool fireproof heat-insulation plate 21, and 20 bottom surface of ceiling board is equipped with LED energy-saving lamps 22
(See Fig. 3).It, can also be in 21 top surface of rock wool fireproof heat-insulation plate if standard relocation housing is for the top layer of one layer of one-storey house or building
It is laid with waterproof layer 23.Rainwater penetrates into when preventing from raining.Terrestrial components 9 and roof assembly 10 are as shown in Figure 5 and Figure 6, ground group
Part 9 is stuck in the card slot formed between the L-type both ends flange of bottom framework;Roof assembly 10 is stuck in the L-type both ends flange of top frame
Between in the card slot that is formed, fixed without welding or bolt;9 top surface of roof assembly is equipped with waterproof layer 3.
Embodiment
The standard relocation housing of the present invention is at present in Jiujiang Wanda, the positive honor in Suzhou, Nanjing The Lalu, positive flourish, Taizhou, Nanjing
Yin Tai, the office for melting 9 projects such as letter platinum gulf, symphysis International Square, Zhujiang River International trade center/hotel, the positive honor of Hongqiao, life
And be applied in production temporary facility, it can fully meet live needs, achieve good effect.
Standard relocation housing length, width and height size of the present invention is 6158 × 3000 × 2700mm;Its width dimensions is than traditional activity room
The small 640mm of width 3640mm, first, without departing from the maximum width of highway transportation requirement when considering transport;Second is that due to width dimensions
It reduces, terrestrial components span is made to reduce, intensity is higher.Standard relocation housing of the present invention by rock cotton board wallboard/18 pieces total containing door and window,
The accessories such as 4, zinc-plated column, 1 set of roof assembly, 1 set of terrestrial components, electric wiring, control cabinet, lamps and lanterns form, 1 standard container
About 1.9 tons of total weight, from heavy and light, is easy to lift and transports.All components of prefabricated house of the present invention are all connected using galvanized bolt,
All using zinc-plating material, corrosion resistance is high for skeleton, wallboard.Present invention connection of each component in design has fully considered assembling
Convenience and agility, can quickly carry out assembly and disassembly.The preferable 3mm thickness Q235 of intensity is used in the design aspect of frame
It is steel column of the L-type both ends with flange that hot-dip galvanizing sheet steel, which is converted into section,;1 both ends of long beam of frame are welded with and short beam and column-type
Shape is identical, the plug connector of undersized, in component cuboid framework, using grafting and the fixed mode of bolt, assembles
It is very convenient.Intensity also meets the requirement being repeatedly used in turn.And it inventory and can repeatedly be used in turn.Standard turnover of the present invention
Room is all connected using galvanized bolt, and assembly is flexible, and installation and removal are quick, and can be actually needed according to scene and be assembled different sides
Product, the office of different purposes, production, life temporary facility.Prefabricated house basis of the present invention is used pours one in entire babinet surrounding
Enclose concrete continuous footing;Terrestrial components use 18mm solid cement pressure plares, the anti-skidding PVC floors of upper berth 1.8mm that can repeatedly have enough to meet the need
It uses;Main body type steel skeleton is welded into connector using the folding of 3mm thickness Q235 hot-dip galvanizing sheet steels, is all connected using galvanized bolt
At cuboid frame structure;Standard relocation housing of the present invention plant-manufactured while institute's live wire being embedded into wallboard,
It can be mounted directly switch and socket when being transported to assembled in situ, be not required to lay house wire again;Standard relocation housing design of the present invention
When aluminum window anti-theft guardrail has been considered, it is disposable when assembled that installation is complete;All components of standard relocation housing of the present invention are whole
It is prefabricated in advance in factory, it transports to assembled in situ, construction speed is fast, cheap, high recycling rate.
The standard relocation housing main body type steel skeleton of the present invention is welded into connection using the folding of 3mm thickness Q235 hot-dip galvanizing sheet steels
Part is mutually connected by screw bolts;Wallboard is the two-sided 0.5mm chromatic steel sandwich plates of 60mm rock wools.Bathroom, toilet, dining room, steamed rice
Between, mark support room using the fire-retardant outer single-faced color steels of 60mm and interior single-side stainless steel battenboard;Roofing top plate uses thickness bis- for 50mm
The face fire-retardant battenboard of 0.5mm coloured silk steel is laid with 50mm rock wool fireproof thermal-insulation layers as ceiling board on ceiling board;Bottom plate uses 18mm
Solid cement pressure plare, and it is laid with the thick anti-skidding PVC floors of 1.8mm;Door and window uses aluminum alloy doors and windows, window to use transparent tempering glass
Glass, and add aluminum alloy anti-burglary railing;Illuminating line uses 1.5mm2Electric wire, air-conditioning system use 2.5mm2Electric wire, electronic box
Using PVC electronic boxs, it is DN25 spools to flow PVC spools day, and office lighting uses 18WLED energy-saving daylight lamps, and dormitory is using 9W's
LED energy-saving daylight lamps;In order to meet Zhong Jian parent companys CI requirements in appearance:Cuboid framework and doorframe build blue in painting,
Wall assemblies and door paint lime color, and material of paint is all using KCC priming paint+polyurethane finish.
Claims (2)
1. a kind of construction method of pin-connected panel standard relocation housing, it is characterised in that:This method is constructed according to the following steps:
Step 1: all professional factory is transferred to be processed by standardisation requirements in designed drawing;
Step 2: constructing standard relocation housing basis at the construction field (site) according to design drawing;
Step 3: component needed for all standard relocation housings that professional factory processes is transported to construction site;
Step 4: on the basis of two root long beams are placed in standard relocation housing with lifting equipment, then two short beams are inserted in long beam-ends
On the horizontal plug connector of head, galvanized bolt is used in combination to fix short beam and plug connector, constitutes bottom framework;
Step 5: installing terrestrial components on bottom framework;
Step 6: four columns are inserted on the vertical plug connector of long beam-ends head, galvanized bolt is used in combination to consolidate column and plug connector
It is fixed;
Step 7: wall assemblies are mounted between two columns;
Step 8: two short beams are inserted on the horizontal plug connector of long beam-ends head on ground, galvanized bolt is used in combination by short beam and are inserted
Fitting is fixed, and top frame is constituted;
Step 9: completing the assembling of roof assembly and top frame on ground;
Step 10: four vertical plug connectors that the top frame bottom of roof assembly will be equipped with lifting equipment and four columns top
Grafting is held, galvanized bolt is used in combination to fix top frame and column;Completion standard relocation housing is assembled;
Standard relocation housing basis be embedded in ground grading prefabricated reinforced concrete item constitute it is corresponding with bottom framework size
The top surface of rectangle frame, rectangle frame is concordant with ground and is in horizontality;Long beam, short beam, column and plug connector are to use Q235
It is steel column of the L-type both ends with flange that hot-dip galvanizing sheet steel, which is converted into section,;The sectional dimension of wherein plug connector is slightly less than short beam and column
Sectional dimension, to be inserted into short beam and column.
2. a kind of pin-connected panel standard relocation housing structure constituted by claim 1 the method, it is characterised in that:The standard week
It is case structure to turn room, including by long beam(1), short beam(2)And column(3)Assembled cuboid framework;Cuboid framework
Each apex angle be equipped with reinforcing plate(4), reinforcing plate(4)Hole for hoist when being equipped with lifting for bundling steel wire rope(5);Long beam
(1)Both ends are respectively welded horizontal plug connector(6)With vertical plug connector(7);Horizontal plug connector(6)With short beam(2)Grafting simultaneously passes through
Galvanized bolt(8)It is fixed to constitute bottom framework and top frame;Vertical plug connector(7)With column(3)Grafting and through galvanized bolt(8)Gu
Surely cuboid framework is constituted;The bottom surface of cuboid framework is equipped with terrestrial components(9), the top surface of cuboid framework is equipped with roof
Component(10);Cuboid framework surrounding is equipped with wall assemblies;Wall assemblies include mounted on the side of cuboid framework two sides
Wall(11)With the headwall mounted on cuboid framework both ends of the surface(12);Headwall(12)It is equipped with door component(15)And/or window assembly
(16), wall assemblies are equipped with power outlet(13), power switch(14)And/or distribution box(24);Terrestrial components(9)With wall
The junction of component is equipped with skirting board(17);It is equipped with ornamental strip with the junction of wall assemblies and the corner of wall assemblies
(25);Side wall(11)And headwall(12)It is made of one group of wallboard, wallboard is chromatic steel sandwich plate(26), the interior filling of chromatic steel sandwich plate
There is rock wool(27);A side of wallboard is equipped with tenon(28), another side of wallboard is equipped with groove(29);Wallboard is through tongue-and-groove assembly
At side wall(11)Or headwall(12);Chromatic steel sandwich plate medial surface is equipped with power outlet(23), control switch(24)And/or distribution box
(25), chromatic steel sandwich plate is interior to be equipped with PVC spools, power cord is equipped in PVC spools, power cord both ends are equipped with connector;Ground group
Part(9)Including cement pressure plate(18), cement pressure plate(18)On be equipped with anti-skidding PVC floor(19);Roof assembly(10)Packet
Include ceiling board(20), ceiling board(20)Top is equipped with rock wool fireproof heat-insulation plate(21), ceiling board(20)Bottom surface is equipped with LED sections
It can lamps and lanterns(22);Terrestrial components(9)It is stuck in the card slot formed between the L-type both ends flange of bottom framework;Roof assembly(10)Card
In the card slot formed between the L-type both ends flange of top frame;Roof assembly(9)Top surface is equipped with waterproof layer(23).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510113456.3A CN105649207B (en) | 2015-03-16 | 2015-03-16 | A kind of construction method and structure of pin-connected panel standard relocation housing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510113456.3A CN105649207B (en) | 2015-03-16 | 2015-03-16 | A kind of construction method and structure of pin-connected panel standard relocation housing |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105649207A CN105649207A (en) | 2016-06-08 |
CN105649207B true CN105649207B (en) | 2018-10-30 |
Family
ID=56481558
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510113456.3A Active CN105649207B (en) | 2015-03-16 | 2015-03-16 | A kind of construction method and structure of pin-connected panel standard relocation housing |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105649207B (en) |
Families Citing this family (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106368311A (en) * | 2016-10-26 | 2017-02-01 | 南宁众创空间科技有限公司 | Simplified house |
CN107060379A (en) * | 2017-01-17 | 2017-08-18 | 优居优住家居装饰(北京)有限公司 | A kind of bathroom construction method |
CN107012950B (en) * | 2017-05-20 | 2019-08-02 | 湖北广盛建筑产业化科技有限公司 | Green energy conservation assembled architecture and construction method |
CN107130684A (en) * | 2017-05-26 | 2017-09-05 | 北京北玻硅巢技术有限公司 | A kind of fabricated structure and its construction method |
CN107327162B (en) * | 2017-06-05 | 2020-06-09 | 南京国荣环保科技有限公司 | Fabricated building |
CN107451327A (en) * | 2017-06-26 | 2017-12-08 | 福建省建筑设计研究院 | The BIM Component Modelings system and modeling method for assigning component tax plus layer are divided with working region |
CN107299685A (en) * | 2017-07-04 | 2017-10-27 | 陈贵 | It is a kind of can the quickly assembled and disassembled removable room of packing and transporting |
CN107355095A (en) * | 2017-07-26 | 2017-11-17 | 长沙天鹏泵业制造有限公司 | Novel all-in-one assembled pump house and its assemble method |
CN107476616A (en) * | 2017-09-27 | 2017-12-15 | 广东电网有限责任公司茂名供电局 | A kind of prefabricated assembled low-voltage power distribution room and manufacture method |
CN108166568B (en) * | 2018-02-11 | 2022-05-06 | 成都市阳光电器工业有限公司 | Assembled integrated pumping irrigation pump house |
CN108301653A (en) * | 2018-03-28 | 2018-07-20 | 广东海悟科技有限公司 | A kind of quick-assembling small-sized antitheft armor computer room |
CN109267644B (en) * | 2018-10-23 | 2021-01-19 | 中国一冶集团有限公司 | Complete-assembly detachable movable building board house |
CN109138523A (en) * | 2018-10-25 | 2019-01-04 | 中冶天工(天津)装备制造有限公司 | The removable assembling type steel structure of corner post builds single open-door toilette modules |
CN109853743B (en) * | 2018-12-27 | 2021-01-29 | 安徽企服工程技术有限公司 | Modular assembly type steel structure building system and assembly method thereof |
CN109663862B (en) * | 2019-01-30 | 2024-04-02 | 河北玉发压瓦机设备有限公司 | Box-type house roof four-edge skin serging machine |
CN110080564A (en) * | 2019-04-25 | 2019-08-02 | 中国电建集团江西省电力设计院有限公司 | A kind of main body module and preparation method thereof of transforming plant assembly type guardroom |
CN110528701B (en) * | 2019-08-23 | 2020-12-08 | 中建科技(福州)有限公司 | Steel bar anchoring connection structure and connection method of prefabricated concrete member |
CN113250344A (en) * | 2021-05-25 | 2021-08-13 | 江苏省苏中建设集团股份有限公司 | Assembled dampproofing building wall |
CN113914664A (en) * | 2021-11-01 | 2022-01-11 | 中国人民解放军32181部队 | Quick-inserting combined movable house with door pocket |
CN114771723B (en) * | 2022-03-17 | 2023-04-18 | 江西朝阳机械有限公司 | Cabin unit for boats and ships of convenient combination |
CN115126156B (en) * | 2022-06-13 | 2023-06-27 | 珠海采筑电子商务有限公司 | Bearing column of assembled movable house and construction method |
CN114809725B (en) * | 2022-07-01 | 2022-09-06 | 北京凯隆分析仪器有限公司 | Assembled movable house |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201151950Y (en) * | 2007-07-16 | 2008-11-19 | 金胜财 | Dismounting type integral hoisting movable dwellings |
CN102913002A (en) * | 2012-11-22 | 2013-02-06 | 北京城乡建设集团有限责任公司 | Integrated steel structure movable room and mounting method thereof |
CN203821595U (en) * | 2014-04-16 | 2014-09-10 | 广东一百集成房屋有限公司 | Container type movable house |
CN104074267A (en) * | 2014-07-04 | 2014-10-01 | 中国石油集团长城钻探工程有限公司工程服务公司 | Dismountable skid-mounted steel structure camping house |
CN203924359U (en) * | 2014-05-14 | 2014-11-05 | 湖南绿广景观新材料有限公司 | A kind of stand column and beam connector |
CN104389349A (en) * | 2014-11-29 | 2015-03-04 | 山东双得利建设科技有限公司 | Novel house capable of being fast disassembled and assembled and assembling method thereof |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AU2008352422A1 (en) * | 2008-03-07 | 2009-09-11 | Francesco Antonio Martino | A transportable building including a roof structure for stacking of multiple buildings |
-
2015
- 2015-03-16 CN CN201510113456.3A patent/CN105649207B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201151950Y (en) * | 2007-07-16 | 2008-11-19 | 金胜财 | Dismounting type integral hoisting movable dwellings |
CN102913002A (en) * | 2012-11-22 | 2013-02-06 | 北京城乡建设集团有限责任公司 | Integrated steel structure movable room and mounting method thereof |
CN203821595U (en) * | 2014-04-16 | 2014-09-10 | 广东一百集成房屋有限公司 | Container type movable house |
CN203924359U (en) * | 2014-05-14 | 2014-11-05 | 湖南绿广景观新材料有限公司 | A kind of stand column and beam connector |
CN104074267A (en) * | 2014-07-04 | 2014-10-01 | 中国石油集团长城钻探工程有限公司工程服务公司 | Dismountable skid-mounted steel structure camping house |
CN104389349A (en) * | 2014-11-29 | 2015-03-04 | 山东双得利建设科技有限公司 | Novel house capable of being fast disassembled and assembled and assembling method thereof |
Also Published As
Publication number | Publication date |
---|---|
CN105649207A (en) | 2016-06-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105649207B (en) | A kind of construction method and structure of pin-connected panel standard relocation housing | |
CN204781329U (en) | Pin -connected panel standard turnover room | |
AU2013100359B4 (en) | Modular Building | |
MX2013003931A (en) | Modular building system. | |
US20160040443A1 (en) | Modular Building System | |
CN106400966B (en) | A kind of assembling method of prefabricated integral assembling formula movable plank house | |
US20170306625A1 (en) | Prefabricated demising and end walls | |
CN204782075U (en) | Have enough to meet need bathroom that room constitutes by standard | |
CN103821229B (en) | Rapid assembly type integrated house and installation method | |
CN204627053U (en) | A kind of multiple field steel work ITS | |
CN204753823U (en) | Have enough to meet need double -decker that room constitutes by standard | |
CN105421818A (en) | Embedded steel structure assembling residence | |
CN111236701B (en) | Integrated assembly type medical radiation-proof room structure and construction method | |
CN105649208B (en) | A kind of method and structure being combined into big room by standard relocation housing | |
CN205296893U (en) | Embedded steel construction assembly house | |
CN206205151U (en) | A kind of prefabricated integral assembling formula movable plank house | |
CN204826205U (en) | Have enough to meet need structure that room made up into big room by standard | |
CN110397158A (en) | A kind of boxboard steel construction assembled architecture system | |
CN217079091U (en) | Bamboo assembled building room | |
WO2004106669A1 (en) | Ready-to-use containerised house | |
CN109162359A (en) | For the assembling type steel structure module faced and built of constructing | |
CN209145011U (en) | For the assembling type steel structure module faced and built of constructing | |
CN205000676U (en) | Novel silver pavilion | |
CN204663036U (en) | A kind of cabinet be made up of standard relocation housing | |
CN204782104U (en) | Have enough to meet need staff canteen that room made up by standard |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |