CN105587128A - Special fixture for mounting wallboard with heat insulation structure and mounting method for first-layer wallboard with heat insulation structure - Google Patents
Special fixture for mounting wallboard with heat insulation structure and mounting method for first-layer wallboard with heat insulation structure Download PDFInfo
- Publication number
- CN105587128A CN105587128A CN201610095764.2A CN201610095764A CN105587128A CN 105587128 A CN105587128 A CN 105587128A CN 201610095764 A CN201610095764 A CN 201610095764A CN 105587128 A CN105587128 A CN 105587128A
- Authority
- CN
- China
- Prior art keywords
- jig
- insulation construction
- wallboard
- construction wallboard
- link
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/167—Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/18—Adjusting tools; Templates
- E04G21/1841—Means for positioning building parts or elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/24—Safety or protective measures preventing damage to building parts or finishing work during construction
- E04G21/26—Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls
Abstract
The invention discloses a special fixture for mounting a wallboard with a heat insulation structure and a mounting method for a first-layer wallboard with a heat insulation structure. The special fixture is composed of four unit fixtures and a fixture connecting frame. Each unit fixture is formed by welding a U-shaped clamp on the end of a fixture screw rod and connecting two steel base plates and two nuts to the fixture screw rod. The nuts, the steel base plates and a region located between the two steel base plates jointly form a clamping structure of the wallboard with the heat insulation structure. The four unit fixtures are used for jointly clamping the wallboard with the heat insulation structure through the clamping structure. The four unit fixtures are all clamped on the fixture connecting frame. The fixture connecting frame is fixedly arranged on the ground at any one side of the wallboard with the heat insulation structure. The mounting state of the wallboard with the heat insulation structure can be regulated through co-rotating the nuts of the fixture screw rod. The special fixture is simple in structure, low in manufacturing cost, portable, safe and reliable. By using the mounting method disclosed by the invention, the problem that the first-layer wallboard with the heat insulation structure cannot be mounted successfully under the condition of a backfill ground is solved, and the mounting stability, safety and accuracy of the first-layer wallboard with the heat insulation structure are ensured.
Description
Technical field
The present invention relates to the frock that a kind of construction is used, particularly relate to a kind of insulation construction wallboard personality card is installedTool and first floor insulation construction wallboard installation method.
Background technology
Prefabricated assembled insulation construction wallboard is structure set, body of wall and is incubated the brand-new patented technology in one. At present, useThe technology applicating adn implementing of this prefabricated thermal insulation structure wallboard construction wall structure there is no precedent. In demonstration project work progress,When first floor insulation construction wallboard is installed on the basis of building structure, because backfill soil ground is fixing not firm in the face of built-in fitting, makeFor installing and the bearing diagonal of fixing insulation construction wallboard cannot be firm fixing by built-in fitting, cause insulation construction wallboard to installSupport in process and support can not get solid support, bring difficulty to installment work. In addition, first floor insulation construction wallboard is installedIn perpendicularity and the adjustment of glacing flatness also because supporting member is fixing unstable and can not get precise positioning, cannot ensure constructionQuality. For this reason, provide and a kind ofly the frock of first floor insulation construction wallboard is installed and utilizes this frock to implement first floor insulation constructionThe method that wallboard is installed, to carry out smoothly the construction of first floor insulation construction wallboard, is problem demanding prompt solution.
Summary of the invention
An object of the present invention is to provide one simple in structure, easy to use, can guarantee that the installation of insulation construction wallboard is suitableProfit, adjusts precisely, can improve the insulation construction wallboard of first floor insulation construction wallboard construction speed and quality special mould clamp is installed.
The object of the invention is to realize. Insulation construction wallboard of the present invention is installed special mould clamp and is characterised in that: instituteState insulation construction wallboard installation special mould clamp and be jointly made up of four unit jigs and jig link, described unit jig is by oneRoot jig screw rod and U-shaped card of jig screw end head welding form, and described jig screw rod is provided with two billets, two steelThe backing plate outside nut that is respectively threaded, the region between described two nuts, two billets and two billets altogetherWith the clamp structure that forms insulation construction wallboard, described four unit jigs are all connected on jig link by U-shaped card, instituteStating jig link is fixed on any side ground of insulation construction wallboard.
Insulation construction wallboard of the present invention is installed special mould clamp, comprises two columns, two in wherein said jig linkColumn connects by upper and lower two crossbeams, and the upper end of each column connects a bearing diagonal, and the lower end of column and bearing diagonal is passed throughGround link connects, and between ground link, connects by two cross bars.
Insulation construction wallboard of the present invention is installed special mould clamp, and wherein said each unit jig U-shaped is stuck in U-shaped sealingEnd is welded on jig screw rod, and described four unit jigs are all connected to the upper bottom rail of jig link by the bayonet socket of U-shaped cardLiang Shang, the insulation construction wallboard of described unit jig clamping has on described clamp structure by the rotating Vortex of two nutsA round motion track.
Insulation construction wallboard of the present invention is installed special mould clamp, and wherein said jig screw rod and U-shaped card are by Φ 10-30 circleSteel is made.
Another object of the present invention is to provide one to utilize insulation construction wallboard installation special mould clamp that building structure is installedThe installation method of first floor insulation construction wallboard, first floor insulation construction wallboard installation method of the present invention is to complete by following steps, comprising:
Step 1: by drawing, making respectively jig screw rod, U-shaped card and two billets, is each jig screw rod apolegamy twoIndividual nut and two billets form a unit jig,
Step 2: press on the ground designing requirement by two root posts, upper and lower two crossbeams, two bearing diagonals, two ground linkForm jig link with two cross bar assemblings,
Step 3: jig link is fixed on the ground of any side in building structure basis,
Step 4: first insulation construction wallboard lifting of the first floor is placed on the basis of building structure,
Step 5: first assemble a nut and a billet in U-shaped card one side of jig screw rod, and four jig screw rods are logicalCross the two ends place that U-shaped card is connected to respectively upper and lower two crossbeams, then jig screw flight end is passed to insulation construction wallboardFour angular positions, insulation construction wallboard is connected on four jig screw rods, expose insulation construction wall at opposite side afterwardsFour jig screw flight ends of plate assemble a billet and a nut again, make monoblock insulation construction wallboard by nut andBillet is clamped on four unit jigs, and is positioned on jig link by four unit jigs,
Step 6: according to measuring requirement, rotating Vortex moves nut and the billet of insulation construction wallboard appointment both sides, an angle,Adjust perpendicularity or the glacing flatness of insulation construction wallboard by jig link, after perpendicularity and glacing flatness meet the requirements, phaseTo locking nut, complete the installation of first block of insulation construction wallboard of the building structure basis first floor,
Step 7: jig link is moved to the operation side of next piece insulation construction wallboard, repeating step five and step 6,Insulation construction wallboard is installed successively second, the 3rd, until complete whole first floor insulation construction wallboardInstallation.
Insulation construction wallboard of the present invention is installed special mould clamp and first floor insulation construction wallboard installation method and prior art notBe that with part insulation construction wallboard installation special mould clamp of the present invention is made up of four unit jigs and jig link. Unit cardTool is by a U-shaped card of jig screw end head welding, and jig screw rod is provided with two billets, and each screw thread connects outside two billetsConnecing a nut forms. Region between two nuts, two billets and two billets forms insulation construction wall jointlyThe clamp structure of plate. Four unit jigs clamp insulation construction wallboard jointly by clamp structure separately. Four unit jigsAll be connected on the crossbeam of jig link by the bayonet socket of U-shaped card. Jig link is fixed on insulation construction wallboard anyOn the ground of side. Two nuts of rotating Vortex jig screw rod, insulation construction wallboard has one for adjusting on clamp structureThe motion track of installment state. Insulation construction wallboard installation special mould clamp of the present invention is simple in structure, cost of manufacture is low, light littleIngeniously, be easy to carry, safe and reliable. Use first floor insulation construction wallboard installation method of the present invention, solved backfill soil ground feelingsUnder condition, the problem of insulation construction wallboard can not be installed smoothly, and ensure stability, safety that first floor insulation construction wallboard is installedProperty and accuracy.
Below in conjunction with accompanying drawing, insulation construction wallboard of the present invention being installed to special mould clamp is described further.
Brief description of the drawings
Fig. 1 is that insulation construction wallboard is installed special mould clamp structural representation (first insulation construction wallboard state is installed).
Fig. 2 is that insulation construction wallboard of the present invention is installed the unary structural representation of special mould clamp.
Fig. 3 is the jig link structural representation that insulation construction wallboard of the present invention is installed special mould clamp.
Fig. 4 is the view that unit jig clamps insulation construction wallboard and is connected with jig link.
Detailed description of the invention
As shown in Figure 1 and Figure 2, insulation construction wallboard installation special mould clamp is total to by four unit jigs 1 and jig link 2With composition. Unit jig 1 is made up of a jig screw rod 1-1 and a jig screw rod 1-1 termination U-shaped card 1-2 of welding. Jig spiral shellBar 1-1 is provided with two billet 1-3, two billet 1-3 outside nut 1-4 that is respectively threaded. Two nut 1-4,Region between two billet 1-3 and two billet 1-3 forms the clamp structure of insulation construction wallboard 3 jointly. FourUnit jig 1 is all connected on jig link 2 by U-shaped card 1-2. Four unit jigs 1 are total to by clamp structure separatelyWith clamping insulation construction wallboard 3, so that range site jig 1 and jig link 2 are installed insulation construction wallboard 3.
As shown in Figure 1, in jig link 2, comprise two column 2-1. Two column 2-1 are by upper and lower two crossbeam 2-2Connect, the upper end of each column 2-1 connects a bearing diagonal 2-3, and ground link is passed through in the lower end of column 2-1 and bearing diagonal 2-32-4 connects, and between ground link 2-4, connects by cross bar 2-5. Jig link 2 is fixed on any side of insulation construction wallboard 3On ground. Bearing carrier when jig link 2 is formed 3 installations of insulation construction wallboard and adjusted by the unit jig 1 connecting.
The U-shaped card 1-2 of each unit jig 1 is welded on jig screw rod 1-1 in U-shaped sealing end. Four unit jigs 1All be connected on the lower and upper cross-member 2-2 of jig link 2 insulation construction that unit jig 1 clamps by the bayonet socket of U-shaped card 1-2Wallboard 3, by the rotating Vortex of two nut 1-4, has a round motion track, insulation construction wallboard 3 on clamp structureReach the object of adjusting perpendicularity and glacing flatness by this motion track.
Insulation construction wallboard of the present invention is installed special mould clamp, wherein said jig screw rod 1-1 and U-shaped card 1-2 by10-30 round steel is made.
First floor insulation construction wallboard installation method of the present invention, is completed by following steps:
Step 1: by drawing, making respectively jig screw rod 1-1, U-shaped card 1-2 and two billet 1-3, is each jigTwo nut 1-4 of screw rod 1-1 apolegamy and two billet 1-3 form a unit jig 1,
Step 2: on the ground by designing requirement by two root post 2-1, upper and lower two crossbeam 2-2, two bearing diagonal 2-3, twoGround link 2-4 and two cross bar 2-5 assemblings form jig link 2,
Step 3: jig link 2 is fixed on the ground of any side in building structure basis,
Step 4: 3 liftings of first block of insulation construction wallboard of the first floor are placed on the basis of building structure,
Step 5: first at the U-shaped card 1-2 of a jig screw rod 1-1 mono-side nut 1-4 of assembling and a billet 1-3, and by fourIndividual jig screw rod 1-1 is connected to respectively the two ends place of upper and lower two crossbeam 2-2 by U-shaped card 1-2, then by jig screw rod 1-1The end of thread through four angular positions of insulation construction wallboard 3, insulation construction wallboard 3 is connected to four jig screw rod 1-1 upper,Four jig screw rod 1-1 screw threads that expose insulation construction wallboard 3 at opposite side are afterwards forged and are assembled a billet 1-3 and one againIndividual nut 1-4, makes monoblock insulation construction wallboard 3 be clamped on four unit jigs 1 by nut 1-4 and billet 1-3, andBe positioned on jig link 2 by four unit jigs 1,
Step 6: according to measuring requirement, rotating Vortex moves insulation construction wallboard 3 specifies nut 1-4 and the steel of both sides, an angleBacking plate 1-3, adjusts perpendicularity or the glacing flatness of insulation construction wallboard 3 by jig link 2, perpendicularity and glacing flatness meetAfter requirement, locking nut 1-4 in opposite directions, completes the installation of first block of insulation construction wallboard 3 of the building structure basis first floor,
Step 7: jig link 2 is moved to the operation side of next piece insulation construction wallboard 3, repeating step five and stepSix, insulation construction wallboard 3 is installed successively second, the 3rd, until complete whole first floor insulation constructionThe installation of wallboard 3.
While using insulation construction wallboard of the present invention that special mould clamp is installed, by the head that erects and be structured on architecture basicsLayer insulation construction wallboard 3 is installed, fixes and adjusted by unit fixture 1 and jig link 2. When first floor insulation construction wallWhen the perpendicularity of plate 3 or glacing flatness do not reach technical requirement, the nut 1-4 of the unit jig 1 by the required adjustment of rotating Vortex,Reach adjustment object.
The above embodiment, is only the description that the preferred embodiment for the present invention is carried out, and is not that the present invention is enteredThe circumscription of row, designs under the prerequisite of spirit not departing from the present invention, and those of ordinary skill in the art are to technology of the present inventionVarious distortion and improvement that scheme is made, all should fall in the definite protection domain of the claims in the present invention book.
Claims (4)
1. insulation construction wallboard is installed a special mould clamp, it is characterized in that: described insulation construction wallboard install special mould clamp byFour unit jigs (1) and jig link (2) form jointly, and described unit jig (1) is by a jig screw rod (1-1) and cardTool screw rod (1-1) termination U-shaped card of welding (1-2) forms, and described jig screw rod (1-1) is provided with two billets (1-3),Two billets (1-3) outsides nut (1-4) that is respectively threaded, described two nuts (1-4), two billets (1-3)And region between two billets (1-3) forms the clamp structure of insulation construction wallboard (3), described four unit cards jointlyIt is upper that tool (1) is all connected to jig link (2) by U-shaped card (1-2), and described jig link (2) is fixed on insulation construction wallOn any side ground of plate (3).
2. insulation construction wallboard according to claim 1 is installed special mould clamp, it is characterized in that: described jig link(2) in, comprise two columns (2-1), two columns (2-1) connect by upper and lower two crossbeams (2-2), each column (2-1)Upper end connects a bearing diagonal (2-3), and column (2-1) is connected by ground link (2-4) with the lower end of bearing diagonal (2-3), groundBetween face connecting rod (2-4), connect by two cross bars (2-5).
3. insulation construction wallboard according to claim 1 and 2 is installed special mould clamp, it is characterized in that: described each unitIt is upper that the U-shaped card (1-2) of jig 1 is welded on jig screw rod (1-1) in U-shaped sealing end, and described four unit jigs (1) all pass throughThe bayonet socket of U-shaped card (1-2) is connected on the lower and upper cross-member (2-2) of jig link (2), the guarantor of described unit jig (1) clampingTemperature structure wallboard (3) has a round motion track by the rotating Vortex of two nuts (1-4) on described clamp structure.
4. a first floor insulation construction wallboard installation method, is characterized in that comprising the following steps in method:
Step 1: by drawing, make respectively jig screw rod (1-1), U-shaped card (1-2) and two billets (1-3), for oftenTwo nuts of individual jig screw rod (1-1) apolegamy (1-4) and two billets (a 1-3 unit jig of formation (1),
Step 2: press on the ground designing requirement by two root posts (2-1), upper and lower two crossbeams (2-2), two bearing diagonal (2-3), the assembling of two ground link (2-4) and two cross bars (2-5) forms jig links (2),
Step 3: jig link (2) is fixed on the ground of any side in building structure basis,
Step 4: first block of insulation construction wallboard of the first floor (3) lifting is placed on the basis of building structure,
Step 5: first assemble a nut (1-4) and a billet (1-in U-shaped card (1-2) side of jig screw rod (1-1)3), and four jig screw rods (1-1) are connected to respectively to the two ends place of upper and lower two crossbeams (2-2) by U-shaped card (1-2), soAfter by the end of thread of jig screw rod (1-1) through four angular positions of insulation construction wallboard (3), insulation construction wallboard (3) is connectedReceive four jig screw rods (1-1) upper, expose afterwards four jig screw rods (1-1) of insulation construction wallboard (3) at opposite sideThe end of thread assembles a billet (1-3) and a nut (1-4) again, makes monoblock insulation construction wallboard (3) by nut (1-4)And billet (1-3) to be clamped in four unit jigs (1) upper, and be positioned at jig link by four unit jigs (1)It is (2) upper,
Step 6: according to measuring requirement, rotating Vortex moves the nut (1-4) of insulation construction wallboard (3) appointment both sides, an angleAnd billet (1-3), by jig link (2) adjust insulation construction wallboard (3) perpendicularity or glacing flatness, perpendicularity andAfter glacing flatness meets the requirements, locking nut (1-4) in opposite directions, completes building structure basis first block of insulation construction wallboard of the first floor (3)Installation,
Step 7: jig link (2) is moved to the operation side of next piece insulation construction wallboard (3), repeating step five HesStep 6, second, the 3rd that insulation construction wallboard (3) is installed successively, protects until complete the whole first floorThe installation of temperature structure wallboard (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610095764.2A CN105587128B (en) | 2016-02-22 | 2016-02-22 | A kind of first floor insulation construction wallboard installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610095764.2A CN105587128B (en) | 2016-02-22 | 2016-02-22 | A kind of first floor insulation construction wallboard installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105587128A true CN105587128A (en) | 2016-05-18 |
CN105587128B CN105587128B (en) | 2017-07-28 |
Family
ID=55927009
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610095764.2A Active CN105587128B (en) | 2016-02-22 | 2016-02-22 | A kind of first floor insulation construction wallboard installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105587128B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111962878A (en) * | 2020-06-19 | 2020-11-20 | 青岛中建联合建设工程有限公司 | Detachable combined wall part position regulator |
CN113047666A (en) * | 2021-04-09 | 2021-06-29 | 西安建筑科技大学 | Limiting device is supported in installation of assembled PC wall |
CN113323420A (en) * | 2021-06-29 | 2021-08-31 | 吉林建筑大学 | Prefabricated building wallboard pre-positioning device and method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3861046A (en) * | 1973-05-11 | 1975-01-21 | Kevin L Arn | Batter board construction |
CN102235094A (en) * | 2010-04-22 | 2011-11-09 | 上海市第七建筑有限公司 | Construction method for carrying out accurate adjustment on position of prefabricated part |
CN103982049A (en) * | 2014-05-08 | 2014-08-13 | 河北联合大学 | Wall body assembling straightening device for shear wall |
CN203808555U (en) * | 2014-05-15 | 2014-09-03 | 中铁二局股份有限公司 | Assembled support for shear wall prefabricated members |
CN104074367A (en) * | 2014-07-18 | 2014-10-01 | 防城港中一重工有限公司 | Mounting adjustment device for prefabricated wall panel |
CN204357150U (en) * | 2014-12-04 | 2015-05-27 | 中国建筑第八工程局有限公司 | Wall support frame |
CN104790676A (en) * | 2015-04-29 | 2015-07-22 | 中国十七冶集团有限公司 | Rapid leveling and alignment device and method for installation of prefabricated wallboards |
CN205000660U (en) * | 2015-09-18 | 2016-01-27 | 重庆合筑实业发展有限公司 | Supplementary tool to lock of adjusting |
CN105297957A (en) * | 2015-10-08 | 2016-02-03 | 安徽同济建设集团有限责任公司 | Prefabricated filled wallboard and mounting method thereof |
CN205804988U (en) * | 2016-02-22 | 2016-12-14 | 北京六建集团有限责任公司 | Prefabricated thermal insulation structural wall board installs special mould clamp |
-
2016
- 2016-02-22 CN CN201610095764.2A patent/CN105587128B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3861046A (en) * | 1973-05-11 | 1975-01-21 | Kevin L Arn | Batter board construction |
CN102235094A (en) * | 2010-04-22 | 2011-11-09 | 上海市第七建筑有限公司 | Construction method for carrying out accurate adjustment on position of prefabricated part |
CN103982049A (en) * | 2014-05-08 | 2014-08-13 | 河北联合大学 | Wall body assembling straightening device for shear wall |
CN203808555U (en) * | 2014-05-15 | 2014-09-03 | 中铁二局股份有限公司 | Assembled support for shear wall prefabricated members |
CN104074367A (en) * | 2014-07-18 | 2014-10-01 | 防城港中一重工有限公司 | Mounting adjustment device for prefabricated wall panel |
CN204357150U (en) * | 2014-12-04 | 2015-05-27 | 中国建筑第八工程局有限公司 | Wall support frame |
CN104790676A (en) * | 2015-04-29 | 2015-07-22 | 中国十七冶集团有限公司 | Rapid leveling and alignment device and method for installation of prefabricated wallboards |
CN205000660U (en) * | 2015-09-18 | 2016-01-27 | 重庆合筑实业发展有限公司 | Supplementary tool to lock of adjusting |
CN105297957A (en) * | 2015-10-08 | 2016-02-03 | 安徽同济建设集团有限责任公司 | Prefabricated filled wallboard and mounting method thereof |
CN205804988U (en) * | 2016-02-22 | 2016-12-14 | 北京六建集团有限责任公司 | Prefabricated thermal insulation structural wall board installs special mould clamp |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111962878A (en) * | 2020-06-19 | 2020-11-20 | 青岛中建联合建设工程有限公司 | Detachable combined wall part position regulator |
CN113047666A (en) * | 2021-04-09 | 2021-06-29 | 西安建筑科技大学 | Limiting device is supported in installation of assembled PC wall |
CN113323420A (en) * | 2021-06-29 | 2021-08-31 | 吉林建筑大学 | Prefabricated building wallboard pre-positioning device and method |
Also Published As
Publication number | Publication date |
---|---|
CN105587128B (en) | 2017-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203640309U (en) | Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame | |
CN102305338A (en) | Adjustable adaptor | |
JP2016094786A (en) | Basic assembly frame of outer wall panel and construction method | |
CN105587128A (en) | Special fixture for mounting wallboard with heat insulation structure and mounting method for first-layer wallboard with heat insulation structure | |
CN206636324U (en) | Without column assembling type enclosing shield | |
CN204785424U (en) | Electric power angle steel tower equipment box mounting base | |
CN213359440U (en) | Adjustable steel truss assembling jig frame | |
CN102626841A (en) | Automatic welding fixture of subway train obverse-reverse side roofs | |
JP5753811B2 (en) | Solar panel mount and its construction method | |
CN107939059A (en) | A kind of installation method of aluminum veneer wallboard | |
CN203256905U (en) | Space truss welded ball positioning and adjusting support | |
CN109403639B (en) | Method for installing large-area roof truss stress conversion layer | |
CN109779247A (en) | The formwork erection device and construction method of steel column cornerite | |
CN213868285U (en) | Large-span factory building steel construction beam column | |
CN103028881B (en) | Welding fixture of heavy truck bumper assembly | |
CN101936049A (en) | Mounting structure of stone curtain wall | |
KR101181493B1 (en) | Improved support system | |
CN205712828U (en) | A kind of Assembled stairs of adjustable tilt angle | |
CN209837464U (en) | Large-area roof truss stress conversion layer | |
CN209704012U (en) | The formwork erection device of steel column cornerite | |
CN205804988U (en) | Prefabricated thermal insulation structural wall board installs special mould clamp | |
CN201124290Y (en) | Combination welding device for girder of stair | |
CN109680958B (en) | Large-area roof truss suspended ceiling module, conversion layer and assembly support mounting method | |
CN207971864U (en) | A kind of signal tower support short circuit clamp for machining | |
CN201744814U (en) | Assembly welding tire frame for brackets of bridge fabrication machines |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |