CN105574775A - Emergency drilling flow digitalization model, control method and drilling method - Google Patents

Emergency drilling flow digitalization model, control method and drilling method Download PDF

Info

Publication number
CN105574775A
CN105574775A CN201510969665.8A CN201510969665A CN105574775A CN 105574775 A CN105574775 A CN 105574775A CN 201510969665 A CN201510969665 A CN 201510969665A CN 105574775 A CN105574775 A CN 105574775A
Authority
CN
China
Prior art keywords
module
rehearsal
event
state
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510969665.8A
Other languages
Chinese (zh)
Inventor
王国平
杨选怀
魏文辉
林昌年
高峰
金逸
费益军
马强
陈捷
韩佳兵
周书进
刘传良
慈文斌
马群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Shandong Electric Power Co Ltd
State Grid Jiangsu Electric Power Co Ltd
Beijing Kedong Electric Power Control System Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Shandong Electric Power Co Ltd
State Grid Jiangsu Electric Power Co Ltd
Beijing Kedong Electric Power Control System Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Shandong Electric Power Co Ltd, State Grid Jiangsu Electric Power Co Ltd, Beijing Kedong Electric Power Control System Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510969665.8A priority Critical patent/CN105574775A/en
Publication of CN105574775A publication Critical patent/CN105574775A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09BEDUCATIONAL OR DEMONSTRATION APPLIANCES; APPLIANCES FOR TEACHING, OR COMMUNICATING WITH, THE BLIND, DEAF OR MUTE; MODELS; PLANETARIA; GLOBES; MAPS; DIAGRAMS
    • G09B9/00Simulators for teaching or training purposes

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Educational Technology (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Stored Programmes (AREA)

Abstract

The invention relates to an emergency exercise visualization application technology field of the electric power system. The invention discloses a multi-role multi-task emergency drilling flow digitalization model, comprising a drilling event module and a connection arc; the drilling event module comprises the motion event that each drilling role correspondingly finishes and the event happened during the drilling; the connection arc connects two event modules, which shows the correlation between the event module and the input and the output; and the emergency drilling flow digitalization model adopts the mode of facing the object to express. The beneficial effects of the invention are that the invention adopts the digitalization mode to perform the emergency drilling flow, wherein the emergency drilling flow graph can be conveniently edited and corrected, and can realize the cooperation drilling of multiple drilling roles.

Description

A kind of emergency drilling flow process digital model, control method and drilling method
Technical field
The present invention relates to the visual applied technical field of the emergency drilling of electric system.
Background technology
The relation of electric power and China's national security, economic development and people's lives is more and more closer.So the large area blackout that electric system occurs, all very serious impact can be caused to public safety, national economy and daily life.Emergency drilling is the important step of power emergency management, can realize giveing training emergent commanding and disposal personnel, for Emergency System sets up personnel's intelligence and skills base.
Also face lot of challenges in current power emergency exercise management and capacity building work, be embodied in:.
Emergency drilling comparatively means is single, main adopts combat exercise or desktop maneuvers, and combat exercise, due to cannot real scene under construction accident, be thus drilled effect and received impact; And desktop maneuvers, owing to mainly adopting the interrogation reply system based on script, lack emulation platform and technical support, thus, the rehearsal degree of depth is affected.
Drilling system is not enough: current electric grid company often adopts specific functional test, mainly carries out rehearsal towards grid company certain department inner or several department, carries out simple closed-loop simulation to outside link.This rehearsal, ignores influencing each other of each link of whole Emergency System, cannot realize the checking to Emergency System overall coordination and rehearsal.
Rehearsal assessment mode disappearance: because digitizing, the modeled degree of drilling prediction scheme are lower, not yet set up towards the evaluation system of each link of emergency drilling and analyzing evaluation method, therefore, can only assess emergent prediction scheme executions degree and accuracy, cannot drill according to reality the checking and assessment that process realizes emulating based on mechanism.By the technology such as digitized simulation, virtual reality of research to power emergency rehearsal, can the digitizing of emergency drilling flow process be undertaken alternately by visual means and rehearsal personnel, emergency drilling for electric power enterprise provides good application platform, improves power grid enterprises' disaster prevention emergency ability and working level.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of method deduced with the simulation of the emergency drilling of polygonal look multitask.
Technical scheme of the present invention is as follows:
An emergency drilling flow process digital model for polygonal look multitask, comprises rehearsal event module and is connected arc; Wherein drill event module and comprise event in the action event or rehearsal completed corresponding to each rehearsal role; Connect arc and connect two event module, associate with input and output between presentation of events module, adopt OO mode to express, it is characterized in that:
Described rehearsal event module comprises as properties:
ID: the sign ID of object, the overall situation is unique;
DisplayName: the module title that user sees;
Shape: the shape that module shows, rectangle or rhombus;
Event_type: the type of rehearsal event;
Execute_role: the role performed an action of present event;
Target_role: the destination object role of present event;
Action_content: the particular content of present event describes, as adjust and ask province for instructions and adjust;
Described connection arc comprises as properties:
From_id: the ID connecting the source event module of arc;
To_id: the ID of the object event model of connection layout.
An emergency drilling procedure Procedure control method for polygonal look multitask, it is characterized in that, described method comprises the steps:
Each rehearsal event module is divided into three kinds of states, comprise do not access state, ready state, be finished state; Do not access the original state that state is event module, represent that this module is not accessed; Ready state represents that this module top-ranking module is finished, and this event module can be performed; The state that is finished represents that this event module is finished; When whole event module be all set to be finished state time, then this flow performing is complete; Concrete flow control method is as follows:
1) find the initiation event module of whole process flow diagram, this module is set to ready state, and add the module collection of ready state;
2) circulation carries out following operation to the module of ready state;
3) executive role of this ready morphotype block operates this module, after end of operation, this module is set to the state that is finished, and removes from ready state set;
4) travel through process flow diagram and find subordinate's event module of this process module, if be access state, be then set to ready state and join the set of ready morphotype block;
5) if ready morphotype set of blocks is empty, then step 6 is performed; Otherwise perform step 2;
6) flow performing is complete.
An overall drilling method for the emergency drilling of polygonal look multitask, is characterized in that:
Comprise rehearsal process control module and rehearsal interactive module; In whole rehearsal process, Exercise Control module is unique, and the loading of primary responsibility digitizing rehearsal script and parsing, adopt the state updating of flow control method flowchart, and carry out the transmission of control and message with rehearsal interactive module; Rehearsal interactive module is used for showing interactive interface to rehearsal role, and carries out the transmission of control and message with Exercise Control module, and each rehearsal role needs startup one to drill interactive module;
Concrete rehearsal step is as follows:
Step 1 carries out digitizing by needing the power emergency of rehearsal rehearsal flow process, and saves as xml form rehearsal script;
Step 2 starts rehearsal process control module, for each rehearsal role starts a rehearsal interactive module;
Step 3 is drilled process control module and is loaded digitizing rehearsal script and to go forward side by side this parsing of traveling far and wide;
Step 4 is drilled process control module and is performed rehearsal flow control method, carries out flow process propelling to rehearsal process flow diagram;
Step 5 is when in process flow diagram, certain event module is set to ready state, and the state transfer of this module of rehearsal process control module gives all rehearsal interactive module;
Step 6 when drilling interactive module and finding that the state that it drills event module corresponding to role is alternately set to ready state, then carries out corresponding process flow diagram display, and adopt this event module of flicker to show, prompting rehearsal role carries out the operation of event module;
Step 7 is drilled after role carried out the operation of event module, and the control information of event is passed to Exercise Control module;
After step 8 Exercise Control module receives event control information, event module correspondence being in ready state is set to the state that is finished;
Step 9 Exercise Control module proceeds Row control, until whole process flow diagram is finished.
Beneficial effect of the present invention is:
(1) adopt digitized mode to carry out emergency drilling flow process, emergency drilling process flow diagram can be edited easily and generate and amendment.
(2) rehearsing in coordination of many rehearsal roles is realized.
Accompanying drawing explanation
Fig. 1 is electric network emergency process flow diagram of the present invention.
Fig. 2 is the overall drilling method process flow diagram of emergency drilling of the present invention.
Embodiment
An emergency drilling flow process digital model for polygonal look multitask, comprises rehearsal event module and is connected arc; Wherein drill event module and comprise event in the action event or rehearsal completed corresponding to each rehearsal role; Connect arc and connect two event module, associate with input and output between presentation of events module, adopt OO mode to express, it is characterized in that:
Described rehearsal event module comprises as properties:
ID: the sign ID of object, the overall situation is unique;
DisplayName: the module title that user sees;
Shape: the shape that module shows, rectangle or rhombus;
Event_type: the type of rehearsal event;
Execute_role: the role performed an action of present event;
Target_role: the destination object role of present event;
Action_content: the particular content of present event describes, as adjust and ask province for instructions and adjust;
Described connection arc comprises as properties:
From_id: the ID connecting the source event module of arc;
To_id: the ID of the object event model of connection layout.
An emergency drilling procedure Procedure control method for polygonal look multitask, it is characterized in that, described method comprises the steps:
Each rehearsal event module is divided into three kinds of states, comprise do not access state, ready state, be finished state; Do not access the original state that state is event module, represent that this module is not accessed; Ready state represents that this module top-ranking module is finished, and this event module can be performed; The state that is finished represents that this event module is finished; When whole event module be all set to be finished state time, then this flow performing is complete; Concrete flow control method is as follows:
1) find the initiation event module of whole process flow diagram, this module is set to ready state, and add the module collection of ready state;
2) circulation carries out following operation to the module of ready state;
3) executive role of this ready morphotype block operates this module, after end of operation, this module is set to the state that is finished, and removes from ready state set;
4) travel through process flow diagram and find subordinate's event module of this process module, if be access state, be then set to ready state and join the set of ready morphotype block;
5) if ready morphotype set of blocks is empty, then step 6 is performed; Otherwise perform step 2;
6) flow performing is complete.
An overall drilling method for the emergency drilling of polygonal look multitask, is characterized in that:
Comprise rehearsal process control module and rehearsal interactive module; In whole rehearsal process, Exercise Control module is unique, and the loading of primary responsibility digitizing rehearsal script and parsing, adopt the state updating of flow control method flowchart, and carry out the transmission of control and message with rehearsal interactive module; Rehearsal interactive module is used for showing interactive interface to rehearsal role, and carries out the transmission of control and message with Exercise Control module, and each rehearsal role needs startup one to drill interactive module;
Concrete rehearsal step is as follows:
Step 1 carries out digitizing by needing the power emergency of rehearsal rehearsal flow process, and saves as xml form rehearsal script;
Step 2 starts rehearsal process control module, for each rehearsal role starts a rehearsal interactive module;
Step 3 is drilled process control module and is loaded digitizing rehearsal script and to go forward side by side this parsing of traveling far and wide;
Step 4 is drilled process control module and is performed rehearsal flow control method, carries out flow process propelling to rehearsal process flow diagram;
Step 5 is when in process flow diagram, certain event module is set to ready state, and the state transfer of this module of rehearsal process control module gives all rehearsal interactive module;
Step 6 when drilling interactive module and finding that the state that it drills event module corresponding to role is alternately set to ready state, then carries out corresponding process flow diagram display, and adopt this event module of flicker to show, prompting rehearsal role carries out the operation of event module;
Step 7 is drilled after role carried out the operation of event module, and the control information of event is passed to Exercise Control module;
After step 8 Exercise Control module receives event control information, event module correspondence being in ready state is set to the state that is finished;
Step 9 Exercise Control module proceeds Row control, until whole process flow diagram is finished.

Claims (3)

1. an emergency drilling flow process digital model for polygonal look multitask, comprises rehearsal event module and is connected arc; Wherein drill event module and comprise event in the action event or rehearsal completed corresponding to each rehearsal role; Connect arc and connect two event module, associate with input and output between presentation of events module, adopt OO mode to express, it is characterized in that:
Described rehearsal event module comprises as properties:
ID: the sign ID of object, the overall situation is unique;
DisplayName: the module title that user sees;
Shape: the shape that module shows, rectangle or rhombus;
Event_type: the type of rehearsal event;
Execute_role: the role performed an action of present event;
Target_role: the destination object role of present event;
Action_content: the particular content of present event describes, as adjust and ask province for instructions and adjust;
Described connection arc comprises as properties:
From_id: the ID connecting the source event module of arc;
To_id: the ID of the object event model of connection layout.
2. an emergency drilling procedure Procedure control method for polygonal look multitask, it is characterized in that, described method comprises the steps:
Each rehearsal event module is divided into three kinds of states, comprise do not access state, ready state, be finished state; Do not access the original state that state is event module, represent that this module is not accessed; Ready state represents that this module top-ranking module is finished, and this event module can be performed; The state that is finished represents that this event module is finished; When whole event module be all set to be finished state time, then this flow performing is complete; Concrete flow control method is as follows:
1) find the initiation event module of whole process flow diagram, this module is set to ready state, and add the module collection of ready state;
2) circulation carries out following operation to the module of ready state;
3) executive role of this ready morphotype block operates this module, after end of operation, this module is set to the state that is finished, and removes from ready state set;
4) travel through process flow diagram and find subordinate's event module of this process module, if be access state, be then set to ready state and join the set of ready morphotype block;
5) if ready morphotype set of blocks is empty, then step 6 is performed; Otherwise perform step 2;
6) flow performing is complete.
3. an overall drilling method for the emergency drilling of polygonal look multitask, is characterized in that:
Comprise rehearsal process control module and rehearsal interactive module; In whole rehearsal process, Exercise Control module is unique, and the loading of primary responsibility digitizing rehearsal script and parsing, adopt the state updating of flow control method flowchart, and carry out the transmission of control and message with rehearsal interactive module; Rehearsal interactive module is used for showing interactive interface to rehearsal role, and carries out the transmission of control and message with Exercise Control module, and each rehearsal role needs startup one to drill interactive module;
Concrete rehearsal step is as follows:
Step 1 carries out digitizing by needing the power emergency of rehearsal rehearsal flow process, and saves as xml form rehearsal script;
Step 2 starts rehearsal process control module, for each rehearsal role starts a rehearsal interactive module;
Step 3 is drilled process control module and is loaded digitizing rehearsal script and to go forward side by side this parsing of traveling far and wide;
Step 4 is drilled process control module and is performed rehearsal flow control method, carries out flow process propelling to rehearsal process flow diagram;
Step 5 is when in process flow diagram, certain event module is set to ready state, and the state transfer of this module of rehearsal process control module gives all rehearsal interactive module;
Step 6 when drilling interactive module and finding that the state that it drills event module corresponding to role is alternately set to ready state, then carries out corresponding process flow diagram display, and adopt this event module of flicker to show, prompting rehearsal role carries out the operation of event module;
Step 7 is drilled after role carried out the operation of event module, and the control information of event is passed to Exercise Control module;
After step 8 Exercise Control module receives event control information, event module correspondence being in ready state is set to the state that is finished;
Step 9 Exercise Control module proceeds Row control, until whole process flow diagram is finished.
CN201510969665.8A 2015-12-22 2015-12-22 Emergency drilling flow digitalization model, control method and drilling method Pending CN105574775A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510969665.8A CN105574775A (en) 2015-12-22 2015-12-22 Emergency drilling flow digitalization model, control method and drilling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510969665.8A CN105574775A (en) 2015-12-22 2015-12-22 Emergency drilling flow digitalization model, control method and drilling method

Publications (1)

Publication Number Publication Date
CN105574775A true CN105574775A (en) 2016-05-11

Family

ID=55884874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510969665.8A Pending CN105574775A (en) 2015-12-22 2015-12-22 Emergency drilling flow digitalization model, control method and drilling method

Country Status (1)

Country Link
CN (1) CN105574775A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106354370A (en) * 2016-08-31 2017-01-25 金现代信息产业股份有限公司 Emergency drilling system interaction method
CN106683512A (en) * 2016-08-30 2017-05-17 大连伟岸纵横科技股份有限公司 Virtual reality training system based on online shopping mall
CN111310330A (en) * 2020-02-12 2020-06-19 广州奥格智能科技有限公司 Safety emergency plan digitalized parameter design method, system, storage medium and computer equipment
CN114064231A (en) * 2021-10-13 2022-02-18 北京市应急管理科学技术研究院 Task configuration method, system, storage medium and electronic equipment

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102609773A (en) * 2012-01-20 2012-07-25 华迪计算机集团有限公司 Digital pre-plan-based emergency dispatching processing system
CN105023200A (en) * 2015-08-04 2015-11-04 中国南方电网有限责任公司 Power emergency drilling system and emergency drilling method thereof

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102609773A (en) * 2012-01-20 2012-07-25 华迪计算机集团有限公司 Digital pre-plan-based emergency dispatching processing system
CN105023200A (en) * 2015-08-04 2015-11-04 中国南方电网有限责任公司 Power emergency drilling system and emergency drilling method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王鹏: "特种设备的三维可视化仿真技术研究", 《中国优秀硕士学位论文全文数据库》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106683512A (en) * 2016-08-30 2017-05-17 大连伟岸纵横科技股份有限公司 Virtual reality training system based on online shopping mall
CN106354370A (en) * 2016-08-31 2017-01-25 金现代信息产业股份有限公司 Emergency drilling system interaction method
CN106354370B (en) * 2016-08-31 2019-06-28 金现代信息产业股份有限公司 Emergency drilling system exchange method
CN111310330A (en) * 2020-02-12 2020-06-19 广州奥格智能科技有限公司 Safety emergency plan digitalized parameter design method, system, storage medium and computer equipment
CN111310330B (en) * 2020-02-12 2024-03-29 奥格科技股份有限公司 Method, system, storage medium and computer equipment for designing digital parameters of safety emergency plan
CN114064231A (en) * 2021-10-13 2022-02-18 北京市应急管理科学技术研究院 Task configuration method, system, storage medium and electronic equipment
CN114064231B (en) * 2021-10-13 2022-07-05 北京市应急管理科学技术研究院 Task configuration method, system, storage medium and electronic equipment

Similar Documents

Publication Publication Date Title
Guo et al. Using game technologies to improve the safety of construction plant operations
CN108230805B (en) Electric power emergency drilling deduction system based on scene construction
CN105574775A (en) Emergency drilling flow digitalization model, control method and drilling method
Bjørner et al. 40 years of formal methods: Some obstacles and some possibilities?
CN105976670A (en) Three-dimensional emergency drilling virtual system and construction method and use method thereof
Li et al. A virtual reality platform for safety training in coal mines with AI and cloud computing
CN103606314B (en) The virtual training operation system of a kind of colliery main shaft hooist
CN105719552A (en) Interactive simulation emergency exercise system
KR20160110867A (en) System and method for constructing of respose on disaster based on scenario
CN105446164A (en) Semi-physical simulation test system
CN104700677A (en) Generating method of simulation drilling and digital drilling of simulation training
CN103678873A (en) Contingency plan co-simulation method for chemical laboratory hazardous material management and systems thereof
CN104700678A (en) Simulation training and simulation drilling system
CN112767529A (en) Three-dimensional visual intelligent fusion platform for mine
CN104299464A (en) Simulating training system for electric safety skills
CN103955144A (en) Multi-Agent based virtual coal mine emergency evacuation simulation method and system based on
CN102592022A (en) Rail transit scene simulation system
CN2916800Y (en) Train failure emulator
KR20140021389A (en) Apparatus and method for separable simulation by model design and execution
CN109003211A (en) A kind of emergency drilling system and method
Chen et al. Digital Mining Technology-Based Teaching Mode for Mining Engineering.
CN106409045A (en) Safety emergency training method and system for hydraulic power plant
Sharaf et al. Simulating architectures of situational-aware cyber-physical space
Di Benedetti et al. Build it and they will come: maintaining students access to fabrication and testing during a pandemic
CN103023732A (en) Information security laboratory device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160511