CN105544464A - Method for embankment construction using removed river deposit from medium and small rivers in mountainous area - Google Patents

Method for embankment construction using removed river deposit from medium and small rivers in mountainous area Download PDF

Info

Publication number
CN105544464A
CN105544464A CN201610001616.XA CN201610001616A CN105544464A CN 105544464 A CN105544464 A CN 105544464A CN 201610001616 A CN201610001616 A CN 201610001616A CN 105544464 A CN105544464 A CN 105544464A
Authority
CN
China
Prior art keywords
embankment
construction method
seepage
mountain area
beach
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610001616.XA
Other languages
Chinese (zh)
Other versions
CN105544464B (en
Inventor
王立华
黄锦林
黄亚梅
张挺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG WATER RESOURCES AND ELECTRIC POWER VOCATIONAL TECHNOLOGY INSTITUTE
Guangdong Research Institute of Water Resources and Hydropower
Original Assignee
GUANGDONG WATER RESOURCES AND ELECTRIC POWER VOCATIONAL TECHNOLOGY INSTITUTE
Guangdong Research Institute of Water Resources and Hydropower
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG WATER RESOURCES AND ELECTRIC POWER VOCATIONAL TECHNOLOGY INSTITUTE, Guangdong Research Institute of Water Resources and Hydropower filed Critical GUANGDONG WATER RESOURCES AND ELECTRIC POWER VOCATIONAL TECHNOLOGY INSTITUTE
Priority to CN201610001616.XA priority Critical patent/CN105544464B/en
Publication of CN105544464A publication Critical patent/CN105544464A/en
Application granted granted Critical
Publication of CN105544464B publication Critical patent/CN105544464B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/128Coherent linings made on the spot, e.g. cast in situ, extruded on the spot
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • E02B3/127Flexible prefabricated covering elements, e.g. mats, strips bags filled at the side

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

本发明公开一种山区中小河流清滩料筑堤施工方法,其包括以下步骤,将山区中小河流的河滩卵砾石、沙土除去杂物后,混合均匀,运至堤身,分层碾压密实;在堤身临河侧表面顺坡上填筑粘土防渗斜墙;在粘土防渗斜墙表面布置反滤层;在反滤层上布置护坡;在堤脚布置护脚。本发明采用清滩料筑堤,打破了筑堤须用均质土的传统思想束缚,采取简便经济的技术措施,确保堤岸稳定和渗流稳定,既可减小清滩料外运,也可避免筑堤均质土的运输,节省工程投资,也保护生态。本发明适用于山区中筑堤施工中。The invention discloses a construction method for embankment construction of beach clearing materials for small and medium-sized rivers in mountainous areas, which comprises the following steps: removing sundries from beach pebbles and sand of small and medium-sized rivers in mountainous areas; Clay anti-seepage sloping walls are filled on the surface of the embankment near the river; anti-seepage layers are arranged on the surface of clay anti-seepage slant walls; slope protection is arranged on the anti-seepage layers; foot guards are arranged at the foot of the embankment. The invention uses beach-clearing materials to build embankments, which breaks the shackles of the traditional idea that homogeneous soil must be used for embankments, and adopts simple and economical technical measures to ensure the stability of embankments and seepage. The transportation of homogeneous soil for embankment saves engineering investment and protects the ecology. The invention is suitable for embankment construction in mountainous areas.

Description

一种山区中小河流清滩料筑堤施工方法A construction method for embankment construction with beach clearing materials for small and medium rivers in mountainous areas

技术领域technical field

本发明涉及一种筑堤施工方法,特别是一种山区中小河流清滩料筑堤施工方法。The invention relates to an embankment construction method, in particular to an embankment construction method with beach clearing materials for small and medium-sized rivers in mountainous areas.

背景技术Background technique

山区河流众多,河流短、比降大,致使洪水来得猛、去得快,且大部分为无堤防或堤防标准低的河流,河道防洪能力低,每逢汛期极易造成泥石流、堤防决口、冲毁村庄和道路、淹没农田等重大灾害,且大部分中小河流两岸土地肥沃,人口密集,洪涝灾害损失较大。There are many rivers in mountainous areas, the rivers are short and have a large gradient, so that the floods come and go quickly, and most of them are rivers with no embankments or low embankment standards, and the flood control capacity of the rivers is low. Major disasters such as destroying villages and roads, submerging farmland, etc., and most of the small and medium-sized rivers have fertile land, dense population, and great losses in flood disasters.

山区中小河流具有流域面积小、流程短、汇流时间短、河道比降大,以及汛期洪水陡涨陡落,而枯水期流量很小,有的基本断流,河岸或河堤承受高水位压力的时间不长、对堤岸的破坏作用相对较小、流岸滩宽阔、堤岸坡度较缓,高度较小,堤后多为农田、降水充沛、气候宜人、有利于植物生长等特点,在山区中小河流的治理中应结合实际,因地制宜,把安全、生态放在首要位置,尽可能保留河流的自然状态,采取生态治理的模式。按照传统的大江大河治理方法和要求,河流堤岸须用均质土填筑,河道清滩料是不能用于筑堤的,因此,一方面,大量山区中小河流治理工程将河道清滩料外运,建设堆场存放,占用了大量土地,堆场往往成为难题;另一方面,从外运入均质土筑堤,对山林造成一定的破坏。这样,一来一回,不仅增大了投资,浪费了土地,毁坏了山林,浪费了资源,破坏了生态,并且,容易增加工程与当地的矛盾,不利于工程建设顺利推进。如果清滩料可用于筑堤,这些问题都将迎刃而解。Small and medium-sized rivers in mountainous areas have small basin area, short flow, short confluence time, large river slope, and steep flood seasons with steep rises and falls, while the flow rate in dry seasons is small, and some of them are basically cut off. Not long, the damage to the embankment is relatively small, the flow bank is wide, the slope of the embankment is gentle, and the height is small. There are mostly farmland behind the embankment, abundant precipitation, pleasant climate, and conducive to plant growth. In the process of governance, we should combine the actual situation and adapt measures to local conditions, put safety and ecology in the first place, preserve the natural state of the river as much as possible, and adopt the model of ecological governance. According to the traditional treatment methods and requirements of large rivers, river embankments must be filled with homogeneous soil, and river beach cleaning materials cannot be used for embankment construction. , The construction of a storage yard for storage takes up a lot of land, and the storage yard often becomes a problem; on the other hand, transporting in homogeneous soil from outside to build embankments will cause certain damage to the mountains and forests. In this way, it not only increases investment, wastes land, destroys forests, wastes resources, and destroys ecology, but also easily increases the contradiction between the project and the local area, which is not conducive to the smooth progress of project construction. If beach clearing materials can be used to build embankments, these problems will be solved.

发明内容Contents of the invention

本发明的目的,在于提供一种山区中小河流清滩料筑堤施工方法,其通过采用清滩料筑堤,打破了筑堤须用均质土的传统思想束缚,采取简便经济的技术措施,确保堤岸稳定和渗流稳定,既可减小清滩料外运,也可避免筑堤均质土的运输,节省工程投资,也保护生态。The purpose of the present invention is to provide a kind of embankment construction method of clearing beach materials for small and medium rivers in mountainous areas, which breaks the shackles of the traditional thought that building embankments must use homogeneous soil by adopting beach clearing materials to build embankments, and takes simple and economical technical measures, Ensuring embankment stability and seepage stability can not only reduce the outbound transportation of beach cleaning materials, but also avoid the transportation of homogeneous soil for embankment, saving project investment and protecting the ecology.

本发明解决其技术问题的解决方案是:一种山区中小河流清滩料筑堤施工方法,其包括以下步骤,The solution of the present invention to solve its technical problem is: a kind of construction method of clearing beach materials for small and medium-sized rivers in mountainous areas, which comprises the following steps,

1)将山区中小河流的河滩卵砾石、沙土除去杂物后,混合均匀,运至堤身,分层碾压密实,分层厚度30cm~50cm;1) Remove debris from the beach pebbles, gravels and sand of small and medium-sized rivers in mountainous areas, mix them evenly, transport them to the embankment, and compact them layer by layer, with a layer thickness of 30cm to 50cm;

2)在堤身临河侧表面顺坡上填筑粘土防渗斜墙,粘土防渗斜墙的厚度30cm~100cm,分层碾压密实,分层高度30cm~50cm;2) Clay anti-seepage inclined walls are filled on the slope along the surface of the side of the embankment, the thickness of the clay anti-seepage inclined walls is 30cm-100cm, and the layers are compacted and compacted, and the layer height is 30cm-50cm;

3)在粘土防渗斜墙表面通过级配砂石和土工布布置反滤层;3) Arrange the reverse filter layer on the surface of the clay anti-seepage inclined wall through graded sandstone and geotextile;

4)在反滤层上通过块石、格宾护垫以及草皮布置护坡,厚度20cm~50cm;4) Arrange slope protection on the reverse filter layer through block stones, gabion pads and turf, with a thickness of 20cm to 50cm;

5)在堤脚通过混凝土、浆砌石、干砌石、格宾网箱以及砌块布置护脚。5) Arrange toe guards at the foot of the embankment through concrete, masonry, dry stone, gabion cages and blocks.

作为上述技术方案的进一步改进,在步骤5)之后,在护脚附近的河床上通过清滩卵砾石、抛石、格宾网箱布置护坦。As a further improvement of the above technical solution, after step 5), the apron is arranged on the riverbed near the foot protection by clearing beach pebbles, gravel, riprap and gabion cages.

作为上述技术方案的进一步改进,在所述堤身顶部通过混凝土、沥青和泥结石布置堤顶路面,所述堤顶路面的厚度10cm~50cm,堤顶路面宽度窄于堤顶宽度。As a further improvement of the above technical solution, concrete, asphalt and mud stones are used to arrange the embankment crest pavement on the top of the embankment, the thickness of the embankment crest pavement is 10cm-50cm, and the width of the embankment crest pavement is narrower than that of the embankment crest.

作为上述技术方案的进一步改进,所述堤身中的分层间隙和粘土防渗斜墙中的分层间隙错开。As a further improvement of the above technical solution, the layer gaps in the dike body and the layer gaps in the clay anti-seepage inclined wall are staggered.

作为上述技术方案的进一步改进,在步骤3)中,所述级配砂石装进木工布后在粘土防渗斜墙表面布置成反滤层,级配砂石的厚度10cm~15cm。As a further improvement of the above technical solution, in step 3), the graded sand and gravel are put into carpentry cloth and arranged on the surface of the clay anti-seepage inclined wall to form a reverse filter layer, and the thickness of the graded sand and gravel is 10cm-15cm.

作为上述技术方案的进一步改进,在步骤5)中,所述护脚位于深泓近岸段时,应延伸至深泓线,并应满足河床最大冲刷深度的要求;所述护脚位于在水流平顺、岸坡较缓段时,宜护至坡度为l:3~1:4的缓坡河床处,护脚宽度0.3m至0.6m,顶高程至设计枯水位。As a further improvement of the above technical solution, in step 5), when the foot protection is located in the nearshore section of the deep stream, it should extend to the deep water line and meet the requirements for the maximum scour depth of the river bed; When the bank is smooth and the slope is relatively gentle, it should be protected to the gentle slope riverbed with a slope of 1:3 to 1:4, the width of the foot protection is 0.3m to 0.6m, and the top elevation is to the design dry water level.

本发明的有益效果是:本发明采用清滩料筑堤,打破了筑堤须用均质土的传统思想束缚,采取简便经济的技术措施,确保堤岸稳定和渗流稳定,既可减小清滩料外运,也可避免筑堤均质土的运输,节省工程投资,也保护生态。The beneficial effect of the present invention is that: the present invention adopts beach-clearing materials to build embankments, breaks the shackles of the traditional idea that homogeneous soil must be used for embankment, adopts simple and economical technical measures, ensures embankment stability and seepage stability, and can reduce the need for beach clearing. Transportation of materials can also avoid the transportation of homogeneous soil for embankment, save engineering investment and protect the ecology.

具体实施方式detailed description

以下将结合实施例对本发明的构思、具体结构及产生的技术效果进行清楚、完整地描述,以充分地理解本发明的目的、特征和效果。显然,所描述的实施例只是本发明的一部分实施例,而不是全部实施例,基于本发明的实施例,本领域的技术人员在不付出创造性劳动的前提下所获得的其他实施例,均属于本发明保护的范围。另外,文中所提到的所有联接/连接关系,并非单指构件直接相接,而是指可根据具体实施情况,通过添加或减少联接辅件,来组成更优的联接结构。The idea, specific structure and technical effects of the present invention will be clearly and completely described below in conjunction with the embodiments, so as to fully understand the purpose, features and effects of the present invention. Apparently, the described embodiments are only some of the embodiments of the present invention, rather than all of them. Based on the embodiments of the present invention, other embodiments obtained by those skilled in the art without creative efforts belong to The protection scope of the present invention. In addition, all the connection/connection relationships mentioned in this article do not refer to the direct connection of components, but mean that a better connection structure can be formed by adding or reducing connection accessories according to specific implementation conditions.

一种山区中小河流清滩料筑堤施工方法,其包括以下步骤,A construction method for building embankments with clearing materials for small and medium rivers in mountainous areas, comprising the following steps,

1)将山区中小河流的河滩卵砾石、沙土除去杂物后,混合均匀,运至堤身,分层碾压密实,分层厚度30cm~50cm;1) Remove debris from the beach pebbles, gravels and sand of small and medium-sized rivers in mountainous areas, mix them evenly, transport them to the embankment, and compact them layer by layer, with a layer thickness of 30cm to 50cm;

2)在堤身临河侧表面顺坡上填筑粘土防渗斜墙,粘土防渗斜墙的厚度30cm~100cm,分层碾压密实,分层高度30cm~50cm;2) Clay anti-seepage inclined walls are filled on the slope along the surface of the side of the embankment, the thickness of the clay anti-seepage inclined walls is 30cm-100cm, and the layers are compacted and compacted, and the layer height is 30cm-50cm;

3)在粘土防渗斜墙表面通过级配砂石和土工布布置反滤层;3) Arrange the reverse filter layer on the surface of the clay anti-seepage inclined wall through graded sandstone and geotextile;

4)在反滤层上通过块石、格宾护垫以及草皮布置护坡,厚度20cm~50cm;4) Arrange slope protection on the reverse filter layer through block stones, gabion pads and turf, with a thickness of 20cm to 50cm;

5)在堤脚通过混凝土、浆砌石、干砌石、格宾网箱以及砌块布置护脚。5) Arrange toe guards at the foot of the embankment through concrete, masonry, dry stone, gabion cages and blocks.

进一步作为优选的实施方式,在步骤5)之后,在护脚附近的河床上通过清滩卵砾石、抛石、格宾网箱布置护坦。As a further preferred embodiment, after step 5), the apron is arranged on the river bed near the foot protection by clearing beach pebbles, riprap, and gabion cages.

进一步作为优选的实施方式,在所述堤身顶部通过混凝土、沥青和泥结石布置堤顶路面,所述堤顶路面的厚度10cm~50cm,堤顶路面宽度窄于堤顶宽度。As a further preferred embodiment, concrete, asphalt and mud stones are used to arrange the embankment crest pavement on the top of the embankment, the thickness of the embankment crest pavement is 10cm-50cm, and the width of the embankment crest pavement is narrower than that of the embankment crest.

进一步作为优选的实施方式,所述堤身中的分层间隙和粘土防渗斜墙中的分层间隙错开。As a further preferred embodiment, the layered gaps in the dike body and the layered gaps in the clay anti-seepage inclined wall are staggered.

进一步作为优选的实施方式,在步骤3)中,所述级配砂石装进木工布后在粘土防渗斜墙表面布置成反滤层,级配砂石的厚度10cm~15cm。As a further preferred embodiment, in step 3), the graded sand and gravel are packed into carpentry cloth and arranged on the surface of the clay anti-seepage inclined wall to form a reverse filter layer, and the thickness of the graded sand and gravel is 10cm-15cm.

进一步作为优选的实施方式,在步骤5)中,所述护脚位于深泓近岸段时,应延伸至深泓线,并应满足河床最大冲刷深度的要求;所述护脚位于在水流平顺、岸坡较缓段时,宜护至坡度为l:3~1:4的缓坡河床处,护脚宽度0.3m至0.6m,顶高程至设计枯水位。As a further preferred embodiment, in step 5), when the foot protection is located in the nearshore section of the deep stream, it should extend to the deep water line and meet the requirements for the maximum scouring depth of the river bed; 1. When the bank slope is relatively gentle, it should be protected to the gentle slope riverbed with a slope of 1:3 to 1:4, the width of the foot protection is 0.3m to 0.6m, and the top elevation is to the design dry water level.

山区中小河流清滩料是一种生态筑堤材料,具有如下特点:Beach clearing material for small and medium rivers in mountainous areas is an ecological embankment material with the following characteristics:

1)就地取材,经济合理,是多孔隙、透水透气、环境友好的天然建筑材料;1) Local materials, economical and reasonable, are porous, permeable, and environmentally friendly natural building materials;

2)在保证安全的前提下,可建设生态良好、景观优美的近自然河岸结构,以保护和创造河岸生物良好的生存环境;2) On the premise of ensuring safety, a near-natural river bank structure with good ecology and beautiful landscape can be built to protect and create a good living environment for river bank organisms;

3)适应河床变形能力应强;3) The ability to adapt to the deformation of the riverbed should be strong;

4)便于施工、修复、加固。4) It is convenient for construction, repair and reinforcement.

以下是本发明优选的一个实施例。The following is a preferred embodiment of the present invention.

将山区中小河流的河滩卵砾石、沙土除去杂物后,混合均匀,用勾机翻运至堤身,分层碾压密实,分层厚度30cm~50cm,堤身断面尺寸应满足设计洪水的要求;Remove debris from the beach pebbles, gravel and sand of small and medium-sized rivers in mountainous areas, mix them evenly, turn them over to the embankment with a hook machine, and compact them layer by layer, with a thickness of 30cm to 50cm. ;

堤身临河侧表面顺坡填筑粘土防渗斜墙,粘土防渗斜墙的材料为粘性土料,粘土防渗斜墙的厚度30cm~100cm,分层碾压密实,分层高度30cm~50cm,渗透系数和密实度应满足设计要求。Clay anti-seepage inclined wall is filled along the slope on the surface of the embankment facing the river. The material of the clay anti-seepage inclined wall is cohesive soil material. The thickness of the clay anti-seepage inclined wall is 30cm-100cm. , permeability coefficient and compactness should meet the design requirements.

在粘土防渗斜墙表面布置反滤层,材料为级配砂石、土工布等,级配砂石厚度10cm~15cm。Arrange the anti-filtration layer on the surface of the clay anti-seepage inclined wall. The material is graded sand and gravel, geotextile, etc., and the thickness of the graded sand and gravel is 10cm to 15cm.

在反滤层上布置护坡,护坡厚度20cm~50cm,材料可以是块石、格宾护垫、草皮等。Arrange slope protection on the filter layer, slope protection thickness 20cm ~ 50cm, materials can be block stones, gabion pads, turf and so on.

在堤脚布置护脚,护脚位于深泓近岸段时,应延伸至深泓线,并应满足河床最大冲刷深度的要求;护脚位于在水流平顺、岸坡较缓段时,宜护至坡度为l:3~1:4的缓坡河床处,护脚宽度0.3m至0.6m,顶高程至设计枯水位。护脚材料包括混凝土、浆砌石、干砌石、格宾网箱、砌块等。Arrange toe guards at the foot of the embankment. When the toe guards are located at the near-shore section of Shenhong, they should extend to the deep Hong line and meet the requirements for the maximum scouring depth of the river bed; To the gentle slope riverbed with a slope of 1:3 to 1:4, the width of the toe guards is 0.3m to 0.6m, and the top elevation reaches the design dry water level. Foot protection materials include concrete, mortar masonry, dry masonry, gabion cages, blocks, etc.

在护脚附近的河床上布置护坦,材料为清滩卵砾石、抛石、格宾网箱等;护坦的厚度、宽度应满足地形和水流稳定的需要。Arrange aprons on the riverbed near the toe guards, and the materials are beach pebbles, riprap, gabion cages, etc.; the thickness and width of the aprons should meet the needs of terrain and water flow stability.

在堤身顶部布置堤顶路面,堤顶路面的厚度10cm~50cm,材料可以是混凝土、沥青、泥结石等,堤顶路面的宽度窄于堤顶宽度。On the top of the embankment, the embankment crest pavement is arranged. The thickness of the embankment crest pavement is 10cm to 50cm.

以上是对本发明的较佳实施方式进行了具体说明,但本发明创造并不限于所述实施例,熟悉本领域的技术人员在不违背本发明精神的前提下还可作出种种的等同变型或替换,这些等同的变型或替换均包含在本申请权利要求所限定的范围内。The above is a specific description of the preferred embodiments of the present invention, but the invention is not limited to the described embodiments, those skilled in the art can also make various equivalent modifications or replacements without violating the spirit of the present invention , these equivalent modifications or replacements are all included within the scope defined by the claims of the present application.

Claims (6)

1. a mountain area middle and small river clear beach material fill construction method, is characterized in that: it comprises the following steps,
1) by after the river shoal boulder and cobble of mountain area middle and small river, sandy soil removing foreign material, mix, be transported to levee body, layered rolling is closely knit, lift height 30cm ~ 50cm;
2) border on the river side surface along slope being filled clay core sloping core at levee body, the thickness 30cm ~ 100cm of clay core sloping core, layered rolling is closely knit, layer height 30cm ~ 50cm;
3) loaded filter is arranged on clay core sloping core surface by graded sand and stone and geotextiles;
4) on loaded filter, bank protection is arranged by block stone, lattice guest protection pad and turf, thickness 20cm ~ 50cm;
5) spats is arranged at levee toe by concrete, stone masonry, dry stone wall, gabion and building block.
2. mountain area according to claim 1 middle and small river clear beach material fill construction method, is characterized in that: after step 5), protection-apron is arranged by clear beach boulder and cobble, jackstone, gabion in the riverbed near spats.
3. mountain area according to claim 2 middle and small river clear beach material fill construction method, it is characterized in that: arrange road on the bank at described levee body top by concrete, pitch and mud calculus, thickness 10cm ~ the 50cm of described road on the bank, road on the bank width is narrower than levee crown width.
4. mountain area according to claim 1 middle and small river clear beach material fill construction method, is characterized in that: stagger in point lamellar spacing in described levee body and point lamellar spacing in clay core sloping core.
5. mountain area according to claim 1 middle and small river clear beach material fill construction method, it is characterized in that: in step 3), described graded sand and stone is arranged to loaded filter on clay core sloping core surface, the thickness 10cm ~ 15cm of graded sand and stone after putting into carpenter's cloth.
6. mountain area according to claim 1 middle and small river clear beach material fill construction method, is characterized in that: in step 5), when described spats is positioned at thalweg offshore section, should extend to talweg, and should meet the requirement of riverbed limiting scour; Described spats is located at that current are smooth-going, bank slope comparatively slow section time, should protect to the gradient is riverbed, the gentle slope place of l:3 ~ 1:4, and spats width 0.3m to 0.6m, crest level is to design low water position.
CN201610001616.XA 2016-01-05 2016-01-05 A kind of clear beach material fill construction method of mountain area middle and small river Expired - Fee Related CN105544464B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610001616.XA CN105544464B (en) 2016-01-05 2016-01-05 A kind of clear beach material fill construction method of mountain area middle and small river

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610001616.XA CN105544464B (en) 2016-01-05 2016-01-05 A kind of clear beach material fill construction method of mountain area middle and small river

Publications (2)

Publication Number Publication Date
CN105544464A true CN105544464A (en) 2016-05-04
CN105544464B CN105544464B (en) 2017-10-10

Family

ID=55823991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610001616.XA Expired - Fee Related CN105544464B (en) 2016-01-05 2016-01-05 A kind of clear beach material fill construction method of mountain area middle and small river

Country Status (1)

Country Link
CN (1) CN105544464B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107542059A (en) * 2017-09-14 2018-01-05 张传河 A kind of method repaired base soil and be lost in buttress

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100577845B1 (en) * 2005-09-29 2006-05-10 주식회사 남원건설엔지니어링 Environment-friendly river shoreline installation structure
CN203383188U (en) * 2013-08-06 2014-01-08 江西省水利规划设计院 Ground sand pebble revetment
CN204282308U (en) * 2014-11-18 2015-04-22 中国电建集团贵阳勘测设计研究院有限公司 Gabion composite dam adapting to deep covering layer
CN204418127U (en) * 2015-01-30 2015-06-24 广东梅雁吉祥水电股份有限公司 A kind of landscape type overfall dam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100577845B1 (en) * 2005-09-29 2006-05-10 주식회사 남원건설엔지니어링 Environment-friendly river shoreline installation structure
CN203383188U (en) * 2013-08-06 2014-01-08 江西省水利规划设计院 Ground sand pebble revetment
CN204282308U (en) * 2014-11-18 2015-04-22 中国电建集团贵阳勘测设计研究院有限公司 Gabion composite dam adapting to deep covering layer
CN204418127U (en) * 2015-01-30 2015-06-24 广东梅雁吉祥水电股份有限公司 A kind of landscape type overfall dam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107542059A (en) * 2017-09-14 2018-01-05 张传河 A kind of method repaired base soil and be lost in buttress
CN107542059B (en) * 2017-09-14 2019-04-09 张传河 A method of it repairing base soil flow and loses buttress

Also Published As

Publication number Publication date
CN105544464B (en) 2017-10-10

Similar Documents

Publication Publication Date Title
CN105178245A (en) Large filling bag ecological embankment and revetment building method for river lake channel
CN105178125B (en) A kind of lake region High-filled emkankment is blown sand embankments construction method and embankment structure
CN106801403B (en) A method for preventing debris flow disasters and recycling debris flow products
CN106149625B (en) A kind of ecological self-purification type landscape revetment reconstruction structure and its construction method
CN108612041A (en) Anti-impact ecotype groynes
CN102953353B (en) A method for ecological slope protection of river embankments reinforced by microorganisms
CN105064291A (en) Step sand-blocking dam ecosystem for reservoir desilting and sand prevention
CN206438465U (en) A kind of ecological self-purification type landscape revetment reconstruction structure
CN206189345U (en) Dry rubble ecological landscape bank protection is filled on concrete check ridge
CN102518136A (en) Flexible reinforced combined protection structure for preventing and treating humidifying damage of soft rock strongly weathered zone
CN207452823U (en) A kind of ecology typed bank revetment sea wall
CN207121477U (en) A kind of combined biological dam
CN108612042A (en) Local overcurrent ecotype groynes
CN109024485A (en) River protection against erosion ecological slope protection structure
CN211420758U (en) Road drainage structure that drainage performance is high
CN204825785U (en) Stain farm ditch is arranged in water logging control of adopting geotextile ecological bag to build shore protection by laying bricks or stones
CN105544464B (en) A kind of clear beach material fill construction method of mountain area middle and small river
CN218880749U (en) Soil and water conservation bank protection system for small watershed
CN203256678U (en) A kind of submerged spur dam suitable for natural edge beach
CN202881901U (en) Stepped undercurrent type ecological embankment structure
CN214832388U (en) River course shore protection structure of reinforcing river bank steadiness
CN215593889U (en) Ecological revetment structure suitable for urban river
CN111321700B (en) An over-current energy-dissipating ecological bank protection method for anti-scour and anti-slope damming
CN205062597U (en) Road bed embankment structure of blowing sand is filled out to lake region height
CN207567719U (en) The dykes and dams that a kind of gangue dead meal fills

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171010

Termination date: 20220105