CN105529686B - A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line - Google Patents

A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line Download PDF

Info

Publication number
CN105529686B
CN105529686B CN201610035165.1A CN201610035165A CN105529686B CN 105529686 B CN105529686 B CN 105529686B CN 201610035165 A CN201610035165 A CN 201610035165A CN 105529686 B CN105529686 B CN 105529686B
Authority
CN
China
Prior art keywords
low
distributing line
separating brake
voltage distributing
branch road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610035165.1A
Other languages
Chinese (zh)
Other versions
CN105529686A (en
Inventor
唐海国
冷华
陈宏�
朱吉然
龚汉阳
张志丹
李红青
陈幸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd, State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610035165.1A priority Critical patent/CN105529686B/en
Publication of CN105529686A publication Critical patent/CN105529686A/en
Application granted granted Critical
Publication of CN105529686B publication Critical patent/CN105529686B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/04Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions for transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
    • H02H7/261Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured involving signal transmission between at least two stations
    • H02H7/262Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured involving signal transmission between at least two stations involving transmissions of switching or blocking orders

Abstract

The invention discloses a kind of overload protection method and system of the distribution transformer of low-voltage distributing line, this method includes calculating the electric current of low-voltage distributing line in real time, according to result of calculation, determines that low-voltage distributing line works in combined floodgate section or separating brake section;When working in combined floodgate section, at least one branch road is returned or connected after delay;When working in separating brake section, low-voltage distributing line or at least one branch road are cut off.The system includes current calculation module, combined floodgate processing module and separating brake processing module.Real-time current of the invention according to low-voltage distributing line; carry out classification processing; the branch road that there will be no overload is connected by the way of delay is sent a telegram in reply; to the branch road of overload be present; processing of rationing the power supply is carried out, the distribution transformer long-term work of low-voltage distributing line can be avoided in time to find and take safeguard measure in overload; the service life of distribution transformer can effectively be extended, improve the reliability and the quality of power supply of low-voltage distributing line.

Description

A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line
Technical field
The present invention relates to field of relay protection in power, more particularly to a kind of distribution transformer of low-voltage distributing line Method and device for overload protection.
Background technology
The quickening of Urbanization Construction so that the load electricity of low-voltage network (low pressure refers to less than 1 kilovolt voltage) is continuously increased, Especially summer peak meeting and seasonal low pressure power load surges during the Spring Festival etc., causes part distribution transformer to be chronically at super negative Lotus running status.By the investigation to somewhere whole year distribution transformer damaged condition and analysis, low pressure overload is distribution One of the main reason for transformer damage.
Low pressure is overloaded:GB/T1094.7-2008《The part of power transformer the 7th:Oil-immersed power transformer loads directive/guide》 In point out, transformer normal expected lifetime value be typically using the continuous duty under the environment temperature of design and specified service condition as Basis.When load is higher than design environment temperature more than nameplate rating and/or environment temperature, transformer will suffer to a certain degree Danger, and aging accelerate, Distribution Transformer Burning will be caused when serious.
On the one hand the reason for low pressure overload occurs at present is because low-voltage customer power load Seasonal is larger, in addition In recent years resident load speedup is very fast, so as to cause summer peak meeting and during the Spring Festival distribution transformer overload be difficult to avoid that;The opposing party Face, the configuration of distribution transformer low-voltage variation are lack of standardization, however it remains low-pressure side does not configure any protection or protection equipment with matching somebody with somebody The unmatched phenomenon of varying capacity, it is difficult to realize effective protection to distribution transformer.
The content of the invention
Present invention aims at providing a kind of method and device for overload protection of the distribution transformer of low-voltage distributing line, with The distribution transformer overload for solving low-voltage distributing line is difficult to avoid that and low-voltage variation configuration caused distribution transformer lack of standardization The flimsy technical problem of device.
To achieve the above object, the invention provides a kind of overload protection side of the distribution transformer of low-voltage distributing line Method, comprise the following steps:
S1:The electric current of low-voltage distributing line is calculated in real time, according to the result of calculation of electric current, determines that low-voltage distributing line works In combined floodgate section or separating brake section;
S2:When low-voltage distributing line works in combined floodgate section, return to step S1 or by low-voltage distributing line after delay At least one branch road connection;
S3:When low-voltage distributing line works in separating brake section, by low-voltage distributing line or low-voltage distributing line at least One branch road cut-out.
Further improvements in methods as the present invention:
In step S1, according to the result of calculation of electric current, determine that low-voltage distributing line works in combined floodgate section or separating brake area Between, comprise the following steps:
S1.1:Calculate I/IN, wherein, I be electric current result of calculation, the INFor distribution transformer low-pressure side it is specified Electric current;
S1.2:If I/IN∈ (0,1.3), it is determined that low-voltage distributing line works in combined floodgate section;
S1.3:If I/IN∈ [1.3 ,+∞), it is determined that low-voltage distributing line works in separating brake section.
Combined floodgate section includes the first combined floodgate section and the second combined floodgate section, step S2 specifically include following steps:
S2.1:When low-voltage distributing line works in combined floodgate section, after delay time t, current I/I is recalculatedN
S2.2:If I/IN∈ (0,0.8), it is determined that low-voltage distributing line works in the first combined floodgate section, then searches low pressure Distribution line whether there is branch road separating brake, if branch road separating brake be present, close the switch of at least one branch road, return to step S1;If In the absence of branch road separating brake, then return to step S1;
S2.3:If I/IN∈ [0.8,1.3), it is determined that low-voltage distributing line works in the second combined floodgate section, delay time t Afterwards, return to step S1.
In step S2.2, after searching low-voltage distributing line and whether there is branch road separating brake, it is found that low-voltage distributing line is present During multiple branch road separating brakes, the switch for next branch road that the telegram in reply strategy points to, return to step S1 are closed.
Separating brake section includes the first separating brake section and the second separating brake section, step S3, specifically includes following steps:
S3.1:When low-voltage distributing line works in separating brake section, according to I/INCarry out following judgement:
S3.2:If I/IN∈ [1.3,2.5), it is determined that low-voltage distributing line works in the first separating brake section, then by low pressure At least one branch road cut-out of distribution line, return to step S1;
S3.3:If I/IN∈ [2.5 ,+∞), it is determined that low-voltage distributing line works in the second separating brake section, then by low pressure Distribution line is cut off.
In step S3.2, at least one branch road of low-voltage distributing line is cut off, comprised the following steps:
S3.2.1:The order of rationing the power supply of the low-voltage distributing line is come into first most preceding branch according to strategy of rationing the power supply is circulated Road is cut off, return to step S1.
The technical concept total as one, present invention also offers a kind of overload of the distribution transformer of low-voltage distributing line Protection device, including:
Current calculation module, for calculating the electric current of low-voltage distributing line in real time, and according to the result of calculation of electric current, selection Job information is sent to combined floodgate processing module or separating brake processing module;
Combined floodgate processing module, for receiving the job information from current calculation module, and according to job information to electric current Computing module, which is sent, to be calculated signal or connects at least one branch road of low-voltage distributing line;
Separating brake processing module, for receiving the job information from current calculation module, and according to job information by low pressure At least one branch road of distribution line or low-voltage distributing line is cut off.
Further improvement as the device of the present invention:
Combined floodgate processing module includes:
Combined floodgate selecting unit, for receiving the job information from current calculation module, and the reality in job information When current value, select to the first combined floodgate processing unit or the second combined floodgate processing unit sending action signal;
First combined floodgate processing unit, for after the action signal of combined floodgate selecting unit is received, by low-voltage distributing line At least one branch road connection;
Second combined floodgate processing unit, for after the action signal of combined floodgate selecting unit is received, to current calculation module Send and calculate signal.
Separating brake processing module includes:
Separating brake selecting unit, for receiving the job information from current calculation module, and the reality in job information When current value, select to the first separating brake processing unit or the second separating brake processing unit sending action signal;
First separating brake processing unit, for after the action signal of separating brake selecting unit is received, by low-voltage distributing line At least one branch road cut-out;
Second separating brake processing unit, for after the action signal of separating brake selecting unit is received, by low-voltage distributing line Cut-out.
The invention has the advantages that:
1st, the overload protection method of the distribution transformer of low-voltage distributing line of the invention, according to the reality of low-voltage distributing line When electric current, carry out classification processing, there will be no the branch road of overload and connected by the way of delay is sent a telegram in reply, to overload be present Branch road, processing of rationing the power supply is carried out, the distribution transformer long-term work of low-voltage distributing line can be avoided in overload, in low-voltage distribution During line work, it can in time find and take safeguard measure, can effectively extend the service life of distribution transformer, improve low pressure The reliability and the quality of power supply of distribution line.
2nd, in a preferred approach, the overload protection method of the distribution transformer of low-voltage distributing line of the present invention, using circulation Tactful and delay telegram in reply of rationing the power supply is tactful, can be protected to greatest extent on the basis of distribution transformer safe and stable operation is ensured Demonstrate,prove low-voltage customer power supply reliability and the fairness of electricity consumption.
3rd, the overload protection arrangement of the distribution transformer of low-voltage distributing line of the invention, it is real-time by current calculation module Calculating current, further according to the size of current value, line delay telegram in reply is entered in selection by combined floodgate processing module to circuit, or by dividing Lock processing module is rationed the power supply to branch road, can be rationed the power supply in time when overloading, and in nonoverload, progressively send a telegram in reply.Energy The damage of distribution transformer is efficiently reduced, extends the service life of distribution transformer, improves power supply quality.
In addition to objects, features and advantages described above, the present invention also has other objects, features and advantages. Below with reference to accompanying drawings, the present invention is further detailed explanation.
Brief description of the drawings
The accompanying drawing for forming the part of the application is used for providing a further understanding of the present invention, schematic reality of the invention Apply example and its illustrate to be used to explain the present invention, do not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the flow of the overload protection method of the distribution transformer of the low-voltage distributing line of the preferred embodiment of the present invention Figure;
Fig. 2 is the stream of the overload protection method of the distribution transformer of the low-voltage distributing line of another preferred embodiment of the present invention Cheng Tu;
Fig. 3 is that the structure of the overload protection arrangement of the distribution transformer of the low-voltage distributing line of the preferred embodiment of the present invention is former Manage block diagram;
Fig. 4 is the daily load rate K of distribution transformer<The overload curves figure allowed when 1;
Fig. 5 is 225A breaker actuation curve maps;
Fig. 6 is 400A breaker actuation curve maps.
Embodiment
Embodiments of the invention are described in detail below in conjunction with accompanying drawing, but the present invention can be defined by the claims Implement with the multitude of different ways of covering.
Referring to Fig. 1, the overload protection method of the distribution transformer of low-voltage distributing line of the invention, comprise the following steps:
S1:The electric current of low-voltage distributing line is calculated in real time, according to the result of calculation of electric current, determines that low-voltage distributing line works In combined floodgate section or separating brake section;
S2:When low-voltage distributing line works in combined floodgate section, return to step S1 or by low-voltage distributing line after delay At least one branch road connection;
S3:When low-voltage distributing line works in separating brake section, by low-voltage distributing line or low-voltage distributing line at least One branch road cut-out.
By above-mentioned steps, it can carry out classification processing according to the real-time current of low-voltage distributing line, there will be no overload Branch road is connected by the way of delay is sent a telegram in reply, and to the branch road of overload being present, being carried out processing of rationing the power supply, can be avoided low-voltage distribution wire The distribution transformer long-term work on road when low-voltage distributing line works, can in time be found and take protection to arrange in overload Apply, can effectively extend the service life of distribution transformer, improve the reliability and the quality of power supply of low-voltage distributing line.
In practical application, in above-mentioned steps, referring to Fig. 2, the mistake of the distribution transformer of low-voltage distributing line of the invention Guard method is carried, can also be optimized, the embodiment after optimization is as follows:
S1:The electric current of low-voltage distributing line is calculated in real time, according to the result of calculation of electric current, determines that low-voltage distributing line works It is specific as follows in combined floodgate section or separating brake section:
S1.1:Calculate I/IN, wherein, I be electric current result of calculation, the INFor distribution transformer low-pressure side it is specified Electric current;
S1.2:If I/IN∈ (0,1.3), it is determined that low-voltage distributing line works in combined floodgate section;
S1.3:If I/IN∈ [1.3 ,+∞), it is determined that low-voltage distributing line works in separating brake section.
S2:When low-voltage distributing line works in combined floodgate section, after delay, return to step S1 or by low-voltage distributing line At least one branch road connection, it is specific as follows:
S2.1:When low-voltage distributing line works in combined floodgate section, after delay time t, current I/I is recalculatedN
For the normal operation of effectively protection distribution transforming, close a floodgate all needs to set by rational delay, combined floodgate delay cycle every time Surely to be determined according to power distribution station low-voltage load with electrical characteristics, by taking urban residents' electricity consumption as an example, the peak times of power consumption of one day occur In evening 18:00~20:00, to avoid peak times of power consumption, then the delay t that will can close a floodgate is set to 2h, and time t determination can pass through terminal Low-voltage distributing line history data is gathered, [1.3I is in by distribution low-voltage side electric currentN~2.5IN] section time meter Calculate delay of closing a floodgate.If overlong time, first removed user can be caused to have a power failure for a long time, influenceing customer power supply can It is horizontal by property and power supply enterprise's good service, if the time is too short user can be caused frequently to have a power failure, power transmission, to distribution transformer Safe and stable operation bring hidden danger, can also influence user power utilization experience.Therefore, telegram in reply of being rationed the power supply and be delayed using circulation is tactful, Low-voltage customer power supply reliability and the fairness of electricity consumption can be effectively ensured on the basis of distribution transforming safe and stable operation is ensured.
S2.2:If I/IN∈ (0,0.8), it is determined that low-voltage distributing line works in the first combined floodgate section, then searches low pressure Distribution line whether there is branch road separating brake, if branch road separating brake be present, close the switch of at least one branch road, return to step S1;If In the absence of branch road separating brake, then return to step S1.After searching low-voltage distributing line and whether there is branch road separating brake, low-voltage distribution is found When circuit has multiple branch road separating brakes, the switch for next branch road that the telegram in reply strategy points to, return to step S1 are closed.
Circulation alleged by embodiment of the present invention strategy of rationing the power supply refers to:When circuit is in the first separating brake section, intelligent distribution transforming Terminal-pair taiwan area outlet switch takes the mode that circulation is rationed the power supply, and carries out round cut to each branch road load, line is returned back out with distribution low-voltage three Exemplified by, circulate strategy of rationing the power supply:Branch road 1, branch road 2, branch road 3 represent low pressure three and return back out line respectively, and low-voltage distributing line electric current is in First separating brake section, then order of rationing the power supply for the first time is branch road 1- branch road 2- branch roads 3, and order of rationing the power supply for the second time is branch road 2- branch roads 3- Branch road 1, order of rationing the power supply for the third time is branch road 3- branch road 1- branch roads 2.Accordingly, the telegram in reply strategy alleged by the embodiment of the present invention follows Ring is rationed the power supply, and strategy is similar, i.e., the corresponding telegram in reply rationed the power supply sequentially is respectively:First time telegram in reply order is branch road 1- branch road 2- branch roads 3, Second of telegram in reply order is branch road 2- branch road 3- branch roads 1, and third time telegram in reply order is branch road 3- branch road 1- branch roads 2.Step S2.2 In, then next branch switch is closed by telegram in reply strategy, referred to:The switch of next branch road pointed by telegram in reply strategy is closed (under i.e. One switch to be closed a floodgate).
S2.3:If I/IN∈ [0.8,1.3), it is determined that low-voltage distributing line works in the second combined floodgate section, delay time t Afterwards, return to step S1.
For distribution transformer, [0~0.8] is up section, can close separating brake according to telegram in reply strategy Branch switch, if [0.8~1.3] then represent distribution transformer be in abnormal operating condition (heavy duty or overload:0.8 ~1.0 be heavy duty, and 1.0~1.3 be overload), can be without rationing the power supply in order to ensure user power utilization reliability, but be also not suitable for Telegram in reply operation.Therefore, combined floodgate section is specifically configured to the first combined floodgate section and the second combined floodgate section, can more accurately monitors and match somebody with somebody The working condition of piezoelectric transformer, is handled in time.
S3:When low-voltage distributing line works in separating brake section, by low-voltage distributing line or low-voltage distributing line at least One branch road cut-out, it is specific as follows:
S3.1:When low-voltage distributing line works in separating brake section, according to I/INCarry out following judgement:
S3.2:If I/IN ∈ [1.3,2.5), it is determined that low-voltage distributing line works in the first separating brake section, then by low pressure At least one branch road cut-out of distribution line, return to step S1;
Wherein, at least one branch road load of cutoff low distribution line, can be rationed the power supply strategy using circulation:
S3.2.1:The order of rationing the power supply of the low-voltage distributing line is come into first most preceding branch according to strategy of rationing the power supply is circulated Road is cut off, return to step S1.
S3.3:If I/IN∈ [2.5 ,+∞), it is determined that low-voltage distributing line works in the second separating brake section, then by low pressure Distribution line is cut off.
Illustrate the embodiment of the present invention by stroke in combined floodgate section and separating brake section below according to the actual conditions of low-voltage network Point threshold value is set to I/IN=1.3, and the division threshold value in the first separating brake section and the second separating brake section is set to I/IN=2.5 original Cause and advantage:
According to DL/T 499-2001《Rural area low-voltage power technical regulation》:The daily load rate of distribution transformer is less than 1 In the case of, it can allow have appropriate overload in peak hours, the multiple of overload can refer to Fig. 4 song with the duration allowed Line determines.Wherein, daily load rate K is the ratio of average load in diel and peak load, it is contemplated that rural power load changes The characteristics of larger, it is apparent from by Fig. 4 curves:Distribution transformer Overflow RateHT (i.e. overload rate) is no more than transformer rated capacity 1.3 again.Therefore I/I is setN=1.3 be the division threshold value in combined floodgate section and separating brake section, the characteristics of more meeting rural power load, symbol Close actual applicable cases.
The overcurrent protection of distribution transformer low-pressure side is realized using mold cased circuit breaker (air switch) more, it then follows GB/ T14048.2-2008《Low voltage switch equipment and control device part 2:Breaker》Relevant criterion.GB/T 14048.2-2008 Chapters and sections 7.2.1.2.1 regulations " disconnect under breaker overload situations:Overcurrent trip inverse time-delay operation about definite value is in benchmark temperature Under degree, at 1.05 times of current setting, i.e., conventional non tripping current when, the electrical apparatus release of each phase pole is powered simultaneously, is opened from cold conditions Begin, should not be threaded off within less than the designated time.In addition, after the designated time terminates, electric current is set to rise to electric current immediately whole 1.30 times of definite value, that is, reach conventional tripping current, and breaker should thread off within less than the designated time as defined in the latter." referring to Table 1:
The reverse time limiting current of table 1 disconnects disconnection acting characteristic of the electrical apparatus release under fiducial temperature
By at present exemplified by wide variety of rated current 225A and 400A mold cased circuit breaker distribution operation curve, When breaker load current reaches the 1.3I of rated currentNAnd 2.5INWhen, overcurrent release turn-off time scope such as table 2, Fig. 5 and Shown in Fig. 6.Using low-voltage variation of the breaker of above acting characteristic as distribution transformer, excessively stream actuation time discreteness compared with Greatly, 1.3I is reached in distribution transformer load electric currentNWhen, breaker actuation time range is between 200s~7000s, it is difficult to realizes distribution transforming Accurate overload protection.
The overcurrent release turn-off time of table 2
Analyzed more than passing through, it can be seen that the mold cased circuit breaker action error that distribution transformer low-pressure side uses is big and mistake Electric current operation curve does not take into full account the overload capacity of distribution transformer, but uses the universal breaker of low pressure as protection Device, 1.3I occurs in distribution transformingN~2.5INDuring overload, effectively overload protection can not be provided, distribution transformer may be caused to burn Ruin.
Knowable to analysis more than, the overload protection side of the distribution transformer of the low-voltage distributing line of the embodiment of the present invention Method, when carrying out classification processing, it can more accurately judge the working condition of low-voltage distributing line, can be with accurate judgement low-voltage distribution The overload of circuit, there is provided effective overload protection so that the Preservation tactics of distribution transformer more meet actual work shape State.
On the basis of the principle of uniformity of the above method, referring to Fig. 3, the distribution transformer of low-voltage distributing line of the invention Overload protection arrangement, including current calculation module, combined floodgate processing module and separating brake processing module, wherein:
Current calculation module, for calculating the electric current of low-voltage distributing line in real time, and according to the result of calculation of electric current, selection Job information is sent to combined floodgate processing module or separating brake processing module;Combined floodgate processing module, Current calculation is come from for receiving The job information of module, and according to job information to current calculation module send calculate signal or by low-voltage distributing line extremely Few branch road connection;Separating brake processing module, for receiving the job information from current calculation module, and according to job information At least one branch road of low-voltage distributing line or low-voltage distributing line is cut off.The device is calculated in real time by current calculation module Electric current, further according to the size of current value, selection is entered line delay to circuit by combined floodgate processing module and sent a telegram in reply, or by separating brake at Reason module is rationed the power supply to branch road, can be rationed the power supply in time when overloading, and in nonoverload, progressively send a telegram in reply.Can be effective Ground reduces the damage of distribution transformer, extends the service life of distribution transformer, improves power supply quality.
In actual applications, in order that device judgement and action it is more accurate, the system is also extendible, wherein, close a floodgate Processing module may include combined floodgate selecting unit, the first combined floodgate processing unit and the second combined floodgate processing unit.Wherein, selection of closing a floodgate is single Member, for receiving the job information from current calculation module, and the real-time current value in job information, select to first Combined floodgate processing unit or the second combined floodgate processing unit sending action signal;First combined floodgate processing unit, for receiving conjunction After the action signal of lock selecting unit, at least one branch road of low-voltage distributing line is connected;Second combined floodgate processing unit, is used for After the action signal of combined floodgate selecting unit is received, sent to current calculation module and calculate signal.The processing of two level combined floodgate is set Unit, the accurate overload protection of distribution transformer can be further realized, is rationed the power supply by intelligent Distribution transformer using circulation With telegram in reply strategy, low-voltage customer power supply reliability and use can be effectively ensured on the basis of distribution transforming safe and stable operation is ensured The fairness of electricity.
Separating brake processing module includes separating brake selecting unit, the first separating brake processing unit and the second separating brake processing unit.Wherein, Separating brake selecting unit, for receiving the job information from current calculation module, and the real-time current value in job information, Select to the first separating brake processing unit or the second separating brake processing unit sending action signal;First separating brake processing unit, is used for After the action signal of separating brake selecting unit is received, at least one branch road of low-voltage distributing line is cut off;At second separating brake Unit is managed, for after the action signal of separating brake selecting unit is received, low-voltage distributing line to be cut off.
Because the overcurrent protection of distribution transformer low-voltage distributing line is largely using pyromagnetic induction type protection element as distribution When the short circuit of taiwan area, overload protection device, but distribution transformer operate in 1.3~2.5 times of overloads, it can not realize effective Overload protection, it using two level separating brake processing unit, can carry on the basis of at utmost ensureing user power utilization reliability, can be achieved Comprehensive, effective protection of distribution transformer, improve low-voltage customer power supply reliability and power supply quality.
The overload protection method and system of the distribution transformer of the low-voltage distributing line of the embodiment of the present invention are in Hunan Province The operation test to be maintained secrecy in Utilities Electric Co.'s part power network, the situation before testing are as follows:
This saves whole year in 2012, and rural power grids 10kV distribution transformer damages 1166 altogether, is the main reason for damage: Overload 32.93%, low-voltage short-circuiting 17.5%, three-phase imbalance 14.24%, thunderbolt 16.21%, apparatus body reason about 14% with And other reasonses about 6%.Specifically, one is due to that rural area load growth is very fast, is especially largely worked during the Spring Festival Personnel return to one's native place, and cause throwing-on, cause the main reason that distribution transformer overload is distribution transformer damage;Two are due to Rural power distribution taiwan area relaying configuration is lack of standardization, however it remains low-pressure side does not configure any protection or protection equipment and distribution transformer The unmatched phenomenon of device capacity, cause quickly cut off failure during distribution transformer short circuit, cause distribution transformer to burn out;Three It is due to that taiwan area lightning protection measures are not in place, the problems such as grounding resistance is excessive, arrester damage is not changed in time is present;Fourth, power supply Institute can not find distribution transforming three-phase imbalance and overload phenomenon in time, cause to distribution transformer general lack of long-range monitoring means Abnormal operating condition processing not in time, the increase-volume of power distribution station can not also be layouted provide data supporting.
Situation after experiment is as follows:
By the overload protection method and system of the distribution transformer of the low-voltage distributing line of the trial operation embodiment of the present invention, The distribution transforming caused by low pressure is overloaded effectively is prevented within 2013 to 2015 to damage, distribution transforming can be reduced and damage 385/year, pressed Per station power distribution transformer, average 10W/ platforms, then can save distribution transformer 38,500,000/year of renewal cost.On the other hand, reduce User has a power failure phenomenon caused by distribution transforming is burnt, and improves the power supply reliability of user, the amount of being supplied with electric power more, improves power supply enterprise Social image.
In summary, by real-time calculating current, classification is handled the present invention, and low pressure is matched somebody with somebody according to different situations Electric line enters line delay telegram in reply and circulation is rationed the power supply, and effectively reduces distribution transformer and is damaged caused by overload, ensures The power supply reliability and the quality of power supply of low-voltage customer, application effect are good.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies Change, equivalent substitution, improvement etc., should be included in the scope of the protection.

Claims (6)

1. a kind of overload protection method of the distribution transformer of low-voltage distributing line, it is characterised in that comprise the following steps:
S1:The electric current of the low-voltage distributing line is calculated in real time;According to the result of calculation of the electric current, the low-voltage distribution is determined Line work comprises the following steps in combined floodgate section or separating brake section:
S1.1:Calculate I/IN, wherein, the I be the electric current result of calculation, the INFor the low-pressure side of distribution transformer Rated current;
S1.2:If the I/IN∈ (0,1.3), it is determined that the low-voltage distributing line works in combined floodgate section;
S1.3:If the I/IN∈ [1.3 ,+∞), it is determined that the low-voltage distributing line works in separating brake section;
S2:When the low-voltage distributing line works in combined floodgate section, the combined floodgate section includes the first combined floodgate section and second Combined floodgate section, after delay, return to step S1 or at least one branch road connection by the low-voltage distributing line, including following step Suddenly:
S2.1:When the low-voltage distributing line works in combined floodgate section, after delay time t, current I/I is recalculatedN
S2.2:If the I/IN∈ (0,0.8), it is determined that the low-voltage distributing line works in the first combined floodgate section, then searches institute State low-voltage distributing line and whether there is branch road separating brake, if branch road separating brake be present, close the switch of at least one branch road, return to step S1;If branch road separating brake, return to step S1 is not present;
S2.3:If the I/IN∈ [0.8,1.3), it is determined that the low-voltage distributing line works in the second combined floodgate section, during delay Between after t, return to step S1;
S3:When the low-voltage distributing line works in separating brake section, by the low-voltage distributing line or the low-voltage distribution wire At least one branch road cut-out on road.
2. overload protection method according to claim 1, it is characterised in that described low searching in the step S2.2 Electric line is press-fitted with the presence or absence of after branch road separating brake, it is found that when the low-voltage distributing line has multiple branch road separating brakes, closes telegram in reply The switch for next branch road that strategy points to, return to step S1;The telegram in reply strategy refers to:Intelligent distribution transformer terminals are to taiwan area outlet Switch takes the mode that delay is sent a telegram in reply, and each branch road load is sent a telegram in reply, and the order of telegram in reply is corresponding with order of rationing the power supply.
3. overload protection method according to claim 1 or 2, it is characterised in that the separating brake section includes the first separating brake Section and the second separating brake section, the step S3, specifically include following steps:
S3.1:When the low-voltage distributing line works in separating brake section, according to the I/INCarry out following judgement:
S3.2:If the I/IN∈ [1.3,2.5), it is determined that the low-voltage distributing line works in the first separating brake section, then by institute State at least one branch road cut-out of low-voltage distributing line, return to step S1;
S3.3:If the I/IN∈ [2.5 ,+∞), it is determined that the low-voltage distributing line works in the second separating brake section, then by institute State low-voltage distributing line cut-out.
4. overload protection method according to claim 3, it is characterised in that described to match somebody with somebody low pressure in the step S3.2 At least one branch road cut-out of electric line, comprises the following steps:
S3.2.1:The order of rationing the power supply of the low-voltage distributing line is come first most preceding branch road and cut according to circulation strategy of rationing the power supply It is disconnected, return to step S1;The strategy of rationing the power supply that circulates refers to:Intelligent distribution transformer terminals take taiwan area outlet switch the side that circulation is rationed the power supply Formula, each branch road load is cut off in turn.
A kind of 5. overload protection arrangement of the distribution transformer of low-voltage distributing line, it is characterised in that including:
Current calculation module, for calculating the electric current of the low-voltage distributing line in real time, and according to the result of calculation of the electric current, Select to send job information to combined floodgate processing module or separating brake processing module;
The combined floodgate processing module, believe for receiving the job information from the current calculation module, and according to the work Cease to send to the current calculation module and calculate signal or connect at least one branch road of the low-voltage distributing line;It is described Combined floodgate processing module includes:
Combined floodgate selecting unit, for receiving the job information from the current calculation module, and according in the job information Real-time current value, select to the first combined floodgate processing unit or the second combined floodgate processing unit sending action signal;
First combined floodgate processing unit, for after the action signal of the combined floodgate selecting unit is received, by the low-voltage distribution At least one branch road connection of circuit;
Second combined floodgate processing unit, for after the action signal of the combined floodgate selecting unit is received, to the Current calculation Module, which is sent, calculates signal;
The separating brake processing module, believe for receiving the job information from the current calculation module, and according to the work Breath cuts off at least one branch road of the low-voltage distributing line or the low-voltage distributing line.
6. overload protection arrangement according to claim 5, it is characterised in that the separating brake processing module includes:
Separating brake selecting unit, for receiving the job information from the current calculation module, and according in the job information Real-time current value, select to the first separating brake processing unit or the second separating brake processing unit sending action signal;
First separating brake processing unit, for after the action signal of the separating brake selecting unit is received, by the low-voltage distribution At least one branch road cut-out of circuit;
Second separating brake processing unit, for after the action signal of the separating brake selecting unit is received, by the low-voltage distribution Circuit is cut off.
CN201610035165.1A 2016-01-19 2016-01-19 A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line Active CN105529686B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610035165.1A CN105529686B (en) 2016-01-19 2016-01-19 A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610035165.1A CN105529686B (en) 2016-01-19 2016-01-19 A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line

Publications (2)

Publication Number Publication Date
CN105529686A CN105529686A (en) 2016-04-27
CN105529686B true CN105529686B (en) 2018-01-05

Family

ID=55771753

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610035165.1A Active CN105529686B (en) 2016-01-19 2016-01-19 A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line

Country Status (1)

Country Link
CN (1) CN105529686B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113241773B (en) * 2021-05-24 2022-07-12 广东电网有限责任公司 Residential area power distribution operation control method and device

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102006003124A1 (en) * 2006-01-23 2007-08-02 Siemens Ag Method for implementing an improved thermo-mechanical overload protection and associated overload protection device
CN102354987B (en) * 2011-09-28 2013-11-13 南京南瑞继保电气有限公司 Control method of overload load-shedding for transformer or circuit
CN202405751U (en) * 2012-02-01 2012-08-29 佛山市三水区通利达电力设计有限公司 Overload protection device of intelligent distribution transformer
CN104362589B (en) * 2014-11-27 2017-08-25 国家电网公司 A kind of sectionalised protection device for high overload distribution transformer

Also Published As

Publication number Publication date
CN105529686A (en) 2016-04-27

Similar Documents

Publication Publication Date Title
CN105591396B (en) The three-phase imbalance guard method of the distribution transformer of low-voltage distributing line and device
CN104882891A (en) Low-voltage distribution voltage-regulation equipment
CN203690938U (en) Low-voltage reactive-power automatic compensation device
CN104659797A (en) Intelligent power load three-phase unbalance handling method at distribution network low voltage side
CN201408981Y (en) Single-phase intelligent power protector
CN103928936B (en) For reducing converter and the conversion equipment that transformer is affected by zero-sequence current
CN206498237U (en) A kind of direct-current charging post circuit
CN209329685U (en) A kind of intelligent electric machine integrated protection controller
CN105529686B (en) A kind of method and device for overload protection of the distribution transformer of low-voltage distributing line
CN102946108A (en) Voltage automatic compensation device
CN103235198B (en) Method for determining phase sequence arrangement modes of conducting wires of same-tower double-circuit transmission lines
CN206573629U (en) A kind of load self-adapting current measurement and protection device
CN202309245U (en) Power supply device taking disc type insulator leakage current as power source
CN112310982B (en) Distribution transformer area three-phase load adjustment method based on user power consumption
CN201188536Y (en) Protector for over voltage, undervoltage and lack phase of power supply
CN204314645U (en) A kind of low-voltage distribution system by screen break-make automaton
CN114336980A (en) Intelligent cloud power distribution method and system based on instruction transmission
CN209200651U (en) A kind of distribution transforming overload monitoring and protecting device based on Internet of Things cloud platform
CN209217694U (en) A kind of low-voltage distribution transformer load distribution device with protective device
CN207691414U (en) A kind of high pressure protector
CN105488621A (en) Loss reduction and energy saving analysis and energy efficiency evaluation system for power grid lab
CN205319552U (en) Intelligent terminal distribution box
CN105353246B (en) A kind of test method of on-load switch element and load cell low-voltage release characteristics
CN210380382U (en) Intelligent power distribution device of cluster well pumping unit
Wu et al. Distribution power flow calculation based on the load monitoring system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant