CN105525630A - Trimming and welding method for HDPE membrane for high-curvature side slope - Google Patents

Trimming and welding method for HDPE membrane for high-curvature side slope Download PDF

Info

Publication number
CN105525630A
CN105525630A CN201510909476.1A CN201510909476A CN105525630A CN 105525630 A CN105525630 A CN 105525630A CN 201510909476 A CN201510909476 A CN 201510909476A CN 105525630 A CN105525630 A CN 105525630A
Authority
CN
China
Prior art keywords
diaphragm
longitudinal edge
cut
line
hdpe film
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510909476.1A
Other languages
Chinese (zh)
Inventor
周晓晖
徐葵
郭建林
肖光婷
孙小华
何家能
罗磊
王磊
陶俊波
甘宇宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Shengyi Environmental Protection Co Ltd
Original Assignee
Shenzhen Shengyi Environmental Protection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Shengyi Environmental Protection Co Ltd filed Critical Shenzhen Shengyi Environmental Protection Co Ltd
Priority to CN201510909476.1A priority Critical patent/CN105525630A/en
Publication of CN105525630A publication Critical patent/CN105525630A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0006Plastics
    • E02D2300/0009PE
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • E02D2450/105Membranes impermeable

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The invention discloses a trimming and welding method for an HDPE membrane for a high-curvature side slope. The trimming and welding method comprises the following steps of a, determining a midpoint trimmed line which passes through the midpoint of the longitudinal edge of the HDPE membrane and is parallel to a slope line; b, setting the midpoint trimmed line as an actual trimmed line after the midpoint trimmed line horizontally moves towards the central direction of the HDPE membrane for an offset distance, wherein the actual trimmed line passes through the longitudinal edge of the HDPE membrane; c, trimming the HDPE membrane along the actual trimmed line, trimming a trimmed membrane, and retaining the left membrane on the side slope; d, rotating the trimmed membrane for 180 DEG to ensure that an untrimmed longitudinal edge II of the trimmed membrane is overlapped on an untrimmed longitudinal edge I of the left membrane, a trimmed longitudinal edge II of the trimmed membrane aligns to a trimmed longitudinal edge I of the left membrane, and meanwhile a horizontal edge II of the trimmed membrane aligns to a horizontal edge I, connected with the untrimmed longitudinal edge I, of the left membrane; and e, welding. An integrated longitudinal edge parallel to the slope line is formed after the left membrane and the trimmed membrane are welded together, so that a laying included angle is eliminated.

Description

A kind of sanction of deep camber side slope HDPE film connects method
Technical field
The present invention relates to landfill yard HDPE film and lay field, especially the sanction of deep camber side slope HDPE film connects method.
Background technology
Southern area landfill yard mostly is mountain valley-type, it is built by the mountain, reservoir area is built usually Harmony with site and is utilized existing chevron through simply showing clearly, repaiies slope and form, the waste burying built maintains the topography and geomorphology of original massif substantially, storehouse basin presents the taper of wide narrow base suitable for reading, just what platform slope has built for anchoring impervious material.Be illustrated in figure 1 the floor map of typical Valley Type Landfill Site 100, the geomorphologic characteristics replaced due to former massif ridge col as seen from the figure and make anchored platform present cranky looks, occur the curve side slope that multiple curvature differs.The laying of landfill slope HDPE film should be parallel to grade of side slope line, ensures that HDPE film is perpendicular to leg wire of slope as far as possible.In curve side slope section, curvature difference due to upper and lower anchored platform can cause line length poor, paved surface is fan-shaped, therefore just there will be when carrying out monoblock HDPE film and laying and lays angle (laying the angle of line and grade line), affect the construction quality of antiseepage film.Occur should revising in time when laying angle, make laying line be parallel to grade line as far as possible, this is an important content of landfill site seepage prevention film construction.
The sanction of curved batter HDPE film connects mode directly affects speed of application and spillage of material, closely related with construction cost.In the big-and-middle-sized Valley Type Landfill Site with Slope with multi-step, often there is more deep camber curved batter (encircled as in Fig. 1), the correcting mode that HDPE film lays angle is just particularly evident on the impact of construction cost.Therefore, in the laying construction process of HDPE, in the construction of especially multistage deep camber side slope, choose a kind of mode that connects of reasonably cutting out just extremely important for quickening speed of application, saving material.
At present, it is " overall cut-off method " that the routine that correction HDPE film laying angle adopts cuts mode.Namely, as shown in Figure 2, lay HDPE film 300 between upper mounting plate anchor line 201 and lower platform anchor line 202 after, produce between the longitudinal edge of HDPE film 300 and grade line 101 and lay angle theta, HDPE film 300 is cut along the cutting line 303 being parallel to grade line 101 bottom HDPE film 300 longitudinal edge, thus cut out and cut diaphragm 302, and retain the longitudinal edges parallel of diaphragm 301 in grade line 101, thus eliminate and lay angle theta.The method has the following disadvantages:
(1) during Valley Type Landfill Site Seepage, limit by orographic condition, the carrying of impervious material often cannot use machinery and have to rely on inefficient a dead lift, costly.Revise and lay angle and cut the residue diaphragm got off and will migrate out stockyard outside the venue, add extra transhipment operation and construction cost.
(2) in irregular curve landform, cut the reason that the diaphragm that gets off differs due to diaphragm length and diaphragm angle theta, be difficult to match the consistent recycling position of specification, be applied to the position compared with small-sized after can only being repaiied by further sanction, this will waste portion of material; And if it is little to cut the diaphragm specification of getting off, recycling will be difficult to and become discarded leftover pieces, and causing all material to waste.
(3) when recycling cuts diaphragm, first will carry out scene to the position occurring laying angle and measure, then select the immediate diaphragm of specification to stockyard, the scene that is finally transported to is carried out sanction and is repaiied installation recycling.Construction sequence is complicated, effort of taking a lot of work, and increases construction cost.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of effective utilization and cuts the sanction that the HDPE film that gets off eliminates the deep camber side slope HDPE film laying angle and connect method.
In order to solve the problems of the technologies described above, the sanction that the invention provides a kind of deep camber side slope HDPE film connects method, to be laid in side slope and the grade line of longitudinal edge and side slope exists the HDPE film laying angle, to comprise the following steps for cutting:
A, determine mid point by the longitudinal edge of HDPE film and be parallel to the mid point cutting line of grade line;
B, mid point cutting line are decided to be actual cutting line after HDPE center membrane direction translational offsets distance, and described actual cutting line is through the longitudinal edge of described HDPE film;
C, cut HDPE film along actual cutting line, cut out and cut diaphragm, residue diaphragm is retained in side slope, and residue the cut longitudinal edge one of diaphragm after cutting is parallel to grade line, and the longitudinal edge one that do not cut remaining diaphragm still exists with grade line and lays angle;
D, the described diaphragm that cuts is rotated 180 °, make to cut diaphragm do not cut that longitudinal edge two is overlapped on residue diaphragm do not cut on longitudinal edge one, make to cut simultaneously diaphragm cut that longitudinal edge two aligns residue diaphragm cut longitudinal edge one, make that the transverse edge two cutting diaphragm aligns residue diaphragm with transverse edge one that is that do not cut longitudinal edge one and be connected simultaneously;
E, welding cut diaphragm cut longitudinal edge two and residue diaphragm cut overlapping part overlap of longitudinal edge one, residue diaphragm and cut the complete longitudinal edge parallel with grade line of the rear formation of diaphragm welding, thus elimination laying angle.
Preferably, described offset distance is 5cm.
Preferably, described HDPE film is laid in the side slope between parallel upper mounting plate anchor line and lower platform anchor line.
Preferably, it is characterized in that: in step e, welded by double track hot-melt welding machine during welding.
Compared with prior art, first the present invention finds out the mid point cutting line through HDPE film longitudinal edge mid point, then mid point cutting line is obtained actual cutting line to center translation, cut out along actual cutting line and cut diaphragm, and remain diaphragm and form area at the diagonal position cutting diaphragm and be less than and cut diaphragm and the vee similar to cutting diaphragm, to cut after diaphragm rotates 180 ° splices at this breach, make to cut diaphragm do not cut that longitudinal edge two is overlapped on residue diaphragm do not cut on longitudinal edge one, make to cut simultaneously diaphragm cut longitudinal edge two and transverse edge two respectively with residue diaphragm cut longitudinal edge one and transverse edge one aligns.After cutting diaphragm welding, the cropped diaphragm of the residue original vee of diaphragm is completely supplementary, and forms the complete longitudinal edge parallel with grade line after remaining diaphragm and cutting diaphragm welding, thus eliminates laying angle.The present invention does not have HDPE film waste material to produce, and improves HDPE film utilization rate; Meanwhile, owing to being the correction realizing laying angle by the cutting of this block HDPE film self, constructing fast and convenient, avoid original construction cost and a dead lift cost.
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, the present invention is described in further detail:
Fig. 1 is the floor map of existing Valley Type Landfill Site in background technology.
Fig. 2 is the laying schematic diagram of existing side slope HDPE film in background technology.
Fig. 3 is the laying schematic diagram of HDPE film in side slope.
Fig. 4 is the schematic diagram that the sanction of deep camber side slope HDPE film of the present invention connects method determination mid point cutting line and actual cutting line.
Fig. 5 is that the sanction of deep camber side slope HDPE film of the present invention connects method and cuts out the schematic diagram cutting diaphragm.
Fig. 6 is that the sanction of deep camber side slope HDPE film of the present invention connects method and cuts diaphragm and rotate the schematic diagram after 180 °.
Fig. 7 be the sanction of deep camber side slope HDPE film of the present invention connect method by cut diaphragm weld with residue diaphragm after schematic diagram.
Detailed description of the invention
As shown in Figure 3, according to laying work area, HDPE film 400 is laid in the side slope 500 between parallel upper mounting plate anchor line 201 and lower platform anchor line 202, HDPE film 400 side longitudinal edge and laying work area are fitted, and the opposite side longitudinal edge 401 of HDPE film 400 still exists with grade line 101 lays angle theta.
For eliminating this this laying angle theta, the sanction present embodiments providing deep camber side slope 500HDPE film connects method, to be laid in side slope 500 and longitudinal edge 401 exists with the grade line 101 of side slope 500 the HDPE film 400 laying angle theta for cutting, to comprise the following steps:
A, as shown in Figure 4, determines mid point by the longitudinal edge 401 of HDPE film 400 and is parallel to the mid point cutting line 402 of grade line 101.
B, as shown in Figure 4, mid point cutting line 402 is decided to be actual cutting line 403 after HDPE film 400 center position translational offsets distance L, actual cutting line 403 must not more than outside the longitudinal edge 401 of HDPE film 400, and namely actual cutting line 403 is through the longitudinal edge 401 of described HDPE film 400.Offset distance L is preferably 5cm.
C, as shown in Figure 5, HDPE film 400 is cut along actual cutting line 403, cut out and leg-of-muttonly cut diaphragm 405, residue diaphragm 404 is retained in side slope 500, residue the cut longitudinal edge one 4042 of diaphragm 404 after cutting is parallel to grade line 101, and the longitudinal edge 1 that do not cut remaining diaphragm 404 still exists with grade line 101 and lays angle theta.Cut rear residue diaphragm 404 and form leg-of-mutton breach at the diagonal position cutting diaphragm 405, this vee with cut diaphragm 405 similar triangles each other, and the area of this vee is less than and cuts diaphragm 405, this vee can supplement by cutting diaphragm 405 in the step below.
D, as shown in Figure 6 and Figure 7, the described diaphragm 405 that cuts is rotated 180 ° of splicings on the breach of step c generation, make to cut diaphragm 405 do not cut that longitudinal edge 2 4051 is overlapped on residue diaphragm 404 do not cut on longitudinal edge 1, make to cut simultaneously diaphragm 405 cut that longitudinal edge 2 4052 aligns residue diaphragm 404 cut longitudinal edge 1, make that the transverse edge 2 4053 cutting diaphragm 405 aligns residue diaphragm 404 with transverse edge 1 that is that do not cut longitudinal edge 1 and be connected simultaneously.According to geometrical principle, the width of this lap is 2 times of offset distance L, i.e. 10cm.
E, welding cut diaphragm 405 cut longitudinal edge 2 4052 with remain diaphragm 404 cut the overlapping part overlapped of longitudinal edge 1, weld preferably by hot-melt welding machine (double track welding) during welding.Cut after diaphragm 405 welds, the residue original vee of diaphragm 404 cropped diaphragm 405 is completely supplementary, and residue diaphragm 404 and cut diaphragm 405 and weld the complete longitudinal edge parallel with grade line 101 of rear formation, thus eliminate laying angle theta.
The present invention does not have HDPE film waste material to produce, and improves HDPE film utilization rate; Meanwhile, owing to being the correction realizing laying angle by the cutting of this block HDPE film self, constructing fast and convenient, avoid original construction cost and a dead lift cost.

Claims (4)

1. the sanction of a deep camber side slope HDPE film connects method, being laid on that side slope (500) is upper and longitudinal edge (401) exists with the grade line (101) of side slope (500) the HDPE film (400) laying angle (θ) for cutting, it is characterized in that comprising the following steps:
A, determine mid point by the longitudinal edge (401) of HDPE film (400) and be parallel to the mid point cutting line (402) of grade line (101);
B, mid point cutting line (402) are decided to be actual cutting line (403) after HDPE film (400) center position translational offsets distance (L), and described actual cutting line (403) is through the longitudinal edge (401) of described HDPE film (400);
C, cut HDPE film (400) along actual cutting line (403), cut out and cut diaphragm (405), residue diaphragm (404) is retained in side slope (500), residue diaphragm (404) longitudinal edge one (4042) that cuts after cutting is parallel to grade line (101), and the longitudinal edge one (4041) that do not cut remaining diaphragm (404) still exists with grade line (101) and lays angle (θ);
D, the described diaphragm (405) that cuts is rotated 180 °, make to cut diaphragm (405) do not cut that longitudinal edge two (4051) is overlapped on residue diaphragm (404) do not cut on longitudinal edge one (4041), make to cut simultaneously diaphragm (405) cut that longitudinal edge two (4052) aligns residue diaphragm (404) cut longitudinal edge one (4042), that the transverse edge two (4053) simultaneously making to cut diaphragm (405) aligns residue diaphragm (404) with transverse edge one (4043) that is that do not cut longitudinal edge one (4042) and be connected,
E, welding cut diaphragm (405) cut longitudinal edge two (4052) with remain diaphragm (404) cut the overlapping part overlapped of longitudinal edge one (4042), the longitudinal edge parallel with grade line (101) that residue diaphragm (404) is complete with cutting the rear formation of diaphragm (405) welding, thus angle (θ) is laid in elimination.
2. the sanction of deep camber side slope HDPE film as claimed in claim 1 connects method, it is characterized in that: described offset distance (L) is 5cm.
3. the sanction of deep camber side slope HDPE film as claimed in claim 1 connects method, it is characterized in that: described HDPE film (400) is laid in the side slope (500) between parallel upper mounting plate anchor line (201) and lower platform anchor line (202).
4. the sanction of the deep camber side slope HDPE film as described in claims 1 to 3 any one connects method, it is characterized in that: in step e, is welded during welding by double track hot-melt welding machine.
CN201510909476.1A 2015-12-09 2015-12-09 Trimming and welding method for HDPE membrane for high-curvature side slope Pending CN105525630A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510909476.1A CN105525630A (en) 2015-12-09 2015-12-09 Trimming and welding method for HDPE membrane for high-curvature side slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510909476.1A CN105525630A (en) 2015-12-09 2015-12-09 Trimming and welding method for HDPE membrane for high-curvature side slope

Publications (1)

Publication Number Publication Date
CN105525630A true CN105525630A (en) 2016-04-27

Family

ID=55768125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510909476.1A Pending CN105525630A (en) 2015-12-09 2015-12-09 Trimming and welding method for HDPE membrane for high-curvature side slope

Country Status (1)

Country Link
CN (1) CN105525630A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1117282A (en) * 1993-02-02 1996-02-21 约翰·堡格 Airbag and manufacturing method therefor
CN101337599A (en) * 2007-07-03 2009-01-07 张进 ,Jigsaw packing box
CN102182209A (en) * 2011-02-01 2011-09-14 深圳市胜义环保有限公司 Hillside water seepage isolation system of ardealite storage yard
KR101081513B1 (en) * 2009-12-07 2011-11-08 주식회사 건화 The method crisis possibility Leaching and rainwater of excavation landfill
CN203373758U (en) * 2013-07-19 2014-01-01 深圳市胜义环保有限公司 Impermeable film laying structure of concave-convex type side slope
CN103542235A (en) * 2013-10-15 2014-01-29 潍坊纳博欧化工科技有限公司 Folding device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1117282A (en) * 1993-02-02 1996-02-21 约翰·堡格 Airbag and manufacturing method therefor
CN101337599A (en) * 2007-07-03 2009-01-07 张进 ,Jigsaw packing box
KR101081513B1 (en) * 2009-12-07 2011-11-08 주식회사 건화 The method crisis possibility Leaching and rainwater of excavation landfill
CN102182209A (en) * 2011-02-01 2011-09-14 深圳市胜义环保有限公司 Hillside water seepage isolation system of ardealite storage yard
CN203373758U (en) * 2013-07-19 2014-01-01 深圳市胜义环保有限公司 Impermeable film laying structure of concave-convex type side slope
CN103542235A (en) * 2013-10-15 2014-01-29 潍坊纳博欧化工科技有限公司 Folding device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
无边界河: "HDPE土工膜施工方案", 《百度文库》 *

Similar Documents

Publication Publication Date Title
CN104988827A (en) Old and new road overlapped connecting method
CN104005522B (en) The lapped configuration of polyethylene polypropylene fiber waterproof coiled material and SBS modified bituminous pitch coiled material and engineering method
CN105417197A (en) Automatic material taking method of bucket wheel machine
CN104912119A (en) Close jointing method for pre-paving macromolecular self-adhesion film waterproof roll
CN214090643U (en) Waterproof structure of concrete roof layer
CN104005313B (en) Asphalt concrete pavement dividing strip road kerb construction method
CN106592368A (en) Asphalt pavement paving no-cutting construction method
CN110081960A (en) A kind of Prefabricated road vehicle dynamic weighing platform and its road construction installation method
CN113597490A (en) Asphalt rolling and leveling machine
CN106192898A (en) The joint construction method of Face Slab of Concrete-faced Rockfill anti-settling deformation
CN105019464A (en) Refuse landfill anti-seepage layer structure achieving anchoring through top of side wall of concrete structure flood interception channel
CN105525630A (en) Trimming and welding method for HDPE membrane for high-curvature side slope
CN109372024A (en) A kind of sole plate waterproof structure for deformation seams and construction method
CN107524447A (en) A kind of path method for correcting error of Super Long Tunnel shield-tunneling construction
CN109267592A (en) A kind of construction method of metope inner corner trim pre-installed and inverted adhered waterproof roll
CN102677632A (en) River bottom anti-seepage treatment for geomembrane
CN205314396U (en) Equipment base watertight fittings is createed to roofing
CN208792804U (en) Holes blocking precast construction and holes blocking structure
CN207032324U (en) The pre- structure of film of hazardous waste landfill
CN205171700U (en) Prevent that peripheral building carrier plate of steel column from leaking structure of starching
CN109372030A (en) A kind of post-cast strip waterproof construction and its construction method
CN108677780A (en) A kind of roadmarking and production method
CN204982916U (en) Utilize concrete structure to cut big vast canal lateral wall top anchor landfill barrier layer structure
CN203867093U (en) Overlapping construction for polyethylene polypropylene fiber waterproof coiled material and SBS modified asphalt waterproof coiled material
CN103696446A (en) Construction method of connector position of rail transit underground station and access passage

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160427